Productivity Standards For Construction
Productivity Standards For Construction
TABLE OF CONTENTS
Pilecap/Footing
Plastering
Beam
Production Rate ,r = 1.000 acre/day for one team (within 3km dump area)
**(depend on distance of dump area)
PRODUCTION TABLE
1 Team
Backhoe = 1 no. General Worker = 4 person
Truck 3 ton= 1 no. Operator = 2 person
PRODUCTION TABLE
NO. OF TEAM POST DUR (Days) FENCE DUR (Days) Plant Labour
Backhoe = 1
Truck 3 ton= 1 neral Worker = 4
1 50 6 0 0 Operator = 2
0 0
Backhoe = 1
Truck 3 ton= 1 neral Worker = 8
2 25 3 0 0 Operator = 4
0 0
Backhoe = 1
Truck 3 ton= 1
0 0 neral Worker = 12
3 17 2
Operator = 6
0 0
Backhoe = 1
Truck 3 ton= 1
0 0 neral Worker = 16
4 13 1
Operator = 8
0 0
Backhoe = 1
Truck 3 ton= 1
0 0 neral Worker = 20
5 10 1
Operator = 10
0 0
SOIL INVESTIGATION
1 Team
Drill Rig = 1 no. Foreman = 1 person
truck (3ton)= 1 no. Operator= 1
no.
Labour= 2 0
Setting = 60 min
Driving = 420 min Production Per Day = (8hr x60min)
(1 rig) time per rig
Total Time = 480 min = 20 lin.m
PRODUCTION TABLE
1 Team
Excavator = 3 no. Foreman = 1 person
Bulldozer = 1 no. Operator = 16 person
Backpusher = 1 no.
Vibrator roller = 2 no.
Dump Truck = 10 no.
Motor Grader = 1 no.
* Truck Speed on site 20 km/hr - Dump Truck , Dump site (on road) 60 km/hr - Tipper Truck
PRODUCTION TABLE
1 Team
Excavator (0.5cu.m bucket)= 1 nos.
Foreman = 1 person
Operator = 1 person
PRODUCTION TABLE
Excavator = 2 Foreman = 1
0 2 Operator = 2
1
Excavator = 3 Foreman = 1
0 3 1 Operator = 3
Excavator = 4 Foreman = 1
0 4 1 Operator = 4
Excavator = 5 Foreman = 1
0 5 0 Operator = 5
Key-in
the
Quantity
PIPING (GAS SERVICE & DISTRIBUTION.Sch 40) Not including Excavation & Backfill
1 Team
Excavator = 1 no. Plumber = 2 person
Crane = 1 no. General Worker = 1 person
Welding Set = 1 no. Operator = 2 person
Pipe Diameter
4"dia. 6"dia. 12"dia. 24" dia
Production of Team 78 55 24 15 lin.m/day
Ref-RSMeans Books Page 100
1 feet = 0.3048 Meter
\ TOTAL DAY REQUIRED FOR 1 2 4 7 days
ABOVE NOS. = 0.2 0.3 0.7 1.1 week
0.0 0.1 0.2 0.3 month
PRODUCTION TABLE
4"dia.= 1 Excavator = 1
6"dia.= 1 Crane = 1 Plumber = 4
2 12"dia.= 2 Welding Set = 2 General Worker = 2
24" dia.= 3 Operator = 4
4"dia.= 0 Excavator = 1
6"dia.= 1 Crane = 1
12"dia.= 1 Welding Set = 3 Plumber = 6
3
24" dia.= 2 General Worker = 3
Operator = 6
4"dia.= 0 Excavator = 1
6"dia.= 0 Crane = 1
12"dia.= 1 Welding Set = 4 Plumber = 8
4
24" dia.= 2 General Worker = 4
Operator = 8
4"dia.= 0 Excavator = 1
6"dia.= 0 Crane = 1
12"dia.= 1 Welding Set = 5 Plumber = 10
5
24" dia.= 1 General Worker = 5
Operator = 10
Key-in the
Quantity
SEWERAGE PIPE (VCP & Concrete Pipe) Not including Excavation & Backfill
1 Team
Excavator = 1 no. Plumber = 2 person
Crane (5 ton)= 1 no. General Worker = 1 person
Welding Set = 1 no. Operator = 2 person
PRODUCTION TABLE
NO. OF TEAM VCP DUR (Days) CULVERT DUR (Days) Plant Labour
4"dia.= 2 24"dia. 2 Excavator = 1
6"dia.= 2 36"dia. 3 Crane (5 ton)= 1 Plumber = 2
1 12"dia.= 4 48"dia. 6 Welding Set = 1 neral Worker = 1
24" dia.= 7 72" dia 9 person 2
1 Team
Excavator = 8 no. Foreman = 2 person
Bulldozer = 1 no. Operator = 41.5 person
Backpusher = 1 no.
Vibrator roller = 2 no.
Tipper Truck = 30 no.
PRODUCTION TABLE
1 Team
Lorry = 1 no. Labour = 8 person
PRODUCTION TABLE
1 71
Lorry = 2 Labour = 16
2 35
Lorry = 3 Labour = 24
3 24
Lorry = 4 Labour = 32
4 18
Lorry = 5 Labour = 40
5 14
VERTICAL DRAIN
1 Team
PVD Rig = 1 no. Foreman = 1 person
Lorry = 1 no. Operator = 2 person
Labour = 2 person
PRODUCTION TABLE
1 Team
Vibro Hammer = 1 no. Foreman = 1 person
Crane = 1 no. (40 ton) Operator = 2 person
Genset = 1 no. General Worker = 4 person
PRODUCTION TABLE
e = 9 m length = 0
PRECAST RC&SPUN PILING
1 Team
Piling Rig = 1 no. Foreman = 1 person
Crane (20ton) = 1 no. Operator = 2 person
Welding Set = 1 no. Welder = 1 person
Labour= 2 person
Setting = 25 min
Driving = 45 min Production Per Day = (8hr x60min)
Welding = 25 min (1 rig) time per rig
Total Time = 95 min = 5 pts.
PRODUCTION TABLE
1 Team
racktor with hammer = 1 no. General Worker = 3 person
Truck 3 ton= 1 no. Operator = 2 person
PRODUCTION TABLE
r with hammer = 1
Truck 3 ton= 1 General Worker = 6
2 2 0 0 Operator = 4
0 0
r with hammer = 1
Truck 3 ton= 1
0 0 General Worker = 9
3 1
Operator = 6
0 0
r with hammer = 1
Truck 3 ton= 1
0 0 General Worker = 12
4 1
Operator = 8
0 0
r with hammer = 1
Truck 3 ton= 1
0 0 General Worker = 15
5 1
Operator = 10
0 0
FOUNDATION - BORE PILING
1 Team
Boring Rig = 1 no. Foreman = 1 person
Crawler Crane = 1 no. Operator = 3 person
Vibro Hammer = 1 no. Bar Bender = 2 person
Bar Bender = 1 no. Bar Cutter = 1 person
Bar Cutter = 1 no. General Worker = 1 person
Concrete Vibrator = 1 no.
Mobile Pumps = 1 no.
PRODUCTION TABLE
1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Mobile Crane = 1 no. Operator = 2 person
Bar Bender = 1 no. Bar Bender = 2 person
Bar Cutter = 1 no. Bar Cutter = 1 person
Concrete Vibrator = 1 no. Carpenter = 3 person
Mobile Pumps = 1 no. Concretor = 2 person
Concrete Mixer = 1 no. General Worker = 1 person
Production of Team
Excavation = 5 min
Lean Con/ Curing = 90 min
Rebar = 30 min Production = 2 caps / 6 days
Formwork = 20 min
Concreting = 15 min
Total Time = 160 min
PRODUCTION TABLE
1 Team
Excav./ Backhoe = 1 no. Carpenter = 3 person
Mobile Pumps = 1 no. General Worker = 1 person
Operator = 1 person
Production of Team
PRODUCTION TABLE
cav./ Backhoe = 1
Mobile Pumps = 1 Carpenter = 6
2 1 General Worker = 2
Operator = 2
cav./ Backhoe = 1
Mobile Pumps = 1
Carpenter = 9
3 1
General Worker = 3
Operator = 3
cav./ Backhoe = 1
Mobile Pumps = 1
Carpenter = 12
4 0
General Worker = 4
Operator = 4
cav./ Backhoe = 1
Mobile Pumps = 1
Carpenter = 15
5 0
General Worker = 5
Operator = 5
Key-in the
PILECAP/FOOTING-REINFORCEMENT Quantity
1 Team
Barbender Machine = 1 no. Barbender = 4 person
Barcuter Machine = 1 no.
Mobile Pumps = 1 no.
Production of Team
PRODUCTION TABLE
Barbender = 4
1 25
Barbender = 8
2 12
3 8 Barbender = 12
4 6 Barbender = 16
5 5 Barbender = 20
Key-in the
PILECAP/FOOTING - PLACE CONCRETE(with crane & bucket) Quantity
1 Team
Mobile Crane (55ton) = 3 no. Concretor = 5 person
Concrete Vibrator = 2 no. Operator = 3 person
Production of Team
PRODUCTION TABLE
Crane (55ton) = 6
Concretor = 10
2 1
Operator = 6
Crane (55ton) = 9
3 1 Concretor = 15
Operator = 9
Crane (55ton) = 12
4 1 Concretor = 20
Operator = 12
Crane (55ton) = 15
5 1 Concretor = 25
Operator = 15
FOUNDATION - PILECAP
1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Mobile Crane = 1 no. Operator = 2 person
Bar Bender = 1 no. Bar Bender = 2 person
Bar Cutter = 1 no. Bar Cutter = 1 person
Concrete Vibrator = 1 no. Carpenter = 3 person
Mobile Pumps = 1 no. Concretor = 2 person
Concrete Mixer = 1 no. General Worker = 1 person
Production of Team
Excavation = 5 min
Lean Con/ Curing = 90 min
Rebar = 30 min
Formwork = 20 min
Concreting = 15 min
Total Time = 160 min
PRODUCTION TABLE
1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Bar Bender = 1 no. Operator = 1 person
Bar Cutter = 1 no. Bar Bender = 2 person
Concrete Vibrator = 1 no. Bar Cutter = 1 person
Carpenter = 3 person
Concretor = 1 person
General Worker = 1 person
Production of Team
Rebar = 10 min
Formwork = 30 min
Concreting = 10 min
Total Time = 50 min
PRODUCTION TABLE
0 0 neral Worker = 5
Key-in the
BEAM (Formworks - 2 use) Quantity
1 Team
Power Tools = 4 no. Carpenter = 4 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Barbender Machine = 9 no. Barbender = 4 person
Barcuter Machine = 9 no.
PRODUCTION TABLE
1 Team
Mobile Crane (55ton) = 1 no. Concretor = 4 person
Concrete Vibrator = 2 no. General Worker = 1 person
PRODUCTION TABLE
1 Team
Power Tools = 4 no. Carpenter = 4 person
General Worker = 1 person
On Grade Elevated
\ TOTAL DAY REQUIRED FOR ABOVE AREA = 1 days 1 days
= 0.1 week 0.2 week
= 0.0 month 0.1 month
PRODUCTION TABLE
SLAB (Rebar - On Grade & Elevated ) 368 kg 0.0011023 ton (US Convertion)
1 Team
Barbender Machine = 1 no. Barbender = 4 person
Barcuter Machine = 1 no.
Mobile Crane (25ton) = 1 no.
SP of 1 Team - Slab on Grade 2.3 ton/day
SP of 1 Team - Elevated Slab 2.9 ton/day (*Ref-Means Books page 154)
On Grade Elevated
\ TOTAL DAY REQUIRED FOR ABOVE AREA = 0 days 0 days
= 0.0 week 0.0 week
= 0.0 month 0.0 month
PRODUCTION TABLE
1 Team
Mobile Crane (55ton) = 1 no. Concretor = 4 person
Concrete Vibrator = 2 no. General Worker = 1 person
Operator = 1 person
PRODUCTION TABLE
1 Team
Mobile Crane (55ton) = 1 no. Mason = 1 person
Concrete Vibrator = 1 no. General Worker = 2 person
Operator = 1 person
PRODUCTION TABLE
1 Team
Mobile Crane = 1 no. Foreman = 1 person
Bar Bender = 1 no. Operator = 1 person
Bar Cutter = 1 no. Bar Bender = 4 person
Concrete Vibrator = 2 no. Bar Cutter = 4 person
Hand Compactor = 1 no. Carpenter = 5 person
Concretor = 4 person
General Worker = 2 person
200 ori
Production of 1 Team for 270 m2
Rebar = 7 day
Formwork = 5 day
Concreting = 2 day
Total Time = 14 day
PRODUCTION TABLE
0 0 Concretor = 84
0 0 neral Worker = 42
Key-in the
COLUMN (Plywood Formworks -12''x12''- 3 use) Quantity
1 Team
Power Tools = 3 no. Carpenter = 3 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Barbender Machine = 3 no. Barbender = 4 person
Barcuter Machine = 3 no.
PRODUCTION TABLE
1 Team
Mobile Crane (55ton) = 1 no. Concretor = 4 person
Concrete Vibrator = 2 no. General Worker = 1 person
PRODUCTION TABLE
1 Team
Mobile Crane = 1 no. Foreman = 1 person
Bar Bender = 1 no. Operator = 1 person
Bar Cutter = 1 no. Bar Bender = 2 person
Concrete Vibrator = 1 no. Bar Cutter = 1 person
Carpenter = 3 person
Concretor = 1 person
General Worker = 1 person
Production of Team
Rebar = 10 min
Formwork = 20 min
Concreting = 10 min
Total Time = 40 min
PRODUCTION TABLE
0 0 neral Worker = 5
Key-in the
RETAINING WALL (Formworks -2.5m - 5m high- 3 use) Quantity
1 Team
Power Tools = 4 no. Carpenter = 4 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Barbender Machine = 1 no. Barbender = 4 person
Barcuter Machine = 1 no.
PRODUCTION TABLE
1 Team
Mobile Crane (55ton) = 1 no. Concretor = 4 person
Concrete Vibrator = 2 no. General Worker = 1 person
PRODUCTION TABLE
1 Team
Excavator = 1 no. Foreman = 1 person
Mobile Crane = 1 no. Operator = 1 person
Bar Bender = 1 no. Bar Bender = 2 person
Bar Cutter = 1 no. Bar Cutter = 1 person
Concrete Vibrator = 1 no. Carpenter = 4 person
Concretor = 1 person
General Worker = 5 person
Production of Team
Rebar = min
Formwork = min
Concreting = min
Total Time = min
PRODUCTION TABLE
0 0 General Worker = 25
PRECAST ELEMENT
1 Team
Tower/Mobile Crane = 1 no. Foreman = 1 person
Concrete Vibrator = 1 no. Operator = 1 person
Installer = 5 person
Concretor = 2 person
General Worker = 2 person
PRODUCTION TABLE
1 Team
Trailer/Low Loader = 2 no. Operator = 4 person
Crane = 2 no. Labour = 4 person
PRODUCTION TABLE
1 Team
obile Crane (90 ton) = 1 no. Foreman = 1 person
Welding set = 1 set Operator = 1 person
Roof Truss Installer = 5 person
Welder = 1 person
PRODUCTION TABLE
1 Team
obile Crane (12 ton) = 1 no. Foreman = 1 person
Power Tools = 1 set Operator = 1 person
Carpenter = 4 person
PRODUCTION TABLE
1 Team
Mobile Crane = 1 no. Foreman = 1 person
Power Tool = 3 set Operator = 1 person
Roof cover inst. = 3 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Concrete Mixer = 1 no. Foreman = 1 person
Brick Layer = 3 person
General Worker = 2 person
PRODUCTION TABLE
1 Team
Concrete Mixer = 1 no. Foreman = 1 person
Plasterer = 3 person
General Worker = 2 person
PRODUCTION TABLE
1 Team
Concrete Mixer = 1 no. Foreman = 1 person
Plasterer = 3 person
General Worker = 2 person
PRODUCTION TABLE
1 Team
Power Tool = 2 set Foreman = 1 person
elding Set(for steel) = 1 set Installer = 2 person
General Worker = 1 person
(*Ref-Means Books)
Production of 1 Team for 13 nos. -Steel Frame Page 278
Production of 1 Team for 2 nos. -Alum Frame Page 280
Production of 1 Team for 14 nos. -Wood Frame Page 282
PRODUCTION TABLE
1 Team
Welding Machine = 1 set Foreman = 1 person
Installer = 2 person
General Worker = 1 person
42
Production of 1 Team : 8 m/day
1 Staircase
Ground Floor - 1st Floor = 8 m
Total length 1st Floor 24 m
PRODUCTION TABLE
1 Team
Foreman = 1 person
Tiler = 1 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Carpenter = 2 person
General Worker = 2 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Carpenter = 2 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Tiler = 1 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Layer = 1 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Tiler = 1 person
General Worker = 2 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Tiler = 1 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Renderer = 2 person
General Worker = 1 person
Screeding = 1 day
Total Time = 1 day
PRODUCTION TABLE
1 Team
Foreman = 1 person
Painter = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Plasterer = 2 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person
Production of 1 Team for 14 nos. - Solid Deco. Tmber Door - Ref RSMeans- Page 282
Production of 1 Team for 3 nos. - Glass Sliding Door - Ref RSMeans- Page 287
PRODUCTION TABLE
1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person
Production of 1 Team for 9 nos. - Single Hung 3'4"x 5' - Ref RSMeans- Page 294
Production of 1 Team for 4 nos. - Sliding Aluminum 9' x 5' - Ref RSMeans- Page 295
PRODUCTION TABLE
1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person
Installation = 1 day
Total Time = 1 day
PRODUCTION TABLE
1 Team
Bar Bender = 1 no. Foreman = 1 person
Bar Cutter = 1 no. Bar Bender = 1 person
Bar Cutter = 1 person
Carpenter = 1 person
General Worker = 1 person
PRODUCTION TABLE
1 Team
Foreman = 1 person
Fixer = 2 person
General Worker = 1 person
Fixer = 1 day
Total Time = 1 day
PRODUCTION TABLE
1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Concrete Vibrator = 1 no. Operator = 1 person
Mobile Pumps = 1 no. General Worker = 5 person
Concrete Mixer = 1 no.
Excavation = 5 min
Lean Con/ Curing = 95 min
ay hrdrain+Con base = 10 min
Brick Wall = 10 min
Plastering = 10 min
Total Time = 130 min
PRODUCTION TABLE
1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Concrete Vibrator = 1 no. Operator = 1 person
Mobile Pumps = 1 no. General Worker = 5 person
Concrete Mixer = 1 no.
Production of 1 Team
PRODUCTION TABLE
1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Concrete Vibrator = 1 no. Operator = 1 person
Mobile Pumps = 1 no. Carpenter = 2 person
Concrete Mixer = 1 no. Barbender = 2 person
Labour = 1 person
Production of 1 Team
PRODUCTION TABLE
1 Team
Excavator = 1 no.
Crane = 1 no. General Worker = 1 person
Operator = 2 person
Production of Team
6"dia. 8"dia. 12"dia. 18" dia
Production of Team 94 94 70 50 lin.m/day
Ref-RSMeans Books Page 103
1 feet = 0.3048 Meter
\ TOTAL DAY REQUIRED FOR 9 9 12 17 days
ABOVE NOS. = 1.5 1.5 2.0 2.8 week
0.3 0.3 0.5 0.6 month
PRODUCTION TABLE
4"dia.= 4 Excavator = 1
6"dia.= 4 Crane = 1 0 0
2 12"dia.= 6 0 0 General Worker = 2
24" dia.= 8 Operator = 4
4"dia.= 3 Excavator = 1
6"dia.= 3 Crane = 1
12"dia.= 4 0 0 0 0
3
24" dia.= 6 General Worker = 3
Operator = 6
4"dia.= 2 Excavator = 1
6"dia.= 2 Crane = 1
12"dia.= 3 0 0 0 0
4
24" dia.= 4 General Worker = 4
Operator = 8
4"dia.= 2 Excavator = 1
6"dia.= 2 Crane = 1
12"dia.= 2 0 0 0 0
5
24" dia.= 3 General Worker = 5
Operator = 10
RCP CULVERT ON SEND BEDDING -not including excavate & backfill
1 Team
Excavator= 1 no. Foreman = 1 person
Mobile Pumps = 1 no. Operator = 2 person
Concrete Mixer = 1 no. General Worker = 2 person
Crane (5 ton) = 1 no.
Production of 1 Team
PRODUCTION TABLE
Excavator= 2 Foreman = 1
Mobile Pumps = 2 Operator = 4
5 Concrete Mixer = 2 General Worker = 4
1 2 31 Crane (5 ton) = 2
Excavator= 3 Foreman = 1
Mobile Pumps = 3 Operator = 6
3 Concrete Mixer = 3 General Worker = 6
1 3 20 Crane (5 ton) = 3
Excavator= 4 Foreman = 1
Mobile Pumps = 4 Operator = 8
3 Concrete Mixer = 4 General Worker = 8
1 4 15 Crane (5 ton) = 4
Excavator= 5 Foreman = 1
Mobile Pumps = 5 Operator = 10
2 Concrete Mixer = 5 General Worker = 10
0 5 12 Crane (5 ton) = 5
5 12
PAVEMENT BASE - SUB BASE (Sand or Quarry Dust) CBR >20
1 Team
otor Grader MG 350 = 1 no. Labour = 1 person
Vibratory Roller = 1 no. (10ton) Operator = 3 person
Backpusher= 1 no.
PRODUCTION TABLE
1 Team
Con. Placer Spreader = 1 no. Labour = 6 person
Con. Slip form Paver= 1 no. Operator = 23 person
Texturing & Curing Machine = 1 no. Carpenter= 3
Longitudinal groove cutting machine = 1 no. barbender= 2
Lorry mixer = 20 no.
Water truck= 1 no.
PRODUCTION TABLE
1 Team
Motor Grader = 1 no. (30,000lbs) Foreman = 1 person
Vibratory Roller = 1 no. (10ton) Operator = 3 person
Dozer = 1 no. (200hp) Labour = 2 person
PRODUCTION TABLE
Granular Material
DBM
ACBC
ACWC
1 Team
Asphalt Paver = 1 no. (130hp) Foreman = 1 person
Tandem Roller = 1 no. (10ton) Operator = 5 person
Pneu. Tyred Roller = 1 no. Labour = 7 person
Tack/Prime Coat Lorry = 1 no.
Water Tanker = 1 no
Air Compressor = 1 no. 1000 max
(*Ref-Means Books)
Production of one team, P = 623 ton/day Page 78 6345 S.Y
0.8361 SY/Sq.m
PRODUCTION TABLE
1 Team
Curb Paver = 1 no. Foreman = 1 person
Lorry = 1 no. Operator = 1 person
Labour = 4 person
Kerb Size = 350mm(H) x 500mm(W)
Milling 300 mm
DBM DBM
Thickness = 0.23 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
ACBC ACBC
Thickness = 0.06 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
Milling 240 mm
DBM DBM
Thickness = 0.18 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
ACBC ACBC
Thickness = 0.08 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
Milling 280 mm
DBM DBM
Thickness = 0.22 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
ACBC ACBC
Thickness = 0.06 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
Milling 270 mm
DBM DBM
Thickness = 0.21 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
ACBC ACBC
Thickness = 0.06 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
Milling 230 mm
DBM DBM
Thickness = 0.17 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
ACBC ACBC
Thickness = 0.06 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =
Milling 60 mm
Mill = 0m Mill =
Width = 3.75 m Width =
Length = 800 m Length =
Volume = 0 m3 Volume =
Estimate = 0 loads @ 30 min/loads Estimate =
Time Required = 0.0 hrs Time Requi=
DBM DBM
Thickness = 0m Thickness =
Width = 3.75 m Width =
Length = 800 m Length =
ACBC ACBC
Thickness = 0.05 m Thickness =
Width = 7.3 m Width =
Length = 800 m Length =
DBM
0.23 m Thickness = 0.13 m
3.65 m Width = 3.75 m
200 m Length = 250 m
ACBC
0.06 m Thickness = 0.06 m
3.65 m Width = 3.75 m
200 m Length = 250 m
DBM
0.18 m Thickness = 0.1 m
3.65 m Width = 3.75 m
200 m Length = 250 m
ACBC
0.08 m Thickness = 0.06 m
3.65 m Width = 3.75 m
200 m Length = 250 m
DBM
0.22 m Thickness = 0.22 m
3.65 m Width = 3.65 m
200 m Length = 180 m
ACBC
0.06 m Thickness = 0.06 m
3.65 m Width = 3.65 m
200 m Length = 180 m
DBM
0.21 m Thickness = 0.21 m
3.65 m Width = 3.65 m
200 m Length = 180 m
ACBC
0.06 m Thickness = 0.06 m
3.65 m Width = 3.65 m
200 m Length = 180 m
DBM
0.17 m Thickness = 0.17 m
3.65 m Width = 3.65 m
200 m Length = 220 m
ACBC
0.06 m Thickness = 0.06 m
3.65 m Width = 3.65 m
200 m Length = 220 m
0m Mill = 0m
3.75 m Width = 3.75 m
200 m Length = 250 m
0 m3 Volume = 0 m3
0 loads @ 30 min/loads Estimate = 0 loads @
0.0 hrs Time Requi= 0.0 hrs
DBM
0m Thickness = 0m
3.75 m Width = 3.75 m
200 m Length = 250 m
0 m3 = 0 tonne Volume = 0 m3 =
0 loads @ 30 min/loads Estimate = 0 loads @
0.0 hrs Time Requi= 0.0 hrs
ACBC
0.05 m Thickness = 0.05 m
3.75 m Width = 3.75 m
200 m Length = 250 m
268.125 tonne
30 min/loads
123.75 tonne
30 min/loads
Mill = 0.16 m
Width = 3.75 m
Length = 300 m
Volume = 180 m3
30 min/loads Estimate = 18 loads @ 30 min/loads
Time Required = 9.0 hrs
DBM
Thickness = 0.1 m
Width = 3.75 m
Length = 300 m
ACBC
Thickness = 0.06 m
Width = 3.75 m
Length = 300 m
Mill = 0.28 m
Width = 3.75 m
Length = 300 m
Volume = 315 m3
30 min/loads Estimate = 32 loads @ 30 min/loads
Time Required = 15.8 hrs
DBM
Thickness = 0.22 m
Width = 3.75 m
Length = 300 m
ACBC
Thickness = 0.06 m
Width = 3.75 m
Length = 300 m
Mill = 0.27 m
Width = 3.75 m
Length = 300 m
Volume = 303.75 m3
30 min/loads Estimate = 30 loads @ 30 min/loads
Time Required = 15.2 hrs
DBM
Thickness = 0.21 m
Width = 3.75 m
Length = 300 m
ACBC
Thickness = 0.06 m
Width = 3.75 m
Length = 300 m
Mill = 0.23 m
Width = 3.75 m
Length = 300 m
Volume = 258.75 m3
30 min/loads Estimate = 26 loads @ 30 min/loads
Time Required = 12.9 hrs
DBM
Thickness = 0.17 m
Width = 3.75 m
Length = 300 m
ACBC
Thickness = 0.06 m
Width = 3.75 m
Length = 300 m
Mill = 0m
Width = 3.75 m
Length = 300 m
Volume = 0 m3
30 min/loads Estimate = 0 loads @ 30 min/loads
Time Required = 0.0 hrs
DBM
Thickness = 0m
Width = 3.75 m
Length = 300 m
ACBC
Thickness = 0.05 m
Width = 3.75 m
Length = 300 m
DBM DBM
Thickness = 0.22 m Thickness = 0.22
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
ACBC ACBC
Thickness = 0.06 m Thickness = 0.06
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
DBM DBM
Thickness = 0.21 m Thickness = 0.21
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
ACBC ACBC
Thickness = 0.06 m Thickness = 0.06
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
DBM DBM
Thickness = 0.17 m Thickness = 0.17
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
ACBC ACBC
Thickness = 0.06 m Thickness = 0.06
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
Mill = 0m Mill = 0
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
Volume = 0 m3 Volume = 0
Estimate = 0 loads @ 30 min/loads Estimate = 0
Time Requi= 0.0 hrs Time Requi= 0.0
DBM DBM
Thickness = 0m Thickness = 0
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
ACBC ACBC
Thickness = 0.05 m Thickness = 0.05
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400
m3
loads @ 30 min/loads
hrs
m
m
m
m3 = 726 tonne
loads @ 30 min/loads
hrs
m
m
m
m3 = 198 tonne
loads @ 30 min/loads
hrs
hrs
m
m
m
m3
loads @ 30 min/loads
hrs
m
m
m
m3 = 693 tonne
loads @ 30 min/loads
hrs
m
m
m
m3 = 198 tonne
loads @ 30 min/loads
hrs
hrs
m
m
m
m3
loads @ 30 min/loads
hrs
m
m
m
m3 = 561 tonne
loads @ 30 min/loads
hrs
m
m
m
m3 = 198 tonne
loads @ 30 min/loads
hrs
hrs
m
m
m
m3
loads @ 30 min/loads
hrs
m
m
m
m3 = 0 tonne
loads @ 30 min/loads
hrs
m
m
m
m3 = 165 tonne
loads @ 30 min/loads
hrs
hrs
MILLING WORKS - PAVEMENT
1 Team
Milling Machine = 1 no. (Writgen W1000) Foreman = 1 person
Lorry = 2 no. Operator = 2 person
Labour = 4 person
Width = 1m
depth = 250mm
Production of one Machine, P = 200 tonne/hr = 960 tonne/day
PRODUCTION TABLE
1 Team
Thermo Striper = 1 no. Foreman = 1 person
Pickup truck = 1 no. Operator = 1 person
Labour = 3 person
PRODUCTION TABLE