You are on page 1of 10

The Revay Report

Volume 20 Published by Construction Consultants


Number 2 Revay and Associates and
June 2001 Limited Claims Specialists

The readers of the


Revay Report, in
responding to a recent
survey, selected delay
analysis as their Concurrent Delay:
number one interest.
We have discussed A Modest Proposal
delay analysis in past R.B. Reynolds and S.G. Revay
issues more than once,
S.G. Revay last time in Number 2 R.B. Reynolds
of Volume 13 (June
1994). Nevertheless the request is
1. INTRODUCTION faulty workmanship, strikes caused by the
understandable considering the rapid contractor, etc. (see: T.J. Trauner, Construc-
evolution of available techniques and more Concurrent delay is experienced on a pro- tion Delays (Kingston, MA: R.S. Means
importantly the judicial treatment of this ject when two or more separate delay Company, Inc., 1990) at p. 4).
topic. No wonder there is no generally events occur during the same time period
accepted technique today. It has often been and each, independently, affects the com- Recent U.S. caselaw continues to demon-
said that delay analysis is an art and not a pletion date. Delays may occur as a result strate an emphasis on the critical path
science. If this statement is true of delay of the actions, or inaction, on the part of analysis approach to treatment of delay.
analysis in general, then it is doubly so with the owner, the contractor, subcontractors, (See, for example, Williams Enterprises
respect to concurrent delay analysis. In this or the designer, and when delays do occur Inc. v. Strait Manufacturing and Welding
article we are trying to chart a possible claims for both extra time and additional Inc., 728 F. Supp. 12 (D.D.C. 1990); Wilner
course for future development. compensation arise. Not infrequently v. United States, 23 Cl. Ct. 241 (1991); PCL
such claims are resisted based upon alle- Construction Services Inc. v. United
gations of concurrent delay, either a con- States, 47 Fed. Cl. 745 (2000).) This
Bruce Reynolds, the co-author of this article,
current delay by the claimant or a method, of course, provides fertile
for those of you who may not know him, is
concurrent delay by another project par- ground for the assertion of concurrent
head of the Construction and Surety
ticipant, which arguably deprives the delay defences.
Professional Group for the national law firm claimant of the ability to establish causa-
of Borden Ladner Gervais LLP. He is listed in tion. To understand the underlying rationale
the Canadian Legal Lexpert Directory 2000 for the principles derived from U.S.
as one of the “most frequently recommended” Most of the literature dealing with concur- caselaw, it is important to recognize that,
construction litigators in Toronto. He is the rent delay comes from the United States as noted above, the defence of concurrent
co-author of Scott and Reynolds on Surety and the majority of it is based on judg- delay arises where the claimant which is
Bonds, and is the author of many papers and ments in the area of federal contracting. contending that certain actions or omis-
articles on construction and surety law. He is Generally, viewed from the perspective of sions on the part of the defendant gave
Past Chair and Legislative Co-ordinator of the owner-general contractor relationship, rise to compensable delay, is met with
the Construction Law Section of the the following principles can be derived either the argument that the claimant
Canadian Bar Association (Ontario) and is a from the U.S. caselaw: itself is responsible for either an excus-
Founding Governor and Past Treasurer able or non-excusable concurrent delay,
• if an excusable (e.g. a force majeure
(1999-2000) of the Canadian College of or the argument that another party
event) or a compensable delay occurs
Construction Lawyers. His practice area for involved in the project was involved in an
concurrently with a non-excusable
excusable or non-excusable concurrent
the past 18 years (called to the Ontario Bar delay, the delay is treated as excusable;
delay. In essence, the defendant takes the
in 1983) has been construction and surety
• if an excusable delay occurs concur- position that, although it (i.e. the defen-
bond law, including construction claims and
rently with a compensable delay, the dant) may have delayed completion of the
construction insurance claims.
delay will be treated as excusable but project, the fact that there was a concur-
non-compensable. rent delay elsewhere on the project,
Mr. Reynolds would like to thank his affecting the critical path, means that the
colleagues Sharon Vogel and Dan Boan for Normally, non-excusable delay arises as a claimant would have suffered the same
their assistance with this paper. result of an event within the contractor’s damages even if the defendant had not
control. Examples of non-excusable delays delayed the project, and that, therefore,
S.G. Revay
include late performance by subcontrac- the claimant cannot prove that the defen-
tors, untimely performance by suppliers, dant caused its damages.
The inequitable aspect of the concurrent reduced this amount by 20% to represent caused delay. However, the calcula-
delay defence is that, where accepted, it the amount of delay which was attribut- tion of such impact costs is a very
results in a wrongdoer avoiding the con- able to Northern. complex exercise and can only be
sequences of its acts. In the paradigm sit- accomplished, if at all, at a trial of the
uation, an innocent claimant can be met Also, in Foundation Co. of Canada v. Unit- issue. Evidence is before me of the
with two or more wrongdoers arguing ed Grain Growers Ltd. (1996), 25 C.L.R. time within which a reasonable con-
that the claimant must bear its own loss (2d) 1 (B.C.S.C.), var’d (1997), 33 C.L.R. tractor could complete the contract,
due to its inability to establish that any (2d) 159 (C.A.), United Grain Growers Ltd. and this is compared to the actual
one of the defendants was the proximate (“United Grain Growers”) entered into a completion time. To reach any proper
cause of the claimant’s damage. Interest- contract with Foundation Co. of Canada conclusion as to the costs from the
ingly, although the defence of concurrent (“Foundation Co.”) for a renovation of its delay one would be required to
delay is widely used by the leading claims grain terminal. CWMM was United Grain analyse the contractor’s progress and
consultants in Canada, the Canadian Growers’s engineer. Foundation Co. sub- determine to what extent the differ-
jurisprudence dealing with construction contracted the sheet metal work to ent causative factors, such as con-
disputes provides no direct assistance in Crosstown Metal Industries Ltd. tractor-caused delays, unavoidable
respect of how to address this significant (“Crosstown Metal”). The construction delays and owner-caused delay con-
defence. was delayed. Foundation Co. sued United tributed to the overall delay experi-
Grain Growers and CWMM for damages enced by the contractor. It would also
Importantly, the general concept of con- for breach of contract and negligent mis- be necessary to evaluate the validity
current delay has been recognized by representation and advanced a claim for of the contractor’s original contract
Canadian courts. For example, in Conti- extras. Crosstown Metal sued Foundation schedule and the “reasonable con-
nental Breweries Inc. v. 707517 Ontario Co. for damages for breach of contract, tractor” schedule.
Ltd. (C.O.B. Northern Algonquin Brewing however, most of these claims were refer-
Co.), [1993] O.J. No. 2395 (Ont. Ct. (Gen. able to the acts and omissions of United However, Wallace J. did not undertake the
Div.)) Northern, as owner, entered into an Grain Growers and CWMM, from which analysis described above, because he was
agreement with Continental Breweries Foundation Co. claimed contribution and of the view that such an exercise could
Inc. (“CBI”), as contractor, to construct a indemnity. United Grain Growers counter- not be undertaken on a motion for judg-
brewing facility. The completion of the claimed against Foundation Co. for eco- ment. Unfortunately, there is a dearth of
brewery was delayed and the facility did nomic losses caused by Foundation Co.’s Canadian caselaw which directly grapples
not “come on stream with a completed delay. At trial, Brenner J. considered each with the issue of the defence of concur-
brewing facility” for one year past the portion of the project which the parties rent delay in terms of conducting the kind
completion date contemplated in the orig- alleged resulted in delay and found that of analysis described by Wallace J. and
inal agreement. As a result, CBI com- Foundation Co. was delayed by the acts determining the resulting apportionment
menced an action against Northern to and omissions of United Grain Growers of responsibility for concurrent delay.
recover for work and materials supplied and/or CWMM for a period of three
In order to appreciate the context within
and for delay. Northern counterclaimed months past completion. Justice Brenner
which expert claims consultants analyse
for lost profits as a result of the delay. also found that Foundation Co. estab-
the issues of concurrent delay, it is useful
After assessing all the evidence in respect lished that there were other delays which
to consider the various analytical
of the delay, Davidson J. found that CBI were the responsibility of United Grain
approaches available.
bore primary responsibility for the delay, Growers and/or CWMM which likely
in that the initial schedules drawn up were delayed Foundation Co., but that these
never met because of its use of inade- delays were concurrent, and therefore 2. ANALYTICAL APPROACHES TO
quate forces, lack of detailed drawings, would not extend the 3-month entitle- SOLVING THE CONCURRENCY
late ordering of material, general lack of ment of Foundation Co. With respect to DILEMMA
experience in projects of that magnitude Crosstown Metal, Brenner J. found that
Foundation Co. contributed to the delays From the claims consultant’s perspective,
and complexity, cash flow problems, and
experienced by Crosstown Metal. Thus, in there is a number of analytical approach-
inability to organize the fundamental
assessing the extent to which Crosstown es available to establish the basis for a
installation of the necessary connected
Metal was entitled to indemnity, Brenner delay claim.
and interdependent elements of the pro-
ject. Justice Davidson also found that J., apportioned responsibility for the
Northern was partly responsible for the delays for which Crosstown Metal was i. The Snapshot Method
delay, since it requested changes for entitled to compensation at 75% for
CWMM and United Grain Growers and In complex claims, simplifying considera-
labelling design, obtaining sufficient
25% for Foundation Co. tions must be adopted by dividing the
labelling information, and changed filters
project into windows of time, where each
which, in turn, delayed CBI. In this The lack of a definitive approach to the window must be analyzed independently.
respect, Davidson J. found that, to a limit- defence of concurrent delay in the Cana-
ed degree, the delay was attributable to dian jurisprudence on construction law Scheduling is a dynamic process. For a
Northern; however, the totality of the represents a troublesome conundrum. schedule to be meaningful and acceptable
delay attributable to Northern was only 12 Justice Wallace, in his decision on a for valid delay analysis it must be kept
weeks since a delay of twelve weeks was motion for judgment, in Pacific Coast current and must reflect both the delays
due to the labelling design and getting Construction Co. Ltd. v. Greater Vancou- or gains as they occur and the then gov-
sufficient label design information and the ver Regional Hospital District (1986), 23 erning planning (e.g. sequencing and
changed filter caused an additional six C.L.R. 35 (B.C. S.C.), highlighted the con- resource loading) of the contractor [see
week delay, but that it was concurrent text within which the concurrency debate Fortec Constructors v. U.S. 760 F.2d 1268
with the 12 week delay of the label normally arises when he stated, in part: (Fed. Cir. 1985)]. Schedules which are not
change. Therefore, Davidson J. attributed kept current (i.e. periodically updated to
80% of the delay to CBI and 20% to North- I find that the contractor is entitled to faithfully reflect the actual status of the
ern. Justice Davidson also allowed North- claim the delay costs incurred by it as project at various intervals) are not con-
ern’s counterclaim for lost profit but a result of the three week owner- sidered a valid medium for delay analysis.

2
Because the snapshot analysis focuses on each window. (This determination can be account the possible relocation of the crit-
specific periods of the project and always based on common sense, the “dominant ical path.
measures gains or delays against the then cause” or “collapsed as–built schedule”
current critical path, it is considered a analysis, as described hereinafter.) iii. Collapsed As-Built Schedule
superior technique for the purpose Perhaps the most authoritative opinion on Method
intended, assuming of course that the the snapshot method was rendered by the
window periods selected are of sufficient- The collapsed as-built schedule method,
Armed Services Board of Contract also known as the “but for” method, has,
ly short duration to properly capture any Appeals, in Gulf Contracting, Inc., ASBCA
significant shifting of the critical path and in recent years, been gaining consider-
Nos. 195, et al., 89-Z BCA (explained in able popularity primarily because of its
that the progress at the end of the period Number 2, Volume 13 of The Revay
represents real progress as opposed to simplicity. Under this method one takes
Report). the as-built schedule, identifies the impact
desired (i.e. invalid) progress.
of delays caused by one or more
The word “snapshot” describing this tech- ii. The Dominant Cause Approach party(ies) (usually the defendant(s)), and
nique underscores the need for relying then removes those impacts from the as-
only on factual as opposed to fictional The line of reasoning used by the court in built schedule. The remaining duration
data. Williams, supra, is very similar to the allegedly represents the schedule within
principle favoured by the English courts, which the claimant could have completed
The schedule run at the end of the win- where it is called the “dominant cause the project “but for” the faults (acts or
dow period (i.e. the snapshot schedule) approach”. According to this approach the omissions) of the defendant. Although
must therefore give effect to the actual plaintiff may recover its damages if it can this apparent simplicity carries inherent
progress achieved as well as to the delays establish that the delay for which the dangers with it (i.e. the method can be
(extended activity duration) and gains defendant must assume responsibility is abused easily), it may nevertheless pro-
(reduction in the activity duration) experi- the overriding or the “dominant” cause of vide a vehicle for the application of con-
enced by the project during the window the loss suffered. Which cause is domi- tributory negligence principles to delay
period. Based on these revisions to activ- nant is a question of fact which is not analysis, as discussed below.
ity duration and the progress actually solved by mere order of occurrence, but is
achieved, the revised project completion to be decided by applying common sense
date is recalculated applying the original 3. THE GENERAL CANADIAN RULE
standards. For example, if progress on a
planning (i.e. the logic used for the sched- section of the work was suspended on a OF ASSESSING DAMAGES
ule in force at the beginning of the win- Monday because an essential piece of In considering the legitimacy of and the
dow period) to the part of the schedule equipment supplied by the owner would treatment to be accorded to the defence
covering the work to be performed not arrive for another ten days, then with- of concurrent delay from a Canadian per-
beyond the end of the window period, out other delays it is safe to assume that spective, it is also useful to review the
including the unprogressed activities or the cost of the suspension should be paid legal context within which such a defence
the remaining portions of those activities to the contractor by the owner. Now, if on functions, i.e. as a bar to the recovery of
which have been partially progressed dur- Wednesday a heavy rain storm caused damages. Generally, Canadian courts
ing the window period. flooding, thereby preventing work on the have adopted the principle that where a
The completion date projected by this entire site for a number of days, is the court determines that the plaintiff has suf-
snapshot schedule, if compared to the contractor still entitled to compensation fered a loss the court must do “the best it
completion date projected by the unpro- for all of its damages? Pursuant to the can” to ascertain its damages.
gressed schedule (the schedule as “dominant cause approach” it would be
entitled to all of its extended duration In this respect, S.M. Waddams in The Law
planned at the beginning of the window
costs relating to the section of work sus- of Damages, looseleaf ed. (Toronto: Cana-
period), indicates the overall delays or
pended, but not to the cost resulting from da Law Book Inc., 1942+) writes, at 13.10
gains resulting from the achieved
the flooding to the other parts of the work. to 13.30, as follows:
progress or lack thereof.
The general burden of proof lies
Although the snapshot schedule is, at There is a long line of English decisions
upon the plaintiff to establish the
times, used as the as-planned schedule which follow the dominant cause
case and to prove the loss for which
for the next window period, more often approach, starting with Leyland Shipping
compensation is claimed. In many
than not the schedule is revised by chang- Co. Ltd. v. Norwich Union Fire Insurance
cases the loss claimed by the plaintiff
ing the sequencing of activities or intro- Society Ltd., [1918] A.C. 350 (H.L.) and
depends on uncertainties; these are
ducing other accelerating measures, continuing through Galoo Limited v.
of two kinds: first, imperfect knowl-
thereby probably shifting the critical path. Bright Grahame Murray, [1995] 1 All E.R.
edge of facts that could theoretically
Most of the time the projected completion 16 (C.A.). All of these English cases and
be known and secondly, the uncer-
date of this “revised” or “updated” sched- arguably also the Williams case represent
tainty of attempting to estimate the
ule is different (usually brought back) relatively straightforward problems suit-
position of the plaintiff would have
from that of the snapshot schedule. able for “common sense” determination.
occupied in hypothetical circum-
Because of the acceleration which might Unfortunately, this is not always the case.
stances, that is to say, supposing that
have been introduced by subsequent On projects that sustain multiple overlap-
the wrong complained of had not
updates, the measure of the total project, ping changes or delays with long dura-
been done.
which has to be determined to assess res- tions (including concurrent delays) , as
ponsibility for the causes giving rise to may be the case, for example, on many American law has had considerable
delays and/or to determine the degree of process or power plants, neither the dom- difficulty with this second type of
entitlement to acceleration cost, is the inant cause approach nor other common uncertainty. The courts have used the
cumulative total of the delays or gains sense approaches may suffice because of requirement of certainty to inhibit or
determined for each snapshot. Allocation all the assumptions that must be made set aside what they consider to be
of liability for the delays will, of course, regarding remaining durations of activi- excessive jury awards, with rigorous
have to be carried out independently for ties being affected not even taking into standards laid down in many cases.

3
The consequence that, where recov- preparing the site by providing a railway The only practical way of measuring
ery is thought to be justified, the connection. Penvidic had to revise its the overall impact and loss of produc-
courts must strive to reconcile the method of construction, and as a result, tivity is in the way that Ms. Tardif has
results desired with prior restrictive suffered increased expenses and delay. done, and that is to attribute the extra
holdings. The evidence proved that International hours spent beyond those estimated
Nickel breached its contract with Penvidic (subject to proof that the estimates are
In Anglo-Canadian law, on the other
and that damages resulted. Penvidic esti- reasonable) to loss of productivity and
hand, perhaps because of the decline
mated its damages by leading evidence impact.
in use of the jury, the courts have
as to the costs of the extra ballasting on
consistently held that if the plaintiff Rosenberg J. held, at page 71, that:
an additional sum-per-ton basis rather
establishes that a loss has probably “although it cannot be precisely mea-
than by ascertaining items of expense
been suffered, the difficulty of deter- sured, the best estimate that I can make is
from its records. The trial judge adopted
mining the amount of it can never that Inco is not responsible for 40% of the
this method to assess damages. On
excuse the wrongdoer from paying delay in the project because of the late
appeal, the Supreme Court of Canada
damages. If the amount is difficult to start, strikes, etc.”
cited the decision of Wood v. Grand Valley
estimate, the tribunal must simply do
Railway Company, supra, for the proposi- Applying the authorities set out above to
its best on the material available,
tion that the court must do “the best it the problem of concurrent delay, an argu-
though of course if the plaintiff has
can” to ascertain the damages and found ment may be advanced that, in cases
not adduced enough evidence that
that under the circumstances, the plaintiff where it is difficult to assess damages,
might have been expected to be
was entitled to the damages which the including issues of concurrency, if the
adduced if the claim were sound, the
trial judge properly assessed. plaintiff proves that the defendant is a
omission will tell against the plaintiff.
wrongdoer and materially contributed to
In Ratcliffe v. Evans, Bowen L.J. said: Another example of the court doing “the the delay and the plaintiff suffered dam-
best it can” is found in the decision of Pot- ages, the court is obligated to do “the best
As much certainty and particular-
ter Station Power Co. v. Inco Ltd. (1998), it can” to assess these damages. Of
ity must be insisted on, both in
43 C.L.R. (2d) 53 (Ont. Ct. (Gen. Div.)). course, it must be recognized that the
pleading and proof of damage,
Bluebird Construction (Potter Station was decisions cited above do not deal specifi-
as is reasonable, having regard
the successor of Bluebird Construction) cally with the issue of concurrent delay,
to the circumstances and to the
entered into a contract with Inco. During yet one is left with the sense that, in rela-
nature of the acts themselves by
the course of Bluebird’s contract a num- tively complex fact situations, where
which the damage is done. To
ber of problems arose, including interfer- issues of concurrency were likely involved
insist upon less would be to
ence and delay. As a result, Bluebird to some degree, Canadian courts have
relax old and intelligible princi-
claimed against Inco for damages, includ- tended to allocate responsibility on a
ples. To insist upon more would
ing, impact costs, head office broad brush approach.
be the vainest pedantry.
overhead/administration, and loss of pro-
This principle was applied by the ductivity. In assessing Bluebird’s impact
Supreme Court of Canada in Wood v. and loss of productivity costs, Rosenberg 4. APPORTIONMENT OF LIABILITY
Grand Valley R. Co. (1915), 51 S.C.R. 283. J., wrote, at page 61, as follows: The concept of apportionment of liability
In Wood the Supreme Court of Canada, may provide a more direct approach to
referring to the decision of Chaplin v. I find that with the number of prob-
address the concurrent delay defence.
Hicks, [1911] 2 K.B. 786, stated, at page lems involved it would be impossible
289, as follows: to calculate the impact and loss of One tool for allocating the responsibility
productivity attributable to each for delay which is available to the courts
It was clearly impossible under the problem. When a part is delayed the of certain of the common law provinces is
facts of that case to estimate with impact and loss of productivity can- contained in legislation addressing the
anything approaching to mathemati- not be determined. The best that can apportionment of liability in negligence.
cal accuracy the damages sustained be done is to estimate the total
Legislation establishing joint and several
by the plaintiffs, but it seems to me to impact of all of the problems and
liability amongst multiple tortfeasors and
be clearly laid down there by the extras on productivity and efficiency.
allowing apportionment of liability in neg-
learned judges that such an impossi-
Justice Rosenberg further wrote, at page ligence has been introduced in all of the
bility can not “relieve the wrongdoer
65, as follows: Canadian common law jurisdictions (see:
of the necessity of paying damages
Negligence Act, R.S.O. 1990, c. N-1; Con-
for his breach of contract” and that
Inco took the position that for each tributory Negligence Act, R.S.N.B. 1973, c.
on the other hand the tribunal to esti-
FWI claimed there should be included C-19; Contributory Negligence Act, R.S.Y.
mate them whether jury or judge
the amount for loss of productivity 1986, c.32; The Tortfeasors and Contribu-
must under such circumstances do
and impact. This may be appropriate if tory Negligence Act, R.S.M. 1987 c. T90;
“the best it can” and its conclusion
there were a few changes and delays Negligence Act, R.S.B.C. 1996, c.333; Con-
will not be set aside even if the
in the contract, but with hundreds of tributory Negligence Act, R.S.A. 1970, c. C-
amount of the verdict is a matter of
such changes there is no practical way 23; Contributory Negligence Act, R.S.N.
guess work. [Emphasis added].
to so allocate. If a piece of equipment 1990, c. C-33; Contributory Negligence
This issue was again considered by the is originally due June 1st and then Act, R.S.N.W.T. 1988, c. C-18; Contributory
Supreme Court of Canada in Penvidic Inco advises that it is now expected Negligence Act, R.S.N.W.T. 1988, c. C-18,
Contracting Co. v. International Nickel Co. June 15th and later advises that it is as duplicated by the Nunavut Act, S.C.
of Canada, [1976] 1 S.C.R. 267. There, Pen- expected July 1st and so on from time 1993, c. 28, as amended; Contributory
vidic entered into a contract with Interna- to time, it is not possible for Bluebird Negligence Act, R.S.N.S. 1989, c.95 and
tional Nickel to lay track and do the top to say, when there are hundreds of the Tortfeasors Act, R.S.N.S. 1989, c. 471;
ballasting on a railroad constructed by such incidents, that this particular inci- Contributory Negligence Act, R.S.P.E.I.
International Nickel. International Nickel dent caused us X dollars as a result of 1988, c. C-1; and The Contributory Negli-
did not complete its preliminary work of the impact and loss of productivity. gence Act, R.S.S. 1978, c. C-31). This legis-

4
lation allows the courts to apportion lia- common law damages could be reason why it should not equally be
bility between plaintiffs which are contrib- apportioned in actions in contract as applicable in cases of contract. …
utories and tortfeasors, as well as well as in actions of tort and that the Mosbeck [the pilot], by negligently
between joint tortfeasors (which remain Contributory Negligence Act, taking the aircraft up, created the sit-
jointly and severally liable to the plaintiff R.S.N.B. 1973, c. C-19, should be uation where the damage occurred
despite any apportionment of liability as applied by analogy, or adopts the the- because of the inadequate shock
between them by the court). (Such legisla- ory of the reasonable expectations of cords installed by the defendant. In
tion is hereinafter referred to as “contrib- the parties, or the notion of reliance such circumstances, there should, in
utory negligence legislation”.) that was either qualified or unreason- my opinion, be apportionment
able, or simply that in fairness and to whether the action be brought in con-
Pitch and Snyder point out that “notwith- do justice the damages ought to be tract or in tort.
standing the similarity of this legislation, apportioned, I do not think that in the
its application by the courts to contract circumstances of this case the trial In apportioning, Saunders J. did not hold
actions has varied from province to judge erred in concluding that the that the Negligence Act applied but rather
province”: see H.D. Pitch & R.M. Snyder, actions of the company president, that “the principles set out in s. 2 of the
Damages for Breach of Contract, 2nd ed. Harold Kane, and of Charles Kane, its Negligence Act seem appropriate to apply
(looseleaf) (Toronto: Carswell, 1989+), at employee, contributed to the compa- to a claim in contract even though the
9§3(b). The technical restriction on the ny’s loss. Nor am I able to say that the statute itself does not apply” (page 341).
application of this legislation to negli- apportionment of the degrees of fault
gence still exists in Alberta, Manitoba, The decision of Saunders J. in Tompkins
of each party is wrong.
New Brunswick, Newfoundland, Ontario, was followed by Grange J. in Ribic v.
Prince Edward Island and Saskatchewan. Also, see Doiron v. Caisse Populaire D’Ink- Weinstein (1982), 140 D.L.R. (3d) 258 (Ont.
On the other hand, the courts of British derman Ltee. (1985), 17 D.L.R. (4th) 660 H.C.J.). Also, in Cosyns v. Smith et al.
Columbia and Nova Scotia have relied on (N.B. C.A.) for an excellent consideration (1983), 41 O.R. (2d) 488 (C.A.), the Court of
negligence legislation in respect of con- of this entire area of the law by Justice La Appeal, in obiter, commented on the rea-
tract claims (see: Pitch & Snyder, Dam- Forest. soning of Saunders J. in Tompkins and
ages for Breach of Contract, supra, at adopted by Grange J. in Ribic as follows:
9§3(b)(i) to (viii)). However, given the gen- The problem of apportionment between a
claimant and a defendant in contract was I am satisfied that, in the present
eral approach of Canadian common law
also addressed in Tompkins Hardware Ltd. case, the duty of the defendants
courts to the application of the principles
v. North Western Flying Services Ltd. et al. arose from the contract. It is not nec-
contained in contributory negligence leg-
(1982), 139 D.L.R. (3d) 329 (Ont. H.C.J.). essary to decide whether a duty also
islation to contractual situations, the dis-
There, the plaintiff took its aircraft to the arose under the law of torts. In any
tinction as to the direct applicability of the
defendant for maintenance and change- event, I do not think that it is neces-
legislation is of diminished significance.
over from floats to skis. The existing shock sary for this court to pronounce on
For example, with relation to apportion- cords were replaced with new cords. An the attractive conclusion reached by
ment between a claimant and a defendant aeronautical engineer employed by the Saunders J. and adopted by Grange
in contract, in the New Brunswick Court of defendant inspected the work and certi- J. I say this because of the conclusion
Appeal case of Coopers & Lybrand v. H.E. fied the aircraft as airworthy. After picking which I have reached on the second
Kane Agencies Ltd. (1985), 17 D.L.R. (4TH) up the aircraft from the defendant, the issue, i.e., the legal validity of the
695, Coopers, an accountancy firm, was plaintiff’s pilot took off for his camp. He finding of contributory negligence
Kane’s auditor and conducted an annual encountered problems controlling the air- made against the plaintiff in this case.
audit of Kane. In its action, Kane alleged craft and made his own temporary repairs [The Court of Appeal found that the
that Coopers failed to exercise reasonable by attaching “tie downs” to the landing plaintiff was not negligent].
care, skill, and competence, or alterna- gear. During a flight the next day the pilot
tively, that it was negligent in the perfor- was forced to make an emergency land- Similarly, in Wells Construction Ltd. v.
mance of its duties to Kane since Coopers ing which resulted in extensive damage to Thomas Fuller Construction Company
failed to detect a system that Charles the aircraft. The plaintiff sued the defen- (1958) Ltd. (1986), 22 C.L.R. 144 (Nfld. S.C.)
Kane, the principal of Kane, devised which dant in both contract and tort. Justice Thomas Fuller contracted with Her
resulted in excessive credit being extend- Saunders found that the defendant failed Majesty in the Right of Canada for the
ed to one of Kane’s customers. The cus- to perform its obligations to the plaintiff in construction of buildings. In turn, Thomas
tomer subsequently went into a workmanlike manner and also that the Fuller subcontracted the excavation and
receivership and Kane was unable to pilot was negligent since it was unreason- backfill, rock removal, clearing and grub-
recover part of its debt. The Court of able for him not to have left the aircraft bing, site grading, and some drilling to
Appeal agreed with the trial court that with the defendant after the first incident Wells. Wells began to experience financial
Coopers did not meet the standard of care when he encountered problems control- difficulties which it attributed to the lack of
and skill called for in the circumstances. ling the aircraft. The plaintiff argued that payment of invoices rendered to Thomas
The Court of Appeal also found that the even if its pilot was negligent, such negli- Fuller for work completed. As a result,
bad business judgment of Charles Kane gence did not reduce the defendant’s lia- Wells withdrew its workers and informed
was a proximate cause of Kane’s loss, bility in contract. In this respect, Saunders Thomas Fuller that it would return to the
however, this conclusion did not provide J. found, at pages 340-341, as follows: site, but only after its progress invoices
Coopers with a complete defence. With were paid. The issues were not resolved
respect to apportionment, Stratton, J.A. The principle that where a man is part and Thomas Fuller completed the work
delivering the judgment of the court, author of his own injury he cannot under the subcontract. Wells commenced
found, at page 708, as follows: call upon the other party to compen- an action to recover from Thomas Fuller
sate him in full, has long been recog- and the bonding company the balance
… I am satisfied that the duty of nized as applying in cases of tort: see due for labour, materials, equipment, and
Coopers & Lybrand arose from their Nance v. B.C. Electric R. Co., [1951] 3 services rendered under the subcontract.
contract of engagement. Whether D.L.R. 705 at p. 711, [1951] A.C. 601 at Thomas Fuller counterclaimed. Part of
one accepts the argument that at p. 611, 2 W.W.R. (N.S.) 665. I see no Thomas Fuller’s counterclaim was based

5
on the damages suffered as a result of learned trial judge apportioned liabil- ticularly in circumstances where the
having to complete the backfill work, ity by disallowing the costs to the claimant has contributed to the delay.
which Wells argued should be appor- Owner of architectural and legal ser-
Such an approach is to be compared with
tioned. With respect to this portion of the vices although he did not express his
that contained in U.S. cases such as Coath
counterclaim, Woolridge J. agreed with reasons in those terms. The result of
& Goss, Inc., A Corporation v. The United
the decision of Saunders J. of Tompkins his decision was that the completion
States, 101 Ct. Cl. 702 (1944), and Blinder-
Hardwood, supra, holding that the princi- costs were borne by the Contractor
man Construction Co., Inc. v. The United
ples set out in Section 2 of The Contribu- and the Owner in a proportion of
States, 695 F.2d 552 (U.S.C.A., 1982), pur-
tory Negligence Act, R.S.N. 1970, c.61 are approximately 77:23.
suant to which apportionment is only
appropriate to apply to a claim in contract.
Further, in Dartmouth (City) v. Acres Con- allowable where there is proof of a clear
As a result, Woolridge J. found that
sulting Ltd. (1995), 138 N.S.R. (2d)163 allocation of the delay and expense attrib-
Thomas Fuller was 80% liable, and Wells
(S.C.), the City engaged Acres to prepare utable to each party.
20% liable, for the costs of the backfill.
the designs and specifications for the Again, however, it does not appear that
Also, in Convert-A-Wall Ltd. v. Brampton construction of ramps and floating docks the issue of the defence of concurrent
Hydro-Electric Commission (1988), 65 O.R. for the Dartmouth cross harbour ferry ter- delay has been specifically addressed by
(2d) 385 (Div. Ct.), Convert-A-Wall (the minals. The City also contracted with the court in the cited Canadian jurispru-
“Contractor”) contracted with Brampton McAlpine as general contractor. dence on apportionment. In other words,
for the construction of additions and mod- McAlpine subcontracted with Semper to where concurrent delay clearly occurs,
ifications to offices and warehouse prop- supply labour, materials, and equipment and the defence is squarely raised, appor-
erty of Brampton. There were delays in the for the installation of the roofing. In turn, tionment, as it has been applied in the
progress of the work which the Contractor Semper subcontracted to Connor to construction context to date, does not
attributed to Brampton and Brampton’s install and supply the roofing in accor- directly address the basic causation issue
architect (the “Architect”). As a result, the dance with the plans and specifications. inherent in the defence.
work was behind schedule. Liens were Construction was completed; however,
also registered and the amounts claimed about five years later water was detected Importantly, the Supreme Court of Cana-
were held back by Brampton. The Contrac- leaking from the ceiling of one of the da in Athey v. Leonati, [1996] 3 S.C.R. 458,
tor began to experience a cash-flow prob- ramps. The City investigated the cause of 140 D.L.R. (4th) 235 can be referenced (by
lem and Brampton continued to hold back the leaks and discovered that the roof had analogy) in this context. Athey v. Leonati
the amount of the claims for lien of which experienced rot and concluded that deals with personal injury; however, Jus-
it had notice. The situation steadily deteri- extensive repairs were required. The City tice Lee considered the principles set out
orated until Brampton terminated the con- commenced an action to recover the in Athey v. Leonati in the context of con-
tract. The court found that the only default costs of these repairs. The evidence current delay in The City of Edmonton v.
by the Contractor was failure to complete showed the presence of considerable Lovat Tunnel Equipment Inc. (2000), 3
in a timely fashion. Brampton was respon- water and moisture within the sandwich C.C.L.T. (3d) 78 (Alta. Q.B.).
sible for some of the delay to the Contrac- construction of the roof which led to the In his decision, Justice Lee, responding to
tor and the trial judge awarded the rotting of the wood and vapour barrier in an argument submitted by the City of
Contractor damages for those delays. The the roof. Justice Grant canvassed several Edmonton that the “collapsed as-built
trial judge also found that Brampton was different causes which led to the roof schedule” delay analysis presented by its
entitled to completion costs. The trial damage and found that McAlpine and scheduling expert was in accordance with
judge found that the delays caused by the Connor failed to follow the specifications. the test adopted by the Supreme Court of
owner, at least in part, led to the Contrac- As a result, Grant J. found that Acres was Canada in Athey v. Leonati, had this to
tor’s default, however, the trial judge not negligent and not liable. Justice say:
found that the Contractor had the respon- Grant did not canvass the law of appor-
sibility of performing the contract in accor- tionment as it applies to claims arising in [520] The court in Athey v. Leonati
dance with its terms and that a reasonable tort and contract, but, in any event, confirmed that causation is estab-
contractor would have anticipated the apportioned the damages in the follow- lished when the plaintiff proves on a
financial problems and the possibility of ing manner: 20 % to the City (10% for balance of probabilities that the
delay. The trial judge essentially appor- accepting changes of materials and 10% defendant has caused or contributed
tioned the completion costs between the for work done by City workers); and 80% to the injury. Generally, a “but for”
Contractor and Brampton by awarding the to McAlpine (20% for negligence in test is employed for causation, pur-
Contractor damages arising as a result of respect of carpentry work and 60% for suant to which the plaintiff must
the delay and Brampton some of its com- negligence in respect of the roofing). Jus- establish that the injury complained
pletion costs. On Appeal, Saunders J., tice Grant also found that the City was to of would not have occurred but for
stated, at page 393, as follows: be indemnified by its consulting engineer the negligence of the defendant.
for 10% of the damages for accepting the [521] Under various circumstances,
The recovery of completion costs is
changes in the roof materials. Further, the Courts will recognize that causa-
akin to damages. Those costs com-
McAlpine was to receive indemnity from tion may be established where the
pensate an owner for an expense
Connor for the 60% of the damages defendant’s negligence materially
which he would not have otherwise
resulting from the roofing negligence as contributed to the occurrence of the
incurred. If an owner is partly respon-
Connor had performed the work. injury. Where there are numerous fac-
sible for the incurring of the expense,
then it is appropriate to apportion the tors contributing to the injury, the
Clearly, where available, the principles
liability in the same manner as is defendant will be liable for all of the
contained in the Coopers & Lybrand,
done in a tort action. injuries caused or materially con-
Tompkins Hardware, and Convert-A-Wall
tributed to by his or her negligence.
… cases contribute an element of flexibility
into the analysis of shared responsibility The Athey v. Leonati decision (written by
The apportionment of liability cannot for damages in contract, including, in the Justice Major), and its forbears, provide
be a precise calculation. In effect, the view of the authors, delay damages, par- authoritative Canadian support for the

6
“material contribution” approach to the material if it falls outside the de min- single cause can be attributed to a
apportionment of damages in negligence, imus range: Bonnington Castings, harm is the “but-for” test. However,
as well, it is contended, in contract. Ltd. v. Wardlaw, supra; see also R. v. the but-for test is unworkable in
Pinske (1988), 30, B.C.L.R. (2d) 114 some situations, particularly where
Justice Major, in addressing apportion-
(B.C.C.A.), aff’d [1989] 2 S.C.R. 979… multiple independent causes may
ment, in Athey v. Leonati makes a very
[…] bring about a single harm.
clear differentiation between tortious and
non-tortious causes, noting that: To understand these cases, and to In cases of negligent donor screen-
Apportionment between tortious see why they are not applicable to the ing, it may be difficult or impossible
causes is expressly permitted by present situation, one need only con- to prove hypothetically what the
provincial negligence statutes and is sider first principles. The essential donor would have done had he or
consistent with the general principles purpose and most basic principle of she been properly screened by the
of tort law. The plaintiff is still fully tort law is that the plaintiff must be C.R.C.S. The added element of donor
compensated and is placed in the placed in the position he or she conduct in these cases means that
position he or she would have been would have been in absent the defen- the but-for test could operate unfair-
in but for the negligence of the defen- dant’s negligence (the “original posi- ly, highlighting the possibility of leav-
dants. Each defendant remains fully tion”). However, the plaintiff is not to ing legitimate plaintiffs
liable to the plaintiff for the injury, be placed in a position better than his uncompensated. Thus, the question
since each was a cause of the injury. or her original one. It is therefore nec- in cases of negligent donor screening
The legislation simply permits defen- essary not only to determine the should not be whether the C.R.C.S.’s
dants to seek contribution and plaintiff’s position after the tort but conduct was a necessary condition
indemnity from one another, accord- also to assess what the “original posi- for the plaintiffs’ injuries using the
ing to the degree of responsibility for tion” would have been. It is the dif- “but-for” test, but whether that con-
the injury. ference between these positions, the duct was a sufficient condition. The
“original position” and the “injured proper test for causation in cases of
In the present case, the suggested position”, which is the plaintiff’s loss. negligent donor screening is whether
apportionment is between tortious the defendant’s negligence “material-
and non-tortious causes. Apportion- The last paragraph, cited above, is clearly
ly contributed” to the occurrence of
ment between tortious and non-tor- in accord with the approach set out by
the injury. In the present case, it is
tious causes is contrary to the Justice Wallace in the Pacific Coast Con-
clear that it did. “A contributing factor
principles of tort law, because the struction Co. Ltd. case.
is material if it falls outside the de
defendant would escape full liability In the result, the Supreme Court did minimis range” (see Athey v. Leonati,
even though he or she caused or con- apportion between tortious and non-tor- [1996] 3 S.C.R. 458, at para. 15). As
tributed to the plaintiff’s entire tious causes in Athey v. Leonati. such, the plaintiff retains the burden
injuries. The plaintiff would not be of proving that the failure of the
adequately compensated, since the The Supreme Court of Canada also adopt-
C.R.C.S. to screen donors with taint-
plaintiff would not be placed in the ed the “material contribution” test, dis-
ed blood materially contributed to
position he or she would have been cussed in Athey v. Leonati, in its recent
Walker contracting HIV from the taint-
in absent the defendant’s negligence. decision of Walker Estate v. York Finch
ed blood. [Emphasis added.]
General Hospital, [2001] S.C.J. No. 24. In
In the following excerpt, Justice Major Walker Estate, three plaintiffs, Osborne,
sets out some of the general principles to In situations where there are concurrent
“M”, and Walker, contracted HIV from
be considered: delays (whether all such delays are non-
blood and blood products supplied by the
excusable or some are non-excusable and
Causation is established where the Canadian Red Cross Society (“Red
one or more are excusable), notwith-
plaintiff proves to the civil standard Cross”). The plaintiffs claimed that the
standing causation concerns, it would
on a balance of probabilities that the Red Cross was negligent in its procedures
appear equitable to apportion damages
defendant caused or contributed to used to screen blood donors. Osborne
amongst the wrongdoers which have
the injury: Snell v. Farrell, [1990] 2 and “M” were successful at trial; however,
materially contributed to the delay, and
S.C.R. 311; McGhee v. National Coal the trial judge found that Walker could not
the consequent damages. For example, in
Board, [1972] 3 All E.R. 1008 (H.L.). prove causation. The Ontario Court of
a situation of pure concurrent delay, such
Appeal agreed with the trial judge’s deci-
that two or more parties have delayed in
The general, but not conclusive, test sion with respect to Osborne and “M”, but
performing their obligations in respect of
for causation is the “but for” test, reversed the trial judge’s decision with
the same time period and the innocent
which requires the plaintiff to show respect to Walker finding that if the trial
plaintiff is unable to prove which party is
that the injury would not have judge applied the correct causal analysis
causally responsible, it would appear
occurred but for the negligence of the he would have found the necessary
clearly inequitable to allow the wrongdo-
defendant: Horsely v. MacLaren, causal link. In dismissing the appeal of the
ers to escape liability and have the inno-
[1972] S.C.R. 441. Red Cross, the Supreme Court of Canada
cent claimant incur the entire damage.
stated as follows, at paras. 87 and 88:
The “but for” test is unworkable in Rather, in appropriate circumstances, the
some circumstances, so the courts With respect to negligent donor courts could apply the principles enunci-
have recognized that causation is screening, the plaintiffs must estab- ated in the relevant contributory negli-
established where the defendant’s lish the duty of care and the standard gence legislation, whether directly or by
negligence “materially contributed” of care owed to them by the C.R.C.S. analogy, and apportion the damages (per-
to the occurrence of the injury: Myers [the Red Cross]. The plaintiffs must haps equally) amongst the wrongdoers.
v. Peel County Board of Education; also prove that the C.R.C.S. caused (In cases where both the claimant and the
[1981] 2 S.C.R. 21, Bonnington Cast- their injuries. The unique difficulties defendant(s) have contributed to the
ings, Ltd. v. Wardlaw, [1956] 1 All E.R. in proving causation make this area delay, it is inequitable for either the
615 (H.L.); McGhee v. National Coal of negligence atypical. The general claimant or the defendant(s) to incur all of
Board, supra. A contributing factor is test for causation in cases where a the damages. In such a case, it may be

7
equitable for the court to apportion the acted independently, judgment was elected to apply contributory negligence
damages (perhaps equally).) given against both of them for the full principles to apportion damages amongst
amount of the plaintiff’s damages wrongdoers (see: Tompkins, supra, and
As contended above, the paradigm situa-
because “if each contributed to the Ribic v. Weinstein et al., supra). Important-
tion in terms of the inequity inherent in
injury, that is enough to bind both”. A ly, however, in provinces where the courts
the concurrent delay defence arises
similar case is Arneil v. Paterson, are unlikely to apply contributory negli-
where at the same time there is an inno-
where two dogs were held responsi- gence legislation directly to contract
cent plaintiff and two or more other pro-
ble for the entire damage “because claims, the courts have nevertheless, in
ject participants in delay. Here, the law of
each dog did in the eye of the law certain instances, arrived at the same
tort, and, in particular, the concept of
occasion the whole of the injury of result by holding the defendant liable to
“material contribution”, is also relevant.
which the pursuers complain”.Thus, if the claimant concurrently in tort and in
A.M. Linden in Canadian Tort Law, 6th ed.
the concurrent negligence of two contract (see: Husky Oil Operations Ltd. v.
(Toronto: Butterworths Canada Ltd., 1997)
people combined to kill someone, Oster (1978), 87 D.L.R. (3d) 86 (Sask. Q.B.);
writes, at pages 109-110, as follows:
each would be equally responsible Canadian Western Natural Gas Co. v.
The “but for” test ran into stormy for the death. A group of polluters Pathfinder Surveys Ltd. (1980), 12 Alta.
sailing where two or more defen- may be jointly liable though the harm L.R. (2d) 135, 12 C.C.L.T. 211 (C.A.); and
dants combined to cause loss. If the caused by each cannot be deter- Dominion Chain Co. Ltd. v. Eastern Con-
injury would have transpired if either mined. struction Co. Ltd. (1976), 12 O.R. (2d) 210
cause alone had been operating, nei- (C.A.), aff’d [1978] 2 S.C.R. 1346 in which
Importantly, it may be possible to arbitrar-
ther party might be a cause under the the Ontario Court of Appeal found that the
ily apportion degrees of fault amongst the
“but for” test. Suppose A and B neg- Ontario Negligence Act does not apply to
wrongdoers. Potentially, this is extremely
ligently light fires at different places actions in contract, but allowed contribu-
significant dealing with the concurrent
and the fires spread to engulf the tion on the basis that the plaintiff sued in
delay defence. Specifically, all contributo-
plaintiff’s house. A and B might argue both tort and contract).
ry negligence legislation provides that if it
that the fire would have resulted is not possible to establish degrees of The leading case on the doctrine of con-
without their negligence. Conse- fault, then the court must apportion liabil- current liability in contract and tort is the
quently, a blinkered court might hold ity equally. For example, Section 1(1) of Supreme Court of Canada decision in
that neither of the defendants, the Contributory Negligence Act, R.S.N.B. Central Trust v. Rafuse, [1986] 2 S.C.R. 147.
although both negligent, was the 1973, c.C-19, as amended, provides as fol- The principal issue on appeal in Central
cause of the loss, because it would lows: Trust v. Rafuse was whether a solicitor
have occurred in any event.
Where by the fault of two or more was liable to a client in tort and contract
This just could not be tolerated and, persons damage or loss is caused to for damages caused by a failure to meet
happily, the courts have handled this one or more of them, the liability to the requisite standard of care in the per-
situation with common sense. They make good the damage or loss is in formance of services for which the solici-
devised the substantial factor test, proportion to the degree in which tor was retained. The Court canvassed the
which holds that if the acts of two each person was at fault but if, having law with respect to concurrent liability in
people are both substantial factors in regard to all the circumstances of the tort and contract and rejected the require-
bringing about the result, then liabili- case, it is not possible to establish ment set out in J. Nunes Diamonds Ltd. v.
ty is imposed on both on the theory different degrees of fault, the liability Dom. Elec. Protection Co., [1972] S.C.R.
that both “materially contributed to shall be apportioned equally. 769, that tort liability must arise indepen-
the occurrence”. Consequently, in dent of contract, holding that the common
Lambton v. Mellish, two merry-go- As discussed above, in jurisdictions law duty of care is not confined to rela-
round operators were sued for nui- where the courts have determined that tionships which arise apart from contract.
sance as a result of the maddening contributory negligence legislation does The effect of the decision was reduced,
noise made by their organs. Injunc- not apply to contractual claims the however, as the Court further stated, at
tions were granted against them indi- authorities nevertheless exist to support page 206, as follows:
vidually, because according to Mr. the proposition that the principles set out
in the contributory negligence legislation A concurrent or alternative liability in
Justice Chitty:
can be applied to allow apportionment in tort will not be admitted if its effect
If the acts of two persons, each contract. Accordingly, the presumption of would be to permit the plaintiff to cir-
being aware of what the other is equal apportionment of liability may be cumvent or escape a contractual
going, amounted in the aggre- available to overcome the causation hur- exclusion of liability for the act or
gate to what is an actionable dle inherent in the concurrent delay omission that would constitute the
wrong, each is amenable to the defence. tort. Subject to this qualification,
remedy against the aggregate where concurrent liability in tort and
cause of complaint. The defen- contract exists the plaintiff has the
5. CONCURRENT LIABILITY IN
dants here are both responsible right to assert the cause of action that
for the noise as a whole so far as TORT AND CONTRACT appears to be most advantageous to
it constitutes a nuisance affect- Another important principle which intro- him in respect of any legal conse-
ing the Plaintiff, and each must duces flexibility into the assessment of quence.
be restrained in respect of his responsibility for damages, and may be
In BG Checo International Ltd. v. British
own share in making the noise. seen as enhancing access to contributory
Columbia (Hydro and Power Authority),
negligence legislation, is the principle of
In another case, Corey v. Havener, the [1993] 1 S.C.R. 12, Hydro contracted with
concurrent liability in contract and tort.
plaintiff, in a horse and wagon, was Checo to erect transmission towers and
passed by two motorists driving at a As stated above, some Canadian courts string transmission lines on a right of
high rate of speed, one on each side. have declined to apply contributory negli- way. The tender documents also provided
The horse took fright and the plaintiff gence legislation to claims arising in con- that Checo was to satisfy itself of the site
was injured. Although the defendants tract. As an alternative, some courts have conditions and that others would clear the

8
right of way. Hydro contracted the clear- sions to the non-recoverability of pure Unlike the other services cases the
ing work to another party and, to Hydro’s economic loss doctrine: owner will, at least in theory, have an
knowledge, the work was done inade- adequate legal remedy already under
• the independent liability of statutory
quately. In fact, no further clearing was the main contract with the general
public authorities;
done which resulted in Checo having diffi- contractor. For this reason and other
culties and increased costs. Checo sued • negligent misrepresentation; reasons, the case in favour of a direct
Hydro seeking damages for negligent action against the subcontractor is
• negligent performance of a service;
misrepresentation, or, in the alternative, not compelling. On the other hand,
breach of contract. The contract contained • negligent supply of shoddy goods or provided the relevant obligation
an exclusion clause which limited Hydro’s structures; breached in the subcontract is identi-
liability for the clearing of the right of way. • relational economic loss. cal to the obligation specified in the
The Court followed its decision of Central main contract, there is little harm in
Trust v. Rafuse, supra, and held at pages However, the Supreme Court of Canada recognizing the direct suit. The gener-
26-27, as follows: has not restricted recovery to cases falling al contractor may be regarded as a
within these categories of exclusions and mere conduit of obligations, and the
In our view, the general rule emerg- has applied the Anns test to determine two contracts in effect collapsed into
ing from this Court’s decision in Cen- novel cases of pure economic loss which one between the owner and the sub-
tral Trust v. Rafuse, [1986] 2 S.C.R. 147, fall outside of these categories. contractor.
is that where a given wrong prima
facie supports an action in contract In the construction context, where a plain- It must be noted, however, that while Pro-
and in tort, the party may sue in tiff claims for delay both in contract and fessor Feldthusen writes that the general
either or both, except where the con- tort, the plaintiff might be able to argue contractor may be regarded as a conduit,
tract indicates that the parties intend- that its claim falls within the categories of the British Columbia Supreme Court dis-
ed to limit or negative the right to sue negligent misrepresentation or negligent missed an owner’s claim against subcon-
in tort. This limitation on the general performance of a service. For example, tractors with which it did not have privity
rule of concurrency arises because it where a general contractor negligently of contract. In Status Electrical Corp. v. Uni-
is always open to parties to limit or represents that it will complete the project versity of British Columbia, [2000] B.C.J.
waive the duties which the common by a particular date, and fails to do so, the No. 2569, the University counterclaimed
law would impose on them for negli- owner will be able to argue that it can against several of the general contractor’s
gence. This principle is of great recover for pure economic loss on the subcontractors alleging that the University
importance in preserving a sphere of basis of negligent misrepresentation. A suffered delay damages as a result of the
individual liberty and commercial more difficult problem arises where the subcontractors’ negligence. On applica-
flexibility. reason for the delay is not a negligent rep- tion, Sigurdson J. dismissed the Universi-
resentation as to the completion date, but ty’s counterclaims finding that this was not
Therefore, the general rule which where the defendant was negligent in per- the type of situation in which a new cate-
emerges from the decisions of Central forming its obligations. gory of recoverable pure economic loss
Trust v. Rafuse and BG Checo, is that a
should be created, nor should one of the
party may sue in both tort and contract Professor Feldthusen in Economic Negli-
current categories be expanded.
unless the contract limits or regulates the gence, 4th ed. (Toronto: Carswell, 2000)
party’s right to sue in tort. sets out the test to determine if a defen- However, Status Electrical is not a case of
dant will be held liable for economic loss concurrent liability in contract and tort.
To the extent that the defendant is liable for negligently performing a service, at Further, it is curious that Sigurdson J. stat-
in negligence, recourse to contributory page 120, as follows: ed that it was not seriously suggested that
negligence legislation and caselaw the facts brought the claims within one of
should be available in all of the common There is a general agreement among
recognized categories. Following the test
law jurisdictions. the courts in all common law jurisdic-
for negligent performance of a service
tions that the defendant will be held
Unfortunately, the utility of the concurrent illustrated by Professor Feldthusen, set
liable for the plaintiff’s economic loss
liability argument may be limited by the out above, it would appear that it may
if: (1) the defendant voluntarily
doctrine of pure economic loss as devel- have been possible to argue that the sub-
undertakes to perform a specific ser-
oped by the Supreme Court of Canada in contractor negligently performed a ser-
vice for the plaintiff’s benefit; (2) the
Canadian National Railway Co. v. Norsk vice, since the subcontractors voluntarily
plaintiff relies on the defendant to
Pacific Steamship Co., [1992] 1 S.C.R. undertook to perform a service which
perform the undertaking; and (3) the
1021; Winnipeg Condominium Corpora- directly benefited the University, the Uni-
negligent performance of the service
tion No. 36 v. Bird Construction Co., [1995] versity relied on the subcontractors, and
injures the plaintiff.
1 S.C.R. 85; Hercules Management Ltd. v. the University suffered loss.
Ernst & Young, [1997] 2 S.C.R. 165; Bow Thus, in the construction context, where
Nevertheless, the doctrine of pure eco-
Valley Husky (Bermuda) Ltd. v. Saint John plaintiff contracts with a defendant to per-
nomic loss must be recognized as a pos-
Shipbuilding Ltd., [1997] 3 S.C.R. 1210; form a service, if the defendant is found
sible limiting factor to advancing a claim
and Martel Building Ltd. v. Canada, [2000] concurrently liable in contract and tort, it
in negligence.
S.C.J. No. 60. is contended that the category of negli-
gent performance of a service would
The Supreme Court of Canada adopted apply and the plaintiff should be able to 6. SUMMARY
the test set out in Anns v. Merton London recover for pure economic loss.
Borough Council, [1978] A.C. 728 (H.L.) in Concurrent delay arises where two sepa-
Kamloops City v. Nielsen, [1984] 2 S.C.R. 2 Where a delay claim is made by an owner rate delay events occur during the same
to determine whether pure economic loss against a subcontractor the courts may time period and both, independently, affect
is recoverable. The Supreme Court of arrive at a different conclusion. In this the completion date. As a result, both par-
Canada has also adopted the category respect, Professor Feldthusen, in Econom- ties causing the delay may argue that the
approach of Professor Feldthusen who ic Negligence, writes, at pages 136-137, as claimant cannot meet the “but for” test
sets out the following categories of exclu- follows: and prove the proximate causation which

9
has been traditionally a condition prece- the context of delay analysis, in consider- repair of the damage caused by each
dent to compensation. Such a conclusion ing the approaches available to a claims requires 10 days to complete. The
bars an innocent claimant from recovery, a consultant, it appears that the collapsed- ship is then taken out of service for 10
result, which on its face, appears to be as-built schedule method may be the days and both repairs are performed
unjust. Even where the claimant has mate- most appropriate vehicle for assessing concurrently. From the perspective of
rially contributed to the delay, it appears damages. Importantly, a court must be the first tortfeasor the fact that the
inequitable to allow a wrongdoer to persuaded that, as between two or more ship had to be taken out of service for
escape responsibility through the occur- wrongdoers, responsibility must be allo- 10 days to repair the damage caused
rence of a fortuitous event. cated so that the innocent party is made by the second tortfeasor would serve
whole. If the claimant is not an “innocent to bar the recovery of damages for
In Canadian common law jurisdictions party”, then the claimant must share the the losses suffered during the deten-
where the courts have found that contrib- responsibility with the wrongdoers. tion. The second tortfeasor could
utory negligence legislation applies to obviously make precisely the same
breach of contract claims, the claimant In essence, the solution to the conundrum
assertion and argue that it should not
not only has an argument that the court of the concurrent delay defence is for the
be held liable for the detention as the
must do the “best it can” to determine the court to accept that, in circumstances of
requirement to repair the damage
apportionment of damages between the concurrent delay(s), each person guilty of
caused by the first tortfeasor meant
wrongdoers, but, as well, the court, if sat- non-excusable delay has “materially con-
that the ship would not have been “a
isfied that the defendant has “materially tributed” to the critical path delay and is
profit-earning machine” during the
contributed” to the delay, may rely upon liable for an apportioned amount of the
repair period even in the absence of
such legislation to overcome the impedi- damages suffered, whether specific
the damage caused by the second
ment to compensation represented by the amounts of damages can be attributed to
tortfeasor. In short, where there are
principle of several liability and to appor- separate causes or not.
two operative causes of the deten-
tion liability (and damages). If the court is tion, it can be argued by the parties
In a legal environment which clearly
unable to determine the appropriate respectively responsible for each that
involves the convergence of contract and
apportionment, then, arguably, the court to the extent the detention was
tort theories, it should be open to the court
may apportion the damages equally. caused by the others’ act, it is not
to embrace the tools of contributory negli-
In Canadian common law jurisdictions gence legislation and the related caselaw responsible. This would serve to bar
where the courts have found that contrib- in order to overcome the hurdle of the the owner from recovering any
utory negligence legislation does not restrictive approach to causation which is detention losses caused by concur-
apply to breach of contract claims, the inherent in the concurrent delay defence. rent repairs due to two separate inci-
claimant may nevertheless argue that the dents that the owner, by default,
The fundamental challenge posed by the would end up bearing the loss.
court must do the “best it can” to deter-
concurrent delay defence itself was clear-
mine the damages, and the claimant may
ly articulated, in obiter, by McLachlin J. This result would appear, ab initio, an
also argue that the court, so long as it is
(as she then was), of the Supreme Court incorrect one and particularly unfair
satisfied that the defendant has “material-
of Canada, (dissenting) in Sunrise Co. v. when all the damage was tortiously
ly contributed” to the delay, should, by
Lake Winnipeg (The), [1991] 1 S.C.R. 3, caused. To avoid such result, it is nec-
analogy, apply contributory negligence
where she stated: essary to introduce a factor other
principles and apportion liability (and
than pure causation. What is required
damages) accordingly, or that the defen- … Moreover, it can be argued that
is a rule that says (a) that one of the
dant(s) are concurrently liable in negli- applying strict logic, adoption of this
two causes of the concurrent loss is
gence, giving rise to the apportionment approach might result in the defen-
responsible (e.g., the “first in time”
powers provided by the contributory neg- dant’s recovering nothing in the case
rule) or (b) that the concurrent delay
ligence legislation. where its ship is damaged by two
should be apportioned between the
consecutive tortfeasors and the time
Normally, it is only after the court is satis- two causes of the concurrent loss.
required to effect both sets of repairs
fied that causation has been established
was the same. Here, Chief Justice McLachlin identified
that it will turn to an assessment of the
damages suffered, the issue as to whether The following example illustrates this the need for a solution to the conundrum
the claimant is contributorily responsible, conclusion. Assume that the ship was of the concurrent delay defence, and, with
and a potential apportionment as damaged in two separate and unre- respect, advanced a modest proposal
between the wrongdoers. Accordingly, in lated tortious collisions, and that the which we have endeavoured to further.

The Revay Report is published by Revay and RAL offices:INFORMATION


CONTACT
Associates Limited, a national firm of Construc- MONTREAL CALGARY ATLANTA
tion Consultants and Claims Specialists, assisting 4333
Please Ste. Catherine St. West,
visit www.revay.com Glenmore
for current Landing
office locations. 3465 Lawrenceville Suwanee Road,
owners and contractors in achieving profitable Suite 500 #D262, 1600 - 90th Avenue SW Suite C
If you would like
MONTRÉAL, Québec H3Z 1P9 to subscribe for The
CALGARY, Revay Report,
Alberta T2V 5A8 click here.
Suwanee, GA 30024
and trouble-free construction projects. Tel.: (514) 932-2188 Tel.: (403) 777-4900 Tel.: (770) 932-0123
Fax: (514) 939-0776 Fax: (403) 777-4903 Fax: (770) 932-8813
Contents may be reproduced, with a credit as montreal@revay.com calgary@revay.com atlanta@revay.com
to source appreciated. Your comments and
TORONTO VANCOUVER http://www.revay.com
suggestions for future articles are most wel- 505 Consumers Road, Suite 306 401 - 1755 W. Broadway
come. TORONTO, Ontario M2J 4V8 Vancouver, B.C. V6J 4S5
Tel.: (416) 498-1303 Tel.: (604) 737-2005
Édition française disponible sur demande. Fax: (416) 491-0578 Fax: (604) 737-2008
toronto@revay.com vancouver@revay.com
Please advise the Montreal office of OTTAWA WASHINGTON, D.C.
any change of address. 39 Robertson Road, Suite 230 1370 Piccard Drive, Suite 140
NEPEAN, Ontario K2H 8R2 Rockville, MD 20850
Tel.: (613) 721-6801 Tel.: (240) 632-1710
Fax: (613) 596-8172 Fax: (240) 632-1712
ottawa@revay.com washington@revay.com

You might also like