17-June-2020

Contract Agreement for Electrical installations

This agreement is made by and between SGI Limited and Contractors Mr. Muhammad Zulifqar having
CNIC

1. This contract has been finalized in PKR 700,000/- by SGI and Contractors. Whereby SGI shall pay in
installments in cash or in Cheque fortnightly or monthly as required by the contractors.
2. The contractors shall do all installations in 1 - 1.5 months as agreed upon by SGI.
3. The SGI shall provide all the electrical materials i.e. cables, circuit breakers, conduits and PVC pipes,
switches etc. as required by the contractors.
4. The contractors shall be responsible for electrical installations i.e. form Transformer to the lower end
machines and shall be responsible for the corresponding electrical panels running in good conditions and
shall rectify any discrepancy encountered thereafter.
5. The following machines are included in this contract agreement
o Tubular Stranding machines X 2
o Extruders X 2
o Laying machine X 1
o Fork stranding machine X 1
o Rigid Stranding machine X 1
o Bull block machine X 1
o Rod breaker machine` X 1
6. The contractors shall provide all the necessary drawing copies for the corresponding machines electrical