Best Practic Instal New Radar TGsystem LNG and Overfilling - 2
Best Practic Instal New Radar TGsystem LNG and Overfilling - 2
Hans Manner
Nicolas Odru
Industry Trends
Engineering standards and guidelines
What equipment do I need?
How do I get it installed on my tank?
How do I get the readings in the control
room?
Safety & Overfill Prevention
Radar
Continuous
Redundancy
Safety Mechanical
IEC 61508
Point Switch
API 2350
Closed systems
Wireless
Openness
Internet
[File Name or Event]
Emerson Confidential
Rosemount Tank Radar AB Confidential
27-Jun-01, Slide 5
Tank Equipment
Look for
– Man ways
– Other nozzles
– Gauge hatches
– Still Pipes
Radar
Temp Sensor
Still Pipes
fitted in
existing
access
hatch
Still Pipe
fitted in
existing
access
hatch
– Roof mounting
• Close to the tank wall to avoid roof flexing influence
– Still pipe
• Slotted
• Fixed at the bottom end
Same location
as the Radar
Fixed Roof tank
Same location
as the Radar
Floating Roof
Tank
Floating Roof
Tank
Roof
penetration
thru a rubber
gasket
Support and
cabling at the
platform level
At Grade Level
Back lit
Done!
[File Name or Event] Mount the radar antenna Mount the new Gauge 32
Emerson Confidential
27-Jun-01, Slide 32
and connect the wiring
Rosemount Tank Radar AB Confidential
How to connect a new system to the Control Room
OLD NEW
Intrinsically
Safe
LAX Airport
[File Name or Event]
Emerson Confidential
Rosemount Tank Radar AB Confidential 35
27-Jun-01, Slide 35
How to connect a new system to the Control Room
Wireless
Wireless
Wireless
Well proven
On 2500+ tanks
Robust
Safe
IEC 62591 standard
9 years at 1 minute
update rate
Min update rate of
1s for control
9 years at 1 minute
update rate
High
Signal Quality
Low
Time
Level PV
Signal quality
[File Name or Event]
Emerson Confidential
Rosemount Tank Radar AB Confidential
27-Jun-01, Slide 43
Rosemount Level Wireless
2160 Fork Switch & 3308 Guided Wave Radar
Inaccessible or uneconomic alarms:
– Fast installation of additional instruments
Intranet
Internet
Portable
devices
Open protocols
OPC
Modbus
WebServer
Time In Use
Emergency
Safety layer
Shut Down
Process
Process control layer
Shutdown
Advantages : To be considered :
Independent safety system ≈ One device for each level
Not affected by process alarm
changes ≈ Power supply needed for
Different types of on/off alarm electronics
output available ≈ No separate fault signal
Functionality is less dependant output
on configuration, mechanical
installation and start up
-70 +260°C
DFF* 1400 Hz
[File Name or Event] *DFF : Dry Forks Frequency
Emerson Confidential Sensor switching limits are percentage of the calibrated frequency
27-Jun-01, Slide 57
2130 – Self Check available on all
Cassettes :
Direct Load
PNP
Relay
Fault Relay*
Namur
8-16mA*
+ -
ION = 15...17 mA
PSU- +
Heartbeat LED On
Dry = On
+ -
IOFF = 7.5...8.5 mA
PSU- +
Dry = On
+ -
IFAULT < 3.7 mA
PSU- +
Dry = On
Dual operation
Gauging
Overfill Alarm
Separated
”Built in Spare”
644 Temperature
3051S Pressure 2120/2160 Transmitter with Single
Transmitter Liquid Level switch Point Temperature Sensor
-3
Old (R85:1998)
-4
-check
Recent projects system solutions, Rex radar gauges combined with Whessoe LTDs
Cheniere - Sabine Pass – Receiving terminal, Louisiana, US. 5 tanks
Fluxys - Zeebrügge - Existing receiving terminal, Belgium
Exxon - Golden Pass LNG – Receiving terminal, Texas US. 5 tanks
Woodside - Pluto LNG – New export terminal. 2 tanks in Ph I.
PTT LNG – Map Ta Put – New receiving terminal
AGA – Nynashamn LNG – New receiving terminal. 1 tk Ph. 1
Chevron - Gorgon – New tanks at export site, 2 LNG + 4 Condensate tanks. Totally 24
[Fileradars
Name or Event]
Emerson Confidential
Polskie LNG – New receiving terminal, 2 tks.
27-Jun-01, Slide 83
Rosemount Tank Radar AB Confidential 83
Rosemount LNG Radar Benefits
No moving parts
No re-calibration
No maintenance
SIL2 / SIL3 safety functions
Built in High Alarm
On-Line verification during operation inside the tank
Custody Transfer Accuracy
Conformance to API, OIML, ISO and other standards
Proven Technology
Many excellent references on LNG and LPG
Anything for a single gauge to a complete LNG Management System
Loop 1
Loop 2
TANK
N°1
LNG Manager
TANK N°1
Loop 1 Serial link
Loop 2
9510
20 mA loop / RS232C DCS
TANK N°2
Loop 1
Serial link LNG Roll-Over
Predictor
Loop 2
9510
20 mA loop / RS232C
LNG Manager
Nynashamn Sweden
Gorgon Australia
Polskie LNG