Professional Documents
Culture Documents
You have been asked to calculate the Cost Performance Index for a project using earned
value Management techniques. It is currently day 20 of the project and the following
summarizes the current status of the project:
Calculate the Scheduled Variance, Schedule Performance Index, and Cost Performance Index
for the project.
Solution :
Startup is 100 percent complete and we are beyond the expected completion date, so budgeted cost
is $1,00,000 for this activity.
Would expect Construction to be 85.714 percent complete and cost $2,78,571 to date.
Construction is actually only 90 percent complete, so budgeted cost for this much of the activity is
(3,25,000 * 0.9) = $2,92,500.
Step 3: Actual Cost (AC) of the project to date $10,05,000 + $ 2,80,000 + $ 2,500 = $3,87500
The project looks good because it is both ahead of schedule and below the budgeted cost.