WORK EXPERIENCED
AUG,. 08,2016 TO AUG. 08, 2017 PIPING SUPERVISOR
PROJECT; JRTP
SEJONG
JIZAN SAUDI ARABIA
- Line checking of every test package and request all erection materials balance.
- Request for inspection for fit-up,,air blowing and Oriface flange.
- Supervision of piping installatrion of above ground piping
- Plan and schedule 3 weeks ahead all tools,materials and equipment needed.
- Supervision of 4 piping foreman
- Request all pipe spool and valve.

AUG 15, 2014 to SEPT.19, 2015 PROJECT PIPING ENGINEER


PROJECT; HICAP PROCESS PIPING EXTENSION 2
WEL CONTRACTING CORPORATION
TECHNOPARK, BINAN LAGUNA, PHILIPPINES
- Supervision of piping installation for process cooling water line, compress air line , chilled
water supply and return, cooling water line supply and return and compress dry air line.
- Submittal approval all mat’ls. needed for piping installation.
- Attend construction coordination meeting for status report and concern of all mepfs and
other field including architectural, structural and civil.
- Submitt shop drawing for rerouting of piping installation w/c.does not suit for actual
installation
- Request all materials and equipment needed 3 weeks ahead to avoid delayed and to update
construction schedule
- Ensure that the latest drawing are in latest revision and approval for fabrication
and construction.
- Make construction schedule for catch up of delay of work including manpower,and
materials loading
- Coordinate to purchaser for all materials requested and all materials approved by the client
- Responsible for shop drawing

NOV. 16, 2013 TO MAY 16,2014 PIPING SUPERVISOR


PROJECT; RMP-2 PROJECT PETRON BATAAN
DAELIM
LIMAY BATAAN
- Conduct checking of all pipe spool delivery at site
- Do punch list of all test package and give to piping supervisor to prioritized each package
- Supervision subcontractor of piping execution in all discipline
- Advised for the most priority line and directly inform all piping discipline.
- Make construction punch list of every test package.
- Verify and check NDT requirement of test package prior to hydrotesting
- Advised piping discipline to add manpower of each area to meet the target schedule.
- Interfaced with engineering and other department to discuss plans or any clarification
for the installation process.
- Monitor all piping works on fabrication shop and fields.
- Conduct regular walkdown, reviewing of the work activities, identifying areas of concern
and any safety hazard require special and attention.
- Assisting construction supervisor in site activities, pipe erection , fit up ,welding and
support installation.
NOV. 20, 2012 TO SEPT.20, 2013 PIPING SUPERVISOR
PROJECT; RMP-2 PROJECT PETRON BATAAN
SUNGDO
LIMAY BATAAN
- Coordinate to engineering department to as built drawing for re-routing of pipe
which does not suit in actual site condition.
- Line checking of every test package and request all erection materials balance.
- Inform and fallow up to piping superintendent of all requested materials
- Request for inspection for fit-up,,air blowing and Oriface flange.
- Supervision of piping installatrion of above ground piping
- Plan and schedule 3 weeks ahead all tools,materials and equipment needed.
- Supervision of 4 piping foreman

Oct. 10, 2011 – Oct. 10, 2012 PIPING ENGINEER


PROJECT; HADEED STEEL MAKING
AL RUSHAID CONSTRUCTION COMPANY
JUBAIL SAUDI ARABIA
- Job role as piping engineer
- Supervised and assist superintendent of piping installation and erection.
- Monitor re-routing of pipe which does not suit actual site condition
and to be coordinate to the client
- Request all erection materials at site.
- As built drawing and coordinate for client for approval.
- Ensure that the latest drawing are in latest revision and approval for fabrication
and construction.
- Report to the piping superintendent to any technical problem.
- Punchclearing of qcbackpunch for material balance and other problem.
- First contact of in site construction issue ,proper interpretation of piping class
analysis,GA,ISO,P& ID.
- Survey qty of materials and equipment needed in the project.
- Monitor all materials; incoming and outgoing materials from and to other section.
- Prepare inspection request and assist inspector when needed
- Received construction drawing prior to fabricate and ensure that the drawing ,specification,
procedure are in correct revision.
- Initiates inspection and make inspection request and conduct regular technical assessment
and site monitoring and see to it that the work are in accordance with schedule, plans and
quality objective of the project.
- View smart plant review for clarification

March 08, 2010 – July 11, 2011 PROJECT SITE ENGINEER


PROJECT; AUTOMATIC FIRE SUPPRESION
SYSTEM OF NESLE PHILIPPINES MEYCAUAN
BULACAN
ABTELCOM ENTERPRISES
MEYCAUAN BULACAN

- Request all materials and equipment needed 3 weeks ahead to avoid delayed and to
update construction schedule.
- Ensure that all manpower needed within the right quantity as per project schedule.
- Check and review specification of the project.
- Direct supervision of all manpower at the project.
Apr. 03, 2008 –MAY. 10, 2009 PROJECT SITE ENGINEER
PROJECT; MECHANICAL INSTALLATION OF
FIRST PHILEC , PHIL.
Mecel, Construction & Electrical Inc.
Mayondon, Los banos, Laguna (049)536-6158

- Request all materials and equipment needed 3 weeks ahead to avoid delayed and to update
construction schedule
- Ensure that the latest drawing are in latest revision and approval for fabrication
and construction.
- Report to the project manager to any technical problem.

Jul. 2007 – Dec. 2007 SERVICE ENGINEER


Advance Newtech
Sta. Rosa Laguna

- Water analysis of h2o contaminant of chilled water, cooling tower and boiler.
- Supervised Chemical treatment and Mechanical cleaning of cooling tower and
water line.

May 2005 - May 2007 HVAC MAINTENANCE STAFF


RAYCOR AIR CONTROL SYSTEM
MANDALUYONG, QUEZON CITY

- Control temperature,humidity, airflow and air filtering.


- Manually adjust control valves of all piping system of hvac for normal operation.
- Maintain and check all air handling units in the bulding.
- Check and maintain cooling tower.

May 2000 to June 2001 BOILER OPERATOR


TAPEX INCORPORATION
BO. MADUYA CARMONA CAVITE

- Operate 3 ton and 5 ton boiler


- Weekly schedule for Backwashing of water softener and demineralizer.
- Maintainance for transfer pump.
- Routine check for bunker oil of the tank.
- Operate atlas copco air compressor.

EDUCATIONAL BACKGROUND:

College COLEGIO DE SAN JUAN DE LETRAN


Calamba City
Bachelor of Science in Mechanical Engineer
1998

PERSONAL:

Born on the 17tn day of June 1975 at Calamba City, single, male, stands 5’7”
135 lbs.

SKILLS:
- Computer literate ( MS Word, Excel , Auto Cad 2000,2d and 3d)
- Good drafting skills and technical manual and cad.
- Interpersonal ,communicate, people management and leader ship skills.
- Knowledge of materials selection substitution in conformity of piping installation.

CHARACTER REFERENCES:

Available upon request.


SEMINAR ATTENDED:

Industrial A/C Motor Control


Meralco Foundation Institute
Pasig, Metro Manila
May 02, 2000 – May 13, 2000

You might also like