Ref. No. ABCI/SITE/AE/NH-54/PKG-5/2020-21/265 Date: 31.10.

2020

M/s TPF-Rodic Consultant Pvt. Ltd. (JV) in association with Anandjiwala Infra Advisory
H. No. 3, House of Samson Zoramthang
House No. 144B, Chanmari E, Lunglei
Dist. Lunglei, Mizoram - 796701
Phone: 0361-2730046
E-mail: pkg5tl@gmail.com

Kind Attn: Mr. H. Muralidhara Pai

Sub: “Widening and up-gradation to 2-lane with paved shoulder configuration and
geometric improvements from km 208.00 to km 250.00 (Package-5) on Aizawl-
Tuipang section of NH-54 in the State of Mizoram on EPC mode with JICA loan
assistance” – Reg. Submission of Plan and Profile Drawings showing retaining
structures.
Ref:
i) LOA No NHIDCL/JICA/NH-54-Miz-2017-18-158/Package-4/2018-19 dated 13.02.2019
ii) Contract Agreement dated 28.02.2019
iii) Supplementary Agreement signed on 25.10.2019
iv) Approved Plan & Profile Drawings
v) Our letter no. ABCI/SITE/AE/NH-54/PKG-5/2020-21/149 dated 02.07.2020
vi) Our letter no. ABCI/SITE/AE/NH-54/PKG-5/2020-21/159 dated 09.07.2020
vii) Our letter no. ABCI/SITE/GOV/NH-54/PKG-5/2020-21/177 dated 24.07.2020
viii) Review Meeting dated 28.07.2020
ix) Our letter no. ABCI/SITE/AE/NH-54/PKG-5/2020-21/192 dated 22.08.2020
Dear Sir,

1. The Contractor earlier submitted complete Plan Profile in four parts vide letter
ABCI/KOL/NHIDCL/PKG-5/2019-20/1637 dated 14.02.2020,
ABCI/KOL/NHIDCL/PKG-5/2019-20/1753 dated 29.02.2020,
ABCI/KOL/NHIDCL/PKG-5/2019-20/1758 dated 02.03.2020 and ABCI/SITE/AE/NH-
54/PKG-5/2020-21/152 dated 04.07.2020 which was duly approved by your good self-
vide letter no. Rodic-Tpf/Mizoram-JICA/Pkg-3/4/5/Aizawl-Tuipang/2020/252 dated
21.02.2020, Rodic-Tpf/Mizoram-JICA/Pkg-3/4/5/Aizawl-Tuipang/2020/300 dated
12.03.2020, RodicTpf/Mizoram-JICA/Pkg-3/4/5/Aizwal-Tuipang/2020/335 dated
25.03.2020 and RodicTpf/Mizoram-JICA/Pkg-3/4/5/Aizawl-Tuipang/2020/622 dated
12.07.2020 respectively.
2. Further, the Contractor submitted proposals of Retaining Structures in line with
Schedule-B and payment procedure given in Schedule-H of Contract Agreement vide
letter cited under reference (e), (f) and (g).
3. Later during the review meeting held on 28.07.2020 it was requested by the Authority’s
Engineer to submit Plan & Profile drawings indicating the retaining structures such as
Retaining walls and Breast Walls.

Page 1
4. Vide letter under reference (i) the advance copy of the Plan and Profile drawings
indicating the retaining structures was submitted for your kind perusal.
5. We are now submitting the following Plan & Profile drawings indicating the retaining
structures certified by the Proof and Safety consultants in triplicate for your kind perusal
and approval.

Sl. No. Drawing No. Drawing Title Rev


1 SAI/TKD-2019016/PKG-5/HW/PW-01 Protection Work drawings from R0
km 208+000 to km 208+500
2 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
01A km 208+000 to km 208+500
3 SAI/TKD-2019016/PKG-5/HW/PW-02 Protection Work drawings from R0
km 208+500 to km 209+000
4 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
02A km 208+500 to km 209+000
5 SAI/TKD-2019016/PKG-5/HW/PW-03 Protection Work drawings from R0
km 209+000 to km 209+500
6 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
03A km 209+000 to km 209+500
7 SAI/TKD-2019016/PKG-5/HW/PW-04 Protection Work drawings from R0
km 209+500 to km 210+000
8 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
04A km 209+500 to km 210+000
9 SAI/TKD-2019016/PKG-5/HW/PW-05 Protection Work drawings from R0
km 210+000 to km 210+500
10 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
05A km 210+000 to km 210+500
11 SAI/TKD-2019016/PKG-5/HW/PW-06 Protection Work drawings from R0
km 210+500 to km 211+000
12 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
06A km 210+500 to km 211+000
13 SAI/TKD-2019016/PKG-5/HW/PW-07 Protection Work drawings from R0
km 211+000 to km 211+500
14 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
07A km 211+000 to km 211+500
15 SAI/TKD-2019016/PKG-5/HW/PW-08 Protection Work drawings from R0
km 211+500 to km 212+000
16 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
08A km 211+500 to km 212+000
17 SAI/TKD-2019016/PKG-5/HW/PW-09 Protection Work drawings from R0
km 212+000 to km 212+500
18 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
09A km 212+000 to km 212+500

Page 2
Sl. No. Drawing No. Drawing Title Rev
19 SAI/TKD-2019016/PKG-5/HW/PW-10 Protection Work drawings from R0
km 212+500 to km 213+000
20 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
10A km 212+500 to km 213+000
21 SAI/TKD-2019016/PKG-5/HW/PW-11 Protection Work drawings from R0
km 213+000 to km 213+500
22 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
11A km 213+000 to km 213+500
23 SAI/TKD-2019016/PKG-5/HW/PW-12 Protection Work drawings from R0
km 213+500 to km 214+000
24 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
12A km 213+500 to km 214+000
25 SAI/TKD-2019016/PKG-5/HW/PW-13 Protection Work drawings from R0
km 214+000 to km 214+500
26 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
13A km 214+000 to km 214+500
27 SAI/TKD-2019016/PKG-5/HW/PW-14 Protection Work drawings from R0
km 214+500 to km 215+000
28 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
14A km 214+500 to km 215+000
29 SAI/TKD-2019016/PKG-5/HW/PW-15 Protection Work drawings from R0
km 215+000 to km 215+500
30 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
15A km 215+000 to km 215+500
31 SAI/TKD-2019016/PKG-5/HW/PW-16 Protection Work drawings from R0
km 215+500 to km 216+000
32 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
16A km 215+500 to km 216+000
33 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
16B km 216+000 to km 216+132
34 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
16C km 216+000 to km 216+132
35 SAI/TKD-2019016/PKG-5/HW/PW-17 Protection Work drawings from R0
km 216+000 to km 216+500
36 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
17A km 216+000 to km 216+500
37 SAI/TKD-2019016/PKG-5/HW/PW-18 Protection Work drawings from R0
km 216+500 to km 217+000
38 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
18A km 216+500 to km 217+000
39 SAI/TKD-2019016/PKG-5/HW/PW-19 Protection Work drawings from R0
km 217+000 to km 217+500

Page 3
Sl. No. Drawing No. Drawing Title Rev
40 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
19A km 217+000 to km 217+500
41 SAI/TKD-2019016/PKG-5/HW/PW-20 Protection Work drawings from R0
km 217+500 to km 218+000
42 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
20A km 217+500 to km 218+000
43 SAI/TKD-2019016/PKG-5/HW/PW-21 Protection Work drawings from R0
km 218+000 to km 218+500
44 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
21A km 218+000 to km 218+500
45 SAI/TKD-2019016/PKG-5/HW/PW-22 Protection Work drawings from R0
km 218+500 to km 219+000
46 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
22A km 218+500 to km 219+000
47 SAI/TKD-2019016/PKG-5/HW/PW-23 Protection Work drawings from R0
km 219+000 to km 219+500
48 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
23A km 219+000 to km 219+500
49 SAI/TKD-2019016/PKG-5/HW/PW-24 Protection Work drawings from R0
km 219+500 to km 220+000
50 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
24A km 219+500 to km 220+000
51 SAI/TKD-2019016/PKG-5/HW/PW-25 Protection Work drawings from R0
km 220+000 to km 220+500
52 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
25A km 220+000 to km 220+500
53 SAI/TKD-2019016/PKG-5/HW/PW-26 Protection Work drawings from R0
km 220+500 to km 221+000
54 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
26A km 220+500 to km 221+000
55 SAI/TKD-2019016/PKG-5/HW/PW-27 Protection Work drawings from R0
km 221+000 to km 221+500
56 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
27A km 221+000 to km 221+500
57 SAI/TKD-2019016/PKG-5/HW/PW-28 Protection Work drawings from R0
km 221+500 to km 222+000
58 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
28A km 221+500 to km 222+000
59 SAI/TKD-2019016/PKG-5/HW/PW-29 Protection Work drawings from R0
km 222+000 to km 222+500
60 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
29A km 222+000 to km 222+500

Page 4
Sl. No. Drawing No. Drawing Title Rev
61 SAI/TKD-2019016/PKG-5/HW/PW-30 Protection Work drawings from R0
km 222+500 to km 223+000
62 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
30A km 222+500 to km 223+000
63 SAI/TKD-2019016/PKG-5/HW/PW-31 Protection Work drawings from R0
km 223+000 to km 223+500
64 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
31A km 223+000 to km 223+500
65 SAI/TKD-2019016/PKG-5/HW/PW-32 Protection Work drawings from R0
km 223+500 to km 224+000
66 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
32A km 223+500 to km 224+000
67 SAI/TKD-2019016/PKG-5/HW/PW-33 Protection Work drawings from R0
km 224+000 to km 224+500
68 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
33A km 224+000 to km 224+500
69 SAI/TKD-2019016/PKG-5/HW/PW-34 Protection Work drawings from R0
km 224+500 to km 225+000
70 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
34A km 224+500 to km 225+000
71 SAI/TKD-2019016/PKG-5/HW/PW-35 Protection Work drawings from R0
km 225+000 to km 225+500
72 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
35A km 225+000 to km 225+500
73 SAI/TKD-2019016/PKG-5/HW/PW-36 Protection Work drawings from R0
km 225+500 to km 226+000
74 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
36A km 225+500 to km 226+000
75 SAI/TKD-2019016/PKG-5/HW/PW-37 Protection Work drawings from R0
km 226+000 to km 226+500
76 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
37A km 226+000 to km 226+500
77 SAI/TKD-2019016/PKG-5/HW/PW-38 Protection Work drawings from R0
km 226+500 to km 227+000
78 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
38A km 226+500 to km 227+000
79 SAI/TKD-2019016/PKG-5/HW/PW-39 Protection Work drawings from R0
km 227+000 to km 227+500
80 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
39A km 227+000 to km 227+500
81 SAI/TKD-2019016/PKG-5/HW/PW-40 Protection Work drawings from R0
km 227+500 to km 228+000

Page 5
Sl. No. Drawing No. Drawing Title Rev
82 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
40A km 227+500 to km 228+000
83 SAI/TKD-2019016/PKG-5/HW/PW-41 Protection Work drawings from R0
km 228+000 to km 228+500
84 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
41A km 228+000 to km 228+500
85 SAI/TKD-2019016/PKG-5/HW/PW-42 Protection Work drawings from R0
km 228+500 to km 229+000
86 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
42A km 228+500 to km 229+000
87 SAI/TKD-2019016/PKG-5/HW/PW-43 Protection Work drawings from R0
km 229+000 to km 229+500
88 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
43A km 229+000 to km 229+500
89 SAI/TKD-2019016/PKG-5/HW/PW-44 Protection Work drawings from R0
km 229+500 to km 230+000
90 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
44A km 229+500 to km 230+000
91 SAI/TKD-2019016/PKG-5/HW/PW-45 Protection Work drawings from R0
km 230+000 to km 230+500
92 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
45A km 230+000 to km 230+500
93 SAI/TKD-2019016/PKG-5/HW/PW-46 Protection Work drawings from R0
km 230+500 to km 231+000
94 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
46A km 230+500 to km 231+000
95 SAI/TKD-2019016/PKG-5/HW/PW-47 Protection Work drawings from R0
km 231+000 to km 231+500
96 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
47A km 231+000 to km 231+500
97 SAI/TKD-2019016/PKG-5/HW/PW-48 Protection Work drawings from R0
km 231+500 to km 232+000
98 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
48A km 231+500 to km 232+000
99 SAI/TKD-2019016/PKG-5/HW/PW-49 Protection Work drawings from R0
km 232+000 to km 232+500
100 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
49A km 232+000 to km 232+500
101 SAI/TKD-2019016/PKG-5/HW/PW-50 Protection Work drawings from R0
km 232+500 to km 233+000
102 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
50A km 232+500 to km 233+000

Page 6
Sl. No. Drawing No. Drawing Title Rev
103 SAI/TKD-2019016/PKG-5/HW/PW-51 Protection Work drawings from R0
km 233+000 to km 233+500
104 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
51A km 233+000 to km 233+500
105 SAI/TKD-2019016/PKG-5/HW/PW-52 Protection Work drawings from R0
km 233+500 to km 234+000
106 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
52A km 233+500 to km 234+000
107 SAI/TKD-2019016/PKG-5/HW/PW-53 Protection Work drawings from R0
km 234+000 to km 234+500
108 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
53A km 234+000 to km 234+500
109 SAI/TKD-2019016/PKG-5/HW/PW-54 Protection Work drawings from R0
km 234+500 to km 235+000
110 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
54A km 234+500 to km 235+000
111 SAI/TKD-2019016/PKG-5/HW/PW-55 Protection Work drawings from R0
km 235+000 to km 235+500
112 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
55A km 235+000 to km 235+500
113 SAI/TKD-2019016/PKG-5/HW/PW-56 Protection Work drawings from R0
km 235+500 to km 236+000
114 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
56A km 235+500 to km 236+000
115 SAI/TKD-2019016/PKG-5/HW/PW-57 Protection Work drawings from R0
km 236+000 to km 236+500
116 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
57A km 236+000 to km 236+500
117 SAI/TKD-2019016/PKG-5/HW/PW-58 Protection Work drawings from R0
km 236+500 to km 237+000
118 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
58A km 236+500 to km 237+000
119 SAI/TKD-2019016/PKG-5/HW/PW-59 Protection Work drawings from R0
km 237+000 to km 237+500
120 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
59A km 237+000 to km 237+500
121 SAI/TKD-2019016/PKG-5/HW/PW-60 Protection Work drawings from R0
km 237+500 to km 238+000
122 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
60A km 237+500 to km 238+000
123 SAI/TKD-2019016/PKG-5/HW/PW-61 Protection Work drawings from R0
km 238+000 to km 238+500

Page 7
Sl. No. Drawing No. Drawing Title Rev
124 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
61A km 238+000 to km 238+500
125 SAI/TKD-2019016/PKG-5/HW/PW-62 Protection Work drawings from R0
km 238+500 to km 239+000
126 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
62A km 238+500 to km 239+000
127 SAI/TKD-2019016/PKG-5/HW/PW-63 Protection Work drawings from R0
km 239+000 to km 239+500
128 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
63A km 239+000 to km 239+500
129 SAI/TKD-2019016/PKG-5/HW/PW-64 Protection Work drawings from R0
km 239+500 to km 240+000
130 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
64A km 239+500 to km 240+000
131 SAI/TKD-2019016/PKG-5/HW/PW-65 Protection Work drawings from R0
km 240+000 to km 240+500
132 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
65A km 240+000 to km 240+500
133 SAI/TKD-2019016/PKG-5/HW/PW-66 Protection Work drawings from R0
km 240+500 to km 241+000
134 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
66A km 240+500 to km 241+000
135 SAI/TKD-2019016/PKG-5/HW/PW-67 Protection Work drawings from R0
km 241+000 to km 241+500
136 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
67A km 241+000 to km 241+500
137 SAI/TKD-2019016/PKG-5/HW/PW-68 Protection Work drawings from R0
km 241+500 to km 241+802.946
138 SAI/TKD-2019016/PKG-5/HW/PW- Protection Work drawings from R0
68A km 241+500 to km 241+802.946

Hope you will find the above in order.


Please note that delay in submission of the aforesaid documents in hard copies duly
verified by Proof and Safety Consultants has been caused solely due to lockdown,
different restrictions, stringent norms imposed by the Govt. Authorities time to time for
the purpose of controlling spread of Covid-19 pandemic.

Thanking you and assuring you of our best services always.


Yours faithfully,
For ABCI Infrastructures Pvt. Ltd.

Authorized Signatory

Page 8
Prafulla Borgohain – Sr. GM

Encl: As stated above

Copy for kind information to:-

1. The Executive Director (P), NHIDCL, RO-Aizawl, Mizoram


2. The General Manager (P), NHIDCL, PMU-Lunglei, Mizoram
3. NHIDCL Site Office (Pkg 5) Lunglei, Mizoram
4. RE office (Pkg 5), Hnanthihal, Mizoram
5. ABCI site Office (Pkg 5), Hnanthihal Mizoram
6. Rodic Consultants Pvt. Ltd., Regional Office, Guwahati