LAIBON VILLA CONSTRUCTION

weekly labor payments details


from 29-06-2020 to 04-07-2020

no work work no ITEM DES rate/ITEM total


1 blocks lifting labor 0 nos 200 0
2 helpers helpers 8 nos 6 8000 384000
3 carpenter fundi 1 nos 6 20000 120000
4 steel fixer fundi 0 nos 6 25000 0
3 masonry water proof 154 sqm 1800 277200
4 masonry block work 568 nos 300 170400
5 masonry plastering 365 sqm 2000 730000
6 sand lifting labor 0 bags 200 0
7 scaffolding labor 2 lifts 200000
total = 1881600

prepared by

authorised by