You are on page 1of 10

Metro de Panamá

Línea 2

By: Josué Ardito


GENERAL OVERVIEW
- Line 2 of the panama metro is
part of the rail transport
system that is scheduled to
end in 3035.

- Line 2 benefits the eastern


sector of the province, which
runs from San Miguelito
(connected with Line 1), to
the Tocumen airport, in its
second stage.
General Overview
- Design
- 21 kms + 2 kms (2nd stage)
- 16 stations + 2 (2nd stage)
- Capacity
- Initial capacity of 16 thousand people per hour per
direction and capacity to expand to 40 thousand.
INITIATION
PROJECT BENEFITS MAP
SCOPE
Design engineering service, construction of civil works, auxiliary
line and station facilities, supply and installation of the integral
railway system that includes rolling stock and commissioning.

OBJETIVES
Line 2 of the Panama Metro, seeks to meet a demand for transport
that accesses in three (3) directions, 22 thousand people per hour in
the North direction, 16 thousand people in the East direction and 11
thousand people in the West direction, all in both directions.

This construction of mass transportation infrastructure in these


districts is integrated into the urban fabric, transforming urban
developments, allowing the densification of the sector and
containing urban growth, thus strengthening the nodes for the
generation of jobs and services established in the Urban
Development Plan for the Metropolitan Areas of the Pacific and
Atlantic.
DELIVERY MODEL

- The project was awarded as a turnkey contract. That is, the


main contractor would be in charge of providing the financing
it.
- The contract between the Panama Metro and the Line 2
Consortium establishes a payment schedule that will run
until 2022.
- The offer of US $ 1,857 million for the works. For the financing
they would charge US $ 205 million.
- The structure originally proposed, which was endorsed by the
Ministry of Economy and Finance, included the participation
of four banks.
Delivery capability and alignment
KEY FACTOR COMPLEXITY PROFILE

HIGH
1. Strategic importance
HIGH
2. Stakeholders/ influencers
MEDIUM
3. Requirements and benefit articulation
MEDIUM
4. Stability of overall context
HIGH
5. Financial impact and value for money
HIGH
6. Execution complexity (including technology)
HIGH
7. Interfaces/ relationships
HIGH
8. Range of disciplines and skills
LOW
9. Dependencies
MEDIUM
10. Extent of change
MEDIUM
11. Organisational capability: performance to date
HIGH
12. Interconnectedness
ANALYSIS

- key on hand.
Recommended for large projects, however, it is not
recommended for small or medium projects.
Facilitates the project for the client, where the main
contractor is responsible for the design and
construction of the project.
Because the risk is mostly passed on to the
contractor, this can raise the cost of the same, due
to the degree of uncertainty, depending on the
information and the clear and concise scope.
Everything we have seen in the different
approaches and models, give us the basis to
achieve a successful project. It is important from
the beginning of a project to use an adequate
model, taking into account each of its involved
parts.
REFERENCES

- https://www.eleconomista.es/
FCC consigue la financiación para la línea 2 del metro de Panamá
Javier Mesones 17/02/2017

- https://www.estrategiaynegocios.net/
Panamá: Redefinen financiación de línea 2 del Metro tras Odebrecht
publicación: 2017-01-16

- https://www.elmetrodepanama.com/linea-2

- https://www.elmetrodepanama.com/contrato-linea-2-del-metro-de-
panama/

You might also like