Immediate Duration Total Cash

Activity
Predecessor (Days) Flow Reqd.
A - 5 25
B - 5 30
C A 10 40
D B 7 28
E A 6 12
F C, D 8 24
G C, D 6 15
H E, F 5 10
I G 4 12

Draw a Gantt Chart for the project.

What is the maximum requirement of cash and on


which day does it occur?
Immediate Duration Manpower
Activity
Predecessor (Days) Required
A - 8 4
B - 7 8
C A 6 5
D B 8 4
E B 4 8
F B 8 6
G C, D 5 5
H E 6 4
I F 6 5
J G, H, I 10 6

Plot a Gantt Chart for resources requirements & a


resource graph over time. If the available man-power is
limited to 20 find out the days of over allocation. Also
find out over allocation days, if available man-power is
limited to 25 days,
Immediate Duration
Activity Required Men
Predecessor (Days)
A - 5 20
B - 4 10
C - 3 10
D A 4 30
E A 6 20
F A 4 10
G B, F 5 10
H B, F 6 20
I C, G 6 10
J C, G 4 30

A project has the activities as given in the above table.


The maximum resource of men available is 40. Prepare
an activity resource allocation schedule under the given
resource constraints. Find the duration of the project