1st Case Study The formulated model consists of only 2 periods
(Day & Night). The process units are the vacuum pans for sugar crystallization and two buffer tanks.
2nd case study The formulated model consists of only 2 periods
(Day & Night). The supply entering would be the uncertainty variable that may cause disruptions. The process units are the vacuum pans for sugar crystallization and two buffer tanks. The product requirements bounded by the lower and upper product requirements periodically.
3rd case study The formulated model consists of 14 periods. The
first 13 periods are on an hourly basis during the daytime, while the 14th period is considered as the night time. The equipment capacity will be treated as the uncertainty variable that can cause disruptions. The process units are the vacuum pans for sugar crystallization and two buffer tanks.