Professional Documents
Culture Documents
Question 1
Which of the following refers to defining the conduct of risk management activities for a
project?
Correct Answer: # 2
Question 2
Which among the following statements about risk management plan is incorrect?
Correct Answer: # 3
Question: Which among the following statements about risk management plan is
incorrect?
1. It describes how Project Risk Management will be structured and performed on the project.
2. It can be informal and broadly framed.
3. It is exclusive of the project management plan.
4. It can be formal and highly detailed.
Justification: Risk Management Plan: Document that describes how Project Risk Management will be
structured and performed on the project. It is contained in or is a subsidiary plan of the project management
plan. It can be informal and broadly framed, or formal and highly detailed, based on the needs of the project.
Information in this plan varies by application area and project size.
Question 3
The following statements are about the objectives of the Plan Risk Management process.
Which one is not true?
Integrate Project Risk Management with all other project management activities.
Correct Answer: # 2
Question: The following statements are about the objectives of the Plan Risk
Management process. Which one is not true?
Justification: The objectives of the Plan Risk Management process are to: o Develop overall risk
management strategy for the project o Decide how risk management processes will be executed o Integrate
Project Risk Management with all other project management activities
Question 4
Correct Answer: # 1
Question 5
What are the two categories of success criteria for risk management?
Correct Answer: # 3
Question: What are the two categories of success criteria for risk management?
Justification: There are two categories of success criteria for risk management: those for success of
the project in general, and those for success of Project Risk Management. • Project-related Criteria: The risk
management plan should present the objectives for the project-related criteria (like cost, time, and scope) to
ensure consistency and agreement among stakeholders. This ascertains the success of Project Risk
Management. • Process-related Criteria: The measures for success in the Project Risk Management
process depend on factors like the inherent level of uncertainty of the project.
Question 6
Correct Answer: # 4
Justification: The risk attitudes of both the organization and the stakeholders, including their tolerance
for uncertainty and the importance to them of achieving or missing specific project objectives, need to be
analyzed for setting thresholds and providing weighting factors in the application of Project Risk
Management processes because these attitudes influence the level of risk considered acceptable in a
project. Communication between the project manager and stakeholders is required to identify changes in
stakeholder risk attitudes and, wherever required, escalate risk-related information to management and
other stakeholders.
Question 7
Which of the following documents the intensity of effort and the frequency with which the
various Project Risk Management processes should be applied?
Risk register
Correct Answer: # 2
Question: Which of the following documents the intensity of effort and the frequency with
which the various Project Risk Management processes should be applied?
1. Risk register
2. Risk management plan
3. Risk response plan
4. Project performance metrics
Justification: The risk management plan should indicate the intensity of effort and the frequency with
which the various Project Risk Management processes should be applied.
Question 8
a) Within the risk management team b) Between the project team and the other project
stakeholders
a) Within the project team b) Between the project team and the other project
stakeholders
Correct Answer: # 4
Question: What are the two levels at which risk-related communication occurs?
Justification: Risk-related communication happens at two levels: (a) within the project team, and (b)
between the project team and the other project stakeholders.
Question 9
Which of the following is not a criterion for a valid risk management plan?
Acceptance by stakeholders
Completeness with respect to the needs of the Project Risk Management process
Correct Answer: # 2
Question: Which of the following is not a criterion for a valid risk management plan?
1. Acceptance by stakeholders
2. Non-alignment with the internal and external constraints on the project
3. Balance between cost/effort and benefit
4. Completeness with respect to the needs of the Project Risk Management process
Question 10
A tool that is a hierarchically organized depiction of the identified project risks arranged
by risk category.
A representation of the project including data about project elements and risks that can
be analyzed by quantitative methods.
A high-level approach to address an individual risk or overall project risk, broken down
into a set of risk actions.
Correct Answer: # 2
Question: Which among the following best defines Risk Breakdown Structure?
Justification: Risk Breakdown structure: [Tool] A hierarchically organized depiction of the identified
project risks arranged by risk category and subcategory that identifies the various areas and causes of
potential risks. It is often tailored to specific project types.
Question 11
Which is not a critical success factor for the Plan Risk Management process?
Correct Answer: # 1
Question: Which is not a critical success factor for the Plan Risk Management process?
Justification: The three critical success factors for the Plan Risk Management process are: • Identify
and address barriers to successful Project Risk Management • Involve project stakeholders in Project Risk
Management • Comply with the organization’s objectives, policies, and practices
Question 12
Fill in the blanks. ______ ______ are recommended to build a common understanding of the
project's risk approach between project stakeholders and to gain agreement on the
techniques to be used for managing risk.
Project descriptions
Planning sessions
Communications plans
Correct Answer: # 3
Question: Fill in the blanks. ______ ______ are recommended to build a common
understanding of the project
1. Project descriptions
2. Risk management guidelines
3. Planning sessions
4. Communications plans
Justification: Planning sessions are recommended to build a common understanding of the project’s
risk approach between project stakeholders and to gain agreement on the techniques to be used for
managing risk.
Question 13
What is the primary purpose of work products like risk status reports, risk breakdown
structures or risk register?
Describe the purposes and objectives of the processes involved in risk management
Correct Answer: # 1
Question: What is the primary purpose of work products like risk status reports, risk
breakdown structures or risk register?
Justification: In order to benefit from experience and existing best practice, risk management planning
should take into account relevant existing templates for work products like risk status reports, risk
breakdown structures or risk register.
Question 14
Adapted in subsequent stages as the needs of the project and its stakeholders become
clearer or change.
Specifies the project’s risk management roles and responsibilities.
Establishes type and level of risk detail to be addressed and provides a template of risk
register.
Inspection by senior management is required; the plan communicates between the
project manager and stakeholders to identify changes in stakeholder risk attitudes.
Correct Answer: # 4
1. Adapted in subsequent stages as the needs of the project and its stakeholders become clearer or
change.
2. Specifies the project’s risk management roles and responsibilities.
3. Establishes type and level of risk detail to be addressed and provides a template of risk register.
4. Inspection by senior management is required; the plan communicates between the project manager
and stakeholders to identify changes in stakeholder risk attitudes.
Justification: Communication between the project manager and stakeholders is required to identify
changes in stakeholder risk attitudes.
Reference: Section 4.1, page 20, Practice Standard for Project Risk Management.
PMI-RMP Chapter 2 Test/Answers
Question 15
Which of the following is NOT a Criteria for valid risk management plan?
Stakeholder acceptance
Correct Answer: # 3
Question: Which of the following is NOT a Criteria for valid risk management plan?
1. Stakeholder acceptance
2. Balance between Cost versus Benefit
3. Project Manager and Stakeholder agreement outside project scope
4. Alignment with internal and external constraints on project
Justification: Criteria for valid risk management plan includes: Acceptance by stakeholders; Alignment
with internal and external constraints on project; Balance between cost/effort and benefit; and Fulfil
requirements of Project Risk Management process.
Reference: Section 4.1, page 19, Practice Standard for Project Risk Management.
PMI-RMP Chapter 2 Test/Answers
Question 16
3. Which of the following options is CORRECT about Critical Success Factors for the Plan
Risk Management Process?
The activities of the risk management plan should be built into an overall project map
and not into a broken down structure.
Chances of failure of the risk management activities decrease with availability of
organizational process assets
Activities of the risk management plan should never be part of the corresponding
schedule, budget, and work-assignment documents.
The inexperience of an organization in risk management planning may be dispelled by
following a proprietary or pre-existing approach without making any changes to it.
Correct Answer: # 2
Question: 3. Which of the following options is CORRECT about Critical Success Factors
for the Plan Risk Management Process?
1. The activities of the risk management plan should be built into an overall project map and not into a
broken down structure.
2. Chances of failure of the risk management activities decrease with availability of organizational
process assets
3. Activities of the risk management plan should never be part of the corresponding schedule, budget,
and work-assignment documents.
4. The inexperience of an organization in risk management planning may be dispelled by following a
proprietary or pre-existing approach without making any changes to it.
Justification: Chances of success of the risk management activities increase with availability of
organizational process assets.
Reference: Section 4.2.1, page 21, Practice Standard for Project Risk Management.
PMI-RMP Chapter 2 Test/Answers
Question 17
Which of the following is INCORRECT about the factor "Involve Project Stakeholders in
Project Risk Management"?
Selected Choice: #
Correct Answer: # 1
Question: Which of the following is INCORRECT about the factor "Involve Project
Stakeholders in Project Risk Management"?
Justification: Involve Project Stakeholders in Project Risk Management cover the following points: •
Project Managers should ensure involvement of stakeholders to build on their skills and to ensure their
understanding of, and commitment to, the Project Risk Management process. • Address and resolve
disagreements between stakeholders in the areas of risk tolerance and evaluation measures.
Reference: Section 4.2.2, page 21, Practice Standard for Project Risk Management.
PMI-RMP Chapter 2 Test/Answers
Question 18
The project manager, members of the organization responsible for risk, and subject
matter experts/facilitators.
The project manager, selected team members, and subject matter experts/facilitators.
D. The project manager, selected team members, other stakeholders, members of the
organization responsible forrisk, and subject matter experts/facilitators.
Correct Answer: # 4
Justification: Planning sessions are recommended in order to build a common understanding of the
project’s risk approach betweenproject stakeholders and to gain agreement on the techniques to be used for
managing risk. Elaboration of the risk management plan often serves to develop an effective means for the
team to work together since a similar consultative team approach will be used in subsequent stages of
the risk management process. The participants should include: the project manager, selected project team
members and other stakeholders, members of the broader organization having responsibility for risk, and
other subject matter experts or facilitators, as needed.
Reference: Section 4.3.1, page 22, Practice Standard for Project Risk Management.
PMI-RMP Chapter 2 Test/Answers
Question 19
Which of the following is NOT a Key area of Focus for the Plan Risk Management Process?
Team Strength
People
Business
Tools
Correct Answer: # 1
Question: Which of the following is NOT a Key area of Focus for the Plan Risk
Management Process?
1. Team Strength
2. People
3. Business
4. Tools
Table 4.1 Key areas of Focus for the Plan Risk Management Process
Reference: Section 4.4, page 23, Practice Standard for Project Risk Management.
PMI-RMP Chapter 2 Test/Answers
Question 20
Correct Answer: # 1