Professional Documents
Culture Documents
Sensitivity Analysis of Hole Cleaning
Sensitivity Analysis of Hole Cleaning
measured. Based on such information, the average in-situ velocity test condition and accuracy, the sampling time can be specified.
for each phase can be determined.
The flow rate is measured by two mass-flow meters. The Mathematical Models
accuracy of the flow-rate measurement is +/-1.0%. The mass-flow
meters are equipped with a densitometer feature that can measure Prediction of Cuttings-Bed Height. The prediction of the
the slurry density. The cuttings injection rate is calculated from cuttings-bed dynamics is important in the design process for
the cuttings injection concentration and the slurry flow rate. efficient drilling operations. In some situations, the flow rate
The instrumentation required for the experiments consist of the required to completely remove the cuttings bed may be so high
following items: that wellbore erosion would occur or the flow rate cannot be
achieved due to pressure limitations. In such cases, it is possible to
1. One airflow meter–thermal mass flow meter, Kurz drill in subcritical conditions, provided the limit on drag is not
502FT. exceeded for the slide drilling. However, prior to tripping, the
2. Two MicroMotion Mass Flow Meter–DS300. wellbore should be flushed clean of all cuttings by circulating for
3. Two Omega pressure transducers located at both inlet some time, perhaps with pills of special drilling fluid. Unless the
and outlet of the test section to determine absolute interaction of the fluids and the cuttings can be predicted then this
pressures at both locations. process is practically an act of faith.
4. One Rosemount differential pressure transducer to We define the “critical deposition velocity” as the average
measure the pressure drop across the test section. velocity in an inclined conduit that can prevent the formation of a
5. One Omega temperature probe at the inlet of the test stationary bed of solids in the lower part of the conduit. In
section. general, for slide drilling with two-phase fluids, the critical
6. Four pneumatic actuating 2-fin. ball valves, 1 velocity is a function of the variables given in Eq. 1.
pneumatic actuating 3-in. butterfly valve, and 1
pneumatic actuating 5-in. knife gate valve.
7. One airflow sequencing valve. vc = f [d p , d1, d2 , hb ,Cv ,(ρs − ρm )g, ρm , µm , β , HL,ε ]. .......... (1)
8. One Kates airflow rate controller.
9. Two 2-in.x2-in. series 75 red valve manual pinch valves. All these variables are defined in the nomenclature. In this
10. One 1-in. bubble tight Meridian check valves. study, the average in-situ liquid velocity at a specific
11. An inclinometer to measure the angle of the test condition was treated as the critical deposition velocity at the
section. same condition. Based on the Buckingham Π theorem,
The data collected from the above listed instrumentation is several dimensionless groups can be defined, and a semi-
recorded with Labview™, a data-acquisition program. Depending empirical correlation was developed to predict the critical
on the sample speed of the data logger and the requirements of the deposition velocity.
For a flow rate of gas and liquid lower than the critical flow dVs
rate, cutings will start to deposit in the wellbore. The cuttings will = qm (C0 − C 0 e − β nt ). ...................................... (6)
grow until the velocity in the open area above the bed is equal to dt
the critical deposition velocity. Steady state is achieved whenever When the circulation mode is used to clean the hole, C0=0,
the cuttings bed will neither erode nor build. Then the velocity in − βnt
the open area above the bed is assumed to be equal to the critical therefore, with boundary condition t → ∝, e → 0 and Vs →
velocity4 0, the Eq. 6 can be integrated as
Vs q
vc = vopen . .............................................................(2) = exp − m0 C 0 t . ......................................... (7)
0
Vs Vs
The bed height can be found based on Eq. 2.
Based on Eq. 7, the hole-cleaning time can be predicted as:
Prediction of Hole-Cleaning Time With Circulation Mode.
There are two basic hole-cleaning modes: circulation mode and Vs0 Vs0
wiper-trip mode. For the circulation mode, the drilling process t= ln . ............................................... (8)
C 0 qm Vs
stops and the drill bit is pulled just off bottom, then fluids are
circulated through the drill pipe down to the bottom of the hole Eq. 8 is a simple model that shows how each individual
and back to surface through the annulus. The circulated fluid parameter affects the hole cleaning time. The usefulness of this
transports the cuttings back to surface. For the wiper-trip mode, model depends on whether the time constant, βn, is easy to predict
the drill pipe is pulled back along the wellbore, and at the same based on a mechanistic analysis of the process. Alternatively, the
time, fluid is circulated. dependencies of the time constant may be assessed from
For the horizontal well section with length L, n sections are experimental data or the cuttings concentrations. C1 to Cn, can be
divided as shown in Fig. 2. In each subsection, the cuttings mass directly predicted based on the correlation (Eq. 1) developed in
balance equation can be expressed as: this study.
dV1 Prediction of Wiper-Trip Speed. For the wiper-trip hole-
= qm (C0 − C1 ) ............................................. (3a) cleaning process, it is assumed that a certain cuttings volume
dt
concentration, C, can be supported by the circulated fluid. Then
dV2 the optimum wiper-trip speed can be predicted as:
= qm (C1 − C2 ) .............................................(3b)
dt Cqm
vw = . ............................................. (9)
(1 − C )Cb Abed
dVn
= qm (Cn −1 − Cn ). ......................................... (3c) For simplicity, assume that when the drillpipe is being pulled
dt
back, the bit/circulation valve will only disturb the local flow
Experimental observations by several researchers13,21,23 suggest pattern. The cuttings adjacent to the bit will be completely
that the sand concentration during the cuttings-bed erosion fluidized while the cuttings in the other sections will be
processes can be represented by a simple logarithmic expression if transported with circulation mode. If the concentration of
the circulation fluid rate was high enough to clean the hole fluidized cuttings is greater than C, then a proportion of the
completely. cuttings will deposit behind the bit. More discussion about the
wiper-trip hole cleaning is included in the section of hole cleaning
Ci = C 0 e − βi t , i=1 to n. ..........................................(4) time prediction in this paper and in Ref. 24.
the in-situ liquid velocity is larger than the critical value, the the annulus of the horizontal wellbore. The experimental
carrying capacity increases dramatically. The dependency of observations in this study also confirm that there is a stationary
carrying capacity on the in-situ liquid velocity results in a cuttings bed in the annulus for the horizontal or near-horizontal
nonlinear relationship between hole cleaning time and liquid flow wellbore (60–90°).
rate. More detailed discussion can be found in the section of hole-
Effect of Inclination Angle. Previous studies3–5 have established
cleaning time prediction.
the importance of the effect of inclination angle on cuttings
As the in-situ liquid velocity approaches the critical value, all
transport. In general, the toughest section for hole cleaning is the
cuttings transport is by saltation. Particles are stripped from the
“build” section rather than the vertical or the horizontal section.
surface of the bed and tumble along its top surface. The shear
The experimental results in this study support the above result and
stress at the interface between cuttings bed and fluid and the
are shown in Fig. 9. The figure shows that for different inclination
transfer of momentum to the particles by small-scale turbulent
angles, the minimum in-situ liquid velocity varies. The highest
eddy currents are the controlling factors. When saltation is the
minimum in-situ liquid velocity is needed around 60°. This is
only mechanism of transport, the effective removal rate is too low
because the cuttings bed tends to become unstable and slide
for economic purposes.
downward along the wellbore. Thus, hole cleaning is most
difficult at approximately 60°. Therefore, in the well-planning
Effect of ROP. Fig. 8 displays the cuttings-bed height in the stage, it is better to avoid tangent sections around 60°. Build rates
horizontal wellbore of 5-in. open hole drilled with 23/8-in. pipe at should be kept as tight as feasible, with 15 to 20°/30m being
different ROPs. This figure indicates that the cuttings bed is suggested as optimum.25
deeper for a higher ROP than it is for a lower ROP with the same Based on the correlation developed in this paper, Fig. 10
circulated fluid rate. It also shows that for a given ROP, higher displays the cuttings-bed height vs. inclination angle for a
circulated fluid flow rate results in a lower bed height. When the wellbore of 5-in. openhole and 23/8-in. drillpipe with the liquid
ROP is constant, increasing the circulation flow rate results in a pump rate of 0.5 m3/min. This figure shows that increasing the
lower cuttings concentration and a decreasing of the bed height. If inclination angle results in a higher cuttings bed. The study of
the circulated liquid flow rate is fixed, increasing ROP results in a Tomren3 reached the same conclusion.
higher cuttings concentration and a higher bed height.
Fig. 8 also indicates that for the practical values of liquid rates
Effect of Circulation Fluid Properties. The cuttings dynamic
(<0.6 m3/min), there is always a cuttings bed covering the drillpipe in
behavior in a flowing media is not only affected by cuttings