PRODUCTIVITY STANDARDS FOR CONSTRUCTION

TABLE OF CONTENTS

INFRASTRUCTURE WORKS BUILDING WORKS ID WORKS


STRUCTURE WORKS ARCHITECTURE WORKS

Pilecap/Footing

Plastering
Beam

Door & Window


Slab

Wall & Floor Finishes


Column
RC Wall
Roofing
SITE CLEARANCE

Standard Production Rate TOTAL AREA = 25.00 acre


(Please fill this)
1 Team Note: 1 acre = 4047 m2
Excavator = 1 nos.
Bulldozer = 1 nos.
Lorry/ Truck = 2 nos.
Foreman = 1 person
Operator = 4 person

Production Rate ,r = 1.000 acre/day for one team (within 3km dump area)
**(depend on distance of dump area)

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 25 days


= 4.2 week
= 1.0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excavator = 1 Foreman = 1
1 1 25 Bulldozer = 1 Operator = 4
Lorry/Truck = 2
Excavator = 2 Foreman = 1
0 2 Bulldozer = 2 Operator = 8
13 Lorry/Truck = 4
Excavator = 3 Foreman = 1
0 3 8 Bulldozer = 3 Operator = 12
Lorry/Truck = 6
Excavator = 4 Foreman = 1
0 4 6 Bulldozer = 4 Operator = 16
Lorry/Truck = 8
Excavator = 5 Foreman = 1
0 5 5 Bulldozer = 5 Operator = 20
Lorry/Truck = 10
FENCING WORKS (Concrete ,dig, erect, fix, post at 1.5 m)
Post Fence/Chainlink
Standard Production Rate TOTAL NOS. = 200.00 nos 100.00 lin.m

1 Team
Backhoe = 1 no. General Worker = 4 person
Truck 3 ton= 1 no. Operator = 2 person

1 feet = 0.3048 Meter


Post Erection (NOS) Fence Erection (LIN.M)

Production of Team/day 4 34 lin.m/day


Ref-RSMeans Books Page 117 &
www.planningplanet.com
\ TOTAL DAY REQUIRED FOR 50 6 days
ABOVE NOS. = 8.3 1.0 week
1.9 0.2 month

PRODUCTION TABLE

NO. OF TEAM POST DUR (Days) FENCE DUR (Days) Plant Labour
Backhoe = 1
Truck 3 ton= 1 neral Worker = 4
1 50 6 0 0 Operator = 2
0 0

Backhoe = 1
Truck 3 ton= 1 neral Worker = 8
2 25 3 0 0 Operator = 4
0 0

Backhoe = 1
Truck 3 ton= 1
0 0 neral Worker = 12
3 17 2
Operator = 6
0 0

Backhoe = 1
Truck 3 ton= 1
0 0 neral Worker = 16
4 13 1
Operator = 8
0 0

Backhoe = 1
Truck 3 ton= 1
0 0 neral Worker = 20
5 10 1
Operator = 10
0 0
SOIL INVESTIGATION

Standard Production Rate TOTAL POINT = 82.00 lin.m

1 Team
Drill Rig = 1 no. Foreman = 1 person
truck (3ton)= 1 no. Operator= 1
no.
Labour= 2 0

Production of One Rig (av. 20m depth)

Setting = 60 min
Driving = 420 min Production Per Day = (8hr x60min)
(1 rig) time per rig
Total Time = 480 min = 20 lin.m

Production Per Day = 20 lin.m


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE POINT = 4 days


= 0.7 week
= 0.2 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Drill Rig = 1 Foreman = 1
0.1576923 1 4 truck (3ton)= 1 Operator= 1
0 0 Labour= 2
0 0
Drill Rig = 2 Foreman = 1
0.0788462 2 2 truck (3ton)= 2 Operator = 2
0 0 Labour= 4
0 0
Drill Rig = 3 Foreman = 1
0.0525641 3 1 truck (3ton)= 3 Operator = 3
0 0 Labour= 6
0 0
Drill Rig = 4 Foreman = 1
0.0394231 4 1 truck (3ton)= 4 Operator = 4
0 0 Labour= 8
0 0
Drill Rig = 5 Foreman = 1
0.0315385 5 1 truck (3ton)= 5 Operator = 5
0 0 Labour= 10
0 0
Drill Rig = 6 Foreman = 1
0.0262821 6 1 truck (3ton)= 6 Operator = 6
0 0 Labour= 12
0 0
Drill Rig = 7 Foreman = 1
0.0225275 7 1 truck (3ton)= 7 Operator = 7
0 0 Labour= 14
0 0
Drill Rig = 8 Foreman = 1
0.0197115 8 1 truck (3ton)= 8 Operator = 8
0 0 Labour= 16
0 0
Drill Rig = 9 Foreman = 1
0.0175214 9 0 truck (3ton)= 9 Operator = 9
0 0 Labour= 18
0 0
Drill Rig = 10 Foreman = 2
0.0157692 10 0 truck (3ton)= 10 Operator = 10
0 0 Labour= 20
0 0
EXCAVATE (CUT & FILL) SUITABLE MATERIAL

Standard Production Rate TOTAL VOLUME = 524,000.00 cu.m

1 Team
Excavator = 3 no. Foreman = 1 person
Bulldozer = 1 no. Operator = 16 person
Backpusher = 1 no.
Vibrator roller = 2 no.
Dump Truck = 10 no.
Motor Grader = 1 no.

Production of One Truck

1 truck = 8 cu.m capacity 1 trip :


Haulage = 20 km Waiting = 2 minutes
Truck speed = 30 km/hr loading = 3 minutes
Travelling = 80 minutes
Travelling time = Haulage unload = 2 minutes
Speed Total = 87 minutes
= 1.3333 hr
= 80.00 minutes Time for 1 trip, n = 100.05 minutes
(15 % more)

* Truck Speed on site 20 km/hr - Dump Truck , Dump site (on road) 60 km/hr - Tipper Truck

\ Production of one truck, Q = (8hr x60min) x capacity


time per trip
= 38.38 cu.m/day

\ Production of one team, P = 384 cu.m/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 1365 days


= 227.5 week
= 52.5 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excavator = 2.5 Foreman = 1
Bulldozer = 0.5 Operator = 16
Backpusher = 0.5
1 1365
Vibrator roller = 2
Dump Truck = 10
Motor Grader = 0.5
Excavator = 5 Foreman = 2
Bulldozer = 1 Operator = 32
Backpusher = 1
2 683
Vibrator roller = 4
Dump Truck = 20
Motor Grader = 1
Excavator = 7.5 Foreman = 2
Bulldozer = 1.5 Operator = 48
Backpusher = 1.5
3 455
Vibrator roller = 6
Dump Truck = 30
Motor Grader = 1.5
Excavator = 10 Foreman = 3
Bulldozer = 2 Operator = 64
Backpusher = 2
4 341
Vibrator roller = 8
Dump Truck = 40
Motor Grader = 2
Excavator = 12.5 Foreman = 4
Bulldozer = 2.5 Operator = 80
Backpusher = 2.5
5 273
Vibrator roller = 10
Dump Truck = 50
Motor Grader = 2.5
Excavator = 15 Foreman = 5
Bulldozer = 3 Operator = 96
Backpusher = 3
6 228
Vibrator roller = 12
Dump Truck = 60
Motor Grader = 3
Excavator = 17.5 Foreman = 6
Bulldozer = 3.5 Operator = 112
Backpusher = 3.5
7 195
Vibrator roller = 14
Dump Truck = 70
Motor Grader = 3.5
Excavator = 20 Foreman = 6
Bulldozer = 4 Operator = 128
Backpusher = 4
8 171
Vibrator roller = 16
Dump Truck = 80
Motor Grader = 4
Excavator = 22.5 Foreman = 7
Bulldozer = 4.5 Operator = 144
Backpusher = 4.5
9 152
Vibrator roller = 18
Dump Truck = 90
Motor Grader = 4.5
Excavator = 25 Foreman = 8
Bulldozer = 5 Operator = 160
Backpusher = 5
10 137
Vibrator roller = 20
Dump Truck = 100
Motor Grader = 5
TRENCH EXCAVATION

Standard Production Rate TOTAL AREA = 500.00 cu.m

1 Team
Excavator (0.5cu.m bucket)= 1 nos.
Foreman = 1 person
Operator = 1 person

Production Rate , = 206.000 cu.m/day RSMeans Page 54


270 c.y

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 2 days


= 0.4 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excavator = 1 Foreman = 1
0 1 2 Operator = 1

Excavator = 2 Foreman = 1
0 2 Operator = 2
1
Excavator = 3 Foreman = 1
0 3 1 Operator = 3

Excavator = 4 Foreman = 1
0 4 1 Operator = 4

Excavator = 5 Foreman = 1
0 5 0 Operator = 5
Key-in
the
Quantity
PIPING (GAS SERVICE & DISTRIBUTION.Sch 40) Not including Excavation & Backfill

Standard Production Rate TOTAL NOS. = 100.00 lin.m

1 Team
Excavator = 1 no. Plumber = 2 person
Crane = 1 no. General Worker = 1 person
Welding Set = 1 no. Operator = 2 person

Pipe Diameter
4"dia. 6"dia. 12"dia. 24" dia
Production of Team 78 55 24 15 lin.m/day
Ref-RSMeans Books Page 100
1 feet = 0.3048 Meter
\ TOTAL DAY REQUIRED FOR 1 2 4 7 days
ABOVE NOS. = 0.2 0.3 0.7 1.1 week
0.0 0.1 0.2 0.3 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


4"dia.= 1 Excavator = 1
6"dia.= 2 Crane = 1 Plumber = 2
1 12"dia.= 4 Welding Set = 1 General Worker = 1
24" dia.= 7 Operator = 2

4"dia.= 1 Excavator = 1
6"dia.= 1 Crane = 1 Plumber = 4
2 12"dia.= 2 Welding Set = 2 General Worker = 2
24" dia.= 3 Operator = 4

4"dia.= 0 Excavator = 1
6"dia.= 1 Crane = 1
12"dia.= 1 Welding Set = 3 Plumber = 6
3
24" dia.= 2 General Worker = 3
Operator = 6

4"dia.= 0 Excavator = 1
6"dia.= 0 Crane = 1
12"dia.= 1 Welding Set = 4 Plumber = 8
4
24" dia.= 2 General Worker = 4
Operator = 8

4"dia.= 0 Excavator = 1
6"dia.= 0 Crane = 1
12"dia.= 1 Welding Set = 5 Plumber = 10
5
24" dia.= 1 General Worker = 5
Operator = 10
Key-in the
Quantity

SEWERAGE PIPE (VCP & Concrete Pipe) Not including Excavation & Backfill

Standard Production Rate TOTAL NOS. = 100.00 lin.m

1 Team
Excavator = 1 no. Plumber = 2 person
Crane (5 ton)= 1 no. General Worker = 1 person
Welding Set = 1 no. Operator = 2 person

1 feet = 0.3048 Meter


VCP Pipe Diameter Reinforce Culvert (Class 5), With gasket
6"dia. 12"dia. 18"dia. 24" dia 24"dia. 36"dia. 48"dia. 72" dia
Production of Team 61 46 27 14 47 34 18 12 lin.m/day
Ref-RSMeans Books Page 107 &112

\ TOTAL DAY REQUIRED FOR 2 2 4 7 2 3 6 9 days


ABOVE NOS. = 0.3 0.4 0.6 1.2 0.4 0.5 0.9 1.4 week
0.1 0.1 0.1 0.3 0.1 0.1 0.2 0.3 month

PRODUCTION TABLE

NO. OF TEAM VCP DUR (Days) CULVERT DUR (Days) Plant Labour
4"dia.= 2 24"dia. 2 Excavator = 1
6"dia.= 2 36"dia. 3 Crane (5 ton)= 1 Plumber = 2
1 12"dia.= 4 48"dia. 6 Welding Set = 1 neral Worker = 1
24" dia.= 7 72" dia 9 person 2

4"dia.= 1 24"dia. 1 Excavator = 1


6"dia.= 1 36"dia. 1 Crane (5 ton)= 1 Plumber = 4
2 12"dia.= 2 48"dia. 3 Welding Set = 2 neral Worker = 2
24" dia.= 4 72" dia 4 Operator = 4

4"dia.= 1 24"dia. 1 Excavator = 1


6"dia.= 1 36"dia. 1 Crane (5 ton)= 1
12"dia.= 1 48"dia. 2 Welding Set = 3 Plumber = 6
3
24" dia.= 2 72" dia 3 General Worker = 3
Operator = 6

4"dia.= 0 24"dia. 1 Excavator = 1


6"dia.= 1 36"dia. 1 Crane (5 ton)= 1
12"dia.= 1 48"dia. 1 Welding Set = 4 Plumber = 8
4
24" dia.= 2 72" dia 2 General Worker = 4
Operator = 8

4"dia.= 0 24"dia. 0 Excavator = 1


6"dia.= 0 36"dia. 1 Crane (5 ton)= 1
12"dia.= 1 48"dia. 1 Welding Set = 5 Plumber = 10
5
24" dia.= 1 72" dia 2 General Worker = 5
Operator = 10
EXCAVATE (CUT AND FILL) SUITABLE MATERIAL

Standard Production Rate TOTAL VOLUME = 1,560.00 ton

1 Team
Excavator = 8 no. Foreman = 2 person
Bulldozer = 1 no. Operator = 41.5 person
Backpusher = 1 no.
Vibrator roller = 2 no.
Tipper Truck = 30 no.

Production of One Truck

1 Tiper truck = 15 ton capacity 1 trip :


Haulage = 25 km Waiting = 2 minutes
Truck speed = 30 km/hr loading = 3 minutes
Travelling = 100 minutes
Travelling time = Haulage unload = 2 minutes
Speed Total = 107 minutes
= 1.6667 hr
= 100.00 minutes Time for 1 trip, n = 123.05 minutes
(15 % more)

\ Production of one truck, Q = (8hr x60min) x capacity


time per trip
= 58.51 ton/day per trip

\ Production of one team, P = 1755 ton/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 1 days


= 0.1 week
= 0.0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excavator = 7.5 Foreman = 2
Bulldozer = 1 Operator = 42
0 Backpusher = 1
1 1
Vibrator roller = 2
Dump Truck = 30
Motor Grader = 0
Excavator = 15 Foreman = 4
Bulldozer = 2 Operator = 83
0 Backpusher = 2
2 0
Vibrator roller = 4
Dump Truck = 60
Motor Grader = 0
Excavator = 22.5 Foreman = 6
Bulldozer = 3 Operator = 125
0 Backpusher = 3
3 0
Vibrator roller = 6
Dump Truck = 90
Motor Grader = 0
Excavator = 30 Foreman = 8
Bulldozer = 4 Operator = 166
0 Backpusher = 4
4 0
Vibrator roller = 8
Dump Truck = 120
Motor Grader = 0
Excavator = 37.5 Foreman = 10
Bulldozer = 5 Operator = 208
0 Backpusher = 5
5 0
Vibrator roller = 10
5 0
Dump Truck = 150
Motor Grader = 0
TURFING

Standard Production Rate TOTAL VOLUME = 68,000.00 sq.m

1 Team
Lorry = 1 no. Labour = 8 person

Production of one labour, P = 15 sq.m/hr = 120 sq.m/day


Production of one Team, P = 960.00 sq.m/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 71 days


= 11.8 week
= 2.7 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Lorry = 1 Labour = 8

1 71

Lorry = 2 Labour = 16

2 35

Lorry = 3 Labour = 24

3 24

Lorry = 4 Labour = 32

4 18

Lorry = 5 Labour = 40

5 14
VERTICAL DRAIN

Standard Production Rate TOTAL VOLUME = 1,419,500.00 lin.m

1 Team
PVD Rig = 1 no. Foreman = 1 person
Lorry = 1 no. Operator = 2 person
Labour = 2 person

Production of one team, P = 3500 lin.m/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 406 days


= 67.6 week
= 15.6 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


PVD Rig = 1 Foreman = 1
16 Lorry = 1 Operator = 2
1 406
Labour = 2

PVD Rig = 2 Foreman = 1


8 Lorry = 2 Operator = 4
2 203
Labour = 4

PVD Rig = 3 Foreman = 1


5 Lorry = 3 Operator = 6
3 135
0 0 Labour = 6

PVD Rig = 4 Foreman = 1


Lorry = 4 Operator = 8
4 101
4 0 0 Labour = 8

PVD Rig = 5 Foreman = 1


Lorry = 5 Operator = 10
5 81
3 0 0 Labour = 10

PVD Rig = 6 Foreman = 1


Lorry = 6 Operator = 12
6 68
3 0 0 Labour = 12
STEEL SHEET PILING

Standard Production Rate TOTAL POINT = 300.00 lin.m

1 Team
Vibro Hammer = 1 no. Foreman = 1 person
Crane = 1 no. (40 ton) Operator = 2 person
Genset = 1 no. General Worker = 4 person

1 sheet pile = 9 m length = 2.74 sq.m

Production of TEAM (av. 7.6m depth)

Production Per Day = 100 sq.m 36

0 \7.6m depth = 13 lin.m

Production Per Day = 13 lin.m


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE = 23 days


= 3.8 week
= 0.9 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Vibro Hammer = 1 Foreman = 1
Crane = 1 Operator = 2
Genset = 1 neral Worker = 4
1 23 0 0 0 0
0 0 0 0
0 0
e = 9 m length = 0
Vibro Hammer = 2 Foreman = 1
Crane = 2 Operator = 4
Genset = 2 neral Worker = 8
2 11 0 0 0 0
0 0 0 0
0 0
e = 9 m length = 0
Vibro Hammer = 3 Foreman = 1
Crane = 3 Operator = 6
Genset = 3 neral Worker = 12
3 8 0 0 0 0
0 0 0 0
0 0
e = 9 m length = 0
Vibro Hammer = 4 Foreman = 1
Crane = 4 Operator = 8
Genset = 4 neral Worker = 16
4 6 0 0 0 0
0 0 0 0
0 0
e = 9 m length = 0
Vibro Hammer = 5 Foreman = 2
Crane = 5 Operator = 10
Genset = 5 neral Worker = 20
5 5 0 0 0 0
0 0 0 0
0 0
5 5

e = 9 m length = 0
PRECAST RC&SPUN PILING

Standard Production Rate TOTAL POINT = 4,059.00 pts.

1 Team
Piling Rig = 1 no. Foreman = 1 person
Crane (20ton) = 1 no. Operator = 2 person
Welding Set = 1 no. Welder = 1 person
Labour= 2 person

Production of One Rig (av. 24m depth)

Setting = 25 min
Driving = 45 min Production Per Day = (8hr x60min)
Welding = 25 min (1 rig) time per rig
Total Time = 95 min = 5 pts.

Production Per Day = 5 pts.


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE POINT = 803 days


= 133.9 week
= 30.9 month

PRODUCTION TABLE

MONTH NO. OF TEAM DURATION (Days) Plant Labour


Piling Rig = 1 Foreman = 1
31 1 803 Crane (20ton) = 1 Operator = 2
Welding Set = 1 Welder = 1
Labour = 2
Piling Rig = 2 Foreman = 1
15 2 402 Crane (20ton) = 2 Operator = 4
Welding Set = 2 Welder = 2
Labour = 4
Piling Rig = 3 Foreman = 1
10 3 268 Crane (20ton) = 3 Operator = 6
Welding Set = 3 Welder = 3
Labour = 6
Piling Rig = 4 Foreman = 1
8 4 201 Crane (20ton) = 4 Operator = 8
Welding Set = 4 Welder = 4
Labour = 8
Piling Rig = 5 Foreman = 1
6 5 161 Crane (20ton) = 5 Operator = 10
Welding Set = 5 Welder = 5
Labour = 10
Piling Rig = 6 Foreman = 1
5 6 134 Crane (20ton) = 6 Operator = 12
Welding Set = 6 Welder = 6
Labour = 12
Piling Rig = 7 Foreman = 1
4 7 115 Crane (20ton) = 7 Operator = 14
Welding Set = 7 Welder = 7
Labour = 14
Piling Rig = 8 Foreman = 1
4 8 100 Crane (20ton) = 8 Operator = 16
Welding Set = 8 Welder = 8
Labour = 16
Piling Rig = 9 Foreman = 1
3 9 89 Crane (20ton) = 9 Operator = 18
Welding Set = 9 Welder = 9
Labour = 18
Piling Rig = 10 Foreman = 2
3 10 80 Crane (20ton) = 10 Operator = 20
Welding Set = 10 Welder = 10
Labour = 20
Key-in the
Quantity
GUARD RAIL (Corrugated Steel, Galv, Steel Post, 6')

Standard Production Rate TOTAL NOS. = 1,000.00 lin.m

1 Team
racktor with hammer = 1 no. General Worker = 3 person
Truck 3 ton= 1 no. Operator = 2 person

Production of Team 259 lin.m/day


Ref-RSMeans Books Page 120
1 feet = 0.3048 Meter
\ TOTAL DAY REQUIRED FOR 4 days
ABOVE NOS. = 0.6 week
0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


r with hammer = 1
Truck 3 ton= 1 General Worker = 3
1 4 0 0 Operator = 2
0 0

r with hammer = 1
Truck 3 ton= 1 General Worker = 6
2 2 0 0 Operator = 4
0 0

r with hammer = 1
Truck 3 ton= 1
0 0 General Worker = 9
3 1
Operator = 6
0 0

r with hammer = 1
Truck 3 ton= 1
0 0 General Worker = 12
4 1
Operator = 8
0 0

r with hammer = 1
Truck 3 ton= 1
0 0 General Worker = 15
5 1
Operator = 10
0 0
FOUNDATION - BORE PILING

Standard Production Rate TOTAL POINT = 1,200.00 pts.

1 Team
Boring Rig = 1 no. Foreman = 1 person
Crawler Crane = 1 no. Operator = 3 person
Vibro Hammer = 1 no. Bar Bender = 2 person
Bar Bender = 1 no. Bar Cutter = 1 person
Bar Cutter = 1 no. General Worker = 1 person
Concrete Vibrator = 1 no.
Mobile Pumps = 1 no.

Production of One Rig (av. 24m depth)


Setting out= 20 min
Casing Driven = 60 min
Drill & Excavation = 45 min Production Per Day = (8hr x60min)
Concreting = 40 min (1 rig) time per rig
Total Time = 165 min = 3 pts.

Production Per Day = 3 pts.


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE POINT = 413 days


= 68.8 week
= 15.9 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Boring Rig = 1 Foreman = 1
Crawler Crane = 1 Operator = 3
Vibro Hammer = 1 Bar Bender = 2
1 413 Bar Bender = 1 Bar Cutter = 1
Bar Cutter = 1 eneral Worker = 1
crete Vibrator = 1
Mobile Pumps = 1
Boring Rig = 2 Foreman = 1
Crawler Crane = 2 Operator = 6
Vibro Hammer = 2 Bar Bender = 4
2 206 Bar Bender = 2 Bar Cutter = 2
Bar Cutter = 2 eneral Worker = 2
crete Vibrator = 2
Mobile Pumps = 2
Boring Rig = 3 Foreman = 1
Crawler Crane = 3 Operator = 9
Vibro Hammer = 3 Bar Bender = 6
3 138 Bar Bender = 3 Bar Cutter = 3
Bar Cutter = 3 eneral Worker = 3
crete Vibrator = 3
Mobile Pumps = 3
Boring Rig = 4 Foreman = 1
Crawler Crane = 4 Operator = 12
Vibro Hammer = 4 Bar Bender = 8
4 103 Bar Bender = 4 Bar Cutter = 4
Bar Cutter = 4 eneral Worker = 4
crete Vibrator = 4
Mobile Pumps = 4
Boring Rig = 5 Foreman = 2
Crawler Crane = 5 Operator = 15
Vibro Hammer = 5 Bar Bender = 10
5 83 Bar Bender = 5 Bar Cutter = 5
Bar Cutter = 5 eneral Worker = 5
crete Vibrator = 5
Mobile Pumps = 5
FOUNDATION - PILECAP

Standard Production Rate TOTAL NOS. = 127.00 nos.

1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Mobile Crane = 1 no. Operator = 2 person
Bar Bender = 1 no. Bar Bender = 2 person
Bar Cutter = 1 no. Bar Cutter = 1 person
Concrete Vibrator = 1 no. Carpenter = 3 person
Mobile Pumps = 1 no. Concretor = 2 person
Concrete Mixer = 1 no. General Worker = 1 person

Production of Team

Excavation = 5 min
Lean Con/ Curing = 90 min
Rebar = 30 min Production = 2 caps / 6 days
Formwork = 20 min
Concreting = 15 min
Total Time = 160 min

Production Per Day = 0.33 nos.


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 381 days


= 63.6 week
= 14.7 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


cav./ Backhoe = 1 Foreman = 1
Mobile Crane = 1 Operator = 2
Bar Bender = 1 Bar Bender = 2
14.668515 1 381 Bar Cutter = 1 Bar Cutter = 1
crete Vibrator = 1 Carpenter = 3
Mobile Pumps = 1 Concretor = 2
oncrete Mixer = 1 eneral Worker = 1
cav./ Backhoe = 2 Foreman = 1
Mobile Crane = 2 Operator = 4
Bar Bender = 2 Bar Bender = 4
7.3342573 2 191 Bar Cutter = 2 Bar Cutter = 2
crete Vibrator = 2 Carpenter = 6
Mobile Pumps = 2 Concretor = 4
oncrete Mixer = 2 eneral Worker = 2
cav./ Backhoe = 3 Foreman = 2
Mobile Crane = 3 Operator = 6
Bar Bender = 3 Bar Bender = 6
4.8895049 3 127 Bar Cutter = 3 Bar Cutter = 3
crete Vibrator = 3 Carpenter = 9
Mobile Pumps = 3 Concretor = 6
oncrete Mixer = 3 eneral Worker = 3
cav./ Backhoe = 4 Foreman = 2
Mobile Crane = 4 Operator = 8
Bar Bender = 4 Bar Bender = 8
3.6671287 4 95 Bar Cutter = 4 Bar Cutter = 4
crete Vibrator = 4 Carpenter = 12
Mobile Pumps = 4 Concretor = 8
oncrete Mixer = 4 eneral Worker = 4
cav./ Backhoe = 5 Foreman = 3
Mobile Crane = 5 Operator = 10
Bar Bender = 5 Bar Bender = 10
5 76 Bar Cutter = 5 Bar Cutter = 5
crete Vibrator = 5 Carpenter = 15
5 76

Mobile Pumps = 5 Concretor = 10


oncrete Mixer = 5 eneral Worker = 5
Key-in the
PILECAP- FORMWORK (Square or rectangular) Quantity

Standard Production Rate TOTAL NOS. = 53.00 sq.m

1 Team
Excav./ Backhoe = 1 no. Carpenter = 3 person
Mobile Pumps = 1 no. General Worker = 1 person
Operator = 1 person

Production of Team

Production Per Day = 27 sq.m


(1 team) (*Ref-Means Books)
page 149
\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 2 days
= 0.3 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


cav./ Backhoe = 1
Mobile Pumps = 1 Carpenter = 3
1 2 General Worker = 1
Operator = 1

cav./ Backhoe = 1
Mobile Pumps = 1 Carpenter = 6
2 1 General Worker = 2
Operator = 2

cav./ Backhoe = 1
Mobile Pumps = 1
Carpenter = 9
3 1
General Worker = 3
Operator = 3

cav./ Backhoe = 1
Mobile Pumps = 1
Carpenter = 12
4 0
General Worker = 4
Operator = 4

cav./ Backhoe = 1
Mobile Pumps = 1
Carpenter = 15
5 0
General Worker = 5
Operator = 5
Key-in the
PILECAP/FOOTING-REINFORCEMENT Quantity

4254 kg 0.0011023 ton (US Convertion)

Standard Production Rate TOTAL NOS. = 52.00 TON

1 Team
Barbender Machine = 1 no. Barbender = 4 person
Barcuter Machine = 1 no.
Mobile Pumps = 1 no.

Production of Team

Production Per Day = 2.1 ton


(1 team) (*Ref-Means Books)
page 154
\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 25 days
= 4.1 week
= 1.0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour

Barbender = 4
1 25

Barbender = 8
2 12

3 8 Barbender = 12

4 6 Barbender = 16

5 5 Barbender = 20
Key-in the
PILECAP/FOOTING - PLACE CONCRETE(with crane & bucket) Quantity

Standard Production Rate TOTAL NOS. = 200.00 cu.m

1 Team
Mobile Crane (55ton) = 3 no. Concretor = 5 person
Concrete Vibrator = 2 no. Operator = 3 person

Production of Team

Production Per Day = 69 cu.m


(1 team) (*Ref-Means Books)
page 160
\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 3 days
= 0.5 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Crane (55ton) = 3
crete Vibrator = 2 Concretor = 5
1 3 Operator = 3

Crane (55ton) = 6
Concretor = 10
2 1
Operator = 6

Crane (55ton) = 9

3 1 Concretor = 15
Operator = 9

Crane (55ton) = 12

4 1 Concretor = 20
Operator = 12

Crane (55ton) = 15

5 1 Concretor = 25
Operator = 15
FOUNDATION - PILECAP

Standard Production Rate TOTAL NOS. = 53.00 nos.

1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Mobile Crane = 1 no. Operator = 2 person
Bar Bender = 1 no. Bar Bender = 2 person
Bar Cutter = 1 no. Bar Cutter = 1 person
Concrete Vibrator = 1 no. Carpenter = 3 person
Mobile Pumps = 1 no. Concretor = 2 person
Concrete Mixer = 1 no. General Worker = 1 person

Production of Team

Excavation = 5 min
Lean Con/ Curing = 90 min
Rebar = 30 min
Formwork = 20 min
Concreting = 15 min
Total Time = 160 min

Production Per Day = 3 nos.


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 18 days


= 2.9 week
= 0.7 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


cav./ Backhoe = 1 Foreman = 1
Mobile Crane = 1 Operator = 2
Bar Bender = 1 Bar Bender = 2
1 18 Bar Cutter = 1 Bar Cutter = 1
crete Vibrator = 1 Carpenter = 3
Mobile Pumps = 1 Concretor = 2
oncrete Mixer = 1 eneral Worker = 1
cav./ Backhoe = 2 Foreman = 1
Mobile Crane = 2 Operator = 4
Bar Bender = 2 Bar Bender = 4
2 9 Bar Cutter = 2 Bar Cutter = 2
crete Vibrator = 2 Carpenter = 6
Mobile Pumps = 2 Concretor = 4
oncrete Mixer = 2 eneral Worker = 2
cav./ Backhoe = 3 Foreman = 2
Mobile Crane = 3 Operator = 6
Bar Bender = 3 Bar Bender = 6
3 6 Bar Cutter = 3 Bar Cutter = 3
crete Vibrator = 3 Carpenter = 9
Mobile Pumps = 3 Concretor = 6
oncrete Mixer = 3 eneral Worker = 3
cav./ Backhoe = 4 Foreman = 2
Mobile Crane = 4 Operator = 8
Bar Bender = 4 Bar Bender = 8
4 4 Bar Cutter = 4 Bar Cutter = 4
crete Vibrator = 4 Carpenter = 12
Mobile Pumps = 4 Concretor = 8
oncrete Mixer = 4 eneral Worker = 4
cav./ Backhoe = 5 Foreman = 3
Mobile Crane = 5 Operator = 10
Bar Bender = 5 Bar Bender = 10
5 4 Bar Cutter = 5 Bar Cutter = 5
crete Vibrator = 5 Carpenter = 15
5 4

Mobile Pumps = 5 Concretor = 10


oncrete Mixer = 5 eneral Worker = 5
FOUNDATION - COLUMN STUMP

Standard Production Rate TOTAL NOS. = 20.00 nos.

1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Bar Bender = 1 no. Operator = 1 person
Bar Cutter = 1 no. Bar Bender = 2 person
Concrete Vibrator = 1 no. Bar Cutter = 1 person
Carpenter = 3 person
Concretor = 1 person
General Worker = 1 person

Production of Team

Rebar = 10 min
Formwork = 30 min
Concreting = 10 min
Total Time = 50 min

Production Per Day = 10 nos.


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 2 days


= 0.3 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


cav./ Backhoe = 1 Foreman = 1
Bar Bender = 1 Operator = 1
Bar Cutter = 1 Bar Bender = 2
1 2 crete Vibrator = 1 Bar Cutter = 1
0 0 Carpenter = 3
0 0 Concretor = 1
0 0 neral Worker = 1
cav./ Backhoe = 2 Foreman = 1
Bar Bender = 2 Operator = 2
Bar Cutter = 2 Bar Bender = 4
2 1 crete Vibrator = 2 Bar Cutter = 2
0 0 Carpenter = 6
0 0 Concretor = 2
0 0 neral Worker = 2
cav./ Backhoe = 3 Foreman = 1
Bar Bender = 3 Operator = 3
Bar Cutter = 3 Bar Bender = 6
3 1 crete Vibrator = 3 Bar Cutter = 3
0 0 Carpenter = 9
0 0 Concretor = 3
0 0 neral Worker = 3
cav./ Backhoe = 4 Foreman = 2
Bar Bender = 4 Operator = 4
Bar Cutter = 4 Bar Bender = 8
4 1 crete Vibrator = 4 Bar Cutter = 4
0 0 Carpenter = 12
0 0 Concretor = 4
0 0 neral Worker = 4
cav./ Backhoe = 5 Foreman = 2
Bar Bender = 5 Operator = 5
Bar Cutter = 5 Bar Bender = 10
5 0 crete Vibrator = 5 Bar Cutter = 5
0 0 Carpenter = 15
0 0 Concretor = 5
5 0

0 0 neral Worker = 5
Key-in the
BEAM (Formworks - 2 use) Quantity

Standard Production Rate TOTAL AREA = 8,352.00 m2

1 Team
Power Tools = 4 no. Carpenter = 4 person
General Worker = 1 person

Production of 1 Team for 54 m2/day (*Ref-Means Books)


Page 149

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 155 days


= 25.8 week
= 5.9 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Power Tools = 4 Carpenter = 4
0 0 eneral Worker = 1
0 0 0 0
1 155

Power Tools = 8 Carpenter = 8


0 0 eneral Worker = 2
0 0 0 0
2 77

Power Tools = 12 Carpenter = 12


0 0 eneral Worker = 3
0 0 0 0
3 52

Power Tools = 16 Carpenter = 16


0 0 eneral Worker = 4
0 0 0 0
4 39

Power Tools = 20 Carpenter = 20


0 0 eneral Worker = 5
0 0 0 0
5 31
Key-in the
Quantity
BEAM (Fix Rebar - Diameter 9.5mm to 22.2mm)
362120 kg 0.0011023 ton (US Convertion)

Standard Production Rate TOTAL AREA = 399.16 Ton

1 Team
Barbender Machine = 9 no. Barbender = 4 person
Barcuter Machine = 9 no.

Production of 1 Team for 1.6 ton/day (*Ref-Means Books)


Page 153

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 249 days


= 41.6 week
= 9.6 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


nder Machine = 4 Barbender = 4
cuter Machine = 8.553533057 0 0
0 0 0 0
1 249

nder Machine = 8 Barbender = 8


cuter Machine = 17.10706611 0 0
0 0 0 0
2 125

nder Machine = 12 Barbender = 12


cuter Machine = 25.66059917 0 0
0 0 0 0
3 83

nder Machine = 16 Barbender = 16


cuter Machine = 34.21413223 0 0
0 0 0 0
4 62

nder Machine = 20 Barbender = 20


cuter Machine = 42.76766529 0 0
0 0 0 0
5 50
Key-in the
BEAM (Concrete with crane & bucket) Quantity

Standard Production Rate TOTAL AREA = 1,646.00 cu.m

1 Team
Mobile Crane (55ton) = 1 no. Concretor = 4 person
Concrete Vibrator = 2 no. General Worker = 1 person

Production of 1 Team for 34.4 cum/day (*Ref-Means Books)


Page 158

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 48 days


= 8.0 week
= 1.8 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane (55ton) = 1 Concretor = 4
Concrete Vibrator = 2 eneral Worker = 1
0 0 0 0
1 48

Mobile Crane (55ton) = 2 Concretor = 8


Concrete Vibrator = 4 eneral Worker = 2
0 0 0 0
2 24

Mobile Crane (55ton) = 3 Concretor = 12


Concrete Vibrator = 6 eneral Worker = 3
0 0 0 0
3 16

Mobile Crane (55ton) = 4 Concretor = 16


Concrete Vibrator = 8 eneral Worker = 4
0 0 0 0
4 12

Mobile Crane (55ton) = 5 Concretor = 20


Concrete Vibrator = 10 eneral Worker = 5
0 0 0 0
5 10
Key-in the
SLAB (Formworks - On Grade & Elevated ) Quantity

Standard Production Rate TOTAL AREA = 65.00 m2

1 Team
Power Tools = 4 no. Carpenter = 4 person
General Worker = 1 person

SP of 1 Team - Slab on Grade 88 m2/day (*HPC Production Rate)


SP of 1 Team - Elevated Slab 46 m2/day (*Ref-Means Books page 147)

On Grade Elevated
\ TOTAL DAY REQUIRED FOR ABOVE AREA = 1 days 1 days
= 0.1 week 0.2 week
= 0.0 month 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Power Tools = 4 Carpenter = 4
On Grade 1 0 0 eneral Worker = 1
0 0 0 0
1 Elevated 1

Power Tools = 8 Carpenter = 8


On Grade 0 0 0 eneral Worker = 2
0 0 0 0
2 Elevated 1

Power Tools = 12 Carpenter = 12


On Grade 0 0 0 eneral Worker = 3
0 0 0 0
3 Elevated 0

Power Tools = 16 Carpenter = 16


On Grade 0 0 0 eneral Worker = 4
0 0 0 0
4 Elevated 0

Power Tools = 20 Carpenter = 20


On Grade 0 0 0 eneral Worker = 5
0 0 0 0
5 Elevated 0
Key-in the
Quantity

SLAB (Rebar - On Grade & Elevated ) 368 kg 0.0011023 ton (US Convertion)

Standard Production Rate TOTAL AREA = 0.41 ton

1 Team
Barbender Machine = 1 no. Barbender = 4 person
Barcuter Machine = 1 no.
Mobile Crane (25ton) = 1 no.
SP of 1 Team - Slab on Grade 2.3 ton/day
SP of 1 Team - Elevated Slab 2.9 ton/day (*Ref-Means Books page 154)

On Grade Elevated
\ TOTAL DAY REQUIRED FOR ABOVE AREA = 0 days 0 days
= 0.0 week 0.0 week
= 0.0 month 0.0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Barbender Machine = 4 Barbender = 4
On Grade 0 Barcuter Machine = 1 0 0
Mobile Crane (25ton) = 1 0 0
1 Elevated 0

Barbender Machine = 8 Barbender = 8


On Grade 0 Barcuter Machine = 2 0 0
Mobile Crane (25ton) = 2 0 0
2 Elevated 0

Barbender Machine = 12 Barbender = 12


On Grade 0 Barcuter Machine = 3 0 0
Mobile Crane (25ton) = 3 0 0
3 Elevated 0

Barbender Machine = 16 Barbender = 16


On Grade 0 Barcuter Machine = 4 0 0
Mobile Crane (25ton) = 4 0 0
4 Elevated 0

Barbender Machine = 20 Barbender = 20


On Grade 0 Barcuter Machine = 5 0 0
Mobile Crane (25ton) = 5 0 0
5 Elevated 0
Key-in the
Slab (Concrete with crane & bucket-0.76 cu.m) Quantity

Standard Production Rate TOTAL AREA = 2,700.00 cu.m

1 Team
Mobile Crane (55ton) = 1 no. Concretor = 4 person
Concrete Vibrator = 2 no. General Worker = 1 person
Operator = 1 person

Production of 1 Team for 73 cum/day (*Ref-Means Books)


Page 159

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 37 days


= 6.2 week
= 1.4 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane (55ton) = 1 Concretor = 4
Concrete Vibrator = 2 eneral Worker = 1
0 0 Operator = 1
1 37

Mobile Crane (55ton) = 2 Concretor = 8


Concrete Vibrator = 4 eneral Worker = 2
0 0 Operator = 2
2 18

Mobile Crane (55ton) = 3 Concretor = 12


Concrete Vibrator = 6 eneral Worker = 3
0 0 Operator = 3
3 12

Mobile Crane (55ton) = 4 Concretor = 16


Concrete Vibrator = 8 eneral Worker = 4
0 0 Operator = 4
4 9

Mobile Crane (55ton) = 5 Concretor = 20


Concrete Vibrator = 10 eneral Worker = 5
0 0 Operator = 5
5 7
Key-in the
TOPPING SLAB Quantity

Standard Production Rate TOTAL AREA = 1,024.00 cu.m

1 Team
Mobile Crane (55ton) = 1 no. Mason = 1 person
Concrete Vibrator = 1 no. General Worker = 2 person
Operator = 1 person

Production of 1 Team for 24 sq.m/day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 43 days


= 7.1 week
= 1.6 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane (55ton) = 1 Mason = 1
Concrete Vibrator = 1 General Worker = 2
0 0 Operator = 1
1 43

Mobile Crane (55ton) = 2 Mason = 2


Concrete Vibrator = 2 General Worker = 4
0 0 Operator = 2
2 21

Mobile Crane (55ton) = 3 Mason = 3


Concrete Vibrator = 3 General Worker = 6
0 0 Operator = 3
3 14

Mobile Crane (55ton) = 4 Mason = 4


Concrete Vibrator = 4 General Worker = 8
0 0 Operator = 4
4 11

Mobile Crane (55ton) = 5 Mason = 5


Concrete Vibrator = 5 General Worker = 10
0 0 Operator = 5
5 9
BEAM & SLAB

Standard Production Rate TOTAL AREA = 10,402.00 m2

1 Team
Mobile Crane = 1 no. Foreman = 1 person
Bar Bender = 1 no. Operator = 1 person
Bar Cutter = 1 no. Bar Bender = 4 person
Concrete Vibrator = 2 no. Bar Cutter = 4 person
Hand Compactor = 1 no. Carpenter = 5 person
Concretor = 4 person
General Worker = 2 person

200 ori
Production of 1 Team for 270 m2

Rebar = 7 day
Formwork = 5 day
Concreting = 2 day
Total Time = 14 day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 539 days


= 89.9 week
= 20.7 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane = 1 Foreman = 1
Bar Bender = 1 Operator = 1
90 Bar Cutter = 1 Bar Bender = 4
21 1 539 Concrete Vibrator = 2 Bar Cutter = 4
Hand Compactor = 1 Carpenter = 5
0 0 Concretor = 4
0 0 neral Worker = 2
Mobile Crane = 2 Foreman = 2
Bar Bender = 2 Operator = 2
45 Bar Cutter = 2 Bar Bender = 8
10 2 270 Concrete Vibrator = 4 Bar Cutter = 8
Hand Compactor = 2 Carpenter = 10
0 0 Concretor = 8
0 0 neral Worker = 4
Mobile Crane = 3 Foreman = 3
Bar Bender = 3 Operator = 3
30 Bar Cutter = 3 Bar Bender = 12
7 3 180 Concrete Vibrator = 6 Bar Cutter = 12
Hand Compactor = 3 Carpenter = 15
0 0 Concretor = 12
0 0 neral Worker = 6
Mobile Crane = 4 Foreman = 4
Bar Bender = 4 Operator = 4
22 Bar Cutter = 4 Bar Bender = 16
5 4 135 Concrete Vibrator = 8 Bar Cutter = 16
Hand Compactor = 4 Carpenter = 20
0 0 Concretor = 16
0 0 neral Worker = 8
Mobile Crane = 5 Foreman = 5
Bar Bender = 5 Operator = 5
18 Bar Cutter = 5 Bar Bender = 20
4 5 108 Concrete Vibrator = 10 Bar Cutter = 20
Hand Compactor = 5 Carpenter = 25
0 0 Concretor = 20
0 0 neral Worker = 10
Mobile Crane = 6 Foreman = 6
Bar Bender = 6 Operator = 6
15 Bar Cutter = 6 Bar Bender = 24
3 6 90 Concrete Vibrator = 12 Bar Cutter = 24
Hand Compactor = 6 Carpenter = 30
0 0 Concretor = 24
0 0 neral Worker = 12
Mobile Crane = 7 Foreman = 7
Bar Bender = 7 Operator = 7
13 Bar Cutter = 7 Bar Bender = 28
3 7 77 Concrete Vibrator = 14 Bar Cutter = 28
Hand Compactor = 7 Carpenter = 35
0 0 Concretor = 28
0 0 neral Worker = 14
Mobile Crane = 8 Foreman = 8
Bar Bender = 8 Operator = 8
11 Bar Cutter = 8 Bar Bender = 32
3 8 67 Concrete Vibrator = 16 Bar Cutter = 32
Hand Compactor = 8 Carpenter = 40
0 0 Concretor = 32
0 0 neral Worker = 16
Mobile Crane = 9 Foreman = 9
Bar Bender = 9 Operator = 9
10 Bar Cutter = 9 Bar Bender = 36
2 9 60 Concrete Vibrator = 18 Bar Cutter = 36
Hand Compactor = 9 Carpenter = 45
0 0 Concretor = 36
0 0 neral Worker = 18
Mobile Crane = 10 Foreman = 10
Bar Bender = 10 Operator = 10
9 Bar Cutter = 10 Bar Bender = 40
2 10 54 Concrete Vibrator = 20 Bar Cutter = 40
Hand Compactor = 10 Carpenter = 50
0 0 Concretor = 40
0 0 neral Worker = 20
Mobile Crane = 11 Foreman = 11
Bar Bender = 11 Operator = 11
8 Bar Cutter = 11 Bar Bender = 44
2 11 49 Concrete Vibrator = 22 Bar Cutter = 44
Hand Compactor = 11 Carpenter = 55
0 0 Concretor = 44
0 0 neral Worker = 22
Mobile Crane = 12 Foreman = 12
Bar Bender = 12 Operator = 12
7 Bar Cutter = 12 Bar Bender = 48
2 12 45 Concrete Vibrator = 24 Bar Cutter = 48
Hand Compactor = 12 Carpenter = 60
0 0 Concretor = 48
0 0 neral Worker = 24
Mobile Crane = 13 Foreman = 13
Bar Bender = 13 Operator = 13
7 Bar Cutter = 13 Bar Bender = 52
2 13 41 Concrete Vibrator = 26 Bar Cutter = 52
Hand Compactor = 13 Carpenter = 65
0 0 Concretor = 52
0 0 neral Worker = 26
Mobile Crane = 14 Foreman = 14
Bar Bender = 14 Operator = 14
6 Bar Cutter = 14 Bar Bender = 56
1 14 39 Concrete Vibrator = 28 Bar Cutter = 56
Hand Compactor = 14 Carpenter = 70
0 0 Concretor = 56
0 0 neral Worker = 28
Mobile Crane = 15 Foreman = 15
Bar Bender = 15 Operator = 15
6 Bar Cutter = 15 Bar Bender = 60
1 15 36 Concrete Vibrator = 30 Bar Cutter = 60
Hand Compactor = 15 Carpenter = 75
0 0 Concretor = 60
0 0 neral Worker = 30
Mobile Crane = 16 Foreman = 16
Bar Bender = 16 Operator = 16
6 Bar Cutter = 16 Bar Bender = 64
1 16 34 Concrete Vibrator = 32 Bar Cutter = 64
Hand Compactor = 16 Carpenter = 80
0 0 Concretor = 64
0 0 neral Worker = 32
Mobile Crane = 17 Foreman = 17
Bar Bender = 17 Operator = 17
5 Bar Cutter = 17 Bar Bender = 68
1 17 32 Concrete Vibrator = 34 Bar Cutter = 68
Hand Compactor = 17 Carpenter = 85
0 0 Concretor = 68
0 0 neral Worker = 34
Mobile Crane = 18 Foreman = 18
Bar Bender = 18 Operator = 18
5 Bar Cutter = 18 Bar Bender = 72
1 18 30 Concrete Vibrator = 36 Bar Cutter = 72
Hand Compactor = 18 Carpenter = 90
0 0 Concretor = 72
0 0 neral Worker = 36
Mobile Crane = 19 Foreman = 19
Bar Bender = 19 Operator = 19
5 Bar Cutter = 19 Bar Bender = 76
1 19 28 Concrete Vibrator = 38 Bar Cutter = 76
Hand Compactor = 19 Carpenter = 95
0 0 Concretor = 76
0 0 neral Worker = 38
Mobile Crane = 20 Foreman = 20
Bar Bender = 20 Operator = 20
4 Bar Cutter = 20 Bar Bender = 80
1 20 27 Concrete Vibrator = 40 Bar Cutter = 80
Hand Compactor = 20 Carpenter = 100
0 0 Concretor = 80
0 0 neral Worker = 40
Mobile Crane = 21 Foreman = 21
Bar Bender = 21 Operator = 21
4 Bar Cutter = 21 Bar Bender = 84
1 21 26 Concrete Vibrator = 42 Bar Cutter = 84
Hand Compactor = 21 Carpenter = 105
21 26

0 0 Concretor = 84
0 0 neral Worker = 42
Key-in the
COLUMN (Plywood Formworks -12''x12''- 3 use) Quantity

Standard Production Rate TOTAL AREA = 6,804.00 m2

1 Team
Power Tools = 3 no. Carpenter = 3 person
General Worker = 1 person

Production of 1 Team for 20 m2/day (*Ref-Means Books)


Page 147 - 220 sfca

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 340 days


= 56.7 week
= 13.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Power Tools = 3 Carpenter = 3
0 0 eneral Worker = 1
0 0 0 0
1 340

Power Tools = 6 Carpenter = 6


0 0 eneral Worker = 2
0 0 0 0
2 170

Power Tools = 9 Carpenter = 9


0 0 eneral Worker = 3
0 0 0 0
3 113

Power Tools = 12 Carpenter = 12


0 0 eneral Worker = 4
0 0 0 0
4 85

Power Tools = 15 Carpenter = 15


0 0 eneral Worker = 5
0 0 0 0
5 68
COLUMN (Fix Rebar - Diameter 9.5mm to 22.2mm) Key-in the
Quantity

133800 kg 0.0011023 ton (US Convertion)


Standard Production Rate TOTAL AREA = 147.49 Ton

1 Team
Barbender Machine = 3 no. Barbender = 4 person
Barcuter Machine = 3 no.

Production of 1 Team for 1.5 ton/day (*Ref-Means Books)


Page 154

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 98 days


= 16.4 week
= 3.8 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


nder Machine = 4 Barbender = 4
cuter Machine = 3.160451571 0 0
0 0 0 0
1 98

nder Machine = 8 Barbender = 8


cuter Machine = 6.320903143 0 0
0 0 0 0
2 49

nder Machine = 12 Barbender = 12


cuter Machine = 9.481354714 0 0
0 0 0 0
3 33

nder Machine = 16 Barbender = 16


cuter Machine = 12.64180629 0 0
0 0 0 0
4 25

nder Machine = 20 Barbender = 20


cuter Machine = 15.80225786 0 0
0 0 0 0
5 20
Key-in the
COLUMN (Concrete with crane & bucket-0.76 cu.m) Quantity

Standard Production Rate TOTAL AREA = 669.00 cu.m

1 Team
Mobile Crane (55ton) = 1 no. Concretor = 4 person
Concrete Vibrator = 2 no. General Worker = 1 person

Production of 1 Team for 31 cum/day (*Ref-Means Books)


Page 158 - 40 C.Y

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 22 days


= 3.6 week
= 0.8 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane (55ton) = 1 Concretor = 4
Concrete Vibrator = 2 eneral Worker = 1
0 0 0 0
1 22

Mobile Crane (55ton) = 2 Concretor = 8


Concrete Vibrator = 4 eneral Worker = 2
0 0 0 0
2 11

Mobile Crane (55ton) = 3 Concretor = 12


Concrete Vibrator = 6 eneral Worker = 3
0 0 0 0
3 7

Mobile Crane (55ton) = 4 Concretor = 16


Concrete Vibrator = 8 eneral Worker = 4
0 0 0 0
4 5

Mobile Crane (55ton) = 5 Concretor = 20


Concrete Vibrator = 10 eneral Worker = 5
0 0 0 0
5 4
COLUMN

Standard Production Rate TOTAL NOS. = 35.00 nos.

1 Team
Mobile Crane = 1 no. Foreman = 1 person
Bar Bender = 1 no. Operator = 1 person
Bar Cutter = 1 no. Bar Bender = 2 person
Concrete Vibrator = 1 no. Bar Cutter = 1 person
Carpenter = 3 person
Concretor = 1 person
General Worker = 1 person

Production of Team

Rebar = 10 min
Formwork = 20 min
Concreting = 10 min
Total Time = 40 min

Production Per Day = 12 nos.


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 3 days


= 0.5 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane = 1 Foreman = 1
Bar Bender = 1 Operator = 1
Bar Cutter = 1 Bar Bender = 2
1 3 crete Vibrator = 1 Bar Cutter = 1
0 0 Carpenter = 3
0 0 Concretor = 1
0 0 neral Worker = 1
Mobile Crane = 2 Foreman = 1
Bar Bender = 2 Operator = 2
Bar Cutter = 2 Bar Bender = 4
2 1 crete Vibrator = 2 Bar Cutter = 2
0 0 Carpenter = 6
0 0 Concretor = 2
0 0 neral Worker = 2
Mobile Crane = 3 Foreman = 1
Bar Bender = 3 Operator = 3
Bar Cutter = 3 Bar Bender = 6
3 1 crete Vibrator = 3 Bar Cutter = 3
0 0 Carpenter = 9
0 0 Concretor = 3
0 0 neral Worker = 3
Mobile Crane = 4 Foreman = 2
Bar Bender = 4 Operator = 4
Bar Cutter = 4 Bar Bender = 8
4 1 crete Vibrator = 4 Bar Cutter = 4
0 0 Carpenter = 12
0 0 Concretor = 4
0 0 neral Worker = 4
Mobile Crane = 5 Foreman = 2
Bar Bender = 5 Operator = 5
Bar Cutter = 5 Bar Bender = 10
5 1 crete Vibrator = 5 Bar Cutter = 5
0 0 Carpenter = 15
0 0 Concretor = 5
5 1

0 0 neral Worker = 5
Key-in the
RETAINING WALL (Formworks -2.5m - 5m high- 3 use) Quantity

Standard Production Rate TOTAL AREA = 438.00 m2

1 Team
Power Tools = 4 no. Carpenter = 4 person
General Worker = 1 person

Production of 1 Team for 28 m2/day (*Ref-Means Books)


Page 147 - 305 sfca
0.0929 sfca/sq.m

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 15 days


= 2.6 week
= 0.6 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Power Tools = 4 Carpenter = 4
0 0 eneral Worker = 1
0 0 0 0
1 15

Power Tools = 8 Carpenter = 8


0 0 eneral Worker = 2
0 0 0 0
2 8

Power Tools = 12 Carpenter = 12


0 0 eneral Worker = 3
0 0 0 0
3 5

Power Tools = 16 Carpenter = 16


0 0 eneral Worker = 4
0 0 0 0
4 4

Power Tools = 20 Carpenter = 20


0 0 eneral Worker = 5
0 0 0 0
5 3
RETAINING WALL (Fix Rebar - Diameter 9.5mm to 22.2mm) Key-in the
Quantity

31100 kg 0.0011023 ton (US Convertion)


Standard Production Rate TOTAL AREA = 34.28 Ton

1 Team
Barbender Machine = 1 no. Barbender = 4 person
Barcuter Machine = 1 no.

Production of 1 Team for 3 ton/day (*Ref-Means Books)


Page 154

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 11 days


= 1.9 week
= 0.4 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Barbender Machine = 4 Barbender = 4
Barcuter Machine = 1 0 0
0 0 0 0
1 11

Barbender Machine = 8 Barbender = 8


Barcuter Machine = 2 0 0
0 0 0 0
2 6

Barbender Machine = 12 Barbender = 12


Barcuter Machine = 3 0 0
0 0 0 0
3 4

Barbender Machine = 16 Barbender = 16


Barcuter Machine = 4 0 0
0 0 0 0
4 3

Barbender Machine = 20 Barbender = 20


Barcuter Machine = 5 0 0
0 0 0 0
5 2
Key-in the
RETAINING WALL (Concrete with crane & bucket-0.76 cu.m) Quantity

Standard Production Rate TOTAL AREA = 311.00 cu.m

1 Team
Mobile Crane (55ton) = 1 no. Concretor = 4 person
Concrete Vibrator = 2 no. General Worker = 1 person

Production of 1 Team for 31 cum/day (*Ref-Means Books)


Page 163 40 Cu yards
0.7646 Cy/Cu.m

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 10 days


= 1.7 week
= 0.4 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane (55ton) = 1 Concretor = 4
Concrete Vibrator = 2 eneral Worker = 1
0 0 0 0
1 10

Mobile Crane (55ton) = 2 Concretor = 8


Concrete Vibrator = 4 eneral Worker = 2
0 0 0 0
2 5

Mobile Crane (55ton) = 3 Concretor = 12


Concrete Vibrator = 6 eneral Worker = 3
0 0 0 0
3 3

Mobile Crane (55ton) = 4 Concretor = 16


Concrete Vibrator = 8 eneral Worker = 4
0 0 0 0
4 3

Mobile Crane (55ton) = 5 Concretor = 20


Concrete Vibrator = 10 eneral Worker = 5
0 0 0 0
5 2
RETAINING WALL

Standard Production Rate TOTAL NOS. = 1,600.00 sq.m

1 Team
Excavator = 1 no. Foreman = 1 person
Mobile Crane = 1 no. Operator = 1 person
Bar Bender = 1 no. Bar Bender = 2 person
Bar Cutter = 1 no. Bar Cutter = 1 person
Concrete Vibrator = 1 no. Carpenter = 4 person
Concretor = 1 person
General Worker = 5 person

Production of Team

Rebar = min
Formwork = min
Concreting = min
Total Time = min

Production Per Day = 22 sq.m


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 73 days


= 12.1 week
= 2.8 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excavator = 1 Foreman = 1
Mobile Crane = 1 Operator = 1
Bar Bender = 1 Bar Bender = 2
1 73 Bar Cutter = 1 Bar Cutter = 1
Concrete Vibrator = 1 Carpenter = 4
0 0 Concretor = 1
0 0 General Worker = 5
Excavator = 2 Foreman = 1
Mobile Crane = 2 Operator = 2
Bar Bender = 2 Bar Bender = 4
2 36 Bar Cutter = 2 Bar Cutter = 2
Concrete Vibrator = 2 Carpenter = 8
0 0 Concretor = 2
0 0 General Worker = 10
Excavator = 3 Foreman = 2
Mobile Crane = 3 Operator = 3
Bar Bender = 3 Bar Bender = 6
3 24 Bar Cutter = 3 Bar Cutter = 3
Concrete Vibrator = 3 Carpenter = 12
0 0 Concretor = 3
0 0 General Worker = 15
Excavator = 4 Foreman = 3
Mobile Crane = 4 Operator = 4
Bar Bender = 4 Bar Bender = 8
4 18 Bar Cutter = 4 Bar Cutter = 4
Concrete Vibrator = 4 Carpenter = 16
0 0 Concretor = 4
0 0 General Worker = 20
Excavator = 5 Foreman = 4
Mobile Crane = 5 Operator = 5
Bar Bender = 5 Bar Bender = 10
5 15 Bar Cutter = 5 Bar Cutter = 5
Concrete Vibrator = 5 Carpenter = 20
0 0 Concretor = 5
5 15

0 0 General Worker = 25
PRECAST ELEMENT

Standard Production Rate TOTAL NOS. = 4,708.00 nos

1 Team
Tower/Mobile Crane = 1 no. Foreman = 1 person
Concrete Vibrator = 1 no. Operator = 1 person
Installer = 5 person
Concretor = 2 person
General Worker = 2 person

Production of One Crane / Team

20 20 minit = 1 Element Precast


480 minit (1day) = 24 Elements Precast

Production Per Day = 24 nos


(1 Crane / team)

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 196 days


= 32.7 week
= 7.5 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane = 1 Foreman = 1
crete Vibrator = 1 Operator = 1
0 0 Installer = 5
1 196 0 0 Concretor = 2
0 0 neral Worker = 2
0 0 0 0
0 0 0 0
Mobile Crane = 2 Foreman = 1
crete Vibrator = 2 Operator = 2
0 0 Installer = 10
2 98 0 0 Concretor = 4
0 0 neral Worker = 4
0 0 0 0
0 0 0 0
Mobile Crane = 3 Foreman = 2
crete Vibrator = 3 Operator = 3
0 0 Installer = 15
3 65 0 0 Concretor = 6
0 0 neral Worker = 6
0 0 0 0
0 0 0 0
Mobile Crane = 4 Foreman = 2
crete Vibrator = 4 Operator = 4
0 0 Installer = 20
4 49 0 0 Concretor = 8
0 0 neral Worker = 8
0 0 0 0
0 0 0 0
Mobile Crane = 5 Foreman = 3
crete Vibrator = 5 Operator = 5
0 0 Installer = 25
5 39 0 0 Concretor = 10
0 0 neral Worker = 10
0 0 0 0
0 0 0 0
ESTIMATION NO. OF LORRY REQUIRED TO DELIVER PRECAST PANEL.

Standard Production Rate TOTAL VOLUME = 37.00 nos/days

1 Team
Trailer/Low Loader = 2 no. Operator = 4 person
Crane = 2 no. Labour = 4 person

Production of One Truck Based on (3m x 4m) Precast Panel

1 Lorry = 6 Panels 1 trip :


Haulage = 60 km Waiting = 10 minutes
Truck speed = 45 km/hr loading = 30 minutes
Travelling = 160 minutes
Travelling time = Haulage unload = 30 minutes
Speed Total = 230 minutes
= 2.67 hr
= 160.00 minutes Time for 1 trip, n = 265 minutes
(15 % more)

\ Production of one truck, Q = (8hr x60min) x capacity


time per trip
= 11 nos/day

\ Production of one team, P = 22 nos/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 2 days


= 0.3 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


r/Low Loader = 2 Operator = 4
Crane = 2 Labour = 4
1 2
0
Key-in the
Quantity

ROOF TRUSSES (Metal Decking) 57783 kg 0.0011023 ton (US Convertion)


64 ton
Standard Production Rate TOTAL AREA = 1,600.00 m2

1 Team
obile Crane (90 ton) = 1 no. Foreman = 1 person
Welding set = 1 set Operator = 1 person
Roof Truss Installer = 5 person
Welder = 1 person

Production of 1 Team for 70


m2/day - large area
13 ton/day
Production of 1 Team for 28 m2/day - Small or Complicated area
8 ton/day
Large Area Small Area
\ TOTAL DAY REQUIRED FOR ABOVE AREA = 23 days 57 days
= 3.8 week 9.5 week
= 0.9 month 2.2 month
Tonnage 5 days 8 days

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Large 23 Mobile Crane (90 ton) = 1 Foreman = 1
Welding set = 1 Operator = 1
1
Small 57 0 0 uss Installer = 5
0 0 Welder = 1
Large 11 Mobile Crane (90 ton) = 2 Foreman = 1
Welding set = 2 Operator = 2
2
Small 29 0 0 uss Installer = 10
0 0 Welder = 2
Large 8 Mobile Crane (90 ton) = 3 Foreman = 1
Welding set = 3 Operator = 3
3
Small 19 0 0 uss Installer = 15
0 0 Welder = 3
Large 6 Mobile Crane (90 ton) = 4 Foreman = 1
Welding set = 4 Operator = 4
4
Small 14 0 0 uss Installer = 20
0 0 Welder = 4
Large 5 Mobile Crane (90 ton) = 5 Foreman = 2
Welding set = 5 Operator = 5
5
Small 11 0 0 uss Installer = 25
0 0 Welder = 5
Key-in the
ROOF TRUSSES (Wood - 7m - 18m span) Quantity

Standard Production Rate TOTAL AREA = 485.00 m2

1 Team
obile Crane (12 ton) = 1 no. Foreman = 1 person
Power Tools = 1 set Operator = 1 person
Carpenter = 4 person

Production of 1 Team for 279 m2/day (*Ref-Means Books)


Page 231

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 2 days


= 0.3 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Large 2 Mobile Crane (12 ton) = 1 Foreman = 1
Power Tools = 1 Operator = 1
1
0 0 0 Carpenter = 4
0 0 0 0
Large 3 Mobile Crane (12 ton) = 2 Foreman = 1
Power Tools = 2 Operator = 2
2
0 0 0 Carpenter = 8
0 0 0 0
Large 5 Mobile Crane (12 ton) = 3 Foreman = 1
Power Tools = 3 Operator = 3
3
0 0 0 Carpenter = 12
0 0 0 0
Large 7 Mobile Crane (12 ton) = 4 Foreman = 1
Power Tools = 4 Operator = 4
4
0 0 0 Carpenter = 16
0 0 0 0
Large 9 Mobile Crane (12 ton) = 5 Foreman = 1
Power Tools = 5 Operator = 5
5
0 0 0 Carpenter = 20
0 0 0 0
Key-in the
ROOF COVER (Clay Tile) Quantity

Standard Production Rate TOTAL AREA = 2,000.00 m2

1 Team
Mobile Crane = 1 no. Foreman = 1 person
Power Tool = 3 set Operator = 1 person
Roof cover inst. = 3 person
General Worker = 1 person

Production of 1 Team for 72 m2 (*Ref-Means Books)


Page 257 - mission tile 225 pcs - 1 pcs = 1'x1'

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 28 days


= 4.6 week
= 1.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Mobile Crane = 1 Foreman = 1
Power Tool = 3 Operator = 1
1 28
0 0 oof cover inst. = 3
0 0 eneral Worker = 1
Mobile Crane = 2 Foreman = 1
Power Tool = 6 Operator = 2
2 14
0 0 oof cover inst. = 6
0 0 eneral Worker = 2
Mobile Crane = 3 Foreman = 1
Power Tool = 9 Operator = 3
3 9
0 0 oof cover inst. = 9
0 0 eneral Worker = 3
Mobile Crane = 4 Foreman = 1
Power Tool = 12 Operator = 4
4 7
0 0 oof cover inst. = 12
0 0 eneral Worker = 4
Mobile Crane = 5 Foreman = 1
Power Tool = 15 Operator = 5
5 6
0 0 oof cover inst. = 15
0 0 eneral Worker = 5
BRICK LAYING (Common 4" x 2-2/3" x 8" ---> 4" Wall) Key-in the
Quantity

Standard Production Rate TOTAL AREA = 134,172.00 m2

1 Team
Concrete Mixer = 1 no. Foreman = 1 person
Brick Layer = 3 person
General Worker = 2 person

Production of 1 Team for 20 m2 (*Ref-Means Books)


Page 177

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 6718 days


= 1119.6 week
= 258.4 month

PRODUCTION TABLE

MONTH NO. OF TEAM DURATION (Days) Plant Labour


Concrete Mixer = 1 Foreman = 1
258 0 0 Brick Layer = 3
1 6718
0 0 General Worker = 2
0 0 0 0
Concrete Mixer = 2 Foreman = 1
129 0 0 Brick Layer = 6
2 3359
0 0 General Worker = 4
0 0 0 0
Concrete Mixer = 3 Foreman = 1
86 0 0 Brick Layer = 9
3 2239
0 0 General Worker = 6
0 0 0 0
Concrete Mixer = 4 Foreman = 1
65 0 0 Brick Layer = 12
4 1679
0 0 General Worker = 8
0 0 0 0
Concrete Mixer = 5 Foreman = 1
52 0 0 Brick Layer = 15
5 1344 0 0 General Worker = 10
0 0 0 0
Key-in the
PLASTERING (Wall under 2.5m high-skimcoat) Quantity

Standard Production Rate TOTAL AREA = 32,000.00 m2

1 Team
Concrete Mixer = 1 no. Foreman = 1 person
Plasterer = 3 person
General Worker = 2 person

Production of 1 Team for 54 m2 Ref- www.planningplanet.com

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 597 days


= 99.5 week
= 23.0 month

PRODUCTION TABLE

MTH NO. OF TEAM DURATION (Days) Plant Labour


Concrete Mixer = 1 Foreman = 1
23 0 0 Plasterer = 3
1 597
0 0 General Worker = 2
0 0 0 0
Concrete Mixer = 2 Foreman = 1
11 0 0 Plasterer = 6
2 299
0 0 General Worker = 4
0 0 0 0
Concrete Mixer = 3 Foreman = 1
8 0 0 Plasterer = 9
3 199
0 0 General Worker = 6
0 0 0 0
Concrete Mixer = 4 Foreman = 1
6 0 0 Plasterer = 12
4 149
0 0 General Worker = 8
0 0 0 0
Concrete Mixer = 5 Foreman = 1
0 0 Plasterer = 15
5 119
5 0 0 General Worker = 10
0 0 0 0
Key-in the
PLASTERING (Wall under 2.5m high-undercoat) Quantity

Standard Production Rate TOTAL AREA = 4,000.00 m2

1 Team
Concrete Mixer = 1 no. Foreman = 1 person
Plasterer = 3 person
General Worker = 2 person

Production of 1 Team for 22 m2 Ref- www.planningplanet.com

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 179 days


= 29.8 week
= 6.9 month

PRODUCTION TABLE

MTH NO. OF TEAM DURATION (Days) Plant Labour


Concrete Mixer = 1 Foreman = 1
7 0 0 Plasterer = 3
1 179
0 0 General Worker = 2
0 0 0 0
Concrete Mixer = 2 Foreman = 1
3 0 0 Plasterer = 6
2 89
0 0 General Worker = 4
0 0 0 0
Concrete Mixer = 3 Foreman = 1
2 0 0 Plasterer = 9
3 60
0 0 General Worker = 6
0 0 0 0
Concrete Mixer = 4 Foreman = 1
2 0 0 Plasterer = 12
4 45
0 0 General Worker = 8
0 0 0 0
Concrete Mixer = 5 Foreman = 1
0 0 Plasterer = 15
5 36
1 0 0 General Worker = 10
0 0 0 0
Concrete Mixer = 6 Foreman = 2
0 0 Plasterer = 18
6 30
1 0 0 General Worker = 12
0 0 0 0
Concrete Mixer = 7 Foreman = 2
0 0 Plasterer = 21
7 26
1 0 0 General Worker = 14
0 0 0 0
Concrete Mixer = 8 Foreman = 2
0 0 Plasterer = 24
8 22
1 0 0 General Worker = 16
8 22
0 0 0 0
Key-in the
DOOR FRAME (3' x 7' Opening) Quantity

Standard Production Rate TOTAL NOS. = 20.00 nos.

1 Team
Power Tool = 2 set Foreman = 1 person
elding Set(for steel) = 1 set Installer = 2 person
General Worker = 1 person
(*Ref-Means Books)
Production of 1 Team for 13 nos. -Steel Frame Page 278
Production of 1 Team for 2 nos. -Alum Frame Page 280
Production of 1 Team for 14 nos. -Wood Frame Page 282

Steel Frame Alum Frame Wood Frame


\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 2 10 1 days
= 0 2 0 week
= 0 0 0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Steel Frame 2 Power Tool = 2 Foreman = 1
Alum Frame 10 Welding Set(for steel) = 1 Installer = 2
1
Wood Frame 1 0 0 General Worker = 1
0 0 0 0
Steel Frame 3 Power Tool = 4 Foreman = 1
Alum Frame 20 Welding Set(for steel) = 2 Installer = 4
2
Wood Frame 3 0 0 General Worker = 2
0 0 0 0
Steel Frame 5 Power Tool = 6 Foreman = 1
Alum Frame 30 Welding Set(for steel) = 3 Installer = 6
3
Wood Frame 4 0 0 General Worker = 3
0 0 0 0
Steel Frame 6 Power Tool = 8 Foreman = 1
Alum Frame 40 Welding Set(for steel) = 4 Installer = 8
4
Wood Frame 6 0 0 General Worker = 4
0 0 0 0
Steel Frame 8 Power Tool = 10 Foreman = 1
Alum Frame 50 Welding Set(for steel) = 5 Installer = 10
5
Wood Frame 7 0 0 General Worker = 5
0 0 0 0
HANDRAIL & RAILING

Standard Production Rate TOTAL NOS. = 3.00 Staircase

1 Team
Welding Machine = 1 set Foreman = 1 person
Installer = 2 person
General Worker = 1 person

42
Production of 1 Team : 8 m/day

1 Staircase
Ground Floor - 1st Floor = 8 m
Total length 1st Floor 24 m

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 3 days


= 0.5 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


ding Machine = 1 Foreman = 1
0 0 Installer = 2
1 3
0 0 eneral Worker = 1
0 0 0 0
ding Machine = 2 Foreman = 1
0 0 Installer = 4
2 2
0 0 eneral Worker = 2
0 0 0 0
ding Machine = 3 Foreman = 1
0 0 Installer = 6
3 1
0 0 eneral Worker = 3
0 0 0 0
ding Machine = 4 Foreman = 1
0 0 Installer = 8
4 1
0 0 eneral Worker = 4
0 0 0 0
ding Machine = 5 Foreman = 1
0 0 Installer = 10
5 1
0 0 eneral Worker = 5
0 0 0 0
Key-in the
WALL TILING (Ceramic Tile 150mmx150mm) Quantity

Standard Production Rate TOTAL AREA = 20,000.00 m2

1 Team
Foreman = 1 person
Tiler = 1 person
General Worker = 1 person

Production of 1 Team for 18 m2


Ref-RSMeans Books -Page 319

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 1111 days


= 185.2 week
= 42.7 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
42.735043 0 0 Tiler = 1
1 1111
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
21.367521 0 0 Tiler = 2
2 556
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
14.245014 0 0 Tiler = 3
3 370
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 4
4 278
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 5
5 222
0 0 eneral Worker = 5
0 0 0 0
Key-in the
DRY WALL PARTITION Quantity

Standard Production Rate TOTAL AREA = 1,200.00 m2

1 Team
Foreman = 1 person
Carpenter = 2 person
General Worker = 2 person

Production of 1 Team for 32 m2/day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 38 days


= 6.3 week
= 1.4 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Carpenter = 2
1 38
0 0 General Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 4
2 19
0 0 General Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 6
3 13
0 0 General Worker = 6
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 8
4 9
0 0 General Worker = 8
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 10
5 8
0 0 General Worker = 10
0 0 0 0
Key-in the
CURTAIN WALL/EXTERNAL FASCADE Quantity

Standard Production Rate TOTAL AREA = 22,000.00 m2

1 Team
Foreman = 1 person
Carpenter = 2 person
General Worker = 1 person

Production of 1 Team for 20 m2/day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 1100 days


= 183.3 week
= 42.3 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Carpenter = 2
1 1100
0 0 General Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 4
2 550
0 0 General Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 6
3 367
0 0 General Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 8
4 275
0 0 General Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 10
5 220
0 0 General Worker = 5
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 12
6 183
0 0 General Worker = 6
0 0 0 0
0 0 Foreman = 1
0 0 Carpenter = 14
7 157
0 0 General Worker = 7
0 0 0 0
FLOOR TILING (Clay, quarry Tiles, Small Area, Little Cutting) Key-in the
Quantity

Standard Production Rate TOTAL AREA = 1,200.00 m2

1 Team
Foreman = 1 person
Tiler = 1 person
General Worker = 1 person

Production of 1 Team for 18 m2 Ref-www.planningplanet.com


Ref-RSMeans Books -Page 318

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 68 days


= 11.4 week
= 2.6 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Tiler = 1
1 68
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 2
2 34
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 3
3 23
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 4
4 17
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 5
5 14
0 0 eneral Worker = 5
0 0 0 0
VINYL FLOORING Key-in the
Quantity

Standard Production Rate TOTAL AREA = 1,200.00 m2

1 Team
Foreman = 1 person
Layer = 1 person
General Worker = 1 person

Production of 1 Team for 23 m2/day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 52 days


= 8.7 week
= 2.0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Layer = 1
1 52
0 0 General Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Layer = 2
2 26
0 0 General Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Layer = 3
3 17
0 0 General Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Layer = 4
4 13
0 0 General Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Layer = 5
5 10
0 0 General Worker = 5
0 0 0 0
GRANITE FLOORING Key-in the
Quantity

Standard Production Rate TOTAL AREA = 1,200.00 m2

1 Team
Foreman = 1 person
Tiler = 1 person
General Worker = 2 person

Production of 1 Team for 12 m2/day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 100 days


= 16.7 week
= 3.8 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Tiler = 1
1 100
0 0 General Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 2
2 50
0 0 General Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 3
3 33
0 0 General Worker = 6
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 4
4 25
0 0 General Worker = 8
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 5
5 20
0 0 General Worker = 10
0 0 0 0
CARPET (Nylon,Olefin, Wool-20oz to 42oz) Key-in the
Quantity

Standard Production Rate TOTAL AREA = 1,200.00 m2

1 Team
Foreman = 1 person
Tiler = 1 person
General Worker = 1 person

Production of 1 Team for 48 m2 Ref-RSMeans Books -Page 318


57 sq.y

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 25 days


= 4.2 week
= 1.0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Tiler = 1
1 25
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 2
2 13
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 3
3 8
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 4
4 6
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Tiler = 5
5 5
0 0 eneral Worker = 5
0 0 0 0
CEMENT RENDER

Standard Production Rate TOTAL AREA = 100.00 m2

1 Team
Foreman = 1 person
Renderer = 2 person
General Worker = 1 person

Production of 1 Team for 100 m2

Screeding = 1 day
Total Time = 1 day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 1 days


= 0.2 week
= 0.0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Renderer = 2
1 1
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Renderer = 4
2 1
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Renderer = 6
3 0
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Renderer = 8
4 0
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Renderer = 10
5 0
0 0 eneral Worker = 5
0 0 0 0
Key-in the
PAINTING (Paint 2 Coats, Smooth Finish, Roller) Quantity

Standard Production Rate TOTAL AREA = 1,000.00 m2

1 Team
Foreman = 1 person
Painter = 1 person

Production of 1 Team for 111 m2 Ref-RSMeans Books -Page 336


1,190sq.f

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 9 days


= 1.5 week
= 0.3 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0.3465003 0 0 Painter = 1
1 9
0 0 0 0
0 0 0 0
0 0 Foreman = 1
0.1732502 0 0 Painter = 2
2 5
0 0 0 0
0 0 0 0
0 0 Foreman = 1
0 0 Painter = 3
3 3
0.1155001 0 0 0 0
0 0 0 0
0 0 Foreman = 1
0 0 Painter = 4
4 2
0.0866251 0 0 0 0
0 0 0 0
0 0 Foreman = 1
0 0 Painter = 5
5 2
0.0693001 0 0 0 0
0 0 0 0
Key-in the
SUSPENDED CEILING (Mineral Fiber,T-bar susp 2'x4' board.) Quantity

Standard Production Rate TOTAL AREA = 52,000.00 m2

1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person

Production of 1 Team for 35 m2 Ref-RSMeans Books -Page 322


380 sq.f

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 1486 days


= 247.6 week
= 57.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Installer = 2
1 1486
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 4
2 743
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 6
3 495
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 8
4 371
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 10
5 297
0 0 eneral Worker = 5
0 0 0 0
FIXED CEILING

Standard Production Rate TOTAL AREA = 7,613.00 m2

1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person

Production of 1 Team for 100 m2

Ceiling Inst. = 1 day


Total Time = 1 day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 76 days


= 12.7 week
= 2.9 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Installer = 2
1 76
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 4
2 38
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 6
3 25
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 8
4 19
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 10
5 15
0 0 eneral Worker = 5
0 0 0 0
PLASTER CEILING (Skim coat to ceilings including final polish)

Standard Production Rate TOTAL AREA = 471.00 m2

1 Team
Foreman = 1 person
Plasterer = 2 person
General Worker = 1 person

Production of 1 Team for 30 m2 From HPC Production Rate

Ceiling Inst. = 1 day


Total Time = 1 day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 16 days


= 2.6 week
= 0.6 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Plasterer = 2
1 16
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Plasterer = 4
2 8
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Plasterer = 6
3 5
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Plasterer = 8
4 4
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Plasterer = 10
5 3
0 0 eneral Worker = 5
0 0 0 0
DOOR PANEL (Door 3' x 7') (Glass Sliding 3 leaf 9' x 6')

Standard Production Rate TOTAL NOS. = 629.00 nos.

1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person

Production of 1 Team for 14 nos. - Solid Deco. Tmber Door - Ref RSMeans- Page 282
Production of 1 Team for 3 nos. - Glass Sliding Door - Ref RSMeans- Page 287

Solid Glass Sliding


\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 45 days 210 days
= 7 week 35 week
= 2 month 8 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Solid 45 0 0 Foreman = 1
0 0 Installer = 2
1
Glass Sliding 210 0 0 eneral Worker = 1
0 0 0 0
Solid 22 0 0 Foreman = 1
0 0 Installer = 4
2
Glass Sliding 105 0 0 eneral Worker = 2
0 0 0 0
Solid 15 0 0 Foreman = 1
0 0 Installer = 6
3
Glass Sliding 70 0 0 eneral Worker = 3
0 0 0 0
Solid 11 0 0 Foreman = 1
0 0 Installer = 8
4
Glass Sliding 52 0 0 eneral Worker = 4
0 0 0 0
Solid 9 0 0 Foreman = 1
0 0 Installer = 10
5
Glass Sliding 42 0 0 eneral Worker = 5
0 0 0 0
WINDOW PANEL (Aluminum Window)

Standard Production Rate TOTAL NOS. = 629.00 nos.

1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person

Production of 1 Team for 9 nos. - Single Hung 3'4"x 5' - Ref RSMeans- Page 294
Production of 1 Team for 4 nos. - Sliding Aluminum 9' x 5' - Ref RSMeans- Page 295

Single Hung Sliding Aliminum


\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 70 days 157 days
= 12 week 26 week
= 3 month 6 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Single Hung 70 0 0 Foreman = 1
0 0 Installer = 2
1
Sliding Alumi 157 0 0 eneral Worker = 1
0 0 0 0
Single Hung 35 0 0 Foreman = 1
0 0 Installer = 4
2
Sliding Alumi 79 0 0 eneral Worker = 2
0 0 0 0
Single Hung 23 0 0 Foreman = 1
0 0 Installer = 6
3
Sliding Alumi 52 0 0 eneral Worker = 3
0 0 0 0
Single Hung 17 0 0 Foreman = 1
0 0 Installer = 8
4
Sliding Alumi 39 0 0 eneral Worker = 4
0 0 0 0
Single Hung 14 0 0 Foreman = 1
0 0 Installer = 10
5
Sliding Alumi 31 0 0 eneral Worker = 5
0 0 0 0
IRONMONGERY

Standard Production Rate TOTAL NOS. = 629.00 nos.

1 Team
Foreman = 1 person
Installer = 2 person
General Worker = 1 person

Production of 1 Team for 25 nos.

Installation = 1 day
Total Time = 1 day

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 25 days


= 4.2 week
= 1.0 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Installer = 2
1 25
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 4
2 13
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 6
3 8
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 8
4 6
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Installer = 10
5 5
0 0 eneral Worker = 5
0 0 0 0
APRON SLAB

Standard Production Rate TOTAL AREA = 100.00 m2

1 Team
Bar Bender = 1 no. Foreman = 1 person
Bar Cutter = 1 no. Bar Bender = 1 person
Bar Cutter = 1 person
Carpenter = 1 person
General Worker = 1 person

Production of 1 Team for 15 m2

Apron Works = 1 day


Total Time = 1 day

\ TOTAL DAY REQUIRED FOR ABOVE AREA = 7 days


= 1.1 week
= 0.3 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Bar Bender = 1 Foreman = 1
Bar Cutter = 1 Bar Bender = 1
1 7 0 0 Bar Cutter = 1
Carpenter = 1
0 0 eneral Worker = 1
Bar Bender = 2 Foreman = 1
Bar Cutter = 2 Bar Bender = 2
2 3 0 0 Bar Cutter = 2
Carpenter = 2
0 0 eneral Worker = 2
Bar Bender = 3 Foreman = 1
Bar Cutter = 3 Bar Bender = 3
3 2 0 0 Bar Cutter = 3
Carpenter = 3
0 0 eneral Worker = 3
Bar Bender = 4 Foreman = 1
Bar Cutter = 4 Bar Bender = 4
4 2 0 0 Bar Cutter = 4
Carpenter = 4
0 0 eneral Worker = 4
Bar Bender = 5 Foreman = 1
Bar Cutter = 5 Bar Bender = 5
5 1 0 0 Bar Cutter = 5
Carpenter = 5
0 0 eneral Worker = 5
PERIMETER DRAIN

Standard Production Rate TOTAL LENGTH = 100.00 m

1 Team
Foreman = 1 person
Fixer = 2 person
General Worker = 1 person

Production of 1 Team for 20 m

Fixer = 1 day
Total Time = 1 day

\ TOTAL DAY REQUIRED FOR ABOVE NOS. = 5 days


= 0.8 week
= 0.2 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


0 0 Foreman = 1
0 0 Fixer = 2
1 5
0 0 eneral Worker = 1
0 0 0 0
0 0 Foreman = 1
0 0 Fixer = 4
2 3
0 0 eneral Worker = 2
0 0 0 0
0 0 Foreman = 1
0 0 Fixer = 6
3 2
0 0 eneral Worker = 3
0 0 0 0
0 0 Foreman = 1
0 0 Fixer = 8
4 1
0 0 eneral Worker = 4
0 0 0 0
0 0 Foreman = 1
0 0 Fixer = 10
5 1
0 0 eneral Worker = 5
0 0 0 0
BRICK DRAIN

Standard Production Rate TOTAL NOS. = 352.00 lin.m

1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Concrete Vibrator = 1 no. Operator = 1 person
Mobile Pumps = 1 no. General Worker = 5 person
Concrete Mixer = 1 no.

Production of Team- lin.m/min

Excavation = 5 min
Lean Con/ Curing = 95 min
ay hrdrain+Con base = 10 min
Brick Wall = 10 min
Plastering = 10 min
Total Time = 130 min

Production Per Day = 3.69 lin.m


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE = 95 days


= 16 week
= 4 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excav./ Backhoe = 1 Foreman = 1
Concrete Vibrator = 1 Operator = 1
Mobile Pumps = 1 General Worker = 5
1 95 Concrete Mixer = 1

Excav./ Backhoe = 2 Foreman = 1


Concrete Vibrator = 2 Operator = 2
Mobile Pumps = 2 General Worker = 10
2 48 Concrete Mixer = 2

Excav./ Backhoe = 3 Foreman = 1


Concrete Vibrator = 3 Operator = 3
Mobile Pumps = 3 General Worker = 15
3 32 Concrete Mixer = 3

Excav./ Backhoe = 4 Foreman = 1


Concrete Vibrator = 4 Operator = 4
Mobile Pumps = 4 General Worker = 20
4 24 Concrete Mixer = 4

Excav./ Backhoe = 5 Foreman = 2


Concrete Vibrator = 5 Operator = 5
Mobile Pumps = 5 General Worker = 25
5 19 Concrete Mixer = 5
5 19
PRECAST U DRAIN

Standard Production Rate TOTAL NOS. = 41,500.00 lin.m

1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Concrete Vibrator = 1 no. Operator = 1 person
Mobile Pumps = 1 no. General Worker = 5 person
Concrete Mixer = 1 no.

Production of 1 Team

Casting U Drain = 20 nos/day = 20 lin.m


Exca. & Lay = 20 lin.m/day

Total Day= 2 day

Production Per Day = 10.00 lin.m


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE = 4150 days


= 692 week
= 160 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excav./ Backhoe = 1 Foreman = 1
Concrete Vibrator = 1 Operator = 1
Mobile Pumps = 1 General Worker = 5
159.61538 1 4150 Concrete Mixer = 1

Excav./ Backhoe = 2 Foreman = 1


Concrete Vibrator = 2 Operator = 2
Mobile Pumps = 2 General Worker = 10
79.807692 2 2075 Concrete Mixer = 2

Excav./ Backhoe = 3 Foreman = 1


Concrete Vibrator = 3 Operator = 3
Mobile Pumps = 3 General Worker = 15
53.205128 3 1383 Concrete Mixer = 3

Excav./ Backhoe = 4 Foreman = 1


Concrete Vibrator = 4 Operator = 4
Mobile Pumps = 4 General Worker = 20
39.903846 4 1038 Concrete Mixer = 4

Excav./ Backhoe = 5 Foreman = 2


Concrete Vibrator = 5 Operator = 5
Mobile Pumps = 5 General Worker = 25
31.923077 5 830 Concrete Mixer = 5
5 830
RC SUMP

Standard Production Rate TOTAL NOS. = 25.00 no.

1 Team
Excav./ Backhoe = 1 no. Foreman = 1 person
Concrete Vibrator = 1 no. Operator = 1 person
Mobile Pumps = 1 no. Carpenter = 2 person
Concrete Mixer = 1 no. Barbender = 2 person
Labour = 1 person

Production of 1 Team

Production Per Day = 0.75 nos


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE = 33 days


= 6 week
= 1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excav./ Backhoe = 1 Foreman = 1
Concrete Vibrator = 1 Operator = 1
Mobile Pumps = 1 Carpenter = 2
1 33 Concrete Mixer = 1 Barbender = 2
Labour = 1

Excav./ Backhoe = 2 Foreman = 1


Concrete Vibrator = 2 Operator = 2
Mobile Pumps = 2 Carpenter = 4
2 17 Concrete Mixer = 2 Barbender = 4
Labour = 2

Excav./ Backhoe = 3 Foreman = 1


Concrete Vibrator = 3 Operator = 6
Mobile Pumps = 3 Carpenter = 6
3 11 Concrete Mixer = 3 Barbender = 3
Labour = 3

Excav./ Backhoe = 4 Foreman = 1


Concrete Vibrator = 4 Operator = 8
Mobile Pumps = 4 Carpenter = 8
4 8 Concrete Mixer = 4 Barbender = 4
Labour = 4

Excav./ Backhoe = 5 Foreman = 1


Concrete Vibrator = 5 Operator = 10
Mobile Pumps = 5 Carpenter = 10
5 7 Concrete Mixer = 5 Barbender = 5
Labour = 5
5 7
Key-in the
Quantity

PIPE CULVERT(SUBDRAINAGE) Not including Excavation & Backfill

Standard Production Rate TOTAL NOS. = 840.00 lin.m

1 Team
Excavator = 1 no.
Crane = 1 no. General Worker = 1 person
Operator = 2 person

Production of Team
6"dia. 8"dia. 12"dia. 18" dia
Production of Team 94 94 70 50 lin.m/day
Ref-RSMeans Books Page 103
1 feet = 0.3048 Meter
\ TOTAL DAY REQUIRED FOR 9 9 12 17 days
ABOVE NOS. = 1.5 1.5 2.0 2.8 week
0.3 0.3 0.5 0.6 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


4"dia.= 9 Excavator = 1
6"dia.= 9 Crane = 1 0 0
1 12"dia.= 12 0 0 General Worker = 1
24" dia.= 17 Operator = 2

4"dia.= 4 Excavator = 1
6"dia.= 4 Crane = 1 0 0
2 12"dia.= 6 0 0 General Worker = 2
24" dia.= 8 Operator = 4

4"dia.= 3 Excavator = 1
6"dia.= 3 Crane = 1
12"dia.= 4 0 0 0 0
3
24" dia.= 6 General Worker = 3
Operator = 6

4"dia.= 2 Excavator = 1
6"dia.= 2 Crane = 1
12"dia.= 3 0 0 0 0
4
24" dia.= 4 General Worker = 4
Operator = 8

4"dia.= 2 Excavator = 1
6"dia.= 2 Crane = 1
12"dia.= 2 0 0 0 0
5
24" dia.= 3 General Worker = 5
Operator = 10
RCP CULVERT ON SEND BEDDING -not including excavate & backfill

Standard Production Rate TOTAL NOS. = 614.00 lin.m

1 Team
Excavator= 1 no. Foreman = 1 person
Mobile Pumps = 1 no. Operator = 2 person
Concrete Mixer = 1 no. General Worker = 2 person
Crane (5 ton) = 1 no.

Production of 1 Team

Exca. & Lay = 12 nos/day 1 nos ~ 3 lin.m


= 36 lin.m/day

Production Per Day = 10.00 lin.m


(1 team)

\ TOTAL DAY REQUIRED FOR ABOVE = 61 days


= 10 week
= 2 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Excavator= 1 Foreman = 1
Mobile Pumps = 1 Operator = 2
10 Concrete Mixer = 1 General Worker = 2
2 1 61 Crane (5 ton) = 1

Excavator= 2 Foreman = 1
Mobile Pumps = 2 Operator = 4
5 Concrete Mixer = 2 General Worker = 4
1 2 31 Crane (5 ton) = 2

Excavator= 3 Foreman = 1
Mobile Pumps = 3 Operator = 6
3 Concrete Mixer = 3 General Worker = 6
1 3 20 Crane (5 ton) = 3

Excavator= 4 Foreman = 1
Mobile Pumps = 4 Operator = 8
3 Concrete Mixer = 4 General Worker = 8
1 4 15 Crane (5 ton) = 4

Excavator= 5 Foreman = 1
Mobile Pumps = 5 Operator = 10
2 Concrete Mixer = 5 General Worker = 10
0 5 12 Crane (5 ton) = 5
5 12
PAVEMENT BASE - SUB BASE (Sand or Quarry Dust) CBR >20

Standard Production Rate TOTAL VOLUME = 211,928.00 sq.m

1 Team
otor Grader MG 350 = 1 no. Labour = 1 person
Vibratory Roller = 1 no. (10ton) Operator = 3 person
Backpusher= 1 no.

Production of one team, P = 3000.00 sq.m/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 71 days


= 11.8 week
= 2.7 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Motor Grader MG 350 = 1 Foreman = 1
Vibratory Roller = 1 Operator = 3
1 71
Backpusher= 1

Motor Grader MG 350 = 2 Foreman = 1


Vibratory Roller = 2 Operator = 6
2 35
Backpusher= 2

Motor Grader MG 350 = 3 Foreman = 1


Vibratory Roller = 3 Operator = 9
3 24
Backpusher= 3

Motor Grader MG 350 = 4 Foreman = 1


Vibratory Roller = 4 Operator = 12
4 18
Backpusher= 4

Motor Grader MG 350 = 5 Foreman = 1


Vibratory Roller = 5 Operator = 15
5 14
Backpusher= 5
RC CONCRETE PAVEMENT (Including joints, finishing and curing)

Standard Production Rate TOTAL VOLUME = 177,600.00 sq.m

1 Team
Con. Placer Spreader = 1 no. Labour = 6 person
Con. Slip form Paver= 1 no. Operator = 23 person
Texturing & Curing Machine = 1 no. Carpenter= 3
Longitudinal groove cutting machine = 1 no. barbender= 2
Lorry mixer = 20 no.
Water truck= 1 no.

Production of one team, P = 1505 sq.m/day Ref: Means Books Page 78


12" thick = 1800 s.y

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 118 days


= 19.7 week
= 4.5 month

PRODUCTION TABLE

MONTH NO. OF TEAM DURATION (Days) Plant Labour


Con. Placer Spreader = 1 Foreman = 2
Con. Slip form Paver= 1 Operator = 23
5 Texturing & Curing Machine = 1 Labour = 6
1 118
Longitudinal groove cutting machine = 1 Carpenter= 3
Lorry mixer = 20 barbender= 2
Water truck= 1
Con. Placer Spreader = 2 Foreman = 3
Con. Slip form Paver= 2 Operator = 46
2 Texturing & Curing Machine = 2 Carpenter= 6
2 59
Longitudinal groove cutting machine = 2 barbender= 4
Lorry mixer = 40
Water truck= 2
Con. Placer Spreader = 3 Foreman = 4
Con. Slip form Paver= 3 Operator = 69
2 Texturing & Curing Machine = 3 Carpenter= 9
3 39
Longitudinal groove cutting machine = 3 barbender= 6
Lorry mixer = 60
Water truck= 3
Con. Placer Spreader = 4 Foreman = 6
Con. Slip form Paver= 4 Operator = 92
1 Texturing & Curing Machine = 4 Carpenter= 12
4 30
Longitudinal groove cutting machine = 4 barbender= 8
Lorry mixer = 80
Water truck= 4
Con. Placer Spreader = 5 Foreman = 7
Con. Slip form Paver= 5 Operator = 115
Texturing & Curing Machine = 5 barbender= 15
5 24
Longitudinal groove cutting machine = 5 barbender= 10
Lorry mixer = 100
Water truck= 5
PAVEMENT BASE - COURSE thick 200mm

Standard Production Rate TOTAL VOLUME = 1,679.00 ton

1 Team
Motor Grader = 1 no. (30,000lbs) Foreman = 1 person
Vibratory Roller = 1 no. (10ton) Operator = 3 person
Dozer = 1 no. (200hp) Labour = 2 person

Production of one team, P = 900 ton/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 2 days


= 0.3 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Motor Grader = 1 Foreman = 1
Vibratory Roller = 1 Operator = 3
1 2
Dozer = 1 Labour = 3

Motor Grader = 2 Foreman = 1


Vibratory Roller = 2 Operator = 6
2 1
Dozer = 2 Labour = 6

Motor Grader = 3 Foreman = 1


Vibratory Roller = 3 Operator = 9
3 1
Dozer = 3 Labour = 9

Motor Grader = 4 Foreman = 1


Vibratory Roller = 4 Operator = 12
4 0
Dozer = 4 Labour = 12

Motor Grader = 5 Foreman = 2


Vibratory Roller = 5 Operator = 15
5 0
Dozer = 5 Labour = 15
Mainline 2700 m

Granular Material

Volume = 31400 m3 = 13382.0 tonne


Estimate = 669 loads @ 30 min/loads
Time Required = 334.6 hrs = 42 Days

Wet Mix Macadam

Volume = 16000 m3 = 35200.0 tonne


Estimate = 1760 loads @ 30 min/loads
Time Required = 880.0 hrs = 110 Days

DBM

Volume = 5100 m3 = 11220.0 tonne


Estimate = 561 loads @ 60 min/loads
Time Required = 561.0 hrs = 70 Days

ACBC

Volume = 185.1 m3 = 425.73 tonne


Estimate = 21 loads @ 30 min/loads
Time Required = 10.6 hrs = 1 Days

ACWC

Volume = 154.2 m3 = 354.66 tonne


Estimate = 18 loads @ 30 min/loads
Time Required = 8.9 hrs = 1 Days
1 Team
Asphalt Paver = 1 no. (130hp) Foreman = 1 person
Tandem Roller = 1 no. (10ton) Operator = 5 person
Pneu. Tyred Roller = 1 no. Labour = 7 person
Tack/Prime Coat Lorry = 1 no.
Water Tanker = 1 no
Air Compressor = 1 no.

lorry tyre load


10 20 ton
6 15 ton
PAVEMENT ACBC & ACWC 50 mm thick

Standard Production Rate TOTAL VOLUME = 2,589.00 ton

1 Team
Asphalt Paver = 1 no. (130hp) Foreman = 1 person
Tandem Roller = 1 no. (10ton) Operator = 5 person
Pneu. Tyred Roller = 1 no. Labour = 7 person
Tack/Prime Coat Lorry = 1 no.
Water Tanker = 1 no
Air Compressor = 1 no. 1000 max
(*Ref-Means Books)
Production of one team, P = 623 ton/day Page 78 6345 S.Y
0.8361 SY/Sq.m

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 4 days


= 0.7 week
= 0.2 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Asphalt Paver = 1 Foreman = 1
Tandem Roller = 1 Operator = 5
Pneu. Tyred Roller = 1 Labour = 5
1 4 Tack/Prime Coat Lorry = 1
Water Tanker = 1
Air Compressor = 1

Asphalt Paver = 2 Foreman = 1


0 Tandem Roller = 2 Operator = 10
0 Pneu. Tyred Roller = 2 Labour = 10
2 2 Tack/Prime Coat Lorry = 2
Water Tanker = 2
Air Compressor = 2

Asphalt Paver = 3 Foreman = 2


0 Tandem Roller = 3 Operator = 15
0 Pneu. Tyred Roller = 3 Labour = 15
3 1 Tack/Prime Coat Lorry = 3
Water Tanker = 3
Air Compressor = 3

Asphalt Paver = 4 Foreman = 2


0 Tandem Roller = 4 Operator = 20
0 Pneu. Tyred Roller = 4 Labour = 20
4 1 Tack/Prime Coat Lorry = 4
Water Tanker = 4
Air Compressor = 4

Asphalt Paver = 5 Foreman = 3


Tandem Roller = 5 Operator = 25
5 1
Pneu. Tyred Roller = 5 Labour = 25
5 1
KERB - MACHINE FORMED

Standard Production Rate TOTAL VOLUME = 3,763.00 lin.m

1 Team
Curb Paver = 1 no. Foreman = 1 person
Lorry = 1 no. Operator = 1 person
Labour = 4 person
Kerb Size = 350mm(H) x 500mm(W)

Production of one team, P = 300 lin.m/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 13 days


= 2.1 week
= 0.5 month

NO. OF TEAM DURATION (Days) Plant Labour


Curb Paver = 1 Foreman = 1
Lorry = 1 Operator = 1
1 13
Labour = 4

Curb Paver = 2 Foreman = 1


Lorry = 2 Operator = 2
2 6
Labour = 8

Curb Paver = 3 Foreman = 1


Lorry = 3 Operator = 3
3 4
Labour = 12

Curb Paver = 4 Foreman = 1


Lorry = 4 Operator = 4
4 3
Labour = 16

Curb Paver = 5 Foreman = 1


Lorry = 5 Operator = 5
5 3
Labour = 20
Production Rate

Milling 300 mm

Mill = 0.3 m Mill =


Width = 3.65 m Width =
Length = 845 m Length =

Volume = 925.275 m3 Volume =


Estimate = 93 loads @ 30 min/loads Estimate =
Time Required = 46.3 hrs Time Requi=

DBM DBM
Thickness = 0.23 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 125.925 m3 = 277.0 tonne Volume =


Estimate = 14 loads @ 30 min/loads Estimate =
Time Required = 6.9 hrs Time Requi=

ACBC ACBC
Thickness = 0.06 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 840 m3 = 1932 tonne Volume =


Estimate = 97 loads @ 30 min/loads Estimate =
Time Required = 48.3 hrs 6 days Time Requi=

Total Time Required = 101.5 hrs Total Time=

Milling 240 mm

Mill = 0.24 m Mill =


Width = 3.65 m Width =
Length = 150 m Length =
Volume = 131.4 m3 Volume =
Estimate = 13 loads @ 30 min/loads Estimate =
Time Required = 6.6 hrs Time Requi=

DBM DBM
Thickness = 0.18 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 98.55 m3 = 216.8 tonne Volume =


Estimate = 11 loads @ 30 min/loads Estimate =
Time Required = 5.4 hrs Time Requi=

ACBC ACBC
Thickness = 0.08 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 43.8 m3 = 96.36 tonne Volume =


Estimate = 5 loads @ 30 min/loads Estimate =
Time Required = 2.4 hrs Time Requi=

Total Time Required = 14.4 hrs Total Time=

Milling 280 mm

Mill = 0.28 m Mill =


Width = 3.65 m Width =
Length = 100 m Length =

Volume = 102.2 m3 Volume =


Estimate = 10 loads @ 30 min/loads Estimate =
Time Required = 5.1 hrs Time Requi=

DBM DBM
Thickness = 0.22 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 120.45 m3 = 265.0 tonne Volume =


Estimate = 13 loads @ 30 min/loads Estimate =
Time Required = 6.6 hrs Time Requi=

ACBC ACBC
Thickness = 0.06 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 32.85 m3 = 72.27 tonne Volume =


Estimate = 4 loads @ 30 min/loads Estimate =
Time Required = 1.8 hrs Time Requi=

Total Time Required = 13.5 hrs Total Time=

Milling 270 mm

Mill = 0.27 m Mill =


Width = 3.65 m Width =
Length = 150 m Length =

Volume = 147.825 m3 Volume =


Estimate = 15 loads @ 30 min/loads Estimate =
Time Required = 7.4 hrs Time Requi=

DBM DBM
Thickness = 0.21 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 114.975 m3 = 252.9 tonne Volume =


Estimate = 13 loads @ 30 min/loads Estimate =
Time Required = 6.3 hrs Time Requi=

ACBC ACBC
Thickness = 0.06 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 32.85 m3 = 72.27 tonne Volume =


Estimate = 4 loads @ 30 min/loads Estimate =
Time Required = 1.8 hrs Time Requi=

Total Time Required = 15.5 hrs Total Time=

Milling 230 mm

Mill = 0.23 m Mill =


Width = 3.65 m Width =
Length = 150 m Length =

Volume = 125.925 m3 Volume =


Estimate = 13 loads @ 30 min/loads Estimate =
Time Required = 6.3 hrs Time Requi=

DBM DBM
Thickness = 0.17 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 93.075 m3 = 204.8 tonne Volume =


Estimate = 10 loads @ 30 min/loads Estimate =
Time Required = 5.1 hrs Time Requi=

ACBC ACBC
Thickness = 0.06 m Thickness =
Width = 3.65 m Width =
Length = 150 m Length =

Volume = 32.85 m3 = 72.27 tonne Volume =


Estimate = 4 loads @ 30 min/loads Estimate =
Time Required = 1.8 hrs Time Requi=
Total Time Required = 13.2 hrs Total Time=

Milling 60 mm

Mill = 0m Mill =
Width = 3.75 m Width =
Length = 800 m Length =

Volume = 0 m3 Volume =
Estimate = 0 loads @ 30 min/loads Estimate =
Time Required = 0.0 hrs Time Requi=

DBM DBM
Thickness = 0m Thickness =
Width = 3.75 m Width =
Length = 800 m Length =

Volume = 0 m3 = 0.0 tonne Volume =


Estimate = 0 loads @ 30 min/loads Estimate =
Time Required = 0.0 hrs Time Requi=

ACBC ACBC
Thickness = 0.05 m Thickness =
Width = 7.3 m Width =
Length = 800 m Length =

Volume = 292 m3 = 642.4 tonne Volume =


Estimate = 32 loads @ 30 min/loads Estimate =
Time Required = 16.1 hrs Time Requi=

Total Time Required = 16.1 hrs Total Time=


0.3 m Mill = 0.19 m
3.65 m Width = 3.75 m
200 m Length = 250 m

219 m3 Volume = 178.125 m3


22 loads @ 30 min/loads Estimate = 18 loads @
11.0 hrs Time Requi= 8.9 hrs

DBM
0.23 m Thickness = 0.13 m
3.65 m Width = 3.75 m
200 m Length = 250 m

167.9 m3 = 369.38 tonne Volume = 121.875 m3 =


18 loads @ 30 min/loads Estimate = 13 loads @
9.2 hrs Time Requi= 6.7 hrs

ACBC
0.06 m Thickness = 0.06 m
3.65 m Width = 3.75 m
200 m Length = 250 m

43.8 m3 = 96.36 tonne Volume = 56.25 m3 =


5 loads @ 30 min/loads Estimate = 6 loads @
2.4 hrs Time Requi= 3.1 hrs

22.6 hrs Total Time= 18.7 hrs

0.24 m Mill = 0.16 m


3.65 m Width = 3.75 m
200 m Length = 250 m
175.2 m3 Volume = 150 m3
18 loads @ 30 min/loads Estimate = 15 loads @
8.8 hrs Time Requi= 7.5 hrs

DBM
0.18 m Thickness = 0.1 m
3.65 m Width = 3.75 m
200 m Length = 250 m

131.4 m3 = 289.08 tonne Volume = 93.75 m3 =


14 loads @ 30 min/loads Estimate = 10 loads @
7.2 hrs Time Requi= 5.2 hrs

ACBC
0.08 m Thickness = 0.06 m
3.65 m Width = 3.75 m
200 m Length = 250 m

58.4 m3 = 128.48 tonne Volume = 56.25 m3 =


6 loads @ 30 min/loads Estimate = 6 loads @
3.2 hrs Time Requi= 3.1 hrs

19.2 hrs Total Time= 15.8 hrs

0.28 m Mill = 0.28 m


3.65 m Width = 3.65 m
200 m Length = 180 m

204.4 m3 Volume = 183.96 m3


20 loads @ 30 min/loads Estimate = 18 loads @
10.2 hrs Time Requi= 9.2 hrs

DBM
0.22 m Thickness = 0.22 m
3.65 m Width = 3.65 m
200 m Length = 180 m

160.6 m3 = 353.32 tonne Volume = 144.54 m3 =


18 loads @ 30 min/loads Estimate = 16 loads @
8.8 hrs Time Requi= 7.9 hrs

ACBC
0.06 m Thickness = 0.06 m
3.65 m Width = 3.65 m
200 m Length = 180 m

43.8 m3 = 96.36 tonne Volume = 39.42 m3 =


5 loads @ 30 min/loads Estimate = 4 loads @
2.4 hrs Time Requi= 2.2 hrs

21.5 hrs Total Time= 19.3 hrs

0.27 m Mill = 0.27 m


3.65 m Width = 3.65 m
200 m Length = 180 m

197.1 m3 Volume = 177.39 m3


20 loads @ 30 min/loads Estimate = 18 loads @
9.9 hrs Time Requi= 8.9 hrs

DBM
0.21 m Thickness = 0.21 m
3.65 m Width = 3.65 m
200 m Length = 180 m

153.3 m3 = 337.26 tonne Volume = 137.97 m3 =


17 loads @ 30 min/loads Estimate = 15 loads @
8.4 hrs Time Requi= 7.6 hrs

ACBC
0.06 m Thickness = 0.06 m
3.65 m Width = 3.65 m
200 m Length = 180 m

43.8 m3 = 96.36 tonne Volume = 39.42 m3 =


5 loads @ 30 min/loads Estimate = 4 loads @
2.4 hrs Time Requi= 2.2 hrs

20.7 hrs Total Time= 18.6 hrs

0.23 m Mill = 0.23 m


3.65 m Width = 3.65 m
200 m Length = 220 m

167.9 m3 Volume = 184.69 m3


17 loads @ 30 min/loads Estimate = 18 loads @
8.4 hrs Time Requi= 9.2 hrs

DBM
0.17 m Thickness = 0.17 m
3.65 m Width = 3.65 m
200 m Length = 220 m

124.1 m3 = 273.02 tonne Volume = 136.51 m3 =


14 loads @ 30 min/loads Estimate = 15 loads @
6.8 hrs Time Requi= 7.5 hrs

ACBC
0.06 m Thickness = 0.06 m
3.65 m Width = 3.65 m
200 m Length = 220 m

43.8 m3 = 96.36 tonne Volume = 48.18 m3 =


5 loads @ 30 min/loads Estimate = 5 loads @
2.4 hrs Time Requi= 2.6 hrs
17.6 hrs Total Time= 19.4 hrs

0m Mill = 0m
3.75 m Width = 3.75 m
200 m Length = 250 m

0 m3 Volume = 0 m3
0 loads @ 30 min/loads Estimate = 0 loads @
0.0 hrs Time Requi= 0.0 hrs

DBM
0m Thickness = 0m
3.75 m Width = 3.75 m
200 m Length = 250 m

0 m3 = 0 tonne Volume = 0 m3 =
0 loads @ 30 min/loads Estimate = 0 loads @
0.0 hrs Time Requi= 0.0 hrs

ACBC
0.05 m Thickness = 0.05 m
3.75 m Width = 3.75 m
200 m Length = 250 m

37.5 m3 = 82.5 tonne Volume = 46.875 m3 =


4 loads @ 30 min/loads Estimate = 5 loads @
2.1 hrs Time Requi= 2.6 hrs

2.1 hrs Total Time= 2.6 hrs


30 min/loads

268.125 tonne
30 min/loads

123.75 tonne
30 min/loads

Mill = 0.16 m
Width = 3.75 m
Length = 300 m
Volume = 180 m3
30 min/loads Estimate = 18 loads @ 30 min/loads
Time Required = 9.0 hrs

DBM
Thickness = 0.1 m
Width = 3.75 m
Length = 300 m

206.25 tonne Volume = 112.5 m3 = 247.5 tonne


30 min/loads Estimate = 12 loads @ 30 min/loads
Time Required = 6.2 hrs

ACBC
Thickness = 0.06 m
Width = 3.75 m
Length = 300 m

123.75 tonne Volume = 67.5 m3 = 148.5 tonne


30 min/loads Estimate = 7 loads @ 30 min/loads
Time Required = 3.7 hrs

Total Time Requir= 18.9 hrs

Mill = 0.28 m
Width = 3.75 m
Length = 300 m

Volume = 315 m3
30 min/loads Estimate = 32 loads @ 30 min/loads
Time Required = 15.8 hrs

DBM
Thickness = 0.22 m
Width = 3.75 m
Length = 300 m

317.988 tonne Volume = 247.5 m3 = 544.5 tonne


30 min/loads Estimate = 27 loads @ 30 min/loads
Time Required = 13.6 hrs

ACBC
Thickness = 0.06 m
Width = 3.75 m
Length = 300 m

86.724 tonne Volume = 67.5 m3 = 148.5 tonne


30 min/loads Estimate = 7 loads @ 30 min/loads
Time Required = 3.7 hrs

Total Time Requir= 33.1 hrs

Mill = 0.27 m
Width = 3.75 m
Length = 300 m

Volume = 303.75 m3
30 min/loads Estimate = 30 loads @ 30 min/loads
Time Required = 15.2 hrs

DBM
Thickness = 0.21 m
Width = 3.75 m
Length = 300 m

303.534 tonne Volume = 236.25 m3 = 519.75 tonne


30 min/loads Estimate = 26 loads @ 30 min/loads
Time Required = 13.0 hrs

ACBC
Thickness = 0.06 m
Width = 3.75 m
Length = 300 m

86.724 tonne Volume = 67.5 m3 = 148.5 tonne


30 min/loads Estimate = 7 loads @ 30 min/loads
Time Required = 3.7 hrs

Total Time Requir= 31.9 hrs

Mill = 0.23 m
Width = 3.75 m
Length = 300 m

Volume = 258.75 m3
30 min/loads Estimate = 26 loads @ 30 min/loads
Time Required = 12.9 hrs

DBM
Thickness = 0.17 m
Width = 3.75 m
Length = 300 m

300.322 tonne Volume = 191.25 m3 = 420.75 tonne


30 min/loads Estimate = 21 loads @ 30 min/loads
Time Required = 10.5 hrs

ACBC
Thickness = 0.06 m
Width = 3.75 m
Length = 300 m

105.996 tonne Volume = 67.5 m3 = 148.5 tonne


30 min/loads Estimate = 7 loads @ 30 min/loads
Time Required = 3.7 hrs
Total Time Requir= 27.2 hrs

Mill = 0m
Width = 3.75 m
Length = 300 m

Volume = 0 m3
30 min/loads Estimate = 0 loads @ 30 min/loads
Time Required = 0.0 hrs

DBM
Thickness = 0m
Width = 3.75 m
Length = 300 m

0 tonne Volume = 0 m3 = 0 tonne


30 min/loads Estimate = 0 loads @ 30 min/loads
Time Required = 0.0 hrs

ACBC
Thickness = 0.05 m
Width = 3.75 m
Length = 300 m

103.125 tonne Volume = 56.25 m3 = 123.75 tonne


30 min/loads Estimate = 6 loads @ 30 min/loads
Time Required = 3.1 hrs

Total Time Requir= 3.1 hrs


Mill = 0.28 m Mill = 0.28
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 367.5 m3 Volume = 420


Estimate = 37 loads @ 30 min/loads Estimate = 42
Time Requi= 18.4 hrs Time Requi= 21.0

DBM DBM
Thickness = 0.22 m Thickness = 0.22
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 288.75 m3 = 635.25 tonne Volume = 330


Estimate = 32 loads @ 30 min/loads Estimate = 36
Time Requi= 15.9 hrs Time Requi= 18.2

ACBC ACBC
Thickness = 0.06 m Thickness = 0.06
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 78.75 m3 = 173.25 tonne Volume = 90


Estimate = 9 loads @ 30 min/loads Estimate = 10
Time Requi= 4.3 hrs Time Requi= 5.0

Total Time= 38.6 hrs Total Time= 44.1

Mill = 0.27 m Mill = 0.27


Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 354.375 m3 Volume = 405


Estimate = 35 loads @ 30 min/loads Estimate = 41
Time Requi= 17.7 hrs Time Requi= 20.3

DBM DBM
Thickness = 0.21 m Thickness = 0.21
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 275.625 m3 = 606.375 tonne Volume = 315


Estimate = 30 loads @ 30 min/loads Estimate = 35
Time Requi= 15.2 hrs Time Requi= 17.3

ACBC ACBC
Thickness = 0.06 m Thickness = 0.06
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 78.75 m3 = 173.25 tonne Volume = 90


Estimate = 9 loads @ 30 min/loads Estimate = 10
Time Requi= 4.3 hrs Time Requi= 5.0

Total Time= 37.2 hrs Total Time= 42.5

Mill = 0.23 m Mill = 0.23


Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 301.875 m3 Volume = 345


Estimate = 30 loads @ 30 min/loads Estimate = 35
Time Requi= 15.1 hrs Time Requi= 17.3

DBM DBM
Thickness = 0.17 m Thickness = 0.17
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 223.125 m3 = 490.875 tonne Volume = 255


Estimate = 25 loads @ 30 min/loads Estimate = 28
Time Requi= 12.3 hrs Time Requi= 14.0

ACBC ACBC
Thickness = 0.06 m Thickness = 0.06
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 78.75 m3 = 173.25 tonne Volume = 90


Estimate = 9 loads @ 30 min/loads Estimate = 10
Time Requi= 4.3 hrs Time Requi= 5.0
Total Time= 31.7 hrs Total Time= 36.2

Mill = 0m Mill = 0
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 0 m3 Volume = 0
Estimate = 0 loads @ 30 min/loads Estimate = 0
Time Requi= 0.0 hrs Time Requi= 0.0

DBM DBM
Thickness = 0m Thickness = 0
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 0 m3 = 0 tonne Volume = 0


Estimate = 0 loads @ 30 min/loads Estimate = 0
Time Requi= 0.0 hrs Time Requi= 0.0

ACBC ACBC
Thickness = 0.05 m Thickness = 0.05
Width = 3.75 m Width = 3.75
Length = 350 m Length = 400

Volume = 65.625 m3 = 144.375 tonne Volume = 75


Estimate = 7 loads @ 30 min/loads Estimate = 8
Time Requi= 3.6 hrs Time Requi= 4.1

Total Time= 3.6 hrs Total Time= 4.1


m
m
m

m3
loads @ 30 min/loads
hrs

m
m
m

m3 = 726 tonne
loads @ 30 min/loads
hrs

m
m
m

m3 = 198 tonne
loads @ 30 min/loads
hrs

hrs

m
m
m

m3
loads @ 30 min/loads
hrs

m
m
m

m3 = 693 tonne
loads @ 30 min/loads
hrs
m
m
m

m3 = 198 tonne
loads @ 30 min/loads
hrs

hrs

m
m
m

m3
loads @ 30 min/loads
hrs

m
m
m

m3 = 561 tonne
loads @ 30 min/loads
hrs

m
m
m

m3 = 198 tonne
loads @ 30 min/loads
hrs
hrs

m
m
m

m3
loads @ 30 min/loads
hrs

m
m
m

m3 = 0 tonne
loads @ 30 min/loads
hrs

m
m
m

m3 = 165 tonne
loads @ 30 min/loads
hrs

hrs
MILLING WORKS - PAVEMENT

Standard Production Rate TOTAL VOLUME = 1,932.00 tonne

1 Team
Milling Machine = 1 no. (Writgen W1000) Foreman = 1 person
Lorry = 2 no. Operator = 2 person
Labour = 4 person
Width = 1m
depth = 250mm
Production of one Machine, P = 200 tonne/hr = 960 tonne/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 2 days


= 0.3 week
= 0.1 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Milling Machine = 1 Foreman = 1
Lorry = 2 Operator = 2
1 2
Labour = 4

Milling Machine = 2 Foreman = 1


Lorry = 4 Operator = 4
2 1
Labour = 8

Milling Machine = 3 Foreman = 1


Lorry = 6 Operator = 6
3 1
Labour = 12

Milling Machine = 4 Foreman = 1


Lorry = 8 Operator = 8
4 1
Labour = 16

Milling Machine = 5 Foreman = 2


Lorry = 10 Operator = 10
5 0
Labour = 20
ROAD MARKING - Thermoplastic

Standard Production Rate TOTAL VOLUME = 21,060.00 lin.m

1 Team
Thermo Striper = 1 no. Foreman = 1 person
Pickup truck = 1 no. Operator = 1 person
Labour = 3 person

Production of one Team, P = 1,219 lin.m/day

\ TOTAL DAY REQUIRED FOR ABOVE VOLUME = 17 days


= 2.9 week
= 0.7 month

PRODUCTION TABLE

NO. OF TEAM DURATION (Days) Plant Labour


Thermo Striper = 1 Foreman = 1
Pickup truck = 1 Operator = 1
1 17
Labour = 3

Thermo Striper = 2 Foreman = 1


Pickup truck = 2 Operator = 2
2 9
Labour = 6

Thermo Striper = 3 Foreman = 1


Pickup truck = 3 Operator = 3
3 6
Labour = 9

Thermo Striper = 4 Foreman = 1


Pickup truck = 4 Operator = 4
4 4
Labour = 12

Thermo Striper = 5 Foreman = 1


Pickup truck = 5 Operator = 5
5 3
Labour = 15