Project Name: QUEEN ANDREA Order Number: xxxx No. of days: 15d
Project Manager: Fernando Remolina Project Start: 21st July 2016 Project Finish: 4th August 2016
TIME COST FORECAST MATERIAL CONTRACTOR
DATE OF MONITORING Project Sales Progress PV EV AC SPI CPI EAC ETC MPI SC -CM
Thu 21st July $ 620,000.00 0% 0 0 0 0 0 0 0 0 0%
Mon 25th July $ 622,000.00 16% 3177 1831 1198 0.58 1.53 12,319.91 11,121.64 0.06 55%
Wed 27th July $ 625,000.00 32% 4879 3612 2400 0.74 1.51 9,591.09 7,191.41 0.09 55%
Fri 29th July $ 625,000.00 53% 7035 6009 3267 0.85 1.84 6,841.10 3,574.18 0.18 70%
Mon 1st August 9871
Wed 3rd August 10779
Fri 4th August 11347
PV EV AC
12000
10779 11347
9871
10000
8000
Man Hours
7035
6000
6009
4879
4000
3177 3612
3267
2000 1831 2400
1198
0 0
Thu 21st July Mon 25th July Wed 27th July Fri 29th July Mon 1st August Wed 3rd August Fri 4th August
Monitoring Date