You are on page 1of 5

Objectives of FAT and SAT

The objective of the Factory Acceptance Test (FAT) is to verify that the system is set up correctly
and will operate as expected from both the hardware and configuration software point of view
before it ships to the site.

The factory acceptance tests are done at the vendor factory site, to make sure that certain
requirements are met.

The objective of the Site Acceptance Test (SAT) is to validate that the control and safety systems
are fully operational in accordance with their functional specifications prior to using them to
operate the processing unit.

Site acceptance tests are done at the worksite and its acceptance leads to the plant start-up.

Factory Acceptance Test


The primary purpose of the FAT is to minimize the occurrence of faults during the process of
commissioning. It is a cost-effective way to fix errors while testing the system.

The loop checking at FAT can save remarkable time and effort during the commissioning and
startup at the plant site.

For FAT, all of the major system components are assembled in one place. Although the final,
installed system may extend to widely dispersed in the actual plant site, the FAT will test the
system in one manageable area.

Using simulations, the test can evaluate the systems network, redundancy, backup/restore, and
other function.

The purpose of the FAT is to make sure that the system works to the satisfaction of the provider
and the end-user.

If the changes are identified during FAT, these identified changes should be done before going for
commissioning or installation.

FAT is a great opportunity to demonstrate system quality and efficiency. These system providers
usually know their products well and popular with them definitely have high confidence that the
FAT will work to their advantage.

As per the agreed terms and conditions in the purchase order, the FAT can be important to an end-
user because it is the last chance to gain assurance about the critical points of a system before
installation work begins.
Depending on contract specifications, the end-user can demand that any fault, small or large, must
be corrected by the system provider before the FAT.

A failure to correct a fault in a pre-agreed time frame can be sufficient justification for the end-
user to even cancel the contract.

It is evident that as systems become more and more complex, the FAT becomes more and more
important.

If the system provider performs the appropriate preparations and test setup, there is little reason
for a system to fail a FAT.

Site Acceptance Test


An SAT is typically a series of tests that range from verifying that all the control equipment has
arrived in good operating condition as specified in the purchase order to validate the proper
functionality of the installed controlled system during the startup of the processing unit.

One of the purposes of an SAT, after a successful FAT, is to provide documented evidence that a
piece of equipment or system that has been delivered to the end-user site has not been affected by
the transportation or installation.

SAT procedure will also verify in detail about the order, material received has been supplied by
checking what has been received against the original purchase order.

The SAT should not only visually check, test the functionality, and performance of the system, but
should also check the accuracy, clarity, and completeness of the documentation.

The SAT documentation presents the guidelines for subsequent troubleshooting, maintenance,
and performance testing.

SAT Documents
The following documents are needed for the SAT:

Process control description.

Instrument Specifications.

System I/O list, datasheets, as-built drawings.

Instrument calibration certificates.

Recommended spares list.

Logic flow diagrams.


Process P&ID.

Termination lists.

Communication interfaces.

Program listings.

Manufacturer manuals, drawings.

Startup procedures.

Punch points list.

The SAT typically consists of follow-up, discussions, and validation of the system functions.

Author: R.Jagan Mohan Rao

Read Next:

SCADA Systems
Remote Factory Acceptance Test
Instrument Heated Enclosure
DCS Commissioning Procedure
Security of Industrial Automation System

Share With Your Friends


FacebookTwitterLinkedInPinterestEmailWhatsApp

PREVIOUS ARTICLE
Level Measuring Instruments Velocities of Propagation
NEXT ARTICLE
Instrument Salesperson Question
RELATED ARTICLES
Ziegler-Nichols Open-Loop Method
Ziegler-Nichols Open Loop Tuning Procedure
Types of Interlocks
How a 4-20mA Transmitter Works?
Cut-outs between Platforms or Grating for Field Instruments
How to Solve Cable Tray Sagging ?
1 COMMENT
Jatin Katrodiya
January 6, 2021 at 10:08 am
The major difference between FAT and SAT would be as follows in terms of the scope of testing.

– Major packages control systems, field instruments, and switchgear are not available during
FAT. Sometimes only partial testing happens with typical subsystems during integrated FAT
(iFAT). This requires a lot of micro-planning because entire testing has to be done and all
stakeholders should be in one place.

– The above-intergrated testing is possible during site during (SAT and iSAT) where all field
instruments, package units, switchgear, and all communication interfaces are available to test
together.

– The major problems found during SAT are


IP Conflicts/mismatches, Network overloads, Communication module hangs, incompatibility of
I/O card w.r.t field devices, Active/passive configuration w.r.t. analog channels, 0-1 status
configuration of digital signals, NO/NC wiring, Alarm flooding etc

REPLY
LEAVE A COMMENT
Your Comment

Name*
Email*
Save my name, email, and website in this browser for the next time I comment.

CATEGORIES

Select Category

RECENT COMMENTS
max on Pressure Gauge Calibration Procedure
Muhammad Fauzi Affan on DCS Troubleshooting Control Valve Loop
Eng Loon on DP Transmitter Dry Leg & Wet Leg Calculations
nikhil on Microprocessors Objective Questions – Set 1
William Trenaman on Tank Level Detection Switches

PLC Courses @2020 - Reproduction without explicit permission is prohibited.


Inst Tools
FacebookTwitterYoutube
HOME
MEASURE
CONTROL
Q&A
EE
MCQ
MORE
COURSES

You might also like