DETAIL A

Note :
- Detail A is equipped with a high capacity pump.
- Should heavy downpour, water from open area and front of
Workshop J10 is expected to flow into detail A.
- All water shall be pumped out to New Drainage System via Drain
Outlet A.
DETAIL B

Note :
- Drainage enlargement completed of Detail B.
- Should heavy downpour, water from the side of Workshop J10 is
expected to flow into Detail B.
- All water shall flow out to the New Drainage System via Drain
Outlet C.
DETAIL C

Note :
- Detail C is equipped with a high capacity pump.
- Water within the perimeter of Workshop J10 is expected to flow in
to Detail C
- All water shall be pumped out to New Drainage System via Drain
Outlet E.
DETAIL D

Note :
- Detail D is equipped with a high capacity pump.
- Should heavy downpour, water from open area is expected to flow
into detail D.
- All water shall be pumped out to New Drainage System via Drain
Outlet F.
DETAIL E

Note :
- 7 New Drainage Lines (A-G) flow discharging of water to seafront.