EARNED VALUE MANAGEMENT REPORT

Project Name: QUEEN ANDREA Order Number: xxxx No. of days: 15d
Project Manager: Fernando Remolina Project Start: 21st July 2016 Project Finish: 4th August 2016
TIME COST FORECAST MATERIAL CONTRACTOR
DATE OF MONITORING Project Sales Progress PV EV AC SPI CPI EAC ETC MPI SC -CM
Thu 21st July $ 620,000.00 0% 0 0 0 0 0 0 0 0 0%
Mon 25th July $ 622,000.00 16% 3177 1831 1198 0.58 1.53 12,319.91 11,121.64 0.06 55%
Wed 27th July $ 625,000.00 32% 4879 3612 2400 0.74 1.51 9,591.09 7,191.41 0.09 55%
Fri 29th July $ 625,000.00 53% 7035 6009 3267 0.85 1.84 6,841.10 3,574.18 0.18 70%
Mon 1st August 9871
Wed 3rd August 10779
Fri 4th August 11347

EARNED VALUE MANAGEMENT CHART - MAN HOURS

PV EV AC

12000
10779 11347
9871
10000

8000
Man Hours

7035

6000
6009
4879

4000
3177 3612

3267
2000 1831 2400

1198
0 0
Thu 21st July Mon 25th July Wed 27th July Fri 29th July Mon 1st August Wed 3rd August Fri 4th August

Monitoring Date