Professional Documents
Culture Documents
for
Process Control Systems
Table of Contents:
1.0 Objective
The objective of this document is to highlight the qualification approach and major project
steps to ensure compliance for process control systems. The systems which are classified
as process control systems are
The purpose of carrying out validation of process control systems is not only to verify the
system configuration (hardware / software / loop and logic) as given by the system supplier;
but also to ensure that the respective process requirement specifications are incorporated in
the system.
During the process control systems validation it is imperative to carry out the Process
Mapping (Control Specifications verified against User Requirements). The configuration
gaps identified as a part of process mapping are to be evaluated for the risk involved (of not
having the respective controls). The High and Medium (in that order) gaps are addressed
either technically (by way of modifying the configuration) or with procedural controls.
Besides addressing the configuration gaps, it is also important to review and prioritize the
alarms and events defined in the systems. The alarm and event handling strategy will
identify the following
Having completed the Process Mapping and Alarm Handling strategy, the validation will be
carried following the GAMP V model.
The following diagram covers the qualification approach for new as well as existing systems.
Existing Systems
Automated
Remediation
System
Plan
Inventory
New Systems
For the new systems being implemented the approach would be as shown in the diagram
which will be following the V model of GAMP.
However, for the existing systems the approach would to perform the Quality System Impact
Analysis (identifying gaps in systems from functional / operational / compliance point of view
including risk assessment); address / close the gaps and then carry out the validation. Each
of these steps is elaborated in the respective Para.
A user requirements document will be developed as part of this validation effort. This
version-controlled document will formally specify client’s intended uses for the various
process control systems.
A Validation Master Plan will be developed to describe the objectives, scope, approach and
responsibilities for the process control systems validation. The validation master plan shall
be approved before any of the protocols are approved.
While the validation master plan shall define the general approach to validation, During each
validation projects (for newly added systems or new facility undergoing International audit); a
validation plan will be prepared which will be the project Specific plan for the activities to be
undertaken.
Preparation / review of all the sops pertaining to operation and maintenance of process
control systems. These sops will cover both it sops and operational sops.
To evaluate the control systems against the functional requirements of the respective
process. The systems’ gaps on respective process to be addressed after due risk
assessment.
Identify the various risk related to GMP to operate the process control system. Evaluate the
system design and if the risk cause not considered in the design then identify the suitable
mitigation and change the system accordingly. All risk identified during assessment process
should be challenged during the operation qualification.
Emphasis will be given to alarm and event conditions defined in the system and the
Prepare installation qualification protocols for each sub system and carry out challenge
testing for recommended installation practices by the manufacturer / developer.
Network qualification is associated with the network infrastructure of the process control
systems (DCS / BMS / SCADA) and is carried out as part of installation qualification.
Functions are verified to establish that the hardware and system software is installed in
accordance with design and vendor/manufacturer recommended practices.
Prepare operational qualification protocols for each sub systems and carry out challenge
testing for systems functional and operational programs.
For the systems involving complex control loops performance qualification to be carried out
for the systems’ response and stability to process condition variations and load changes.
The test result summary and qualification status at the end of protocol execution to be
recorded in the validation report.
6.12 Documentation
• URS / FS
• Validation Master Plan.
• Validation Plan ( or project plan)
• Process mapping and quality system impact
• Risk Assessment Report.
• Installation Qualification Protocol and Report.
• Network Qualification Protocol and Report.
• Operation Qualification Protocol Report.
• Performance Qualification Protocol and Report.
• Deviation Reports.
• Qualification Summary Report.
The completion of the qualification activities will initiate the on going validation and
maintenance qualification.
8.0 Summary
Validation of process control systems is carried out on the basis of prevailing GAMP
guidelines which emphasizes risk based validation with life cycle approach. The activities
covered will be right from system user requirement specifications to maintenance
qualification and revalidation till the system is discontinued from the operations.
9.0 References
The publication listed below form part of this project being the reference documents. Each
publication shall be the latest revision and addendum in effect on the date of this proposal
shall be approved for execution unless noted otherwise.