. 17MW RANOLIA HYDROPOWER PROJECT i> omy Duser, District KOHISTAN, KPK Monthly Progress/Activity Report November, 2020 Submitted By: Cemtech Engineering Services Pvt. Ltd (O&M Contractor) ,EMTECH => rCEMTECH — 1 Project Management Construction « Power © Real tare Ref: CEM/RAN/1103-1936 Dated: 4" December, 2020 To, The Director, Operation & Commercial, Pakhtunkhwa Energy Development Organization (PEDO), Government of Khyber Pakhtunkhwa, PEDO House, 38/B-2 Phase-V, Hayatabad, Peshawar, KPK. Subject: MONTHLY PR{ REPORT FOR THE MONTH OF NOVEMBER 2020 Je RANOLIA HPP- O&M PROJECT (DUBAIR-KOH Respected Sir, 'n pursuance to the provision of contract agreement of the subject project, enclosed, please find Progress/activity report covering the month of November, 2020. Our report broadly covers the following parts: * Generation Data Energy Statement Operational Statistics-Testing Phase Maintenance Data Unit/Line Tripping Trouble Tickets Tripping Report Bottlenecks/Punch List see e ene Trust you will find our report in order and if you have any queries please do let us know. ‘Thank you for your time and Yours Faithfully, Authorized Signatory Bl cM ta , Cemtech-slamabad. ( Me ov Gaur Copy to: * Chief Engineer &C-PEDO, Peshawar * Resident Engineer, RHPP, PEDO, Kohistan Enclosures: 1. Monthly Progress Report- November 2020 fe Cemtech Engineering Services (Pvt) Limited | pac o/ 1 a es ‘3088, #30, F112, lamabad TE O51-2110812, 0518730689 FactS-110803 EI EESE'S' AZMW Ranolia HPP, Duber Kohistan, ‘Monthly Progress Report CONTENTS 1. PROJECT OVERVIEW AND INSTITUTIONAL ARRANGEMENT.. 2. SPILLWAY CHANNEL... 3. FOREBAY....... ‘4. 132KV RANOLIA-KHAN KHWAR TRANSMISSION LINE 5. MONTHLY STATISTICS OF 17 MW RANOLIA HPC. & OPERATION STATISTICS OF 17MW RANOLIA HPC (TESTING PHASE) 7. HYDROLOGY OF RANOLIA KHWAR HPP HYDRO POWER COMPLEX... ‘8. DAILY GENERATION DATA/ENERGY EXPORT. 9. RANOLIA KHWAR HPP PERFORMANCE... 10, ANNUAL MONTH WISE SYNOPSIS... 11. ENERGY STATEMENT. 12. UNIT TRIPPINGS... 13, LINE TRIPPINGS... 14, TROUBLE REPORTS .. 15. MONTHLY MAINTENANt 'V. DC & UPS SYSTEM... V. DEWATERING PUMPS VI. LUBE OIL SYSTEM. Vil, COOLING WATER SYSTEM... VII. OVER HEAD CRANE. X. GOVERNOR SYSTEM... EXCITATION PANELS. XIV. 132 KV SWITCHYARD... 17, TRAININGS... 18. Nov, 2020 * The Employer/Owner: Pakhtunkhwa Energy Development Organi: * The Engineer/Consultant: M/s AGES Consultants * The Contractor (Civil): M/s DESCON * The Contractor (Electro-Mechanical): M/s TRIED * The Contractor (ORM): Comtech Engineering Services Pvt: Ltd. 2. SPILLWAY CHANNEL 3. FOREBAY To follow the standard nat to operate the Power Plant below 25% of nominal Power and also to Frovide 0.5 cumecs water inthe river bed for the needs of locale in the current low flow season, the Power Plant is being operated as follow. Zhe Forebay is filled 100-200 mm below the maximum level (keeping in view the safe limit of spill) satisfactory till now. 5. ATION OF GSM/GPF 1T COMMUNIATION MODULE Metering committee constituted by manager NTDC 500 kV circle Peshawar visited Ranolia HPP on November 06, 2020 for installation of GSM communication ‘module for bringing the existing COP meter online, Testing and recalibration of meter rectifying fault in back up meter reading, Considering the energy meters installed and perfarmed the. following activates. “GSM Module having a jazz sim was installed on primary meter no, ‘and its satisfactory configuration was conformed, Nov, 2020) — EE SESS ;:“'Ss— A7MW Ranolia HPP, Duber Kohistan. Monthly Progress Report |i. The backup energy meter installed on 132 KV line # 2 was tested and the result were beyond the permissible limits. The committee declared the Energy Meter having Sr. No, 72440370 faulty and recommended for replacement with the healthy one. 4. 132KV RANOLIA-KHAN KHWAR TRANSMISSION LINE On 18 and 19 Nov, as per RCC approved shutdown for tightening of jumpers Nuts/Botts and instaltation/provision of the missing Nuts/Bolts in Khan Khwar switchyard, 132 KV transmission line between RHPP and Khan was isolated/De-energized by opening the controlling SF6 circuit breaker/ isolators and the line was earthed by closing the earth switch in RHPP switchyard. After completion of work and cancellation of PTW the line was energized by the instruction of RCC ‘slamabad. 5. MONTHLY STATISTICS OF 17MW RANOLIA HPC Tat Bo i ia aay [BERT ] | 2 | Auxiliary Consumption during the Month 1727 | wn Total Enray Generate during the Moh ln | 4 | MOT during the Month 587 yw | 5 | Staton Peak Load recorded at 0800Hirs, Dated: 5 11.2020 3am © | Monthy Load Factor aly | 7) hres Water ow daring the Ware TB comecs 6. OPERATION STATISTICS OF 17MW RANOLIA HPC (TESTING PHASE: [41 | installed Capacity & Date of Commissioning _| UNIT #03 UNIT #02 1 [insta capacity Tas [aw 3s |mw | i Date of First Synchronization 11.03.2019 11.08.2019, 1 | Curent Month Generation 30.130 [kwh |_133,470 [kwh Iv | Progressive since testing 1038 [own | 270 own | |__¥ | Operation % age during the Month of OCTOBER, 2020 23 |% 10 |x 42 _| Current and Progressive Run Hours ‘| i LOperation Hours Currené Month — ass lie | 74 ies, 8 | Progressive since testing - 3376 | Hrs. | 2,368 | rs. 43_| Outage Hours during the month — i | Schedule Outage Hours =the | = [hes Schedule Outage Percentage () EMTECH Monthly P | i | Outages incurred on the instructions of NPCC (%) -|% -Jx_] iy | Standby Hours 552 | Hrs. 645 |Hrs._| v | Standby Percentage (4) mix | m0 |% | Ca Forced Outage Hours | Hrs. 0 | Hrs. vi | Forced Outage Percentage (%) om o|% | vil | System Fault Outage Hours [Hs = ars. ix | System Fault Outage Percentage (%) 21% -|x | x | Unit availabilty (Operation + Standby Hours) 720 | Hrs. 720 | es. Xi | Avaitabitty Percentage (6) - 100 |% 100 |_| 7. HYDROLOGY OF RANOLIA KHWAR HPP HYDRO POWER COMPLEX ‘The Hydrology of RHPP is dependent upon Discharges from RHPP Unit discharges. * The month of NOVEMBER has an observed water indent of more than (0.92) Cumecs (CMS) from Ranolia Khwar to Ranolia HPC. * Inflow available during the month was restricted to less load due to Spillway Land slide and Spill channel rehabilitation. This resulted in an average Flow discharge of (0.63) Cumecs from Ranolia Khwar. RHPP INTAKE VS UNIT DISCHARGE AT RHPP Kinwar (OMS) am Avg. Water Discharge (CMS) = FS Cumecs BUI CI Iirininininininininicirinii ag ma 23 = " s 9 0.473 sa 06: oes saa 0523 0614 06 06: os 0 0.604 062 0534 06s? 066 osos 0se4 0.602 08: 0.806 089 073 0.682 056 0627 0627 0.3: 3 0617 osea sa 0618 Nov, 2020 8. DAILY GENERATION DATA/ENERGY EXPORT — 3. Subject to availabilty and the PEDO’s ability to deliver to the NTDC, at the sole cost and expense the PEDO, energy for testing and emergencies at the relevant tariff then charged by the NTDC, shall Nov, 2020 Page 4|a7 accept and purchase for the consideration of all the Net Electrical Output produced and shall be implemented and completed within the technical limits. 'b. As per CPPA the Monthly Calculated Energy Benchmark for the month of NOVEMBER is (2.24) Gwh, therefore a daily Energy export of (74.66) MWh, was required to achieve the target. © Dally water discharge from Ranolia Khwar during the month, resulted in average daily exported (18) MWh, eventually total energy exported during the month of (NOVEMBER-2020) is (0.54) GWh 4. Less target generation of (2,24-0.54) ie. (1.7) GWh less NEO is due to less availability of water at Ranolia khwar and spill Channel design revision, which has design discharge less than design value of ‘5 Cumecs. Construction and rehabilitation work on spillway is in progress. Daily Generation (kWah| ‘80,000 z ZeegST ees TSSS Ses SSS SH gS SSSSS§ SSSTISSTTSASHLHSHSSSHGTETESE SS f= Wet Elect. Export (kWh) ‘Total KWh Generated during the Month of (NOVEMBER, 2020) = (536,327) kWh Nov, 2020 PageS|i7 01-11-2020 02-11-2020 [ 12950 [3.278 328 12,950 0.604 03-11-2020 [32740 [0 13,095 355 12,740 0.61 0411-2020 | 6430 4500 [11,280 350 10,930 0534 (05-11-2020 ° -f 9870 10,237 357 | 9.870 473 06-11-2020 | 1740 11470 13,566 356 13,210 0.523 07-11-2020 | 5200 6170 11,707 337 12,370 0.635 08-11-2020 | 6760 7500 14,611 351 14,260 0.652 09-11-2020 | 7290 7840 15,473 343 15130 [0687 10-11-2020 0 6180 6529 349 6180 0.66 qiti2020 [5520 | so20 t 11,892 352 11,540 0594 12-11-2020 | 6580 5940 12,898 378 12,520 0584 1311-2020 | __s3i0 6130 11,804 364 11,440 0.602 1411-2020 | _a7310 o 17,703 393 17,310 O64 [45-11-2020 | _soseo ° 51,342 482 50,860 0.832 16-11-2020 | 71640 0 72,110 470 72,640 0.806 17-11-2020 | 54890 ° 55,323 [- 433, 54,890 oss | 18-11-2020 7780 7 ° 3,084 30a [7,780 073 19-11-2020 | 12310 0 12,743 433 32,310 0.652 20-11-2020 [7670 oO 8,031 361, 7,670 056 21-11-2020 | 6890 4980 12,279 409) 11,870 06 2112020 | 0 11650 22113 463 13,650 0.627 23-11-2020 © | 13350 11,808 458 12,350 0.627 24-11-2020 ° 10350 10,807 457, 10,350 0632 25-11-2020 7500 7280 15,339 459 14,780 0.63 [_ 2611-2020 | 18490 o :: 13931 | aaa 18,490 0.617 27-1200 | 1710 ° 18,122 42 [47,710 0.584 [_ 28-11-2020 17960 ° 18,372 412 17,960 0.59 29-11-2020 aauis0_ [0 14,479 389) 14,190 0.58 30-11-2020 0 16240 16,626 386 16,240 0.618 Nov, 2020 age 617 EEE SESE ~~ eee ce ATM Ranolia HPP, Duber Kohisten, BCEMTECH ‘Monthly Progress Report anne Coreen so TRE 9. RANOLIA KHWAR HPP PERFORMANCE The Hydrology of RHPP is dependent upon inflows from Ranolia Khwar to Ranolia Power House. The attached chart shows Generation of Ranolia against available inflow from Ranolia Khwar. The average indent for the whole month remained limited due to less availability of water inflow at Ranolia Khwar. Generation (kWh) Vs Available Flow (Cumecs) ym) | roo 60,000 ‘ soon . 10000 & sao , © so : 100% 7 1 1 I F SEERSSEEREE2888888 aaaee3 88 PPIPPPPPPPPPEDRT LEG aannaas Seaege edad Sig as Gea s gaa FR727 23 a coe: 0 hy ie Wate cht (EMS) rr mar cs) oy. (et Het apr a) 2 Mo. AN He. ago MA) ~~ tna RAPP a eR) monthly generation s 5: 00,000, 500,000 400,000 300,000 Total Generation (wh) 200,000 in Net Elect. Expore (kWh) 109, : MI s8.20y

You might also like