We have successfully supplied and installed ( ) numbers of Conventional Earthing at

(Manitowoc crain ltd. Khalumbare)plant. Readings was taken on ( ) are results are found satisfactorily as
mentioned below

EARTHING READINGS
SR NO EARTHPIT AREA
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
l Earthing at
) are results are found satisfactorily as

EARTHING VALUE
We have successfully supplied and installed ( 78 NOS ) numbers of Conventional Earthing at
(Manitowoc crain ltd. Khalumbare)plant. Readings was taken on (10 NOV 2017) are results are found satisfactorily as mention

EARTHING READINGS
SR NO EARTHPIT AREA
1 EP-1 to EP -14 HT KIOSK AND 2 POLE STRUCTURE
2 EP-15 SECURITY CABIN
3 EP-16 to EP -29 TRANSFORMER , DG AND 2 POLE STRUCTURE
4 EP-30 to EP -32 LT PANEL
5 EP-33 to EP -34 & EP-77 ADMIN BLOCK
6 EP-35 to EP -43 MAST LINE
7 EP-44 to EP -45 CRANE CARE
8 EP-46 to EP -50 PAINT SHOP
9 EP-51 to EP -54 & EP-57 to EP -59 ASSY. LINE
10 EP-55 to EP -56 LIGHTENING ARRESTOR
11 EP-61 to EP -76 ALL SHOP FLOOR GRID EARTHING AND FLEX MFG
12 EP-78 SHOP FLOOR MACHINE EARTHING
onal Earthing at
7) are results are found satisfactorily as mentioned below

ADINGS
SPECIFIED VALUE EARTHING VALUE

< 2 OHM 0.7 OHM TO 1.9 OHM