How to Use the

Unit Price Pages

3
The following is a detailed explanation of a sample entry in the Unit
Price Section. Next to each bold number below is the described item Description
with the appropriate component of the sample entry following in (Concrete In Place, etc.)
parentheses. Some prices are listed as bare costs; others as costs that Each line item is described in detail. Sub-items and additional
include overhead and profit of the installing contractor. In most cases, sizes are indented beneath the appropriate line items. The first
if the work is to be subcontracted, the general contractor will need to line or two after the main item (in boldface) may contain
add an additional markup (RSMeans suggests using 10%) to the figures descriptive information that pertains to all line items beneath
in the column ‘‘Total Incl. O&P.’’ this boldface listing.
Items which include the symbol CN are updated in The

1 Division Number/Title
(03 30/Cast-In-Place Concrete)
Use the Unit Price Section Table of Contents to locate
RSMeans Quarterly Update Service online. To obtain access
to this service contact RSMeans customer service at
1-800-334-3509.

4䡺
specific items. The sections are classified according to the
CSI MasterFormat 2004 system. Reference Number
Information

2 Line Numbers
(03 30 53.40 3920)
Each unit price line item has been assigned a unique 12-digit
code based on the CSI MasterFormat classification.
-50
You’ll see reference numbers shown in
R033053 shaded boxes at the beginning of some
sections. These refer to related items in the
Reference Section, visually identified by a vertical gray
bar on the page edges.
The relation may be an estimating procedure that should be
read before estimating, or technical information.
The ‘‘R’’ designates the Reference Section. The numbers refer
to the MasterFormat 2004 classification system.
It is strongly recommended that you review all reference
numbers that appear within the section in which you are
working.

4
5 Crew (C-14C)
The ‘‘Crew’’ column designates the typical trade or crew used
to install the item. If an installation can be accomplished by
one trade and requires no power equipment, that trade and the
number of workers are listed (for example, “2 Carpenters”).
If an installation requires a composite crew, a crew code
8 Bare Costs:
Mat. (Bare Material Cost) (142)
The unit material cost is the “bare” material cost with no
overhead or profit included. Costs shown reflect national
average material prices for January of the current year and
include delivery to the job site. No sales taxes are included.
designation is listed (for example, “C-14C”). You’ll find full
details on all composite crews in the Crew Listings. Labor (117)
• For a complete list of all trades utilized in this book The unit labor cost is derived by multiplying bare labor-hour
and their abbreviations, see the inside back cover. costs for Crew C-14C by labor-hour units. The bare labor-hour
cost is found in the Crew Section under C-14C. (If a trade is
listed, the hourly labor cost—the wage rate—is found on the
inside back cover.)
Labor-Hour Labor-Hour
Cost Crew C-14C x Units = Labor
$36.62 x 3.20 $117.00

Equip. (Equipment) (.70)


Equipment costs for each crew are listed in the description of
each crew. Tools or equipment whose value justifies purchase

6
or ownership by a contractor are considered overhead as
Productivity: Daily Output (35.0)/ shown on the inside back cover. The unit equipment cost is
Labor-Hours (3.20) derived by multiplying the bare equipment hourly cost by the
The “Daily Output” represents the typical number of units labor-hour units.
the designated crew will install in a normal 8-hour day. To Equipment Cost Labor-Hour
find out the number of days the given crew would require to x = Equip.
Crew C-14C Units
complete the installation, divide your quantity by the daily
output. For example: $.22 x 3.20 = $.70

Quantity ÷ Daily Output = Duration Total (259.70)


35.0/ 2.86 The total of the bare costs is the arithmetic total of the three
100 C.Y. ÷ Crew Day = Crew Days previous columns: mat., labor, and equip.
Material + Labor + Equip. = Total
The ‘‘Labor-Hours’’ figure represents the number of
labor-hours required to install one unit of work. To find out $142 + $117 + $.70 = $259.70
the number of labor-hours required for your particular task,

9
multiply the quantity of the item times the number of
labor-hours shown. For example: Total Costs Including O &P
This figure is the sum of the bare material cost plus 10% for
Quantity x Productivity Rate = Duration profit; the bare labor cost plus total overhead and profit (per
3.20 Labor-Hours/ 320 the inside back cover or, if a crew is listed, from the crew
100 C.Y. x C.Y. = Labor-Hours listings); and the bare equipment cost plus 10% for profit.
Material is Bare Material Cost +

7
= $156.20
Unit (C.Y.) 10% = 147 + 14.20
The abbreviated designation indicates the unit of measure Labor for Crew C-14C =
upon which the price, production, and crew are based Labor-Hour Cost (57.27) x = $183.64
(C.Y. = Cubic Yard). For a complete listing of abbreviations, Labor-Hour Units (3.20)
refer to the Abbreviations Listing in the Reference Section Equip. is Bare Equip. Cost +
= $ .77
of this book. 10% = .70 + .07
Total (Rounded) = $ 340