PT. JP3 Schedule Major Overhaul Unit #2 PT.

LED
ID % Task Mode Task Name Duration Start Finish February 2020 March 2020
Complete 22 25 28 31 3 6 9 12 15 18 21 24 27 1
1 77% MAJOR OVERHAUL TURBINE & AUXILIARY 31 days Tue 1/28/20 Thu 3/5/20
UNIT 2
2 77% LED Motor Overhaul Project Batch #1 25.67 days Wed 1/29/20 Fri 2/28/20

3 100% IDF # Gudang 2 days Wed 1/29/20 Fri 1/31/20

17 15% Boiler Feed Pump #2A 6 days Fri 1/31/20 Fri 2/7/20

31 0% Boiler Feed Pump #2B 6 days Fri 1/31/20 Fri 2/7/20

47 87% AC Lube pump #2 3 days Sat 2/22/20 Tue 2/25/20

63 91% DC Lube Pump #2 3 days Tue 2/25/20 Sat 2/29/20

79 91% HP Lube Pump #2 3 days Tue 3/17/20 Fri 3/20/20

95 91% Coal Mill #2A 5 days Fri 2/28/20 Thu 3/5/20

111 91% Coal Mill #2B 5 days Mon 3/2/20 Sun 3/8/20

127 91% Coal Mill #2C 5 days Fri 3/6/20 Thu 3/12/20

143 91% Seal Airfan #2A 3 days Tue 3/10/20 Fri 3/13/20

159 87% Seal Airfan #2B 3 days Tue 3/10/20 Fri 3/13/20

175 99% FDF #2A 3 days Fri 2/7/20 Tue 2/11/20

191 99% FDF #2B 3 days Tue 2/11/20 Fri 2/14/20

207 89% PAF #2A 3 days Fri 2/14/20 Tue 2/18/20

223 91% PAF #2B 3 days Tue 2/18/20 Fri 2/21/20

239 93% IDF #2A 4 days Fri 2/7/20 Wed 2/12/20

255 0% IDF #2B 3 days Fri 3/13/20 Tue 3/17/20

Task Project Summary Manual Task Start-only Deadline

Project: 01 31 Major Overhaul M Split Inactive Task Duration-only Finish-only Progress


Date: Mon 2/10/20 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone