You are on page 1of 2

Learning legacy

Lessons learned from the London


2012 Games construction project

Using Earned Value/stable baselines with


NEC Contract projects
Earned Value (EV) was chosen by the Olympic Delivery Authority (ODA) Olympic Delivery Authority

to objectively and consistently measure project performance across the


Programme Baseline Report
Summary
November 2007

London 2012 construction programme. Combining scope, schedule and cost


measurement into an integrated system allowed programme-wide progress
to be established efficiently, and gave early warning of potential performance
issues. Early warning allowed rapid deployment of mitigation actions or
amended delivery strategies and this became one of the key enabling factors
for the programme’s ultimate success.
Strategic decisions Project and programme controls
report
ODA mandated the use of EV for framework
monitoring performance on the With the strategy set, the building
London 2012 Olympic and Paralympic blocks of the project/programme
Games programme. The strategy control regime were established in
combined programme-level Q2 2007 and matured through
Performance Management Baseline 2008. During this time:
(PMB) with project-level contract –– a delivery driven Work Breakdown
management to provide a cohesive Structure (WBS) was established;
EV reporting framework. –– a robust change control process
was implemented to control the Programme Baseline report published in
All EV reports use money to compare
baseline; November 2007 (Yellow Book)
the three fields measured:
–– the Original Baseline Budget
–– Budget Cost of Work Scheduled
(OBB) or ‘Yellow Book’, including
(BCWS): Baseline or Planned Value
PMB, was published based on
–– Budget Cost of Work Performed
novated contracts and cost plans
(BCWP): Earned Value
for proposed scopes;
–– Actual Cost of Work Performed
–– the PMB modelled in controls
(ACWP): Actual Cost
systems was precisely reconciled
As many London 2012 programme with the OBB and ODA Finance
stakeholders were unfamiliar with Business Plan;
EV, standard terminology was –– links between management
simplified (as above) to make subsystems for baseline, costs and
reports easier to understand. schedule were established via the
WBS and procurement codes;
The controls methodology – and EV
–– a ‘control culture’ and trust in the
implementation in particular – was
accuracy of reporting were built
also moulded by the use of NEC3 Earned Value graph
up through training, coaching,
contracts. This gives contractors
support and, when appropriate,
the right to amend their ‘Accepted
intervention;
Programme’ each month, negating
–– two forecast datasets were
their use as a stable low-level
created in P6: contractors’ version
baseline. How this was overcome
to capture monthly progress and
is explained below.
logic updates (the NEC3 Accepted
Programme); and PM’s independent –– Deltek Cobra for Cost and EV –– Criteria 8: Maintain PMB at
assessment, including known management. Control Account level
mitigations, which was compared –– Criteria 15: CBB = approved
The OBB was captured in P6 to
to the stable PMB to give current project budgets + contingencies
produce a budget-loaded Level 2
status; and –– Criteria 17: Prohibit multiple
integrated programme. This was then
–– all works contracts stipulated accounting as direct costs are
imported into Cobra which became
Project Controls requirements summarised through the WBS
the repository for the baseline. As
in Works Information schedules –– Criteria 22: Produce monthly
baseline changes were approved
covering systems, data content, file performance measurement data at
within the monthly cycle, they were
format and transmission protocols. Control Account level
implemented by updating P6 and
–– Criteria 28: Incorporate all
re-imported into Cobra to create
Refining performance measurement authorised changes in a timely
the Current Baseline Budget (CBB)
and the link to quantities manner
each period.
Physical progress measurement was
Baselines were modified via change
varied according to the work-type, Progress was updated in P6 each
control to mirror current delivery
complexity and delivery phase of month and imported into Cobra where
strategies. This made performance
each project. Techniques of varying it was applied to the CBB to produce:
highly visible, but did lose the more
accuracy were used, ranging from –– an EV figure: also used for
theoretical forecasting aspects of a
tracking key quantities – such as programme progress calculations
purist EV implementation.
number of piles, tonnes of steel, –– a percent complete
metres of cable – through assigning Contractors’ staff new to EV
Actual costs were imported from
value to milestones, down to Level required much training to ensure
ODA’s ORACLE finance system
of Effort (LOE). implementation gave meaningful
and reconciled to ensure that figures
measurement. This issue later drove
All progress was expressed as were agreed before P6 and Cobra
simplification of the PMB with
percent complete, applied to budget- were locked-down and archived
high-level milestones to trace the
loaded summary activities then for reporting.
critical path and key interfaces, and
aggregated to an EV figure and
Cobra was the programme’s summary budget-loaded activities
percent complete for the project.
‘single source of truth’ for reporting mapped onto contractor and PM
As the team’s fluency with EV Baseline, EV and Actual Costs. The forecast datasets via the WBS.
reporting grew, demand-led services most important of the various reports
like logistics were separated out produced were the monthly CBB
to give a clearer picture of capital Report and the Cost Performance Project
delivery. Capital projects derived EV Report (CPR). Programme Controls
from measured progress and services
exclusively used LOE where EV = Lessons learned Supplier
Planned Value. This suppresses any EV was pivotal in the successful CLM – Delivery Partner
variances from services, allowing programme controls used for London
programme status to be reported 2012. All 32 criteria specified in Authors
consistently but without obscuring ANSI/EIA 748 were applied, the David Birch – Head of Programme
real performance issues. most influential being: Controls, CLM
–– Criteria 1: Define authorised work Gavin McGuire – Head of Cost
Systems integration and resources via WBS Management, CLM
The programme used standard ‘off –– Criteria 3: Ensure management
the shelf’ products: subsystems support each other,
–– Primavera P6 for budget-loaded the WBS and the Organisational
scheduling; Breakdown Structure (OBS)

© 2011 Olympic Delivery Authority. The official Emblems of the London 2012 Games are © London Organising Committee of the Olympic Games and
Paralympic Games Limited (LOCOG) 2007. All rights reserved.

The construction of the venues and infrastructure of the London 2012 Games is funded by the National Lottery through the Olympic Lottery Distributor, the
Department for Culture, Media and Sport, the Mayor of London and the London Development Agency.

For more information visit: london2012.com/learninglegacy Published October 2011


ODA 2010/374

You might also like