Professional Documents
Culture Documents
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
COMMERCIAL BULDING, ME-9 / C-128 ABU DHABI 576d 15/Jun/13 16/Apr/15 0d 16/Apr/15, C
230 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 11/Aug/14 18/Aug/14 0d 11/Aug/14 18/Aug/14, Steel Reinf,Formwork & Conc
240 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 18/Aug/14 20/Aug/14 0d 18/Aug/14 20/Aug/14, Formwork,Steel Reinf & Conc
MEZZANINE FLOOR (MF) 16d 25/Aug/14 11/Sep/14 0d 11/Sep/14, MEZZANINE FLOOR (MF)
250 Slab & Beam Reif, Formwork & Concrete Casting 8d 25/Aug/14 02/Sep/14 0d 25/Aug/14 02/Sep/14, Slab & Beam Reif, Formwor
260 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 03/Sep/14 10/Sep/14 0d 03/Sep/14 10/Sep/14, Steel Reinf,Formwork & Co
270 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 09/Sep/14 11/Sep/14 0d 09/Sep/14 11/Sep/14, Formwork,Steel Reinf & Co
1ST FLOOR (1F) 17d 13/Sep/14 01/Oct/14 0d 01/Oct/14, 1ST FLOOR (1F)
280 Slab & Beam Reif, Formwork & Concrete Casting 8d 13/Sep/14 21/Sep/14 0d 13/Sep/14 21/Sep/14, Slab & Beam Reif, Formw
290 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 22/Sep/14 29/Sep/14 0d 22/Sep/14 29/Sep/14, Steel Reinf,Formwork &
300 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 29/Sep/14 01/Oct/14 0d 29/Sep/14 01/Oct/14, Formwork,Steel Reinf &
2ND FLOOR (2F) 17d 02/Oct/14 21/Oct/14 0d 21/Oct/14, 2ND FLOOR (2F)
310 Slab & Beam Reif, Formwork & Concrete Casting 8d 02/Oct/14 11/Oct/14 0d 02/Oct/14 11/Oct/14, Slab & Beam Reif, Form
320 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 12/Oct/14 19/Oct/14 0d 12/Oct/14 19/Oct/14, Steel Reinf,Formwork
330 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 19/Oct/14 21/Oct/14 0d 19/Oct/14 21/Oct/14, Formwork,Steel Reinf
3RD FLOOR (3F) 14d 22/Oct/14 06/Nov/14 0d 06/Nov/14, 3RD FLOOR (3F)
340 Slab & Beam Reif, Formwork & Concrete Casting 5d 22/Oct/14 27/Oct/14 0d 22/Oct/14 27/Oct/14, Slab & Beam Reif, Fo
350 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 28/Oct/14 04/Nov/14 0d 28/Oct/14 04/Nov/14, Steel Reinf,Formwo
360 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 04/Nov/14 06/Nov/14 0d 04/Nov/14 06/Nov/14, Formwork,Steel Re
4TH FLOOR (4F) 17d 08/Nov/14 26/Nov/14 0d 26/Nov/14, 4TH FLOOR (4F)
370 Slab & Beam Reif, Formwork & Concrete Casting 8d 08/Nov/14 16/Nov/14 0d 08/Nov/14 16/Nov/14, Slab & Beam Reif,
Remaining Level of Effort Critical Remaining W... Page 2 of 13 STAMP
Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
380 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 17/Nov/14 24/Nov/14 0d 17/Nov/14 24/Nov/14, Steel Reinf,Formw
390 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 24/Nov/14 26/Nov/14 0d 24/Nov/14 26/Nov/14, Formwork,Steel R
5TH FLOOR (5F) 17d 27/Nov/14 16/Dec/14 0d 16/Dec/14, 5TH FLOOR (5F)
400 Slab & Beam Reif, Formwork & Concrete Casting 8d 27/Nov/14 06/Dec/14 0d 27/Nov/14 06/Dec/14, Slab & Beam Re
410 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 07/Dec/14 14/Dec/14 0d 07/Dec/14 14/Dec/14, Steel Reinf,For
420 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 14/Dec/14 16/Dec/14 0d 14/Dec/14 16/Dec/14, Formwork,Stee
6TH FLOOR (6F) 17d 17/Dec/14 05/Jan/15 0d 05/Jan/15, 6TH FLOOR (6F)
430 Slab & Beam Reif, Formwork & Concrete Casting 8d 17/Dec/14 25/Dec/14 0d 17/Dec/14 25/Dec/14, Slab & Beam
440 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 27/Dec/14 03/Jan/15 0d 27/Dec/14 03/Jan/15, Steel Reinf,F
450 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 03/Jan/15 05/Jan/15 0d 03/Jan/15 05/Jan/15, Formwork,S
7TH FLOOR (7F) 17d 06/Jan/15 25/Jan/15 0d 25/Jan/15, 7TH FLOOR (7F)
460 Slab & Beam Reif, Formwork & Concrete Casting 8d 06/Jan/15 14/Jan/15 0d 06/Jan/15 14/Jan/15, Slab & Beam
470 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 15/Jan/15 22/Jan/15 0d 15/Jan/15 22/Jan/15, Steel Reinf
480 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 22/Jan/15 25/Jan/15 0d 22/Jan/15 25/Jan/15, Formwork
ROOF FLOOR 16d 26/Jan/15 12/Feb/15 54d 12/Feb/15, ROOF FLOOR
490 Slab & Beam Reif, Formwork & Concrete Casting 6d 26/Jan/15 01/Feb/15 54d 26/Jan/15 01/Feb/15, Slab & Be
500 Parapet Walls & Columns, Reinf, Formwork & concrete casting 5d 02/Feb/15 07/Feb/15 54d 02/Feb/15 07/Feb/15, Parapet
520 Steel reinf, formwork & Concrete casting for Base fo Chiller & Water Tank 5d 02/Feb/15 07/Feb/15 54d 02/Feb/15 07/Feb/15, Steel rein
521 Anchor Bolts for Track of Craddle 5d 02/Feb/15 07/Feb/15 54d 02/Feb/15 07/Feb/15, Anchor B
ROOF INSULATION & WATERPROFING WORK 5d 08/Feb/15 12/Feb/15 54d 12/Feb/15, ROOF I
528 Roof insulation and waterproofing System 5d 08/Feb/15 12/Feb/15 54d 08/Feb/15 12/Feb/15, Roof ins
529 500x500x500mm thick tile loosely laid 5d 08/Feb/15 12/Feb/15 54d 08/Feb/15 12/Feb/15, 500x500
EMBEDDED MEP (SUPERSTRUCTURE) 140d 11/Aug/14 20/Jan/15 64d 20/Jan/15, EMBEDDE
MEP 2 Embedded Conduits in Concrete Work 140d 11/Aug/14 20/Jan/15 64d 11/Aug/14 20/Jan/15, Embedded
ROUGH FINISHES INTERNAL 209d 02/Aug/14 01/Apr/15 13d 01/Apr/15, RO
BASEMENT NO 02 (2B) 24d 02/Aug/14 28/Aug/14 138d 28/Aug/14, BASEMENT NO 02 (2B)
530 Masonary Work 12d 02/Aug/14 14/Aug/14 32d 02/Aug/14 14/Aug/14, Masonary Work
540 Plastering Work 12d 05/Aug/14 18/Aug/14 32d 05/Aug/14 18/Aug/14, Plastering Work
541 Floor Screed and Water proofing at Wet Areas 7d 14/Aug/14 21/Aug/14 115d 14/Aug/14 21/Aug/14, Floor Screed and Water proo
550 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 23/Aug/14 28/Aug/14 126d 23/Aug/14 28/Aug/14, Flooring Work & Threshold(G
555 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 24/Aug/14 28/Aug/14 138d 24/Aug/14 28/Aug/14, Wall finishes & Skirting ( Gla
BASEMENT NO 01 (1B) 24d 21/Aug/14 17/Sep/14 126d 17/Sep/14, BASEMENT NO 01 (1B)
560 Masonary Work 12d 21/Aug/14 03/Sep/14 27d 21/Aug/14 03/Sep/14, Masonary Work
570 Plastering Work 12d 25/Aug/14 07/Sep/14 27d 25/Aug/14 07/Sep/14, Plastering Work
571 Floor Screed and Water proofing at Wet Areas 7d 03/Sep/14 10/Sep/14 105d 03/Sep/14 10/Sep/14, Floor Screed and Water pr
580 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 11/Sep/14 17/Sep/14 115d 11/Sep/14 17/Sep/14, Flooring Work & Threshol
585 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 13/Sep/14 17/Sep/14 126d 13/Sep/14 17/Sep/14, Wall finishes & Skirting ( G
LOWER GROUND (LG) 26d 13/Sep/14 12/Oct/14 110d 12/Oct/14, LOWER GROUND (LG)
590 Masonary Work 12d 13/Sep/14 25/Sep/14 32d 13/Sep/14 25/Sep/14, Masonary Work
600 Plastering Work 12d 16/Sep/14 29/Sep/14 32d 16/Sep/14 29/Sep/14, Plastering Work