You are on page 1of 8

Sensitivity Analysis of Hole Cleaning

Parameters in Directional Wells


Jeff Li, SPE, and Scott Walker, SPE, BJ Services & Co.
Summary
drop. However, such models are not able to model cuttings
In this study, 600 tests were conducted and a new computer transport at medium inclination angles (35–55°) due to the chaotic
program was developed for the prediction of cuttings transport in motion of the cuttings.1 Furthermore, there are various unknown
the multiphase system (gas+liquid+cuttings). The sensitivity of parameters, such as friction coefficients and a turbulent diffusion
cuttings bed height with respect to liquid/gas volume flow rate coefficient, involved in the models. These coefficients have to be
ratio, in-situ liquid velocity, rate of penetration (ROP), inclination determined based on comprehensive test results. There is still a gap
angle, and circulation fluid properties was conducted. The hole- between the model development and field application.21
cleaning time with both circulation mode and wiper trip is also Most of the previous cuttings transport studies in the drilling
discussed. The results from the sensitivity analysis presented in industry mainly focused on finding the minimum critical velocity
this paper indicate, first, that the fraction of the circulation liquid and bed height or total cuttings concentration in the wellbore
has a significant impact on the cuttings transport in underbalanced annulus for conventional rotary drilling with mud fluids. Recently,
drilling with gasified fluids; second, that among different Rodriguez22 conducted solids-transport tests with gasified fluids in
variables, the in-situ liquid velocity is the most important variable near-horizontal wellbores. Based on the concept of critical
for cuttings transport; and, finally, the hole-cleaning time velocity, he developed correlations to predict the minimum air and
decreases nonlinearly with increasing fluid circulation rate. water flow rates required in order to avoid the formation of a
stationary solids bed. However, this concept still lacks
Introduction information related to cuttings transport with two-phase fluids and
Cuttings transport has a major impact on the economics of the the prediction of the hole-cleaning time. In fact, there are different
drilling process. Problems that may be caused by poor hole transport mechanisms during the bed erosion (ROP=0) process
cleaning include stuck pipe, reduced weight on bit leading to and during cuttings transport while drilling (ROP>0).21
reduced ROP, transient hole blockage leading to lost circulation In this study, a comprehensive experimental test of cuttings
conditions, excessive drill pipe wear, extra cost for special mud transport with two-phase fluids was conducted. The effect of
additives, and wasted time by wiper-trip maneuvers. liquid/gas volume flow rate ratio, in-situ liquid velocity, ROP,
Sand production is a common problem faced by many of the oil inclination angle, and circulation fluid properties on cuttings
producers, especially in the heavy oil industry. Several cleanout transport was investigated. However, this paper’s main focus is on
options have been developed over the years, employing a number of angles close to horizontal. Based on the test results, a computer
different technical approaches. One of most common options is program was developed and the sensitivity analysis of cuttings
running in with coiled tubing and circulating the sand out with a transport parameters, such as cuttings-bed height and hole-
liquid or gasified liquid. An important consideration in designing cleaning time, was conducted.
cleanout operations is the proper selection of the pump rate and
circulation fluid. These parameters should be optimized in order to Experimental Setup
transport the sand to surface with the least cost. High circulation The test apparatus (Fig. 1) was designed and constructed in
rates can cause higher costs and other operational problems. accordance with the following requirements.
Over the past two decades, considerable effort has been expended 1. Annular-flow steady-state conditions must prevail in
into the research of cuttings transport in deviated wells with a every test case.
single-phase flow. A large number of experiments have been 2. The apparatus must allow the selection of the most
conducted to study the effects of various parameters on cuttings-bed important drilling variables (gas and liquid flow rates,
formation. A brief literature review was given by TUDRP.1–2 well inclination, annular geometry configuration, cuttings
Experimental research on cuttings transport in inclined wells has concentration, and drill pipe size/eccentricity, etc.).
been conducted using flow loops at the U. of Tulsa,3–6 the U. of The flow loop, shown in Fig. 1, was used throughout this
Heriot-Watt,7 Mobil R&D Corp., M-I Drilling Fluid Co., BP project. The loop consists of a 20-ft transparent Lexan pipe with a
Research Center, Inst. Francais du Petrole, and Petrobras.8–12 5-in. inner diameter simulating the openhole and a 23/8-in. steel
Several hole-cleaning correlations/models have been developed.4–6,13 inner pipe to simulate a drillpipe. The inner pipe is positioned on
Larsen,4 Jalukar,5 and Bassal6 conducted a total of 2,076 tests using the the bottom of Lexan pipe to simulate the worst case for the
TUDRP’s 5-in. and 8-in. flow loops. Based on the test results, they cuttings transport (eccentricity=100%).
developed correlations to predict the critical velocity and cuttings-bed The loop is mounted on a rigid guide rail and can be inclined at
height. The correlations provide a means of analyzing cuttings any angle in the range of 0 to 100° from vertical. The slurry is
transport as a function of operating conditions (flow rate, penetration stored in a 1 m3 tank. The slurry is agitated with a mixer driven by
rate, and rotation speed), mud properties (density, rheology), well a hydraulic motor. The slurry is pumped into the annulus by a
configuration (angle, hole size, and pipe size), and cuttings size. centrifugal pump No. 1 with a capacity of approximately 800
Adari et. al.13 developed empirical models to correlate the cuttings- liter/min. Compressed air is introduced into the slurry flow before
bed height and the hole-cleaning time to drilling fluid properties and entering the test section. A simple open tank is used to separate
flow rate for the wellbore near the horizontal position. the gas from the slurry, and the slurry left in the separator is
Similar to the models developed in the mining industry,14–16 circulated back to the storage tank with pump No. 2. When the
layer mechanistic models to predict the bed height and pressure flow reaches a steady state condition (two mass flow meter
readings are the same), the pneumatic actuating valves isolate the
_____________________________________
test section. Flow is maintained in the remainder of the loop
Copyright  2001 Society of Petroleum Engineers through a bypass line. The cuttings-bed height, cuttings volume,
This paper (SPE 74710) was revised for publication from paper SPE 54498, first
water, and gas volumes in the annulus of the test section can be
presented at the 1999 SPE/ICoTA Coiled Tubing Roundtable, Houston, Texas,
25-26 May. Original manuscript received for review 10 April 2000. Revised manuscript
received 2 May 2001. Manuscript peer approved 20 May 2001.

356 December 2001 SPE Journal


Fig. 1—Schematic of cuttings transport flow loop.

measured. Based on such information, the average in-situ velocity test condition and accuracy, the sampling time can be specified.
for each phase can be determined.
The flow rate is measured by two mass-flow meters. The Mathematical Models
accuracy of the flow-rate measurement is +/-1.0%. The mass-flow
meters are equipped with a densitometer feature that can measure Prediction of Cuttings-Bed Height. The prediction of the
the slurry density. The cuttings injection rate is calculated from cuttings-bed dynamics is important in the design process for
the cuttings injection concentration and the slurry flow rate. efficient drilling operations. In some situations, the flow rate
The instrumentation required for the experiments consist of the required to completely remove the cuttings bed may be so high
following items: that wellbore erosion would occur or the flow rate cannot be
achieved due to pressure limitations. In such cases, it is possible to
1. One airflow meter–thermal mass flow meter, Kurz drill in subcritical conditions, provided the limit on drag is not
502FT. exceeded for the slide drilling. However, prior to tripping, the
2. Two MicroMotion Mass Flow Meter–DS300. wellbore should be flushed clean of all cuttings by circulating for
3. Two Omega pressure transducers located at both inlet some time, perhaps with pills of special drilling fluid. Unless the
and outlet of the test section to determine absolute interaction of the fluids and the cuttings can be predicted then this
pressures at both locations. process is practically an act of faith.
4. One Rosemount differential pressure transducer to We define the “critical deposition velocity” as the average
measure the pressure drop across the test section. velocity in an inclined conduit that can prevent the formation of a
5. One Omega temperature probe at the inlet of the test stationary bed of solids in the lower part of the conduit. In
section. general, for slide drilling with two-phase fluids, the critical
6. Four pneumatic actuating 2-fin. ball valves, 1 velocity is a function of the variables given in Eq. 1.
pneumatic actuating 3-in. butterfly valve, and 1
pneumatic actuating 5-in. knife gate valve.
7. One airflow sequencing valve. vc = f [d p , d1, d2 , hb ,Cv ,(ρs − ρm )g, ρm , µm , β , HL,ε ]. .......... (1)
8. One Kates airflow rate controller.
9. Two 2-in.x2-in. series 75 red valve manual pinch valves. All these variables are defined in the nomenclature. In this
10. One 1-in. bubble tight Meridian check valves. study, the average in-situ liquid velocity at a specific
11. An inclinometer to measure the angle of the test condition was treated as the critical deposition velocity at the
section. same condition. Based on the Buckingham Π theorem,
The data collected from the above listed instrumentation is several dimensionless groups can be defined, and a semi-
recorded with Labview™, a data-acquisition program. Depending empirical correlation was developed to predict the critical
on the sample speed of the data logger and the requirements of the deposition velocity.

December 2001 SPE Journal 357


Fig. 2—Mass Balance for hole-cleaning prediction.

For a flow rate of gas and liquid lower than the critical flow dVs
rate, cutings will start to deposit in the wellbore. The cuttings will = qm (C0 − C 0 e − β nt ). ...................................... (6)
grow until the velocity in the open area above the bed is equal to dt
the critical deposition velocity. Steady state is achieved whenever When the circulation mode is used to clean the hole, C0=0,
the cuttings bed will neither erode nor build. Then the velocity in − βnt
the open area above the bed is assumed to be equal to the critical therefore, with boundary condition t → ∝, e → 0 and Vs →
velocity4 0, the Eq. 6 can be integrated as
Vs  q 
vc = vopen . .............................................................(2) = exp  − m0 C 0 t  . ......................................... (7)
0
Vs  Vs 
The bed height can be found based on Eq. 2.
Based on Eq. 7, the hole-cleaning time can be predicted as:
Prediction of Hole-Cleaning Time With Circulation Mode.
There are two basic hole-cleaning modes: circulation mode and Vs0  Vs0 
wiper-trip mode. For the circulation mode, the drilling process t= ln  . ............................................... (8)
C 0 qm  Vs 
stops and the drill bit is pulled just off bottom, then fluids are
circulated through the drill pipe down to the bottom of the hole Eq. 8 is a simple model that shows how each individual
and back to surface through the annulus. The circulated fluid parameter affects the hole cleaning time. The usefulness of this
transports the cuttings back to surface. For the wiper-trip mode, model depends on whether the time constant, βn, is easy to predict
the drill pipe is pulled back along the wellbore, and at the same based on a mechanistic analysis of the process. Alternatively, the
time, fluid is circulated. dependencies of the time constant may be assessed from
For the horizontal well section with length L, n sections are experimental data or the cuttings concentrations. C1 to Cn, can be
divided as shown in Fig. 2. In each subsection, the cuttings mass directly predicted based on the correlation (Eq. 1) developed in
balance equation can be expressed as: this study.
dV1 Prediction of Wiper-Trip Speed. For the wiper-trip hole-
= qm (C0 − C1 ) ............................................. (3a) cleaning process, it is assumed that a certain cuttings volume
dt
concentration, C, can be supported by the circulated fluid. Then
dV2 the optimum wiper-trip speed can be predicted as:
= qm (C1 − C2 ) .............................................(3b)
dt Cqm
vw = . ............................................. (9)
(1 − C )Cb Abed
dVn
= qm (Cn −1 − Cn ). ......................................... (3c) For simplicity, assume that when the drillpipe is being pulled
dt
back, the bit/circulation valve will only disturb the local flow
Experimental observations by several researchers13,21,23 suggest pattern. The cuttings adjacent to the bit will be completely
that the sand concentration during the cuttings-bed erosion fluidized while the cuttings in the other sections will be
processes can be represented by a simple logarithmic expression if transported with circulation mode. If the concentration of
the circulation fluid rate was high enough to clean the hole fluidized cuttings is greater than C, then a proportion of the
completely. cuttings will deposit behind the bit. More discussion about the
wiper-trip hole cleaning is included in the section of hole cleaning
Ci = C 0 e − βi t , i=1 to n. ..........................................(4) time prediction in this paper and in Ref. 24.

Summation of Eqs. 3a through 3c allows Vs=V1+V2+…+Vn Results and Discussion


results in
More than 600 tests have been conducted using 20/40 (USA
mesh) Carbolite and 20/40 Frac sand at various concentrations
dVs over a range of liquid and gas rates at angles of 33, 45, 60, 75, and
= qm (C0 − Cn ). ..............................................(5) 90°. The results and discussion in this paper focus on the
dt
situation in which the drillpipe is positioned at the bottom of the
Substituting Eq. 4 into Eq. 5 results in open hole (eccentricity=100%).

358 December 2001 SPE Journal


Fig. 3—Predicted bed height based on the correlation vs. the Fig. 4—Predicted error of bed height based on the correlation
measured bed height at different wellbore inclination angles for different wellbore inclination angles.
3
(5-in. openhole and 2 /8-in. pipe; eccentricity = 100%; for
air/water/sand tests, the data only were collected at the rate, increasing gas volume flow rate results in a lower bed height.
horizontal wellbore). However, the constant liquid flow rate curves are flatter than the
constant gas volume flow rate curves. This indicates that changing
Based on the test results, a correlation was developed to predict the liquid flow rate has more of an effect on the bed height than
the critical velocity. With Eq. 2, the bed height can be predicted the gas volume flow rate. Rodriguez’s experimental observation28
for a given condition. The input information of particles and also confirms that cuttings are only transported by the liquid phase.
circulation fluid properties is listed in Table 1. Fig. 3 displays the The range of liquid fraction may be limited because of the need
predicted cuttings-bed height vs. the measured cuttings bed to maintain underbalanced conditions or due to pressure
height. This figure shows that the prediction accuracy of the bed limitations of the drill pipe. Therefore, a common job design
height is very good. The prediction errors are less than ±10% for requirement is to predict the critical gas volume fraction beyond
most cases (Fig. 4). which the hole cleaning may be significantly impaired. Fig. 6
The critical deposition velocity correlation developed in this indicates the effect of gas volume fraction on the bed height. For a
study can be used by the field drilling engineers to optimize the constant total flow rate, increasing gas volume fraction results in a
cuttings transport for a particular underbalanced drilling job with higher bed height, especially when the gas volume fraction is
the slide drilling mode. In addition, the correlation can be used to higher than 0.5. That means that if the gas volume fraction is
estimate the cuttings concentrations, C1 to Cn, in Eq. 3 at any higher than 50%, the cuttings carrying capacity of gas-liquid
particular time. Therefore, the time history of the cuttings-bed mixtures significantly decreases.
height or cuttings-carrying capacity during the hole-cleaning
process can be predicted, and the efficiency of hole cleaning can Effect of Annular In-Situ Liquid Velocity. Regardless of all
be evaluated. other factors, the liquid flow rate dominates the cuttings transport
There are many variables that can affect cuttings transport in process. The most important variable is the in-situ liquid velocity
the drilling process. However, only the effect of the following owing to the combined effects of higher density and viscosity of
variables on cuttings transport are investigated in this study. the liquid phase and the greater contact of the cuttings with liquid
• Liquid/gas volume flow rate ratio. phase. Fig. 7 shows how the in-situ liquid velocity nonlinearly
• Annular in-situ liquid velocity. affects the carrying capacity. When the in-situ liquid velocity is
• ROP less than a critical value, the carrying capacity is negligible. When
• Hole inclination angle.
• Properties of circulation fluid.

Effect of Liquid/Gas Volume Flow Rate Ratio. The fraction of


the circulation liquid has a significant impact on the cuttings-
bed height in underbalanced drilling with gasified fluids. Based
on the test results, Fig. 5 shows how the total flow rate (liquid
flowrate + in-situ gas volume rate) affects the cuttings bed height.
In Fig. 5, L100 represents liquid flow rate of 100 liters/min, and
G100 represents 100 liters/min of in-situ gas volume flow rate.
There is a similar meaning for L200 to L600 and G200 to G600.
For a given gas volume flow rate, increasing liquid flow rate
results in a lower bed height. Similarly for a given liquid flow

Fig. 5—Effect of liquid/gas volume flow rate on bed height for


3
the horizontal wellbore of 5-in. openhole and 2 /8-in. pipe with
1.5% of cuttings injection concentration, eccentricity = 100%.

December 2001 SPE Journal 359


Fig. 6—Effect of gas volume fraction on bed height for the (5 Fig. 7—Effect of in-situ liquid velocity on cuttings carrying
3 3
horizontal wellbore of 5-in. openhole and 2 /8-in. pipe 1.5% of capacity at the horizontal wellbore 5-in. openhole and 2 /8-in.
cuttings injection concentration, eccentricity = 100%. drillpipe, eccentricity = 100%).

the in-situ liquid velocity is larger than the critical value, the the annulus of the horizontal wellbore. The experimental
carrying capacity increases dramatically. The dependency of observations in this study also confirm that there is a stationary
carrying capacity on the in-situ liquid velocity results in a cuttings bed in the annulus for the horizontal or near-horizontal
nonlinear relationship between hole cleaning time and liquid flow wellbore (60–90°).
rate. More detailed discussion can be found in the section of hole-
Effect of Inclination Angle. Previous studies3–5 have established
cleaning time prediction.
the importance of the effect of inclination angle on cuttings
As the in-situ liquid velocity approaches the critical value, all
transport. In general, the toughest section for hole cleaning is the
cuttings transport is by saltation. Particles are stripped from the
“build” section rather than the vertical or the horizontal section.
surface of the bed and tumble along its top surface. The shear
The experimental results in this study support the above result and
stress at the interface between cuttings bed and fluid and the
are shown in Fig. 9. The figure shows that for different inclination
transfer of momentum to the particles by small-scale turbulent
angles, the minimum in-situ liquid velocity varies. The highest
eddy currents are the controlling factors. When saltation is the
minimum in-situ liquid velocity is needed around 60°. This is
only mechanism of transport, the effective removal rate is too low
because the cuttings bed tends to become unstable and slide
for economic purposes.
downward along the wellbore. Thus, hole cleaning is most
difficult at approximately 60°. Therefore, in the well-planning
Effect of ROP. Fig. 8 displays the cuttings-bed height in the stage, it is better to avoid tangent sections around 60°. Build rates
horizontal wellbore of 5-in. open hole drilled with 23/8-in. pipe at should be kept as tight as feasible, with 15 to 20°/30m being
different ROPs. This figure indicates that the cuttings bed is suggested as optimum.25
deeper for a higher ROP than it is for a lower ROP with the same Based on the correlation developed in this paper, Fig. 10
circulated fluid rate. It also shows that for a given ROP, higher displays the cuttings-bed height vs. inclination angle for a
circulated fluid flow rate results in a lower bed height. When the wellbore of 5-in. openhole and 23/8-in. drillpipe with the liquid
ROP is constant, increasing the circulation flow rate results in a pump rate of 0.5 m3/min. This figure shows that increasing the
lower cuttings concentration and a decreasing of the bed height. If inclination angle results in a higher cuttings bed. The study of
the circulated liquid flow rate is fixed, increasing ROP results in a Tomren3 reached the same conclusion.
higher cuttings concentration and a higher bed height.
Fig. 8 also indicates that for the practical values of liquid rates
Effect of Circulation Fluid Properties. The cuttings dynamic
(<0.6 m3/min), there is always a cuttings bed covering the drillpipe in
behavior in a flowing media is not only affected by cuttings

Fig. 9—Effect of inclination angle on the minimum in-situ liquid


Fig. 8—Effect of ROP on bed height for the horizontal wellbore velocity that corresponds to the zero carrying capacity (5-in.
3
of 5-in. openhole and 2 /8-in. pipe, pipe eccentricity = 100%, 3
openhole and 2 /8-in. drillpipe, eccentricity = 100%, gas volume
gas volume fraction = 0%. fraction = 0%).

360 December 2001 SPE Journal


Fig. 11—Sensitivity of circulation time ratio vs. removed
cuttings volume ratio based on the lump model.
Fig. 10—Effect of inclination angle on bed height for the
3
wellbore of 5-in. openhole and 2 /8-in. pipe, circulation liquid enough shear force at the interface to efficiently erode the cuttings
3
flow rate = 0.5 m /min, pipe eccentricity = 100%, gas volume
bed, a higher flow rate is required.
fraction = 0%.
Martins23 experimentally studied the cuttings removal rate
using the circulation mode. Their results indicate that it only
characteristics but also by the properties of circulation fluid
takes one characteristic time (550 seconds) to remove 66% of
properties. The shear stress at the bed interface for a near-
the removable solids from an 84-ft test section, but it takes about
horizontal wellbore plays the key role in cuttings transport.
five times the characteristic time (45.8 minutes) to remove 99%
Therefore, the flow regime, geometric combination of
of the removable solids. Our own observations are in broad
hole/drillpipe, and eccentricity also affect the degree of the effect
agreement with Martins.23 To optimize hole cleaning efforts, it
of circulation fluid properties (yield point, plastic viscosity, and must be recognized that complete removal of the cuttings bed is
density) on the cuttings transport. Detailed discussion about this too time-consuming. It is possible that for coiled tubing, it is
issue is beyond the scope of this study. See Ref. 27 for more
beneficial to have the hole restricted by a cuttings bed.
information. However, a consistent conclusion13,26,27 indicates that Depending on the buckling behavior of the drillpipe and the
for horizontal/near-horizontal wellbore, hole cleaning is more
requirement of weight on bit, it may not be necessary to remove
efficient if a low-viscosity fluid is pumped in a turbulent flow the cuttings bed fully before resuming drilling.
regime rather than a high-viscosity fluid in laminar. We confirmed
this trend by comparing water, HEC, and Xanvis polymers.28 For
the vertical/near-vertical wellbore, hole cleaning is more efficient Wiper-Trip Hole-Cleaning Mode. Owing to the absence of
if a high-viscosity fluid is pumped in laminar flow regime rather pipe rotation and limited fluid rate, common field practice is to
than a low-viscosity fluid in turbulent flow. perform frequent wiper trips to enhance the hole cleaning for
slide drilling. Fig. 12 shows that the time to clean per unit
length decreases dramatically with increasing wiper trip speed
Hole Cleaning Time Prediction when the wiper-trip speed is less than 25 m/min. In the most
Circulation Hole Cleaning Mode. Because of the nonlinear practical process, the wiper-trip speed is less than 25 m/min.
relationship between the carrying capacity and the in-situ Therefore, it is crucial to select a proper wiper-trip speed to
liquid velocity shown in Fig. 7, it is expected that the hole- clean the hole economically. If the speed is too high, there is
cleaning time will also change nonlinearly with circulation potential to create a cuttings bridge, which may cause the drill
fluid flow rate. Eq. 8 indicates that increasing the liquid pipe to become stuck. In addition, a higher speed may not fully
circulation rate results in a lower hole cleaning time. For a clean the cuttings owing to the limited cuttings pick-up capacity.
specific combination of open hole and drillpipe, a higher
cuttings-bed height means there is a higher cuttings volume
0
( Vs ) accumulated in the wellbore annulus, and it therefore
takes longer to clean the hole.
Fig. 11 displays the hole-cleaning time ratio vs. the cleaned-out
cuttings volume ratio based on Eq. 8. Here the time required to
0
clean 95% of the initial cuttings volume ( Vs / Vs =0.05) is
assumed to be the base time (100%). The figure shows that if half
of the initial cuttings volume is cleaned out, it only takes about
23% of the base time. In other words, if it takes 100 minutes to
clean 95% initial cuttings volume, it only takes 23 minutes to
clean 50% of the initial cuttings volume. For field applications, it
means that the most efficient hole cleaning period is the first few
minutes. After cleaning the hole for a while, pumping a higher
liquid rate would result in a more efficient hole-cleaning mode
rather than keeping the circulation rate constant. This is because
the bed height is reduced after a certain cleaning period and the
in-situ liquid velocity decreases. Therefore, the shear force Fig. 12—Sensitivity of wiper-trip time per unit wellbore length
acting at the bed interface is reduced. In order to generate a high versus wiper trip speed.

December 2001 SPE Journal 361


Based on Eq. 9, the wiper trip speed not only depends on the Cb = cuttings volume concentration in the bed,
circulation fluid rate, qm, and initial bed area, Abed, but also on the assumed as 0.52
cuttings pickup capacity, C. In fact, the cuttings pickup capacity C0 = initial cuttings concentration, in decimal
also depends on the bit agitation, cuttings size, fluid type, two- C0 to Cn = cuttings volume concentration at each interface
phase flow, deviation angle, and fluid flow rate.24 As mentioned between the subsections, cuttings true
earlier with Eq. 9, there is an assumption that when the drillpipe is
volume/mud volume, in decimal
being pulled back, the bit will only disturb the local flow pattern.
The cuttings adjacent to the bit will be completely fluidized, while Cv = cuttings volume concentration, cuttings true
the cuttings in the other sections will be transported by the volume/
circulation fluids, which is the same process as the one used (cuttings true volume + mud volume), %
before the drilling was stopped. With the correlation developed in d1 = drillpipe diameter, m
this study, the cuttings initial bed cross-sectional area, Abed, can be d2 = openhole diameter, m
accurately predicted. Therefore, the prediction of a suitable d50 = particle diameter such that 50% by weight of the
wiper-trip speed with Eq. 9 depends on the accuracy of the material below this size, m
cuttings pickup capacity model. More studies are conducted in dp= cuttings particle size, m; dp = d50 in this study
Ref. 24. dV1 dVn
Because of the bit agitation and the tubing drag effects, the to = cuttings volume change rate in Subsection 1 to n,
wiper-trip mode may need a shorter time to clean the hole, but the dt dt
wiper trip has a negative effect on coiled tubing fatigue life. For respectively; m3/min
the circulation mode, the fatigue damage owing to the movement g = gravitate acceleration constant, 9.81 m/s2
of the tubing can be eliminated, but the lack of the bit agitation hb = bed height, m
could be detrimental to the hole cleaning. More studies need to be HL = liquid holdup, in decimal
conducted to determine an optimized strategy for hole-cleaning L = the length of the horizontal wellbore section, m
time based on the specific operation conditions. qm = circulated mud flow rate, m3/min
t = hole cleaning time, minute
Conclusions vc = the critical velocity defined in Eq. 1, m/s
Based on the experimental study and the analysis of the hole- vopen = in-situ liquid velocity in the open area above
cleaning process in this paper, the following conclusions can the cuttings bed, m/s
be summarized: Vs = total cuttings volume remained in the
1. A computer program was developed to predict the bed height wellbore annulus, m3
0
for different inclination angles at different operating Vs = initial cuttings volume remained in the
conditions. Such a program can be used to optimize the wellbore annulus, m3
cuttings transport for the slide drilling process. vw = wiper trip speed, m/min
2. The volume fraction of the liquid has a significant impact on V1 to Vn = cuttings true volume remained in Subsection
the cuttings transport in underbalanced drilling with gasified 1 to n, respectively; m3.
fluids. The changing of liquid flow rate has more of an effect β = wellbore inclination angle from vertical; 90°
on the cuttings transport than the gas-volume flow rate does.
refers to the horizontal position
When the liquid volume fraction is less than 50%, cuttings
transport is significantly reduced. βI = the time constant defined in Eq. 4, 1/minute,
i = 1 to n.
3. There are many variables that can affect cuttings transport.
ε = eccentricity of drillpipe, 2•χ/(d2-d1), in decimal
The most important variable is the in-situ liquid velocity.
There is a minimum in-situ liquid velocity below which µm = viscosity of mud or mixture viscosity
carrying capacity is negligible. This emphasizes the need for of gas and liquid, Pa.s
multiphase flow correlations that have been derived from ρs = cuttings density, kg/m3
empirical data in the presence of cuttings beds, pipe ρm = mud density or mixture density of gas and liquid,
eccentricities, and differing hole/pipe size ratios. kg/m3
4. Hole-cleaning time using the circulation mode decreases χ = the distance between the centers of open hole and
nonlinearly with the increasing of the circulation fluid flow drillpipe, m
rate. Optimizing hole cleaning will depend on having a
reliable method to quantify the characteristic time constant Acknowledgments
for a given set of downhole conditions, or using the critical
deposition velocity correlation developed in this study to The authors would like to express their appreciation to BJ
predict the profile of cuttings concentration along the Services for the opportunity to present this paper. We would
wellbore. also like to thank Graham Wilde of BJ Services for his review
5. For the slide drilling process, it is crucial to select the most of this paper and his valuable technical input.
economic method for cleaning the hole. Circulation rate
increases or making a wiper trip at the optimum speed are References
two choices available to ensure efficient hole cleaning. The 1. Azar, J.J. and Sanchez, R.A.: “Important Issues in Cuttings
present cuttings transport model can be used to predict the Transport for Drilling Direction Wells,” paper SPE 39020
wiper-trip speed based on the predicted bed height, cuttings presented at the 1997 Latin American and Caribbean Petroleum
pickup capacity and actual in-situ fluid flow rate. Engineering Conference and Exhibition, Rio de Janeiro, 30
August–3 September.
Nomenclature 2. Pilehvari, A.A., Azar, J.J., and Shirazi, S.A.: “State-of-the-Art
Cuttings Transport in Horizontal Wellbores,” paper SPE 37079
Abed = initial cuttings bed cross area, m2 presented at the 1996 SPE International Conference on
C = the cuttings pick-up capacity, in decimal

362 December 2001 SPE Journal


Horizontal Well Technology held in Calgary, 18–20 21. Li, J.: “Cuttings Transport in a Multi-Phase Flow System,”
November. internal report, BJ-Nowsco Well Services Ltd., Calgary,
3. Tomren, P.H., Iyoho, A.W., and Azar, J.J.: “Experimental Study of Alberta, Canada (1997).
Cuttings Transport in Directional Well Drilling,” SPEDE 22. Rodriguez, P.V.: “Experimental Determination of Minimum
(February 1986) 43. Air and Water Flow Rates for Effective Cuttings Transport in
4. Larsen, T.I.: “A Study of the Critical Fluid Velocity in Cuttings High Angle and Horizontal Wells,” MS thesis, U. of Tulsa,
Transport,” MS thesis, U. of Tulsa, Tulsa, Oklahoma (1990). Tulsa (2001).
5. Jalukar, L.S.: “A Study of Hole Size Effect on Critical and Sub- 23. Martins, A.L. et al.: “On the Erosion Velocity of a Cuttings Bed
critical Drilling Fluid Velocities in Cuttings Transport for Inclined During the Circulation of Horizontal and Highly Inclined Wells,”
Wellbores,” MS thesis, U. of Tulsa, Tulsa, Oklahoma (1993). paper SPE 39021 presented at the 1997 SPE Latin American and
6. Bassal, A.A.: “The Effect of Drillpipe Rotation on Cuttings Caribbean Petroleum Engineering Conference and Exhibition, Rio
Transport in Inclined Wellbores,” MS thesis, U. of Tulsa, De Janeiro, 30 August–3 September.
Tulsa (1995). 24. Walker, S. and Li, J.: “Coiled-Tubing Wiper Trip Hole Cleaning in
7. Peden, J.M. et al.: “Comprehensive Experimental Investigation of Highly Deviated Wellbores,” paper SPE 68435 presented at the
Drilled Cuttings Transport in Inclined Wells Including the Effects 2001 SPE/ICoTA Coiled Tubing Roundtable, Houston, 7–8 March.
of Rotation and Eccentricity,” paper SPE 20925 presented at SPE 25. Elsborg, C., Carter, J., and Cox, R.: “High Penetration Rate
Europec 90, The Hague 22–24 October. Drilling with Coiled Tubing,” paper SPE 37074 presented at the
8. Sifferman, T.R. and Becker, T.E.: “Hole Cleaning in Full-Scale 1996 SPE International Conference on Horizontal Well
Inclined Wellbores,” SPEDE (June 1992) 115; Trans., AIME, 293. Technology, Calgary, 18–20 November.
9. Zamora, M., Jefferson, D.T., and Powell, J.W.: “Hole-Cleaning 26. Leising, L.J. and Walton, I.C.: “Cuttings Transport Problems and
Study of Polymer-Based Drilling Fluids,” paper SPE 26329 Solutions in Coiled Tubing Drilling,” paper SPE 39300 presented
presented at the 1993 SPE Annual Technical Conference and at the 1998 IADC/SPE Drilling Conference, Dallas, 3–6 March.
Exhibition, Houston, 3–6 October. 27. Okrajni, S.S. and Azar, J.J.: “The Effects of Mud Rheology on
10. Brown, N.P., Bern, P.A., and Weaver, A.: “Cleaning Deviated Annular Hole Cleaning in Directional Wells,” SPEDE (August
Holes: New Experimental and Theoretical Studies,” paper SPE 1986) 297.
18636 presented at the 1989 SPE/IADC Drilling Conference, New 28. Walker, S. and Li, J.: “The Effects of Particle Size, Fluid
Orleans, 28 February–3 March. Rheology, and Pipe Eccentricity on Cuttings Transport,” paper
11. Martin, M. et al.: “Transport of Cuttings in Directional Wells,” SPE 60755 presented at the 2000 SPE/ICoTA Coiled Tubing
paper SPE 16083 presented at the 1987 SPE/IADC Drilling Roundtable, Houston, 5–6 April.
Conference, New Orleans, 15–18 March.
12. Martins, A.L. et al.: “Optimizing Cuttings Circulation in SI Metric Conversion Factors
Horizontal Drilling,” paper SPE 35341 presented at the 1996 SPE
International Petroleum Conference and Exhibition of Mexico, Ft × 3.048 E–01 = m
Villahemosa, Mexico, 5–7 March.
13. Adari, R.B. et al.: “Selecting Drilling Fluid Properties and Flow
in. × 25.4 E–03 = m
Rates for Effective Hole Cleaning in High-Angle and Horizontal in.3/min × 1.6387 E–05 = m3/min
Wells,” paper SPE 63050 presented at the 2000 SPE Annual
Technical Conference and Exhibition, Dallas, 1–4 October. gal (US) × 3.785 E + 00 = L
14. Doron, P., Granica, D.G., and Barnea, D.: “Slurry Flow in psi × 6.8948 E–03 = MPa
Horizontal Pipes―Experimental and Modeling,” Int. J. Multiphase
Flow (1987) 13, 535. *Conversion factor is exact.
15. Doron, P. and Barnea, D.: “A Three-Layer Model for Solid-Liquid
Flow in Horizontal Pipes,” Int. J. Multiphase Flow (1993), 19, 1029.
16. Gillies, R.G., Shook, C.A., and Wilson, K.C.: “An Improved Two- Jeff Li is currently a senior project engineer with BJ Services
Layer Model for Horizontal Slurry Pipeline Flow,” Cdn. J. Chem. Co. in Calgary. e-mail: Jli@nowsco.com. Previously he worked
Eng. (February 1991) 69, 173. with Canadian Fracmaster as a staff engineer in the Coil
17. Gavignet, A.A. and Sobey, I.J.: “Models Aids Cuttings Tubing Dept. His interests include solids transport, wellbore
Transport Prediction,” JPT (September 1989) 916. hydraulic simulation, and downhole tools. He holds BS and MS
18. Walton, I.C.: “Computer Simulator of Coiled Tubing Wellbore
degrees in P.R. China. He also holds MS and PhD degrees in
Cleanouts in Deviated Wells Recommends Optimum Pump
mechanical engineering from the U. of Saskatchewan,
Rate and Fluid Viscosity,” paper SPE 29491 presented at the
1995 SPE Production Operations Symposium, Oklahoma City, Canada. Scott Walker is a project engineer with BJ Services
Oklahoma., 2–4 April. Co. in Calgary. e-mail: swalker@nowsco.com. He started
19. Martins, A.L. et al.: “Evaluating the Transport of Solids working with BJ Services Co., formerly known as Nowsco Well
Generated by Shale Instabilities in ERW Drilling,” paper SPE Service Ltd., and has been employed with the company for 7
50380 presented at the 1998 SPE International Conference on years. Walker’s work there has encompassed various
Horizontal Well Technology, Calgary, 1–4 November. operations, including well services such as stimulation
20. Nguyen, D. and Rahman, S.S.: “A Three-Layer Hydraulic cementing and various coiled-tubing operations, and 5 years
Program for Effective Cuttings Transport and Hole Cleaning in Highly studying solids transport research. Walker holds a BS degree
Deviated and Horizontal Wells,” SPEDC (September 1998) 182. from the U. of Alberta in chemical engineering.

December 2001 SPE Journal 363

You might also like