PT. JP3 Schedule Major Overhaul Unit #2 PT.

LED
ID % Task Mode Task Name Duration Start Finish February 2020 March 2020
Complete 22 25 28 31 3 6 9 12 15 18 21 24 27 1
1 73% Boiler Cleaning 20 days Sat 2/1/20 Mon 2/24/20

2 100% Preparation for Tools 4 days Fri 1/24/20 Tue 1/28/20

8 100% Economizer 10 days Sat 2/1/20 Wed 2/12/20

9 100% Cleaning Economizer 5 days Sat 2/1/20 Fri 2/7/20

10 100% Collecting Dust & Particle 5 days Tue 2/4/20 Sun 2/9/20

11 52% Air Pre Heater 10 days Sun 2/9/20 Thu 2/20/20

12 38% Cleaning Air Pre Heater 5 days Sun 2/9/20 Fri 2/14/20

13 65% Collecting Dust & Particle 5 days Fri 2/14/20 Wed 2/19/20

14 0% Finishing 4 days Thu 2/20/20 Mon 2/24/20

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Progress Boiler_9 Feb 2
Summary Manual Summary Rollup Progress
Date: Mon 2/10/20
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only