Hydro test procedure must be verified & approved by Saudi Aramco before any test
are carried out.
Certified work permit receiver will obtain a properly signed work permit from Saudi
Aramco Representative prior to start hydro test water disposal into evaporation
pound.
Evaporation ponds must meet the requirements of SAES-A-104 Section 14.2. New
evaporation ponds may require an environmental impact assessment per SAEP-13
Appropriate barricades & Warning signs must be installed around the evaporation
pond to avoid the entry of unauthorized personnel & other animals that live in desert
Only authorized personnel are allowed to enter evaporation pond area.