Professional Documents
Culture Documents
Project Management Notes
Project Management Notes
Change in the order of the day. In a business set up, for growth or sometimes even for survival or
for the continued running operations, some changes take place. The organization needs to install
equipment, or replace an old machine, or setup a factory, or construct an office building. These
are all instances of projects undertaken by the organization. Every organization big or small, in
service or in manufacturing sector, at some point of the time undertakes some project or the
other. A school organizing its Annual Day, in simple terms, is undertaking a project; or
organizing a seminar by Management Department is also an instance of a project.
According to Project Management Institute (PMI), project can be defined as a one shot, time
limited, goal directed, major undertaking, requiring the commitment of varied skills and
resources. It is also defined as a combination of human and non- human resources pooled
together in a temporary organization to achieve a specific purpose.
On the basis this definition, a project, starts with the achievement of some objective, has a start
and end date, and requires various kind of resources like men, material, machine and money. It is
of temporary nature as with completion of project, the organization also integrates.Organizing
conference by a management department is an instance of project. It begins with the objective of
knowledge sharing and dissemination, has defined dates (eg. 3 rd to 5th of February, 2008), the
various paper presenters are the constituents of the project, the paper presenters and the
organizing secretary and its team members involved in organizing the conference are resources
of the project, the technical sessions are inter-related, and the inauguration and valedictory
sessions mark the start and the end of the project. It is temporary in nature as with end of the
conference all members go back to respective department and carry on with usual work.
For launch of Nano, GirishWagh, the Vice President of Tata Motors was the Project Director.
According to Harold Karzner, Project have specific objectives, have definite start and end, have
funding limits, and consume resources.
Project starts with a generation of idea, has definite objective, and completes when the objectives
are fulfilled. It starts with a definite mission, generates activities involving a variety of human
and non-human resources all directed towards the fulfilment of the mission and stops once the
mission is fulfilled. The purpose and the set of objectives which can achieve that purpose
distinguish one project from other.
A project should be technically feasible, commercially viable, politically suitable and socially
acceptable. The technology required to execute the project should be available in the country, or
one should be able to import it. This is technically feasibility. Further it should not be too costly
for the project party to install – this defines economic feasibility. Project should also be
politically suitable. The Sagarwala Project (development of ports) or the recent Swatch Bharat
Abhivigyan project (initiated by the Modigovt) was initiated by one government. After change in
political power, the present government may or may not be support it; if it does not support, it is
found to be politically unsuitable. Another instance is of project politically suitable is the
Singur(WB) project which faced much resistance and had to be shifted to Sanand in
Gujarat.Projects should be commercially viable. Example is of Concorde Project wherein two
governments France and Britain pooled in resources to create the Concorde. It was technically
feasible but commercially not viable. Project should also be socially acceptable. When a factory
is set up in rural area, fumes and smoke emanates to create pollution. Further there would also be
noise and sound pollution. This is negative social impact of the project. Some benefits also
accrue on setting up on the factory; they could be employment generation of unemployed rural
poor or connectivity of the rural area with nearby town. This is the positive social impact.
Therefore project should also be is socially acceptable.
Further, project should be undertaken with care. Project decisions are of great importance
because of three major reasons:
Long Term Effect: Consequences of projectdecisions (good or bad) extend far in the
future. Automating a bank would accrue benefits to the organization for a considerable
period of time. Therefore careful thought and analysis have to be undertaken before
committing resources.
Irreversibility: These decisions are irreversible decisions. If a bank has automated its
operations, and for some reason the computer mal functions or the speed of processing is
not as fast as desired, then it would be too costly to do away with the project.Nano plant
at Singur, is a decision which was not sustainable; as a result Tata Motors made huge
losses because 80% of construction of plant was complete and they had to abandon the
work. Project decisions are irreversible decisions and therefore they should be taken with
care.
Substantial Outlay: Projects generally involve huge sums of money. Therefore such
decisions require an in-depth analysis before selection and final commitment of funds.
(A) They may be grouped into two broad categories as national and international projects.
National projects refer to the projects undertaken by the government like the Golden
Quadrilateral. These projects may be industrial or agricultural in nature (that is agro-
based projects). International projects are those that are undertaken by international
bodies like the UNO.
(B) Depending upon the size, project may also be classified as-mega, major, medium and
mini project.
Mega: more or equal to $ 1 billion, more than three years time span, has economic, social and
ecological implications, defence and space projects are examples of such projects.
Major: more or equal to $ 100 million, more than two years time span, many contractors and
consultants involved, airport construction is an example.
Medium: more or equal to $10 million, spans a period of 1-3 years time, industrial or public
work (road construction) are examples of such projects.
Mini: less than $ 10 million, less than 1 year, example are housing or building projects.
Brownfield Projects: In such projects work is following a prior work This refers to an
expansion or any change being brought about in an existing project. Therefore it involves
demolishing, renovation, upgradation or modernisation of something already existing. It may
be shifting of the existing plant from one place to another. Godrej plans to foray into food
retailing. It may do so through the acquisition route. This is an instance of Brownfield project
as it would acquire an existing set up. Brownfield projects in software development, means to
start a project based on prior work or to re-build (re-engineer) a product from an existing one.
(D) Depending upon the nature of work executed, they may also be classified as replacement
and modernization, integration, diversification or divestment projects.
Modernization-Sails modernization plan
Integration-Vertically integrated projects. Forward integration is a move towards the
market or customer. From oil exploration, to oil refining to distribution is an instance of
forward integration.
Backward integration is a move towards the source of supply- From food retail to
manufacturingis an instance of backward integration.
Diversification- A move into dis-related area of business. For example ITC moved from
manufacturing of cigarettes, to paper to hotel is an instance of diversification.
Divestment projects-where we scale down the business or totally close the business.
(E) According to its speed of impletion, projects may be classified as normal, crash on
disaster projects:
Normal Projects: In these projects, everything goes as desired. That is the project is
completed on time and also with the laid budget. This means that adequate time is provided
for completion of the project and all phase are completed on time. Generally there is no
increase in cost or spillage in time; also the quality is as desired.
Crash projects: In such cases, the focus is to be complete the project in lesser time span than
budgeted. Therefore maximum overlap of phase takes place. There is often an increase in
cost as well as a compromise in quality of project. Example-when you want to lauch a new
product and you come to know that your competitor is also prepared to launch a similar
product, you try to “crash” the time inorder to deliver earlier in the market (before your
competitor.
Disaster Projects: Disaster projects are those where the environmental factors interfere in
smooth completion of projects and nothing much can be done to save the project from
abandonment. Therefore there is only one option-save the project in any way else abandon
the project. Therefore anything needed to gain time is allowed. It is said that any vendor who
can supply yesterday is selected irrespective of cost. There is often a compromise on quality.
Any quality is accepted to gain time and avoid failure. Work is undertaken round the clock.
Therefore, capital cost increases and time is hereby reduced. The Gujarat earthquake or
Orissa flood of late 90’sand early 2000 which disrupted the normal continuity of all projects
in these areas, are instances of crash projects.
Refer to the chart below. It depicts the impact of these projects on cost, time and quality of
the project.
Normal
Crash
or
Disaster
A project does not exist in isolation. It is a part or off-shoot of a family which is called
project family tree. A project originates from a higher level activity called a plan. Therefore,
it starts from a plan-a corporate plan for an organization or a national level plan of the
government. The following diagram depicts the project family tree.
PLAN
PROGRAMME
PROJECT
WORK PAKAGE
TASK
ACTIVITY
Plan: This refers to national plan undertaken by the government or a corporate plan undertaken
by a business house. The objectives are broad and not well defined. The objectives are kept
broad to enable a company to move in any direction or tap on any existing business opportunity.
For instance, the government lays down a national plan of upliftment of society. The objective is
kept very broad. A plan answers what of actions.
Programme: This further refines plan laid above. This answers how of actions. At this stage, the
objective defined is refined in terms of how to achieve them. Upliftment of society can be
brought about by a health programme, education programme, science and technology
programme, poverty eradication programme, to name a few. This is different from project as the
scope or boundary is not specified yet and time is also not defined.
Project: A project has well defined objectives. It has a defined start and end date. For instance,
education programme could be achieved either through adult literacy programme or through free
education for every child programme. Similarly, health programme could be through a water and
sanitation scheme or through immunization scheme or free eye operation. These are all instances
of project. Each project has to be converted with in a time frame.
Work Package: This stage decide upon resources (man power and material resources). For
instance an immunization scheme involves identification of material (medicines), equipment
(surgical or others), and manpower (doctors, technicians and nurses) resources too. A work
package is not a project; several work packages make up a project.
Task: This stage defines the responsibility centres; that is, who will do what. Who will hire the
men, purchase (or take on lease) the equipments, who will secure permission from the
government (or local authority where the camp would be set up for free eye operation or
immunization) to name a few.
Activity: This refers to actual implementation of the project. This lays down the activities to be
undertaken and the actual sequence of actions in which they are to be undertaken. For example,
foundation of dispensary, setting up of camps for the free eye operation is the sequence of action
for eye-operation camp.
Another Example: Project Family Tree for “Nano”.
Plan: A plan could be growth or an increase in market share.For a corporate house, project
family tree could be depicted thus.
Programme: This is converted into a programme where they target the bottom of the pyramid
through a new product launch or by entering new geographical territories.
Activity: This refers to setting up the plant at Singur for production of Nano cars.
*Saving Land Degradation (and preserving natural resources): Solid Waste Management
That is identify the area where WOW is to be implemented, identify people who would cover
each area, they would distribute bags, they would collect the segregated wastes, where would
they deposit the wastes, and so on.
1. Objectives: Each project has a fixed objective. It starts from the definition of objectives.
It is define in concrete terms. Once the objective has been achieved, the project stops
existing. Projects are expressed in terms of cost, time and quality (TCQ) parameters. For
constructing an office building, the budgeted cost and time involved is laid down and the
objectives are achieved once the building is set up. For instance, for a flyover the
objective is to reduce traffic congestion by distributing traffic and reducing commuting
time. For organizing a conference, knowledge sharing is the basic objective.
2. Uniqueness: Each project is unique in itself that is each project is different from other. No
two projects are similar. They are different in terms of cost, time and performance
criteria. Even if the cost, time and quality standards are the same, they would be different
in terms of location, people involved, agency or contractors involved, infrastructure,
people or skill required.
3. Single Entity: Every project is a single entity under one responsibility centre. The costs
and profits of each responsibility center are determined separately. Therefore an
organization can undertake many projects at the same time and the costs and profits for
each are arrived separately. A Management Department can have many projects like
starting a new course, organizing a conference, or creating a new building. These are all
separate projects and single entity in themselves.
4. Team Work: Every project needs team work for its successful implementation. It requires
contribution from various departments or disciplines. For instance, referring to the same
example of construction of an office building, people from finance department would be
required to make an estimate of financial requirement, for civil engineering department
for making the design and an accountant would be needed for book-keeping and a
metallurgical engineer would provide an estimate of the metal frame and beam
requirement, an electrical engineer would provide estimate of the cable layout. Therefore
only through effective team work can a project become achievable.
5. Life Cycle: All human beings have a life cycle. They come to being (birth), pass through
adolescence, adulthood, grow old and die. Products also have life cycle. They go through
the stages of introduction, growth, maturity and decline. Project start through
conceptualization, planning and organizing, implementation and termination.
6. Life Span: Projects exist for the period of time. Projects have a start and end date be it 3
months or 7 years. It cannot continue endlessly. It generally starts with setting of
objectives and ends once the objectives have been achieved. For CII holding a conference
is may be of three days while a construction of road network may run over years.
7. Successive Principle: At the beginning of project life cycle, one cannot predict the entire
project processes. Nor can one predict the end. At the very beginning of the project, the
impediment, the hurdles or constraints one will face once the project starts cannot be
visualized. One cannot predict how a project would progress. As and when the project
progresses, things get clearer. For instance, once constructional activity has started, prices
of cement may shoot up. The organization may decide to halt production for a period of
time. If you halt production, what do you do about equipment which you have hired for a
week, ordered for material which is to arrive in a day, and how do handle labour which is
reporting daily. If the work is halted what would be done with the equipment (crane for
instance) which has been hired for a period of one month. How would labour be handled
when no production is taking place are all issues which would arise would need to be
looked into. Therefore as the project progresses details get clearer gradually. This is
called tip-of-ice-berg syndrome. (That is only a fraction -1/8 of it is above the surface-
that is 90% approx under water, and only when one gets closer and on impact, does one
get to know the magnanimity of the ice-berg).
8. Risk of Uncertainty: Every project has an element of uncertainty associated with it. The
more ill defined (unplanned) the projects are, the greater would be the element of
uncertainty involved. Risks are of three kinds-schedule risk, cost risk and also
performance risk. Cost risk result in cost overrun and one uses Work Breakdown
Structure to manage this risk. Schedule risk refers to risk of time overruns taking place
and PERT, CPM, and Gantt Charts and also more recently Monte Carlo techniques are
used to mange this risk. Managing performance risk is most difficult; because methods
used to manage cost and schedule risk remains the same across all industry but they vary
in case of performance risk. Quantifying relationship between different aspects of
performance can be difficult. Therefore to reduce the element of uncertainty, project
should be undertaken after detailed study and analysis.
9. Made-to-Order: Projects are made to order. Each customer defines his requirements.
They are made as per requirements of the customers. The customers also put constrains
with in which projects must be executed. Constraints are in the form of cost and time. For
constructing an office building, how many rooms would be required or how many store
would be required is determined by the users.
10. Sub-contracting: A large percentage of work is done through contractors. The more the
complexities involved in the project, the more the need for sub contracting. Also if the
organization lacks expertise, much of the work would be given to sub contractors.
11. Unity in Diversity: Projects use a mix of many diverse elements –a variety of skills,
people, technology, equipment, machine, and material. All of these are integrated to
achieve the objective of the project.
12. Scope Changes: Many changes occur when the project starts. This is called scope creep.
For instance, a project was to construct a bridge across a river. Once construction activity
has started, one may decide to make it a two way bridge. Further, it was decided to create
pedestrian paths on each side. Further, it was decided to look into electrification and
beatification of the bridge. These are instances of scope creep. This often leads to new
products, new product features in the product; and often emerges when projects are not
completely defined and described in detail; and often not backed by systematic study.
Often therefore it leads to change in overall objective, and often to project overruns.
These refer to intentional changes introduce into a project as the project progresses. This
is different from successive principle, where one had not visualized the changes that
would have come once you moved into implementation face. This is a result of
environmental factors.
13. Long Term decisions: Projects involve long term decision consequences of such
decisions (good or bad) extend far into the future.Automating a bank accrue benefits to
the organization for a considerable period of time.
14. Capital Outlay: Projects generally involve huge sums of money. Therefore such
decisions require an in-depth analysis before selection and final commitment.
15. Irreversibility: Project decisions are irreversible decisions. Every project involves huge
sums of money. Therefore cost of reversing these decisions would be very high.
Therefore careful thought and analysis have to be undertaken before committing
resources.
Human beings have a life cycle. They come to being by birth, pass through the stages of infancy,
adolescence, adulthood and old age and death. Similarly products also have a life cycle starting
with introduction, growth, maturity and decline. Products also have a life cycle. There is no
consensus among the industry as to what constitute project phases or shape of life cycle. Some
define it in term of four, some five; yet some define it in terms of seven phases. This is because
of diverse nature of industry and projects in which they operate.
ENGINEERING
Start-up MANUFACTURING
Definition Formation
Main Build up
Engineering Production
Phase Out
Final Audit
COMPUTER
PROGRAMMING
Conceptual
CONSTRUCTION
Planning
Planning, Data Gathering & Procedure
Definition & Design
Studies & Basic Engineering
Implementation
Major Review
Conversion
Detailed Engineering
Construction
Most often five phases are used (Refer
chart below). These are conceptualization Testing & Commissioning
phase, definition, planning and
organizing phase, implementation and clean-up phase.
Peak effort
level
Level of effort
Conception* Selection
definition
Pl, Sch, monitor & Control Evaluation &
phase* Termination
Level of Effort
Is in terms of person or hours or resources expended per unit of
time
Conception Phase:In this phase, the project idea is conceived. It could be conceived by anybody
in the organization- the CEO, an R & D person, or any person in the origination. At this stage a
preliminary evaluation of the idea takes place, in terms of time, cost and performance criteria. In
other words, it is put into black and white, and compared with other competitive project ideas to
test its feasibility or relevance. The idea is examined in the light of objectives and constraints and
what finally becomes acceptable may form the project. For instance, a cement plant’s capacity
may be underutilized or may be consuming more power. This is the problem and solution could
be deploying new technology. Therefore often search for solution of an existing problem
germinates into a project.
Definition Phase: This is basically a refinement of the earlier phase. This develops on the idea
generated during the conception phase. This provides a detail of resources needed along establish
time, cost and performance criteria in realistic terms. For a situation which involves competitive
bidding, the conceptualization phase considers decision between whether to bid or not to bid
(while definition phase develops the complete bid package). This phase clears the ambiguities
and uncertainties associated with conception phase as it produces a document describing the
project in sufficient detail. On the basis of documentation, does a financial institution grant credit
for the project idea. Generally, industry practices make DPR (Detailed Project Report) in such a
way that it readily gets a go signal. Banks lay down strict appraisal procedure for clearance of
projects and on the basis of DPR do projects get cleared.
Planning and Organization Phase: This involves updating of detailed plans conceived and
defined in the earlier phases. This further involves identifying and organizing resources like
material, equipment, labour, etc. This involves organizing and planning for man power,
scheduling of budgets, securing license and government clearance, arranging for finances,
creation of project team and selection of project manager. This phase involves activities for
project to take off smoothly. Therefore at this stage all paper work is over. There is no more
paper work or thinking but organizing or arranging for the needed items.
Implementation Phase: This is a phase which involves hectic activity. The project visibility takes
shape here as some field work start in this phase.If the project involves a new product, then this
phase refers to the product introduction phase. For capital equipment project, it involves its
receipt, placing order for raw material, equipment and machine erection, civil construction,
electrical piping work etc, and trial run and commissioning of the plant in itself. It is observed
that maximum work is done during this phase (Approximately 85% of the work is done here in
this phase). Also this phase involves maximum time. Therefore project managers are keen to
start this phase fast and they often put in efforts to complete it in minimum time span. Therefore
efforts are made to fast track the project by overlapping as many sub-phases are possible. Often
engineering, ordering, receipt, construction, commissioning are the sub-phases that are
overlapped. The amount of fast tracking depends upon who is doing the project. If the design and
construction is by different subcontractors, then the scope of fast tracking would get limited. Else
if design, supply and construction all are as a package with one sub-contractor, fast tracking
would be to the maximum extent possible.
Clean-up Phase: This refers to transition phase during which plant commissioned is handed over
to a different agency (customer) for production. In case of turkey projects, the project is set up by
an agency and handed over for commissioning and operation to the customer. Eg Steel Plant set
up and handed over for production. Eg in a University, the construction of residential
accommodation is undertaken by some builder and on completion is handed over to University
Property (Estate) Department for allotment.
In this stage, the payments are made, dues are cleared and accounts are closed. All the people
associated with the project leave the project organization. They move back to the respective
departments to which they belonged and in most cases, they go in the very way that they had
joined. The design engineers are the first to leave followed by others. However, plan for clean-up
phase must start much before the actual clean up takes place. This is the stage for feedback
where the lessons learnt are noted; like what impact the project had on the image of the
company, technical advancements in the area and the problems faced, if any. These act as
feedback for future projects.
1.6 Project Life Cycle Curve-An Analysis: Most projects go through similar stages from origin
to completion. This is depicted by PLC. Project is born, project team created, project manager
selected, resources assembled, work programme organized, works get underway and momentum
builds up. Project progress is made. The project completion or final stage is time consuming
because number of parts must come together takes time. Therefore it represents slow-rapid-slow
progress. Peak rises and tapers off as projects near completion. This is shown by the S Curve
(Progress curve). It is also called effort curve.
The following table represents the relationship of different stages with cost time and
performance.
Cost (C) Schedule (T) Performance (Q/P)
Formation 1 1 1
Build-up 3 1 2
Main 3 1 1
Phase Out 3 1 1
At beginning of project, “p” took precedence over “c ”& “t” during life of project; Cost
important during peak “t” important during “end” as client wants delivery.
Recent review- “t” & ”p” more important than “c” all along
100%
Slow finish
% Project
Completion
Slow Start
Time
In S Curve, percentage of project completion is closely co-related with cost or use of resources.
Inverse-S
Fast growth Slow down in middle
New technology project have multiple parts, each independent part results in different
incremental benefits.
A company will install that part first which will result in “big bang” for bucks that is which gives
maximum benefits first. Therefore great progress first, slightly less next, and continually
dwindling off as remaining parts installed. This results in “inverse s” curve.
100%
% Project
Completion
J-Curve
J Curve:
Project
Completion
Time
Fig “a”
Project
Cost
Time
t0 t1 t2
Fig “b”
Much
Uncertainty
Task Routine
Little
Concept Def(n) Plann. Execution
Termination
n
Uncertainty
The DPR also mentions the methods of financing proposed. It further also specifies the
equipmentsneeded, the cost of equipment, duties, taxes and excise on them, raw material,
manpower requirements, and their associated costs. Cost benefit analysis is also undertaken
(Payback period method, NPV etc). It also mentions whether clearance has been procured from
local authorities, land is available, forest control clearance obtained, clearance from pollution
control board obtained or not. It also analyses the technological parameters, description of
technology to be used, broad technical specification, evaluation of existing resources, etc. This is
a very important document as appraisal is based on it and banks also grant loans/ financing based
on details of mentioned in the DPR.
It contains the following details in the manner described below: The first page is the title page.
This contains the name of the project, its affiliation and the date. Then it is followed by these:
Abbreviations
Executive summary
Technical Analysis
Financial Analysis
Recommendation
--------------------------------------------
For organisations where projects are a recurring feature, the entire project team goes to the next
project. The team remains intact and therefore termination is not stressful. For construction
companies, the entire team takes up a new construction once one project is complete. GMR, for
instance, constructed the Indira Gandhi International Airport (IGIA) in the year 2006 and once
complete they undertook construction of Hyderabad International Airport in 2008. But for
organisations where projects are a non-recurring feature, the entire project team disintegrates and
does not necessarily go to the next project. Members do not know when the next project would
be undertaken and whether they would be part of the new project or not. The team disintegrates
and therefore termination is very stressful. It is akin to a family break-up. It is the skill pf a
project manager as to how he manages the termination- makes it less stressful, terminates with
minimum trouble and administrative dislocation.
A project is said to be terminated when the substance of the project has ceased to exist, when it is
so slow that almost no progress is made, is much delayed, resources get allocated elsewhere and
also project manager and CEO do not see eye to eye.
There are four ways in which projects are terminated. They are
Case-1: Projects are stopped because the objective of the project was achieved. For instance,
a new product was launched or new software was installed and is running successfully.
Case-2: Projects are stopped because the project was unsuccessful. For instance a drug test
failed; it was superseded because a new and cheaper alternative became available or because
it was too costly or took too long.
In case of termination by extinction, all activity on substance of project ceases to exist. But
much organisation activity needs to be done like release of team member and re-assignment
to other activities. Also property, material and equipment belonging to the project need to be
disbursed according to project contract or in accordance to established procedures of parent
organisation. Finally, the Project Final Report (PFR) needs to be prepared.
(b) Termination by Addition: Such projects are managed in-house. Such projects are carried
by the project team for use in ‘parent organisation’. If successful, it is terminated by
institutionalizing it as a formal part of the organisation. And often a separate SBU
(strategic business unit) is created for such projects. Telco after its ERP implementation
created a separate set up for the skilled IT pool it now had. In a university new courses
and department get created in this manner. In such cases, personnel, property, and
equipment get transferred to the new entity. New staff and budget is also created;
however, the administrative and budgetary practices of the parent organisation prevail.
Also the new entity no more has the political protection that it enjoyed earlier when it
was part of the parent organisation.
(c) Termination by Integration: This is the most common method adopted for dealing with
successful projects. It is also the most complex. All property, material, equipment and
personnel get distributed among the parent organisation. All problems of termination by
additional are also found here. One critical problem is when people get integrated within
the parent organisation, person is seen as an imposter (outsider) and is not welcome in the
parent organisation.
(d) Termination by Starvation: This refers to slow starvation due to budget decrement. This
is a strategy to mask a termination. Here harsh budget cuts are resorted to or there are
many small budget cuts imposed. Also personnel get allocated to other projects so that
ultimately no progress is made. The project exist in name as a legal entity and every year
the secretary issues a ‘no progress’ report.
The decision to terminate project is a difficult decision particularly with “in house projects. It is
hard to identify and quote reasons standards or mathematical formula on the basis of which one
can say you need to terminate projects.
Buell 1967 put forth a list of questions which may enable one to decide to terminate.These are:
Dean:According to Dean (1968), two most important reasons have been quoted for termination
of projects. They are: Technical and commercial failure. The Concorde project was a technical
success but a commercial failure. It was British-French supersonic jet .**
(**It had a maximum speed over twice the speed of sound at Mach 2.04 (1,354 mph or
2,180 km/h at cruise altitude), with seating for 92 to 128 passengers. It was jointly developed and
manufactured by Aérospatiale and the British Aircraft Corporation (BAC) under an Anglo-
French treaty. Twenty aircraft were built, including six prototypes and development aircraft but
Air France (AF) and British Airways (BA) were the only airlines to purchase and fly Concorde.
The aircraft was primarily used by wealthy passengers who could afford to pay a high price in
exchange for Concorde's speed and luxury service.)
Pinto, etal, 1987, 1988 listed ten critical success factor for projects. They in order of importance
are:
According to Baker etal critical success feature different for different industries, different
organisations and types of projects. However, there is consensus on the reasons for failure.
They are :
The company used project form of organization which we not needed for the particular
task.
1) Lack of Top Management Support:
It did not had support of top management in term of finance people and time allocated
often functional departments via for resources which is scares even CEO was not
committed to project.
2) Project Manager:
Project manager had maximum technical skills needed for the project but lacked of
managerial skills so very essential to managing project.
3) Poor Planning:
Lack of planning is often a major cause of failure when there is no systematic plan laid
down often uncertainties associated with project cannot be visualized as a result of which
nothing goes as deserved. Errors creep in mistakes become a part of everyday life, project
go behind the schedule all become “chaotic”.
The causes of failure make one realise the almost need for a careful evaluation of all the stages of
a project before a project is undertaken.
a) Decision Process
b) Implementation Process
Second is the implementation process; if decision is to terminate, (yes) then termination has to
be executed.
1) Decision Process: In decision process we make use of models which enables one to
decide to terminate or not to terminate projects and these models fall into two categories.
(i) A model which defines a list of factors for successful (or failed) project. This tests
how far your project qualifies to be called successful (or failed) project.
(ii) A model which enables you to assess how for your project was able to meet the
objective and goals of the project.
These are “project selection models” and these are often are used for project termination.
But many do not agree or find this suitable because of many reasons.
i) The data needed for project selection models is too large and too costly to justify this
as a method.
ii) Projects are evaluated at every stage of PLC and evaluation of factors in project
selection model change that is the selection criteria changes over the period (life) of
project. That is may be one set of standards are used when project was started and yet
another set of standards (factors) when project has run over years that is in another
stage of PLC.
For instance technical success of project is more in early PLC stage but reduces as project
progresses therefore such criteria cannot used. This would induce manager to terminate “current
ongoing project” in favour of new ones.In conclusion it can be said that it depends on whether
the organization is willing to invest time and cost needed to complete the project based on what
is “current status” of the project and at the moment what you expect the outcome to be.
2) Implementation Process:
Once it has been decided to terminate a project the process of termination starts. The actual
termination process should not be hurried and haphazard but should be backed by planning,
should be orderly, should be budgeted and scheduled like it is done for any stage of PLC. The
following figure (design for project termination) illustrates it. Often help of a checklist is also
undertaken to identify tasks to do and ensure that they have been done.
Personnel Report
These tasks are: organisational, financial, purchase oriented, engineering or site oriented to name
a few.
Financial: Close financial documents and reports, charge audit, collect receivables, and prepare
the final report.
Purchase: For each purchase order and sub-contractor, prepare compliance and completion
document, supplier be notified of project closure and make all final payment.
Engineering: Compile and store all engineering document, prepare final technical project report.
Site oriented: Close down the facility and dispose of all material and equipment.
i) Subcontractors: all task related with project should be complete including task
including subcontractors.
ii) Delivery: Project delivery and installation to client.
iii) Final Report: Prepare final report.
iv) Billing & Invoice: Clear all bills
v) Redistribution of All Resources: personal material equipment etc.
vi) Legal Counsel: Clear project with legal counsel / Consultant and file for patent if
any.
vii) Record Keeping: Determine what record to keep where to keep them in right place
and hand over responsibilities to parent organizations.
viii) Product Support Requirement: If any product supportrequirement like spare
services is needed in future decide how that should be met and assign responsibility
for same.
The process of project termination or close out is often conducted under the direct supervision of
the project manager.Many a time this is not resorted to as the project manager tries to prolong the
termination process as it indicates the end of the rule and power of the project leader or simply
because of the love of project.
2.3 THE PROJECT FINAL REPORT (What is it, what it contains, how it is written)
What is it?
The final report is the history of the project. It is the chronicle of the life of the project which
describes the project in detail. It describes what the project went through in different stages
of the life cycle. A list of what went right and a list of what went wrong,is also made.
Further, a list of persons (who all) whowere associated with the project and in what capacity
is also made. It also details how the project was managed, learnigs from the project is also
listed and this also acts as a prelude to new projects.
How it is written?
How the project is written is of less significance; as compared to the content. It is contents of
PFR which is of importance.
i) Chronological Order: Some are organized chronologically as and when events took
place although no specific method is advocated.
ii) Administrative & Technical Section: Sometimes they are divided into two sections-
one devoting to administrative aspects and the other devoting to the technical aspect
of the project.
iii) Narrative: Sometimes they are written in narrative style.
iv) Commentaries: Sometimes they are written as short and small commentaries of
events and are all put together to form the complete PFR.
What is contains?
1) Project Performance:
i) Comparison: This compares the project proposal that is what project tries to
achieve with the terminal evaluation that is what the project achieved.
ii) Deviation: This also explains the reason of deviation if any, in as much detail as
possible.
iii) Earned value: this explains “good judgement” (prudent decision) made by
project manager in different situations and reasons for success or future. For
instance although Tata Motors had constructed 85% of the plant at Singur in West
Bengal; yet it decided to shift the plant to Sanand in Gujarat; this was a prudent
decision.
iv) Recommendation: Often a set of recommendation (or learnings) from project is
also listed.
2) Administrative Performance:
a) Substance versus Administration: the substance of project is important but so is the
administrative aspect of the project. But often it is given less importance or even
ignored.
b) Review: Administrative practices should be reviewed and good points highlighted.
c) Reasons: The reason as to why same practice was effective (or ineffective) in light of
the environment of the organization should also be highlighted.
d) Recommendation: On the basis of the above recommendation what will work and
what will not.
Conclusion:
Many informal procedures that speeds up budget prepration, ease scheduling help in improve
forecast are often adopted and decisions are also taken based on faith and hunch of project
manager. This is also listed and made a part of project history. This is often listed in projects.
This is because the purpose of “history” is to make future project successful.
Many a time the project manager maintains a personal diary. This also becomes the part of the
project history. Many a time, later on, this exploits knowledge of project manager which should
not be last. This is a kind of diary that any adolescent maintains. And often valuable insights can
be drawn from these. It is a rich source of unconventional wisdom.
The origin of WBS goes back to 1957 when US Department of Defence (DoD) used it in Navy to
support the development of Polaris missile program. Though the term WBS was not used; but it
did organize the task into product-oriented categories. In 1962, DoD, NASA published a
document for PERT/COST system which infact described the WBS approach. This guide was
endorsed by the Secretary of Defence for all services. In 1968, DoD issued a WBS for Defence
Material Items (MIL-STD-881) a military standard requiring the use of WBS across the DoD.
The document has been revised several times and the most recent one was in 2011 and found in
Work Breakdown Structure for Defence Material Item (MIL-STD-881C).
In 1987, the PMI documented the expansion of this technique across non-defence organizations.
A Work Breakdown Structure (WBS) is used by the project manager to break a project into
manageable components. This makes a complex project more manageable by subdividing the
project into smaller work packages.
It helps in
better estimation of cost
better estimation of time (scheduling)
better resource allocation
assigning responsibilities (and creates accountability and commitment)
indicates the control points
indicates the project milestones
risk management-reducing the risk of missing important tasks and work during the
project period.
WBS lays the foundation for accurate project costing. This tool helps management carry-
out a bottom-up project costing and estimation which is the most accurate estimating
method.
It also gives an accurate picture of the project schedule because it includes all the tasks
which are needed to complete the project in time.
Beyond this the WBS also helps the project team to easily manage the tasks and to have a better
overview of the milestones which need identification during the project period. Also it helps in
engaging the project team members because the team members are forced to share their
knowledge within their field with each other in order to develop the WBS. Furthermore, it gives
an overview of the ambiguities and uncertainty within the project and highlights important issues
of the project at an early stage. It helps in defining the scope of the project.
In short, work breakdown structure is a chart or a document which is used to organize project
work into a list of focus areas. It ensures that all work stays on track to meet the project goals.
(i) Deliverable Oriented WBS: Here one identifies the deliverables (or outcomes). One
defines the project work in terms of components (physical or functions) that must be
made. Eg: Module A or Engine. This is also called Product-Breakdown-Structure and
is the preferred type by PMI. This is often used in new product development.
It is then broken into activities that must be executed to achieve the outcome.
Therefore it is sometimes called Task-Oriented WBS as it defines the project work in
terms of action that must be taken. Eg: design an engine, or develop a computer. The
parts of a computer would consist of the VDU (visual display unit), mother board,
key board, etc.
(ii) Process-Centered or Process Oriented WBS: defines the project work in terms of time
phases. They are used for very long projects. This is also called Time-Oriented
WBS.The process- centered WBS includes the Level 2 activities which are phases
within the project. Examples of activities in software development would be phases
such as Initiation, Planning, Design, and so on; Level 3 would include the activities
required in order to complete the second level. The additional levels in the hierarchy
depend on the duration of the phase and the level of details required to reliably make
an estimate of the cost and the schedule of the project.
There is no set format for creation of a WBS. It can take a variety of forms that serve a variety of
Within the WBS every item within the hierarchy level has been assigned a unique number so the
work can be identified and tracked over time (to its origin). The numbers have varying numbers
of decomposition levels; one follows a general scheme for numbering for each level. An
illustration is given below: (Distribute the diagram)
Level 1: Designed by 1.0. This is the first level. This is the top level of the hierarchy of the
WBS and is usually the name of the project. This is assigned the number 1.
Level 2: This is the second level. This is broken into two components Deliverable- 1 and
Deliverable-2 and have been assigned numbers 1.1 and 1.2.
Level 3: This is the third level. Deliverable-1 is broken into two component activities and
numbered 1.1.1 and 1.1.2 Deliverable-2 is broken into two component activities and
numbered 1.2.1 and 1.2.2.
Level 4: This is the fourth level. The first activity is broken into three tasks and assigned a
number 1.1.1.1; 1.1.1.2 and 1.1.1.3 respectively and so on.
For an understanding of the hierarchy of the WBS it is important to understand the main
structure of the management tool.
The WBS is modelled after four different areas: They are Scope, Time, Cost and Resources. This
is needed to demonstrate how a work breakdown structure is conducted in a project team. Four
different areas of WBS are:
(i) Scope: The scope is the broad strategy of the project which is planned. The scope is
an important step for developing the WBS because it determines a list of specific
projects goals, objectives, main deliverables, tasks, cost and the deadline.
(ii) Time: An estimation of the accurate time is also important. It helps to set the deadline
for the deliverables and the planning process of the project. In this step a WBS
dictionary is created. The WBS dictionary includes entries for each WBS component
that briefly defines the scope or the statement of the work (SOW). The SOW is a
document that defines project- specific activities, deliverables and timelines.
Furthermore, the SOW typically also includes detailed requirements and pricing.
(iii) Cost: Cost is an essential part when planning a project. The cost within WBS involves
budgeting and an integrated earned value management system (EVMS) which is also
known as Earned value management (EVM). EVM is a project management
technique for measuring the project performance and progress. EVM is unique as it
has the ability to combine measurements of the project management triangle that is
scope, time and costs. And therefore, EVM has the ability to provide accurate
forecasts of project performance problems. .Figure: EVM (Discussed in class)
(iv) Resource: The last step of the WBS is identifying the resources required for the
project. The resources are determined with the help of responsibility matrix.
Source: Where the capital letters represent the following (and this can change-use you creativity here for
assigning) Where R – Responsible, A – Accountable, C – Consult, and I – Inform.
They may be defined in different ways using different alphabets to represent responsibility;
or different figures like a circle, or a triangle, or a boxto represent different roles. Different
numbers can also be used.
For clarifying decision roles and improve decision making, Bain & Co has introduced the
RAPID.
R- Recommend Role represents who do 80% of the work in a decision. He gathers inputs
andlays down a course of action.
A- Agree Role represents who give formal approval of a recommendation
P- Perform Role represents who is responsible for execution once a decision is taken.
I- Input Role represents who give relevant information so that ‘R’ and ‘D’ can take decision.
I role is advisory.
D-Decide Role represents is a single person who is ultimately accountable for making the
final decision, committing the group to action and ensuring the decision gets implemented.
Problems in creation of WBS: WBS is prepared to determine the exact nature of tasks
required to complete the project. There are many problems encountered while creating a
WBS.
(i) Problem-1: Some managers want to create according to outcomes while some want
according to specific tasks (activities). And many mix the two. Therefore often a list
of tasks, activities and outcomes are made and each activity leads to which outcome
or which activities are associated with which outcome is first arrived at. These
activities and outcomes are decomposed into sub-activities and sub-divide again
successively
So, WBS is tailored to be used in different ways. But it should reflect how each piece
of project contributes to the whole in terms of performance, budget (cost), schedule
(time) and responsibility. Therefore for each work package one needs to identify
relevant data.
(ii) Problem-2: Senior managers allocate budget for each work package. Junior feels the
budget is insufficient to fulfil the task at hand. So there is intense fight between the
two. Discussion between the two ensues. Senior says our estimate is based on ‘past
experience’ while subordinate says we are executing so we know the fact/the reality.
If subordinate is involved in estimation (budget prepration) then the difference
reduces. In participative management style, the subordinate is more willing to accept
budget as they too were involved in budget-decision-process.
Superior establishes budget as “B” while subordinate estimates it to be “b” and in a
perfect world B=b which does not take place.
Always a deviation is found in estimate of Senior and the subordinate for the following reasons.
(a) It has been observed that the further one moves up the organization hierarchy, away for
immediate responsibility and execution of the task, the easier, the cheaper and the less
time consuming the task appears to him. This is mainly because either the superior does
not know the minute details, or it suits him to forget the details and the problems
associated with implementation of the task.
(b) He wants to project the project to be less cumbersome and less costly to his
superiors.(and more profitable).
(c) Subordinate believe in the operation of Murhy’s Law which lead them to build in some
level of protection against failure and as such they increase the budget or the time needed
to complete the project.
*Named after Captain Edward A Murphy, an engineer working on AIR FORCE PROJECT
MX981. His words were “If anything can go wrong, it will”.
2.5 Earned Value Analysis:
WBS helps in monitoring projects through monitoring of work packages and also the entire
project. Individual task performance must be monitored carefully because the timing and co-
ordination between individual tasks is important. We use the concept of Earned Value (EV) for
this purpose. EV is a project management tool which uses information on cost, schedule and
work performed to establish current state of the project. It combines the concept of the three
critical factors that of time, cost and performance in one tool. It allows a project manager to
extrapolate current trends to predict their likely final effect.
One often faces difficulty in comparing actual expenditures against budgeted expenditure
(baseline expenditure) for any period of time (say T). The comparison often fails to take into
account the amount of work done (work accomplished) relative to cost incurred. The earned
value of work performed (value completed) for those tasks in progress is found by multiplying
the estimated percent physical completion of work for each task by the planned cost for those
tasks. The result is the amount that should have been spent on the task thus far. This can be
compared with the actual amount spent.
For instance, the project task was budgeted to be complete in 6 weeks at ‘x’ cost. We have
completed 6 weeks (the time) and incurred ‘x’ cost (the cost). But maybe only 1/3 of the work is
complete (work accomplished is 1/3). Therefore it is necessary to measure performance also.
The concept of Earned Value takes into accounts all of these-the T, the C, as well as the P.
See diagram below:
The concept of earned value combines cost reporting and aggregate performance reporting into
one comprehensive chart. The baseline cost to completion is called the ‘budget to completion’
(BAC). The actual cost to date can also be projected to completion and is referred to as the
estimated cost at completion (EAC).
A negative variance is ‘bad’ and the cost variances and schedule variances are calculated thus.
The cost variance is the difference between the amount of money we budgeted for the work that
has been performed to date (work accomplished), that is, the earned value (EV) and the actual
cost of that work (AC).
The schedule variance (SV) is the difference between the earned value (EV) and the cost of the
work we scheduled to be performed to date, or the planned value (PV).
The time variance (TV) is the difference in the time schedule for the work that has been
performed (ST) and the actual time used to perform it (AT).
Cost Variance (CV) = Earned Value (EV)-Actual Cost (AC) (CV, overrun is negative)
Schedule Variance (SV)= Earned Value (EV)- Planned Value (PV) (SV, behind is negative)
Time Variance (TV)= (ST)-(AT)
These variances are also formulated in the form of ratios:
The Cost Variance becomes the Cost Performance Index (CPI)= EV/AC
The Schedule Variance becomes the Schedule Performance Index (SPI) = EV/PV
And
The Time Variance becomes the Time Performance Index (TPI) = ST/AT.
Such ratios are very helpful in comparing more than one project; or the same project over
different periods of time.
Illustration 1: The operations on a work package were expected to cost Rs 1, 500 (for the
complete package). The original schedule for completion was 3 days. It was found that on the
third day, Rs 1,350 has been spent. The proportion of work completed is 2/3. What are the cost
and schedule variances?
Cost variance
For 2/3 of the work package Rs 1000 should have been the expenditure.
(that is 2/3 of 1500=1,000)
But total actual spent is Rs 1350.Therefore the Cost variance is difference between budgeted
cost, for that amount of work, and actual cost.
Therefore Cost variance is Rs 1000- 1350=Rs -350 (negative as it is excess spent)
Schedule variance
Total cost associated with three days is Rs 1500.
Cost per day would be 1/3*1500=Rs 500
NOW
2/3 would have been complete in 2/3*3=2 days.
Expenditure for 2 days should have been Rs 1000
Therefore schedule variance (expressed in terms of cost) =Rs 1000-Rs 1500= Rs -500
Time Variance (TV) = ST-AT =
Time to be taken to complete 2/3 of work is 2/3*3=2 days
Actual time taken was 3 days
Therefore TV = ST – AT = 2-3 =-1 day.
Illustration 2: The planned cost of an advertising project was Rs 12,000. The project was for 7
days. But the actual cost (spent) to date (on the 7thday ) was Rs 10,000. But the value of work
completed (accomplished) was only 70 percent. Calculate the cost and schedule variances
If the work was to be completed in a week, find also the time variance.
Cost Variance (CV)= Earned Value (EV)-Actual Cost (AC)
(12,000*70/100) – 10,000 = 8,400 – 10,000 = -1,600
Schedule Variance (SV)= Earned Value (EV)- Planned Value (PV)
(12,000*70/100) – 12,000 = 8,400 – 12,000 = 3,600
Time Variance (TV)= (ST)-(AT)
(70/100*70) – 7 = 4.9 -7 = -2.1
Distribute Sheet on numerical of EV-Filename-project-numerical
(Also refer to numerical distributed on March 11, 2020; when project monitored at end of
project life and when monitored in between. And two page notes with formula)
The Agile Manifesto is comprised of four (4) foundational values and also twelve (12) supporting
principles which define the Agile approach to software development. These values are:
According to the team of 17, while there is value in the items on the right, they value the items on the
left more.”
Agile also laid down twelve (12) Principles of Agile. They are:
1. Customer satisfaction through early and continuous software delivery– Customers are
happier when they receive working software at regular intervals rather than waiting for long
periods of time for the software to be released.
2. Accommodate changing requirements throughout the development process – The agile
suggests change to be incorporated and avoiding delay when a requirement or feature request
changes.
3. Frequent delivery of working software – Customers prefer to receive software at frequent
intervals.
4. Collaboration between the business stakeholders and developers throughout the project –
Better decisions are made when the business and technical team are aligned and work together.
5. Support, trust, and motivate the people involved – Teams should get support, and be
motivated to deliver their best.
6. Enable face-to-face interactions – Communication is more successful when development teams
are co-located.
7. Working software is the primary measure of progress – Delivering functional software to the
customer is the ultimate factor that measures progress.
8. Agile processes to support a consistent development pace – Teams establish a repeatable and
maintainable speed at which they can deliver working software, and they repeat it with each
release.
9. Attention to technical detail and design enhances agility – It is necessary to have right skills
and a good design so that the team can improve the product, and sustain change.
10. Simplicity – Focus should be on simplicity; just having enough to get the work executed.
11. Self-organizing teams encourage great architectures, requirements, and designs – Self
organized teams are highly motivated teams as they are comfortable working with each other and
also can rely and trust each other. Such teams who have decision-making power, take ownership,
communicate regularly, and share ideas that deliver quality products.
12. Regular reflections on how to become more effective – Self-improvement, process
improvement, advancing skills, and techniques help team members to work more efficiently.
The intention of Agile is to align development with business needs, and the success of Agile is
clear. Agile projects are customer focused and encourage customer guidance and participation. As
a result, Agile has come to be accepted as method for software development throughout the
software industry and has taken the position of an industry.
Business Case
User Requirement
System Specification
.........DECIDE................
System Design
Component Design
...........DESIGN................................................
Construct Component
Test
............DEVELOP.................................................................
............DEMONSTRATE......................................................
Sys Design
Interface Test
Construct Component
It means determining what of these are needed, in what quanity are they needed, what is their
source of supply, if a shortage is faced; wherefrom would they be arranged for.
An organisation gets many new projects (multiple projects). There are many problems which
arise in managing projects they being:
Delay in execution of projects-Delay in one project causes delay in other projects too; this is
because all these projects use common resources.
If care is taken in selecting projects, the chances of projects being completed successfully would
increase.
What is Project Selection? Project selection is the process of evaluating proposed projects or
group of projects, and then choosing to implement some set of them so that the objective of the
parent organisation is achieved.
Choosing one out of many projects is difficult; but choosing a number of different projects (a
portfolio) is even more difficult and complex too. Several techniques are used. To help us decide
we often make use of models.
What is a Model? Models extract the relevant issues about a problem from the mass of detail in
which the problem is embedded. It allows to strip away all of the reality from a problem leaving
only the relevant aspects of the ‘real situation’ for us to deal with.
The process of taking away the unwanted reality is called modelling the problem. It is an
idealized version of the problem. A firm should keep these points in mind while selecting a
problem. These are:
Capability: It should have the capability to deal with the relevant aspects of the problem.
Ease of Use and ease of implementation: It should be easy to use and implement.
Cost: Cost associated with gathering data and modelling it should not be very high.
Models
Non Numeric Models: These models are basically qualitative models which do not undertake
numerical values for assessing projects.
(i) The Sacred Cow: In this the project idea is suggested by a senior official or powerful
person in the organisation. He suggests by using words like “ If you have a chance to
see this proposal...” or “Why don’t you look at this and see if it could be tried out...”.
Such ideas are visibly supported by the powers to be. The idea could be for a new
product launch, entering new market or just about anything. Prime Minister’s Swach
Bharat Abhiyaan or the Nano Project fall under this category. Nano was RatanTata’ s
baby. The project is scared in the sense that it will be maintained unless successfully
concluded or abandoned if the boss declared it as failure. The steel plant at Port
Talbot in UK is a classic example of a project of this nature. Tata steel has 11 plants
in UK in Newport, Crosby, Rotherhamand Warwick to name a few out of which this
Port Talbot plant is the largest with 4000 employees. This is running at losses and
cannot be turned around. It was proposed to be sold off in March 2016. However,
after Mistry’s removal one billion pounds has been invested in the plant.
(ii) Operating Necessity: This refers to those projects which are required in order to
keep the system operating. It ensures that there is no halt in carrying out with daily
operations of the organisation. A project to build a ‘protective dike’ in case of an
impending flood which is expected to disrupt the plant operation falls in this category.
For such projects, no detailed or formal evaluation is undertaken. However, the cost is
kept as low as possible.
(iii) Competitive Necessity: Projects undertaken to maintain competitive position of the
organisation fall in this category. Modernization of plant at SAIL is an instance.
Academic institute undertaking re-structuring of course curriculum is yet another.
Projects falling under operating necessity are given priority over projects falling
under competitive necessity. For these projects also, no detail or numeric analysis is
undertaken.
(iv) Product Line Extension: Such projects are undertaken to fill a gap in the existing
product line or extend a product line. These are based on the foresight of the CEO as
to the likely impact such projects would have on the performance of the total system.
The top five automobile players have 85% of the market share while SKODA has
only 1% market share. The company realized this is because India is a market for
small cars and SKODA does not have a single car in its portfolio. As such it now
plans to launch one. This is an instance of product line extension by ‘fiiling the gap’.
(v) Comparative Benefit: When an organisation has many projects to consider, it would
select a ‘subset’ of these. It is often difficult to decide as to which to select. This is
mainly because the projects differ in terms of nature, benefits, costs and associated
risks involved. For instance, project for new product development, project for
automation of organisational functioning, which machine to select in part fabrication
process, etc are all of different from each other but all needed by the organisation. In
such cases, we can use ‘Q Sort’ method developed by Helin, et al. It involves a set of
steps.
Step-1: Put the projects in three categories; they being good, fair and poor.
Step-2: If any category (group) has eight or more than eight projects; mark each as
fair-plus or fair-minus.
Step-3: So each group should have eight or less than eight projects. Now projects in
each group are ‘ranked’ from best to worst. Any criteria may be used for ranking (or
an overall general criteria may be used).
A committee does this process of ranking of projects. First, members of this
committee individually mark them; this is followed by a consensus arrived at by all
members.
Step-4: Projects selected on the basis of ranking are then evaluated financially before
a final selection.
Numeric Models can be categories as ‘scoring based models’ and profitability based
models’.
Scoring Models: Such models use multiple criteria to evaluate a project. Such
models vary widely in their complexity and information requirements.
(i) Unweighted 0-1 Factor Model: Under this model, a set of relevant factors
are selected by management. These are listed. One or more raters score the
project on these factors. These raters are chosen from senior management
based on
(a) An understanding of organisation’s goals
(b) Knowledge of firm’s potential project portfolio.
The major advantage of this model is that it uses more than one factors in its
decision making process. However, its disadvantage is that it assumes all factors
(criteria) to be of equal importance.
Illustration-1.
Project:............
Rater:............... Date:.........
(ii) Unweighted Factor Scoring Model: This removes the disadvantage of the
earlier model. This incorporates the ‘degree’ to which the project meets each
criteria which is listed on a scale of 0-5 where ‘5 represents very good’, ‘4
represents good’, ‘3 represents fair’, ‘2 represents poor’ and ‘1 represents very
poor’.
Illustration-2.
Project:............
Rater:............... Date:.........
5 4 3 2 1
Illustration-3.
Project:............
Rater:............... Date:.........
(weights) (5 4 3 2 1)
Table-1
Style Reliability Fuel Eco
Style 1/1 1/2 3/1
Reliability 2/1 1/1 4/1
Fuel Eco 1/3 1/4 1/1
Now, Rank the Priorities:
Eigenvector
Iterate
1. Take successive squared power of matrix
2. Normalize the rows
3. Repeat, until difference between the successive row sums is less than a pre-
specified value
Steps to follow:
Step-5
Style Reliability Fuel Eco
Style 1/1 1/2 3/1
Reliability 2/1 1/1 4/1
Fuel Eco 1/3 1/4 1/1
Step-6
Cell 2: (1*.5)+(0.5*1)+(3*0.25)=1.75
12.750
22.333
04.833
.5595
.1211
Next: On subtracting values of step 11 from values of step 12, we get the following
values(-0.0002), (0.0011) and (-0.0009)
0.5584
0.1220
Profitability Based Models: These models see the return from the project and compare then with
the cost incurred.
These are-Payback Period Method, Net Present Value, Internal Rate of Return, and Profitability
Index Method.
There are also extension of NPV and IRR that is, Modified NPV and Modified IRR. These were
discussed in class.
Problems in AHP.
1. I have to choose between Dell (D), Lenovo (L) and Apple (A). Seeing the hardware
configuration (HC)
Apple is 6 times better than Dell
Apple is 8 times better than Lenovo
Dell is 4 times better than Lenovo
(Priority vectors-0.754, 0.181 and 0.065)
User friendly (UF)
Apple is 5 times better than Dell
Apple is 4 times better than Lenovo
Lenovo is 3 times better than Dell
(Priority vectors-0.674, 0.101 and 0.226)
Hardware Maintainability (HM)
Apple is 7 times better than Dell
Lenovo is 5 times better than Apple
Lenovo is 8 times better than Dell
(Priority vectors-0.223, 0.055 and 0.713)
Financing Availability (FA)
Apple is 8 times better than Dell
Apple is 6 times better than Lenovo
Lenovo is 4 times better than Dell
(Priority vectors-0.754 ,0.065 and 0.181)
Find final priority if HC, UF, HM, and FA are 0.553, 0.131, 0.271 and 0.045
respectively.
Ans: .0.680, 0.130 and 0.190
(Feb.10, 2015)
FOR LITERATURE ON NPV (and modified NPV) AND IRR (modified IRR) refer to
PROJECT MANAGEMENT BY PRASANNA CHANDRA. AVAILABLE IN SEMINAR.
So far we have considered independent decisions. We take up mutually exclusive projects and
compare them when project life is different and project size is different. Also both costs that is
capital as well as operating costs are considered.
Here we will focus on cost spread for one year (that is its equivalent cost for a year).
Example: ABC is considering buying a machine. Two alternatives exist-A and B, whose details
are:
Machine-A Machine-B
Capital Cost Rs 75,000 Rs 50,000
Life 5 yrs 3 yrs
Operating Cost Rs 12,000 Rs 15,000
Assuming cost of capital to be 12%, which would you opt for.
=75,000+12,000*3.605
=75,000+43,260=1,18,260
=50,000+15,000*2.402
=50,000+36,060=86,060
But we need to spread these costs for the life of the project which is 5 years for A and 3 years for
B.
This we do by dividing the total cost arrived at by PVIFA. This is the UAE.
UAE for A=1,18,260/ PVIFA for 5 years at 12%
= 1,18,260/3.605
=32,804
=86,060/*2.402
=35,815
4.1 Introduction:
Infrastructure financing refers to capital required to produce economic services like electricity,
gas, telecommunication, water and transport works (like road, brides, sea port and air port and is
necessary for economic activity.
The major characteristics of infrastructure projects are: they are highly capital intensive, involves
sunk cost and have long operating cycle.
It is important that government play an important role in planning and promoting infrastructure
projects because infrastructure is needed for economic development, it is an essential service,
such projects have a social dimension associated with it and also the project size is huge.
In India, infrastructure projects are largely owned and managed by the government or a
government undertaking but because of requirement of huge capital, and they being managed
better by the private sector; private sector participation is being encouraged.
Private initiative can take various forms-they can be in the form of contracted operations of
public utilities to full operation, operation, ownership and maintenance of the facility. Some
projects have significant social value like a low cost transportation; this is more suited for
government ownership while one which has a strong commercial attraction like
telecommunication project, it is more suited for private participation.
Infrastructure financing is different from conventional project financing mainly because most of
them are PPP and therefore they have to be handled carefully. A detailed understanding, analysis
and evaluation of the complexities and risks involved in the project have to be taken.
What is a PPP?
Also called 3P and P3, is a c-operative arrangement between two or more public and private
sectors for a long term period. Historically, government all across the world has been using this
arrangement; however, it has got up lately. There is no consensus of how to define a PPP; but it
refers to long term arrangement involving infrastructure development. Most PPPs focus on
sharing of risk, long term relationship between public and private, and the use of private finance.
PPP refers to a contractual partnership between the public and private sector agency in which the
private sector is entrusted with the task of providing infrastructure facilities and services that
were traditionally provided by the public sector. Eg: A toll expressway project financed,
constructed and operated by a private developer.
This does not mean that the government is not involved in any way. The government has the
responsibility for ensuring that quality of service is being provided by the private party, and
reasonableness of cost is ensured of. The role of the government is to facilitate, enable and
monitor the service while the role of private partner is to finance, build and operate the service.
There is a genuine sharing of risks between the government and the private sector (Jaypee
Group).
The process of finalising a PPP involves a detailed cost appraisal, risk appraisal, bidding
procedure, stakeholder management and long negotiations before final closure. Therefore it is a
must to have a clear regulatory, legal and financial framework laid down.
The ownership and operation of infrastructure projects are separable and therefore a variety of
models exist to meet the characteristics of projects. They are: BOOT and BOT.
Noida Toll Bridge Company Limited (NTBCL) was incorporated in 1996. It was promoted by
Infrastructure Leasing and Financial Services (ILFS) and New Okhla Industrial Development
Authority (NOIDA) and Delhi administration, as a SPV (Special Purpose Vehicle) to develop,
construct, operate and maintain the DND Flyway on a BOOT basis.
BOT: A road project the private sector may have been invited to build the facility, operate
during the concession period and finally at the end of the concession period, transfer the facility
back to the government without actually ever owning the same. In this case, ownership of the
road remains with the government and the private sector recovers the investment and a return
thereon by charging a levy on users of the road during the concession period. Yamuna
Expressway in an instance of the BOT project.
Since a number of risks are associated with infrastructure projects, project sponsors follow
some arrangement while implementing these projects. These are discussed under the
heading-SPV, Sponsors Contribution, Project Parties and Debt Equity.
(i) Special Purpose Vehicle (SPV): Projects are implemented in a SPV. SPV is a distinct
corporate entity incorporated with the objective of implementing and operating the
project. This ensures that the risks associated with the project are ‘ring-fenced’ and
does not flow back to the sponsors entities.
(ii) Sponsors Contribution: Project sponsors take an equity stake in the project. The
equity stake depends upon the project cost, sponsors ability, objectives of the project
and also on the lenders requirements.
(iii) Project Parties: The SPV enters into contractual agreements with various parties like
project contractors, off-takers, operators, government and project lenders.
(iv) Debt-Equity: Infrastructure projects can be financed at a relatively higher gearing
ratio (debt-equity ratio) as compared to conventional projects.
Eg: In Indian road projects, where private enterprise would construct, operate, and
maintain the road during the concession period and would earn an assured annuity
from NHAI irrespective of the actual level of traffic, lenders may be willing to
consider a higher gearing of up to 4:1.
In case of power projects, where off-take is assured to the extent of certain Plant Load
Factor (PLF) by the concerned SEB, lenders have traditionally financed on a debt-
equity (DER) of 2.33:1.
For conventional projects, where the project (and therefore the lenders) is exposed to
pure market risks, DER would rarely exceed 2:1.
Conclusion:
In infrastructure projects, each project party ensures that contracts are:
-as iron-clad as possible,
-very little is left to interpretation
-objectives and obligations are clearly laid down
-risks are clearly allocated
-must have financial and legal advisors who would advise the SPV and sponsors on
appropriate risk allocation
-And a legal framework should exist to ensure that risk allocation is correctly defined.
For power projects, lenders consider PPA to be a very important project document. The
lenders evaluate the sufficiency of negotiated tariffs especially if the ‘fixed charges’
element is pre-determined and not cost based. The lenders also evaluate the need of inter-
connection facilities. Lenders also evaluate the ability of the SEB to complete
construction of this facility prior to COD (Commercial Operation Date) of the project. A
key provision of the PPA is the security and credit enhancement mechanism and lenders
need to be satisfied with the above.
Management of Risks
Type of project Cons Oprn Mkt Int Payt Regl
PORT H M M PrSp L L
AIRPORT H H H PrSp L M
POWER M L L PrSp H H
UNIT-5
Unit-5 Risk Assessment, Contract Management & People Management in Projects
It goes without saying that every business is subject to numerous risks. We need to identify all
the areas where our business is vulnerable only with the aim of hedging those components.
This is important as only when one knows where the risks are can one think of protecting
oneself from these risks and dangers. Therefore you need an assessment of risk. You need to
assess risk because only then will our business have a higher chance of staying or becoming
successful. Also it would keep one ahead of the competition.
What are the areas which are most vulnerable? They could be ones supply chain, ones
customers or even ones employee.
Supplier: If number of suppliers is few, it is of concern. What if they do not supply on time?
Customer: Another is customer. But if ones company’s products are rare and in great demand;
one does not face much risk. B but if high competition one can run the risk of losing its
customers.
Employee: Our managerial and business structure can also be a huge financial risk. For
instance if one rely on only one individual to keep the company running, what do you do
when that person is no longer available? This is often the case with small businesses, and
some larger ones, where the operations are handled by only one manager.
Therefore a company needs to make an assessment of its risks.
What is 'Risk Assessment'
Risk assessment is a general term used across many industries to determine the likelihood of loss
on a particular asset, investment or loan. The process of assessing risk helps to determine if an
investment is worthwhile, what steps may be taken to mitigate risk and, through specific ratios,
the upside reward compared to the risk profile. It determines what rate of return is necessary to
make a particular investment succeed.
Project Risk
Insufficient
Labor Rate Scope Creep
Resources
Changes
Sub-contractors Inexperienced Regulation
Performance Estimators Changes
Often risk is seen consisting of four kinds of risk-they being technical risk, external risk,
organizational risk and project management risk.
Project Risk
Estimators
Control
Communication
Risk identification is usually done in the beginning of a project; but new risks can be identified
throughout the project life cycle as the result of internal or external changes to a project.
Therefore risk identification remains an iterative process and is undertaken throughout the life of
the project.
The main purpose of risk identification is to minimize the negative impact of project, and
to maximize the positive impact of project opportunities. Once risks have been identified, a
project manager tries to control the impact of a risk on a project. If one is aware of the project
risks; it improves the chances of project success.
Risk identification also provides information for the next step of the risk management process:
that is risk analysis.
1. Creating a systematic process for risk identification- The risk identification process
should begin with identification of project objectives and success factors.
2. Information gathering – One needs to gather reliable and high quality information for
effective risk management.
3. Apply risk identification tools and techniques - The choice of the best suitable
techniques will depend on the types of risks and activities, and also on organizational
maturity.
4. Documenting the risks – The risks identified is documented in a risk register and a risk
breakdown structure is created.
5. Documenting the risk identification process - To bring improvement in the risk
identification process and also make the process easy for future projects, it is important to
record the approach, participants, and scope of the process.
6. Assess the effectiveness of the process – It is necessary to analyse the effectiveness of
the chosen process.
A tool found useful for systematic risk identification is SWOT analysis. It consists of:
Both opportunities and threats are risks that can have a positive or negative effect on a project,
and therefore each requires risk responses.
Risk Prioritization-This helps to rank the risks from most critical risk to least critical risk.
Different qualitative and quantitative techniques are used for Risk Impact Assessment and
prioritization.
See below for an example: RISK IMPACT MATRIX
High
Mod C2
Low
Vlow
rare occs sfre freq vfre
Risk Response Development- This helps develop strategic options, and determine action to
enhance opportunities and reduce threats to project objectives.
A member of the project team is assigned the responsibility of each risk response.
Avoid-Try to eliminate the cause of risk and thus eliminate the threat
Mitigate- All risks cannot be eliminated. Try to reduce the impact and thus mitigate the risk.
Transfer-Try to transfer risk to other party; like in insurance purchase or warranty or guarantee
The risk response strategy for opportunity is:
ACCEPT-A passive acceptance means what action would be taken is left to the chance or
occurrence of risk. An active acceptance means devising a contingency plan which would be
carried out in case risk occurs.
And therefore it means that cost and time has to be allocated. A decision to accept the `risk must
be communicated to all stakeholders.
Whenever a project manager responds to risk (threats or opportunities); it must be ensured that:
1. The response strategy is decided upon by team leader or any team member.
A risk register
Project Documents –All these need to be updated as outputs of Plan Risk Response.
Project Management Plans can be updated by new work or activities or work packages that are
added, removed, assigned to different sources.
Residual Risks- These are risks which remain after completion of risk response planning. These
are those risks that are accepted and contingency plans are developed.
Secondary Risks- Risk which may be created due to implementation of current risk response.
Contingency Plans-If specific risk occurs (x risk), this (y) would be the response.
Risk Response Owner-The risk is assigned to an individual who would develop risk response
and implement them if risk occurs.
Fall Back Plans-If risk response plan fails (Contingency Plans), the action to be taken.
Control Response:
Determine likelihood of risk triggers, identify and monitor residual risks, Use risk
identification as an iterative process, evaluate the effectiveness of risk response.
(And this is put as additional columns in the table on risk impact matrix shown above.
*Sending reminders
----------------
Construction projects are complex. They are full of uncertainties. Therefore, risk analysis and its
management is important. Risks emerge from a number of the different sources.
2. The construction industry is heterogeneous and enormously complex. There are several
major classifications of construction that differ markedly from one another. These could
be housing, non-residential building, heavy, highway, utility, and industrial. Further,
construction projects could include new construction, renovation, and demolition for both
residential and non-residential projects, as well as public works projects, such as streets,
roads, highways, utility plants, bridges, tunnels, and overpasses.
3. Change in the project environment-The problem multiplies with the size of the project as
uncertainties in project outcome increase with size. Large construction projects face more
uncertainities as compared to projects of a smaller size. Large construction projects are
exposed to uncertain environment because of such factors as planning, design and
construction complexity, involvement of various interest groups (owner, consultants,
contractors, suppliers, etc.), resources (manpower, materials, equipment, and funds)
availability, environmental factors, the economic and political environment and statutory
regulations. Construction projects therefore can be very vulnerable to changes in
environment and can be unpredictable.
4. Cost of risk-is one of the largest expense items-. Construction projects are largely
affected by cost escalations. These cost escalation can be with respect to material (cement
and steel) required to name a few.
5. Maintaining relationship with the many parties: There are many parties involved in such
projects and maintaining smooth relationship with so many becomes a big issue.
6. Uniqueness of Construction projects: Construction projects are subject to more risks due
to its unique features, such as long duration, complicated processes, unpredictable
environment, financial intensity and dynamic organisational structures.
Many approaches on risk classification have been suggested particularly for construction
projects.
(i) Risks has been categorized into two groups in accordance with the nature of the
risks, i.e. external and internal risks.
(ii) Risks has also been categorized into into six groups- local, global, economic,
physical, political and technological change.
(iii) The internal risks are relevant to all projects irrespective of whether they are local
or international. International projects tend to be subjected to the external risk
such as unawareness of the social conditions, economic and political scenarios,
unknown and new procedural formalities, regulatory framework and governing
authority, etc.
Most common way to classify the construction risks are into four groups they being- technical,
external, organizational, and project management risks. SEE DAIGRAM BELOW.
Risk
Environmental Risks
Social Factors
Environmental
Factors
Technical Risks: Technical risks could be design process risks, construction risks and
environmental risks.
Construction Risks-Inaccurate contract time estimates, Work permission, Worker and site safety,
Construction cost overrun, Technology changes are some of the construction risks.
External Risks: External risks could be contractual relations risks, Force Majeure risks, social
factors and environmental factors.
Force Majeure-Exchange rate changes, Changes in political climate are some instances of Force
Majeure.
Social Factors-Local communities pose objection is an example of risk associated with social
factors.
Organisational Risks:-Inconsistent time, cost and quality objectives; Inexperienced staff; loss
of critical staff, project manager heavy workload are instances of organizational risks.
*There are many parties involved in a construction project. The main parties are
1. Employer/client
Client refers to one who is getting the work done.It is the party procuring the work (typically, a
land owner or land developer). In relation to building contracts, this entity is usually referred to
as the 'employer'. He party is commonly referred to as the 'client'.
2. Contractor
A main building contractor is engaged by the employer to carry out and complete the works. The
contractor engages a number of sub-contractors to carry out and complete separate parts (small
components) of the work.
3. Professional team
Often a team of professional consultants is appointed. These consultants can be broken down
into two categories.
4. Financier
Financier is also a party to the contract. This refers to the banks and other institutions and parties
(for example, government organisations in the case of urban infrastructure). They give finance.
Depending on the size of the project, there may be more than one financer, that is may be one
bank or a syndicate of banks.
There are many perspectives from which one can study Contract Management (eg a legal angle).
We will study or approach Management of Contract from the perspective of a Project
Manager. For this we refer to project management as consisting of “processes”; which is
defined as a process of Defination, Planning Implementation, and Close.
Usually there are two (or more) different legal parties involved in a project. In most cases, it
is the customer (or client) and the contractor or the contractor and the supplier. So it’s a
customer-contractor relationship or a contractor-supplier relationship.
In dealing with project of a large size,there is a “proposal team” who represents the
contractor, who own the project process and has responsibility of the project till the
planning stage (that is he own the project from definition to planning stage (Eg Architect
involved in design and planning) until the contract is signed. Then they hand over the project
to an implementation team. So in the first two phases, a proposal manager is in charge and he
transfers the project responsibility to a project manager for implementation and closure of the
project.
Definition of a Contract: A contract is any agreement between two or more parties where
one party agrees to provide certain deliveries or services, and the other party agrees to pay
for those deliveries or services. Refer to diagram-2 below:
Negotiation…
= CONTRACT
Customer Accepts with
Changes
= + Acceptance byCustomer
New offer by Customer
Therefore, a contract can be defined as an offer by a company and acceptance of the offer by
the customer. Some negotiations do take place between the two parties, in most cases, before
one of them accepts the ‘last’ offer of the other party (but this is not reflected in the contract).
Many a time contracts lead to dispute and end up in a legally binding contract situation.
Therefore the offer has to be prepared with a lot f care.
Contract management activities are the responsibility of the project manager and the entire
project team. However, in case of larger projects which involve large contracts, the best
practice would be to involve a full-time contract manager who would bring in his
professional expertise and experience, takes responsibility for the process and ensure the
contribution of all team members.
Contract preparation involves analysis and evaluation of the other parties’ requirements, a
clear statement of one’s owns requirements and negotiation in order to reach agreement
between the two parties involved. On signing the contract and handing over of the project, it
is the duty of the implementation team to look into a few things. They need to analyse the
contract to ensure that they understand what has been signed and what needs to be
implemented. When preparing and signing the contract during the definition and planning
phase, one anticipates how one would like to implement the project and this is written in the
planning document. This implies that that all project planning is based on how the project
environment would develop over the implementation and closure phase.
Environment may change and one may have to deviate from what was planned and from the
contract (from what had been specified in the contract). Therefore it is always advisable and
also helpful to prepare a project plans and contracts in such a way so that the necessary
changes can be implemented with mutual agreement of all the parties involved.
Therefore a “change management process” is also integrated into the contract.
In many instances,
Change mutualOffer
requirement: agreement is more
of one or not reached because
alternative of difference
solutions: addressedintowards
interpretation
the of
technical, commercial and contractual requirements. However the execution of the change takes
contract partner
place in order to comply with the higher prioritized project requirements or goals. This is called a
‘claim situation’. And a claim management process is also integrated within the contract.
1. Negotiation between the two contract parties: In most cases, disputes are settled after
negotiation between the two parties.
2. Independent Expert Opinion: Both the parties agree to call a ‘neutral third party’ for
determination of specified elements of the contract, interpreting them, and giving an ‘expert
opinion’ on the case.
3. Mini-Trial or Executive Tribunal: This process is often called a ‘mini-trial’. In this process,
the parties make a formal and a brief presentation of their case to a panel of senior
executives from each party and a mediator (or expert) who acts as a neutral chair-person.
After, the presentations by both the parties, the executives meet (with or without the expert) to
negotiate a settlement on the basis of what was presented.
5. Conciliation or Mediation: These are similar to each other. Conciliation refers to a process in
which the third party takes a more activist role in putting forward terms of settlement or
any opinion on the case between both the parties. In case of mediation, the third party
provides support to the parties during negotiation but does not interfere with the content of
the case or its settlement.
6. Adjudication: In this a neutral party acts as the adjudicator. He makes summary binding
decisions on contractual disputes without adhering to the procedures of arbitration.
7. Arbitration: This is a formal process to which both parties agree. There are three
arbitrators who are neutral and independent. They make a formal and binding decision in
the first instance. On an average the process takes two to three years. It follows the
arbitration clauses set by the International Chamber of Commerce (ICC), Paris, and it
requires support of external lawyers.
8. Court Trial: Arbitration is the first instance. After arbitration as the first instance, one can go
for a formal court trialas second and then third instance.
Steps one to six are not legally binding but as disputes do arise in the course of fulfillment of
contract they have to be kept in mind. Arbitration and court trial have a formal character, is
time consuming (takes years) and also expensive, the first six are advisable options and
therefore the parties should arrive at a consensus on which of the options they would opt for in
case dispute do take place.
Claim
Strategy
A cohesive team could be said to be one that works well together, is able to steer clear of
obstacles, also very amicably resolve differences which arise among team members. A strategy
that a manager can adopt a cohesive team is given below:
1. Diversity: While creating a team, create a diverse team consisting of members of various
generation, functional areas and cultures. That would be a team with many ideas and
perspectives while a team with similarity of thoughts would score low on the ‘idea
scale’.
2. Skill Sets: One great team for one project may be unsuitable for another project as the
requirements of that project may differ. Therefore, consider the skill sets of each team
member and the requirement of the project.
3. Managing Team: Project manager has to be involved all through in managing the
project. Help in the decision making process, resolve conflicts when they arise.
4. Clarity of Goals: Every project has a clear set of goals but those goals should be
understood by all team members. Also define which team member is responsible for
which part of the work.
5. Communication: Project manager must be a good communicator and also a good
listener. All differences get sorted out only by effective communication. If there is no
way one can vent his anger, frustration, disappointments, a member would be
discouraged and spoil the entire project team spirit.
6. Motivation:Motivate team members and ensure that you trust them and rely on them.
7. Brain-Storming: Before a project begins, brain storming sessions are advisable as an
individual’s thoughts can be turned into an idea that everyone gets interested in. Group
think often provides a bonding between team members.
But now the question arises...Does your team know where it is heading??
For this we need to create a Team Charter.
1. Context: This is the introduction to the charter. It answers the ‘WHY’. It lays down
why the team was formed, what problem it is trying to solve, how the problem (the
project) fits in with the broader objectives of the organization and the consequences if
the problem is unchecked.
It answers:
What is the problem?
What are the deliverables?
Why is it important?
Eg: The team has to increase co-operation and cohesion between a multinational
company’s business units in different countries.
2. Mission: Mission is at the heart of the Charter. With the mission the team knows
what it has to achieve. Without mission in their sight, each individual starts to pursue
their individual goals.
Eg: Mission is to develop a plan that increases cohesion between different business
units so that they start selling common product range.
3. Goals & Objectives: The mission is converted into measurable goals and objectives.
These act as targets and milestones. Goals and objectives should be SMART-
Specific, Measurable, Attainable, Relevant and Time-bound. Eg: Find out why
countries are not working in tandem.
4. Composition & Roles: Identify that members have the skills necessary to achieve the
objectives. Also ensure that sufficient number of people is there in the team to pursue
the goals. Ensure that the team is well represented from different functional areas.
Analyse mission and objectives to identify what skills and experience are needed,
who therefore is needed in the team, what each is expected to do to achieve the
objective. Therefore, list each member name, and against his name, list his role. Also
identify who would be the team leader.
5. Authority & Empowerment: Identify team members and what they can do and what
they can not do. Also analyse do they have sufficient resources in terms of time, and
money?
6. Resources: Identify the resources available to the team to accomplish their goals.
This includes money, time, equipment and people. Changes to resource need should
be monitored regularly and new members and additional funds may be deployed if
need be.
7. Operations: This lays down how the team will operate on a daily basis. This may be
very detailed or in brief depending upon the situation or project in hand. Often for
large projects they are very detailed and for small project spanning a short time period
they are in brief.
8. Negotiation and Agreement: A good charter is a result of extensive discussion with
all team members. Discussion is essential to ensure
Team charter is creditable
Team charter is achievable
Sufficient resource is available
Also it is signed by all members and commit to the principles it contains and the roles assigned.
The project manager must have a number of skills to get the task completed successfully,
on time and within budget.
Foresight: Vision and foresight is essential. He should be able to see far into the future as to
how the project would evolve overtime and also make contingency plan if he expects something
to go wrong. He should have the ability to see the big picture as well as be able to break it down
into manageable chunks of work through creation of work break down structure..
Communication and Interpersonal Skills:Members of a project are from diverse area,
background, different departments. Good communication and interpersonal skills are essential
features to bind the members of the project team together. It has been observed that ninety
percent of his time is spent in communicating and interacting with team members.
Communication also means he should keep all members informed and updated about the project
and its progress.
Ability to Motivate: He should have a positive mindset, be motivated all the time and also have
the ability to motivate his team members to pursue project goals.
Planning and Budget Management: This is also an essential ingredient. Budget refers to
budgeting of time, money and also people resources. Therefore he should be efficient as well as
organised. He must follow schedules; have time management skills and the ability to meet
deadlines.A good project manager will set achievable deadlines for their team and understands
what steps to take and how to get there.
Emotional and Practicality: He should be passionate and emotional about the project at hand
but should also be practical to see it through and secure timely funding.
Empathy: He should be good at managing people, should trust team members and also secure
their trust. He would be able to secure their trust and confidence only when he is empathetic.
Honest &Transparency: He should be a person team members can rely on. He should be
transparent about his work. A great project manager always means what they say, and approach
everything with honesty so their team members know that they can trust them. He should also
have courage to admit his mistakes.
Knowledge: He must have technical knowledge and also knowledge about the project at hand.
Then the team members would look up to him. This helps command respect and authority. Often
project managers have lack of understanding of tools and he lacks understanding of how project
management should work. The skill needed for executing a project is often lacking. Often
various tools like PERT, CPM, Gantt charts, leveling diagrams are often lacking in a project
manager.
....................... ....................... ................