Professional Documents
Culture Documents
7ACCN018W
Financial Analysis for Managers
May 2018
Marking Scheme
Question 1 – (2.5 marks per concept – Total 10 marks)
Costs concerning a future period must be carried forward as a prepayment for that
period and not charged in the current profit statement. For example, payments made
in advance such as the prepayment of rent would not be treated as an expense in
the current accounting period.
It is assumed that the company is to continue for the foreseeable future which is taken
to mean at least 12 months from the approval of the financial accounts, and accounting
information reflects this. If the company is about to cease trading then all non-current
assets become current assets and all non-current liabilities become current liabilities.
Also, some assets are likely to have much lower values than their current book values.
This concept suggests that all transactions should be recorded at their values at the
time the transaction took place and not the values at the time the accounts are
drawn up. So, a fixed asset bought five years ago will be shown at cost less
accumulated depreciation in the accounts of the company in the subsequent five
years.
Money measurement is used for all assets and liabilities, incomes and expenses.
Thus any item which cannot be objectively measured will not be included in the
accounts (e.g. human resources that a company has at its disposal do not appear in
the balance sheet)
Question 3
Part (a) – 3 marks (2 marks for correct calculation and 1 mark for decision to
accept/reject)
Part (c) – 4 marks (0.5 mark per valid point – max 4 marks)
Despite its limitations, the payback is still quite useful as a filtering technique.
Additionally, it is also used because:
It is easy to calculate as you do not need to forecast the cash flows beyond
the desired payback period.
It is very easy to understand
Assumes cash flows after payback period are so risky as to be of no value
It is also a good technique in:
Times when liquidity is more important than profitability
Times of high inflation
Economic uncertainties
Political uncertainties
Question 4
Zero based budgeting also refers to the identification of a task or tasks and then
funding resources to complete the task independent of current resourcing.
Disadvantages
Question 5
Part (a) – 5 marks (please give 0.5 for each correct formula)
Note - If all three variance are correct, then give full 5 marks
Part (b) – 5 marks (please give 0.5 for each correct formula)
Note - If all three variance are correct, then give full 5 marks
(Total: 10 marks)
Section B – Answer Any Two Questions
Question 6
Part (a) – 10 marks (2 mark for definition & 2 marks per each function explained –
max 10 marks)
Functions of budgets
1. To aid the planning of actual operations:
by forcing managers to consider how conditions might change and what
steps should be taken now.
by encouraging managers to consider problems before they arise.
5. To control activities:
by comparison of actual with budget (attention directing/management by
exception).
NPV = 32,470
Payback is the time that it takes to recover the initial investment. As a general rule,
the shorter the payback period, the more attractive is the project.
It is easy to calculate since only cash flows for the required payback period
need be calculated as it assumes cash flows after payback period are so risky
as to be of no value
It is also very easy to understand.
A good technique in:
o Times when liquidity is more important than profitability
o Times of high inflation
o Economic uncertainties
o Political uncertainties
Question 8
Part (a) – 4 marks
Selling Price 295
VC – production -160
VC – Transport -14
VC – Import duty -32
--------
Contribution 89
Part (f) – 3 marks (1 mark for any valid point – Max 3 marks)
The break-even graphs assume that cost and revenue behaviour patterns are
known and change on a straight-line basis as activity levels change.
It may not always be feasible to split costs neatly into variable and fixed
categories. Some costs show mixed behaviour.
Break-even analysis assumes input and output volumes are the same, so that
there is no build-up of stocks and work-in-progress.
Break-even charts and simple analyses can only deal with one product at a time.
It is assumed that cost behaviour depends entirely on volume