You are on page 1of 4

No Manpower Qty Remarks

1 Site Manager 1
2 Engineer 1
3 Qc 1
4 Qs 1
5 Supervisor 1
6 Drafter 1
7 HSE 1
8 Logistic
9 Warehouse 1
10 Operator 1
11 Surveyor 1
12 Mechanic 1
13 Scaffolder 2
14 Driver 1
15 Electric 1
16 Worker 24
Total 39
NO MANPOWER QTY REMARKS
1 Staff 15
2 Worker 24
Total Today 39

NO EQUIPMENT QTY REMARKS


1 Excavator 2
2 Dump Truck 1
3 Crane -
4 Compactor 1
Start Target Finish Duration Manpower
No Area Work Description
Actual Actual (Days) Actual

1 Cable Trench Civil and Structural Works 28-Jul-20 15-Dec-20 139 5


Piperack west side
2 Civil and Structural Works 3-Aug-20 21-Dec-20 140 4
CT existing

Demin Plant Area


(MCC Room, Water
3 Treatment Plant, Civil and Structural Works 11-Aug-20 25-Jan-21 165 35
Acid and Alkali
zone, Iron Tank,
Pump foundation)
4 20 KV Building Civil and Structural Works 19-Aug-20 8-Dec-20 111 20
5 Generator Room Civil and Structural Works 30-Aug-20 29-Nov-20 90 0
6 Wall Of MCC Civil and Structural Works 10-Nov-20 24-Jan-21 75 4
Room MPH
7 Dry Coal Shed Civil and Structural Works 23-Nov-20 2-May-21 161 12
Progress
Remaining Works
Plan Actual
100.00% 78.91% 21.09%
85.43% 52.97% 47.03%

78.95% 22.67% 77.33%

73.95% 67.83% 32.17%


25.46% 25.51% 74.49%
2.92% 2.92% 97.08%
81.13% 37.02% 63%