Weather Date Day Period
0
15 C, Sunny 24-Jan-21 Sunday 151
MAN
No. IN DIRECT MAN HOUR No. EQUIPMENT Qty. Unit Remarks
POWER
1 Project Manager 1 10 1 Big-Small Generator 6 No.
2 QC Manager 1 10 2 Small mixer 2 No.
3 Planning Engineer 1 10 3 Backhoe 1 No.
4 QC Engineer 1 10 4 Telehandler 1 No.
5 QS Engineer 1 10 5 Bobcat 1 No.
6 Construction Manager 1 10 6 Air compressor 2 No.
7 Civil Engineer 1 10
SUB -TOTAL (In- Direct) 7 70
MAN
No. DIRECT MAN HOUR
POWER
1 Supervisor 3 30
2 Foreman 6 60
3 Permit Receiver 2 20 GRAND TOTAL 13
4 Driver 1 10 URGENT CONCERNS

5 Clerk 2 20 1

6 Mechanic 1 10 2

7 Operator 4 40 3
8 Purchaser 1 10 SAFETY STATISTIC
9 Storekeeper 1 10
No. DESCRIPTION Total
10 Safety Officer 2 20
11 Carpenter 20 200 1 Safe Man-hours (MH) 141,964

12 Steelfixer 12 120 2 Total Man-hours (MH) 141,964

13 Mason 31 310 3 Number of S.O. Rs raised (MFQ) 70

14 Scaffolder 7 70 4 Number of S.O. Rs Corrective Action (MFQ) 65

15 Plumber 8 80 5 Work Permits received 163

16 Painter 5 50 6 Number of S.O.Rs (RCL) raised 250

17 Helper 32 320 7 Number of S.O. Rs (RCL) Corrective Action 226

18 Electrician 2 20
19 Nurse 1 10
SUB - TOTAL 141 1410
GRAND TOTAL 148 1,480
No. DESCRIPTION OF ACTIVITIES
1 Dividing wall - Pouring Concrete-373 15 Slope Lining- Pouring Concrete-328,334
2 Dividing wall - Surface Grit Blasting -366,367 16 Slope Lining- Concrete Chipping-265,348,351,340,266
3 Dividing wall - Concrete Chipping-96,97 17 Slope Lining- Concrete Cutting-269
4 Dividing wall - Install Formwork -376,378 18 Slope Lining- Surface Preparation-268,349
5 Dividing wall (Reskinning) - Pouring Concrete-324,326 19 Slope Lining- Install Wiremesh -267,349
Slope Lining- Concrete Curing-
6 Dividing wall (Reskinning) - Concrete Chipping-303,379 20 325,315,312,318,327,320,322,324,331,326,314,333,270,272,
329,335,274,276,330,332
7 Dividing wall (Reskinning) - Concrete Cutting-303 21 Kemya Bridge (P-2) Capping beam - Concrete Curing - 297
8 Dividing wall (Reskinning) -Drill holes in wall-318 22 Horizontal Canal Lining- Dewatering- 297,240,110
9 Dividing wall (Reskinning) - Install Anchoring Rebar -318
10 Dividing wall (Reskinning) - Install Rebar -318
11 Dividing wall (Reskinning) - Install Formwork -324
12 Dividing wall (Reskinning) -Scaffolding Erection -342
13 Dividing wall (Reskinning) -Scaffolding Dismantling -318,324
Dividing wall- Concrete Curing-335,295,337,289,
14 300,302,339,338,349,315,350,304,354,308,363,370,272,275,3
72,371,306,310,374