COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM

DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
COMMERCIAL BULDING, ME-9 / C-128 ABU DHABI 576d 15/Jun/13 16/Apr/15 0d 16/Apr/15, C

GENERAL REQUIREMENTS & PRELIMINARIES 576d 15/Jun/13 16/Apr/15 0d 16/Apr/15, G

PROJECT MILESTONES 576d 15/Jun/13 16/Apr/15 0d 16/Apr/15, P


ST-100 Start of Project 0d 15/Jun/13 0d Start of Project, 15/Jun/13
ST-110 End of Project 0d 16/Apr/15 0d End of Project,
PRELIMINARIES 151d 15/Jun/13 07/Dec/13 0d 07/Dec/13, PRELIMINARIES
PRE 10 Fencing at Site & Installation of Sign Bords 10d 15/Jun/13 25/Jun/13 0d 25/Jun/13, Fencing at Site & Installation of Sign Bords
PRE 15 Site Clearence 6d 15/Jun/13 20/Jun/13 0d 20/Jun/13, Site Clearence
PRE 30 Mobilization Work 10d 22/Jun/13 02/Jul/13 0d 02/Jul/13, Mobilization Work
PRE 50 Receival Of Building Permit 5d 03/Jul/13 08/Jul/13 03/Jul/13
0d 08/Jul/13, Receival Of Building Permit
PRE 60 N.O.C for Existing services (Power, Water, Sewerage, Telephone & Storm Water )130d
& Route
09/Jul/13
Approval 07/Dec/13 09/Jul/13
0d 07/Dec/13, N.O.C for Existing services (Power, Water, Sewerage, Teleph
CONSTRUCTION WORKS 430d 02/Dec/13 16/Apr/15 0d 16/Apr/15, C

SUBSTRUCTURE 267d 02/Dec/13 08/Oct/14 135d 08/Oct/14, SUBSTRUCTURE


EARTH WORK 80d 02/Dec/13 04/Mar/14 0d 04/Mar/14, EARTH WORK
05 Asphalt Cutting & Passco Removal 10d 02/Dec/13 12/Dec/13 0d 02/Dec/13 12/Dec/13, Asphalt Cutting & Passco Removal
07 Excavation For existing Services Relocation 5d 14/Dec/13 18/Dec/13 0d 14/Dec/13 18/Dec/13, Excavation For existing Services Relocation
10 Shifting of existing services & Back filling 20d 19/Dec/13 11/Jan/14 0d 19/Dec/13 11/Jan/14, Shifting of existing services & Back filling
15 Permanent Shoring Work (Secant Piling System) 25d 09/Jan/14 06/Feb/14 0d 09/Jan/14 06/Feb/14, Permanent Shoring Work (Secant Piling System)
20 Excavation for Foundation 30d 21/Jan/14 24/Feb/14 0d 21/Jan/14 24/Feb/14, Excavation for Foundation
25 Disposal Work 5d 22/Feb/14 26/Feb/14 0d 22/Feb/14 26/Feb/14, Disposal Work
30 Backfilling in 20cm layer to achieve required levels 3d 27/Feb/14 02/Mar/14 0d 27/Feb/14 02/Mar/14, Backfilling in 20cm layer to achieve required levels
32 Anti -Termite Spray 2d 03/Mar/14 04/Mar/14 0d 03/Mar/14 04/Mar/14, Anti -Termite Spray
DEWATERING WORK 180d 21/Jan/14 18/Aug/14 179d 18/Aug/14, DEWATERING WORK
38 Dewatering 180d 21/Jan/14 18/Aug/14 179d 21/Jan/14 18/Aug/14, Dewatering
SUBSTRUCTURE WATER PROOFING WROK 31d 05/Mar/14 09/Apr/14 0d 09/Apr/14, SUBSTRUCTURE WATER PROOFING WROK
40 Horizontal Waterproofing including 50mm Protection Screed 15d 05/Mar/14 22/Mar/14 0d 05/Mar/14 22/Mar/14, Horizontal Waterproofing including 50mm Protec
50 Vertical Waterproofing 15d 12/Mar/14 29/Mar/14 0d 12/Mar/14 29/Mar/14, Vertical Waterproofing
70 Water Stops for all construction jo ints 2d 08/Apr/14 09/Apr/14 0d 08/Apr/14 09/Apr/14, Water Stops for all construction joints
RAFT FOUNDATION 25d 30/Mar/14 27/Apr/14 0d 27/Apr/14, RAFT FOUNDATION
80 100mm thick Blinding Concrete 3d 30/Mar/14 01/Apr/14 0d 30/Mar/14 01/Apr/14, 100mm thick Blinding Concrete
90 Steel Reinforcement for Raft 20d 05/Apr/14 27/Apr/14 0d 05/Apr/14 27/Apr/14, Steel Reinforcement for Raft
91 Formwork for Raft Foundation 5d 05/Apr/14 09/Apr/14 0d 05/Apr/14 09/Apr/14, Formwork for Raft Foundation
92 Concrete Casting for Raft Foundation 2d 10/Apr/14 12/Apr/14 0d 10/Apr/14 12/Apr/14, Concrete Casting for Raft Foundation
BASEMENT NO 02 (2B) 17d 16/Apr/14 05/May/14 0d 05/May/14, BASEMENT NO 02 (2B)
100 Slab on grade for 2B Floor 4d 16/Apr/14 20/Apr/14 0d 16/Apr/14 20/Apr/14, Slab on grade for 2B Floor
105 Steel Rein, Formwork & Concrete casting for Base Slab of U.G.W.Tank # 01 3d 16/Apr/14 19/Apr/14 0d 16/Apr/14 19/Apr/14, Steel Rein, Formwork & Concrete casting for
110 Steel Reinforcement, Formwork & Concrete Casting for Retaining Wall & Columns 10d 20/Apr/14 30/Apr/14 0d 20/Apr/14 30/Apr/14, Steel Reinforcement, Formwork & Concrete
115 Formwork, Steel Reinf & Concrete Casting for Core Walls & Walls 12d 20/Apr/14 03/May/14 0d 20/Apr/14 03/May/14, Formwork, Steel Reinf & Concrete Casting
130 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 03/May/14 05/May/14 0d 03/May/14 05/May/14, Formwork,Steel Reinf & Concrete Casting

Remaining Level of Effort Critical Remaining W... Page 1 of 13 STAMP


Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
BASEMENT NO 01 (1B) 36d 10/May/14 19/Jun/14 0d 19/Jun/14, BASEMENT NO 01 (1B)
140 Slab & Beam Reif, Formwork & Concrete Casting for 1B 12d 10/May/14 22/May/14 0d 10/May/14 22/May/14, Slab & Beam Reif, Formwork & Concrete
150 Steel Reinforcement. Formwork & Concrete Casting for Retaining Wall & Columns 15d 27/May/14 12/Jun/14 0d 27/May/14 12/Jun/14, Steel Reinforcement. Formwork & Con
155 Steel Reinf, Formwork & Concrete Casting for Core Walls & Walls 12d 02/Jun/14 15/Jun/14 0d 02/Jun/14 15/Jun/14, Steel Reinf, Formwork & Concrete Ca
160 Steel Rein, Formwork & Concrete Casting for Walls of U.G.W.Tank # 01 5d 12/Jun/14 17/Jun/14 0d 12/Jun/14 17/Jun/14, Steel Rein, Formwork & Concrete Cas
170 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 17/Jun/14 19/Jun/14 0d 17/Jun/14 19/Jun/14, Formwork,Steel Reinf & Concrete Ca
LOWER GROUND (LG) 36d 21/Jun/14 31/Jul/14 0d 31/Jul/14, LOWER GROUND (LG)
180 Formwork,Reif, & Concrete Casting for (LG 30,60, 120 cm) Slabs & Beams 15d 21/Jun/14 07/Jul/14 0d 21/Jun/14 07/Jul/14, Formwork,Reif, & Concrete Casting
and also for UGW Tank #01 Slab
190 Steel Reinforcement, Formwork & Concrete Casting for Retaining Wall & Columns 15d 08/Jul/14 24/Jul/14 0d 08/Jul/14 24/Jul/14, Steel Reinforcement, Formwork &
195 Steel Reinf, Formwork & Concrete Casting for Core Walls & Walls 5d 22/Jul/14 27/Jul/14 0d 22/Jul/14 27/Jul/14, Steel Reinf, Formwork & Concrete
200 Steel Reinf, Formwork & Concrete Casting for Base and Walls of U.G.W 8d 21/Jul/14 29/Jul/14 0d 21/Jul/14 29/Jul/14, Steel Reinf, Formwork & Concret
Tank # 02
210 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 29/Jul/14 31/Jul/14 0d 29/Jul/14 31/Jul/14, Formwork,Steel Reinf & Concrete
EMBEDDED MEP (SUBSTRUCTURE) 60d 28/Apr/14 06/Jul/14 19d 06/Jul/14, EMBEDDED MEP (SUBSTRUCTURE)
MEP 1 Embedded conduits in Concrete works 60d 28/Apr/14 06/Jul/14 19d 28/Apr/14 06/Jul/14, Embedded conduits in Concrete works
WATER TANK LINING 15d 22/Sep/14 08/Oct/14 22d 08/Oct/14, WATER TANK LINING
WTL 1 Fix 2mm thk W.P Additive & Fiber Glass linning on all faces 15d 22/Sep/14 08/Oct/14 22d 22/Sep/14 08/Oct/14, Fix 2mm thk W.P Additiv
SUPERSTRUCTURE 168d 02/Aug/14 12/Feb/15 54d 12/Feb/15, SUPER
GROUND FLOOR (GF) 17d 02/Aug/14 20/Aug/14 0d 20/Aug/14, GROUND FLOOR (GF)
220 GF Slab ,UGW Tank #2 Slab,Beam Reif, For mwork & Concrete Casting 8d 02/Aug/14 10/Aug/14 0d 02/Aug/14 10/Aug/14, GF Slab ,UGW Tank #2 Slab,B

230 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 11/Aug/14 18/Aug/14 0d 11/Aug/14 18/Aug/14, Steel Reinf,Formwork & Conc
240 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 18/Aug/14 20/Aug/14 0d 18/Aug/14 20/Aug/14, Formwork,Steel Reinf & Conc
MEZZANINE FLOOR (MF) 16d 25/Aug/14 11/Sep/14 0d 11/Sep/14, MEZZANINE FLOOR (MF)
250 Slab & Beam Reif, Formwork & Concrete Casting 8d 25/Aug/14 02/Sep/14 0d 25/Aug/14 02/Sep/14, Slab & Beam Reif, Formwor
260 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 03/Sep/14 10/Sep/14 0d 03/Sep/14 10/Sep/14, Steel Reinf,Formwork & Co
270 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 09/Sep/14 11/Sep/14 0d 09/Sep/14 11/Sep/14, Formwork,Steel Reinf & Co
1ST FLOOR (1F) 17d 13/Sep/14 01/Oct/14 0d 01/Oct/14, 1ST FLOOR (1F)
280 Slab & Beam Reif, Formwork & Concrete Casting 8d 13/Sep/14 21/Sep/14 0d 13/Sep/14 21/Sep/14, Slab & Beam Reif, Formw
290 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 22/Sep/14 29/Sep/14 0d 22/Sep/14 29/Sep/14, Steel Reinf,Formwork &
300 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 29/Sep/14 01/Oct/14 0d 29/Sep/14 01/Oct/14, Formwork,Steel Reinf &
2ND FLOOR (2F) 17d 02/Oct/14 21/Oct/14 0d 21/Oct/14, 2ND FLOOR (2F)
310 Slab & Beam Reif, Formwork & Concrete Casting 8d 02/Oct/14 11/Oct/14 0d 02/Oct/14 11/Oct/14, Slab & Beam Reif, Form
320 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 12/Oct/14 19/Oct/14 0d 12/Oct/14 19/Oct/14, Steel Reinf,Formwork
330 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 19/Oct/14 21/Oct/14 0d 19/Oct/14 21/Oct/14, Formwork,Steel Reinf
3RD FLOOR (3F) 14d 22/Oct/14 06/Nov/14 0d 06/Nov/14, 3RD FLOOR (3F)
340 Slab & Beam Reif, Formwork & Concrete Casting 5d 22/Oct/14 27/Oct/14 0d 22/Oct/14 27/Oct/14, Slab & Beam Reif, Fo
350 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 28/Oct/14 04/Nov/14 0d 28/Oct/14 04/Nov/14, Steel Reinf,Formwo
360 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 04/Nov/14 06/Nov/14 0d 04/Nov/14 06/Nov/14, Formwork,Steel Re
4TH FLOOR (4F) 17d 08/Nov/14 26/Nov/14 0d 26/Nov/14, 4TH FLOOR (4F)
370 Slab & Beam Reif, Formwork & Concrete Casting 8d 08/Nov/14 16/Nov/14 0d 08/Nov/14 16/Nov/14, Slab & Beam Reif,
Remaining Level of Effort Critical Remaining W... Page 2 of 13 STAMP
Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
380 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 17/Nov/14 24/Nov/14 0d 17/Nov/14 24/Nov/14, Steel Reinf,Formw
390 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 24/Nov/14 26/Nov/14 0d 24/Nov/14 26/Nov/14, Formwork,Steel R
5TH FLOOR (5F) 17d 27/Nov/14 16/Dec/14 0d 16/Dec/14, 5TH FLOOR (5F)
400 Slab & Beam Reif, Formwork & Concrete Casting 8d 27/Nov/14 06/Dec/14 0d 27/Nov/14 06/Dec/14, Slab & Beam Re
410 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 07/Dec/14 14/Dec/14 0d 07/Dec/14 14/Dec/14, Steel Reinf,For
420 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 14/Dec/14 16/Dec/14 0d 14/Dec/14 16/Dec/14, Formwork,Stee
6TH FLOOR (6F) 17d 17/Dec/14 05/Jan/15 0d 05/Jan/15, 6TH FLOOR (6F)
430 Slab & Beam Reif, Formwork & Concrete Casting 8d 17/Dec/14 25/Dec/14 0d 17/Dec/14 25/Dec/14, Slab & Beam
440 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 27/Dec/14 03/Jan/15 0d 27/Dec/14 03/Jan/15, Steel Reinf,F
450 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 03/Jan/15 05/Jan/15 0d 03/Jan/15 05/Jan/15, Formwork,S
7TH FLOOR (7F) 17d 06/Jan/15 25/Jan/15 0d 25/Jan/15, 7TH FLOOR (7F)
460 Slab & Beam Reif, Formwork & Concrete Casting 8d 06/Jan/15 14/Jan/15 0d 06/Jan/15 14/Jan/15, Slab & Beam
470 Steel Reinf,Formwork & Concrete Casting for Walls & Columns 7d 15/Jan/15 22/Jan/15 0d 15/Jan/15 22/Jan/15, Steel Reinf
480 Formwork,Steel Reinf & Concrete Casting for Stair Case 3d 22/Jan/15 25/Jan/15 0d 22/Jan/15 25/Jan/15, Formwork
ROOF FLOOR 16d 26/Jan/15 12/Feb/15 54d 12/Feb/15, ROOF FLOOR
490 Slab & Beam Reif, Formwork & Concrete Casting 6d 26/Jan/15 01/Feb/15 54d 26/Jan/15 01/Feb/15, Slab & Be
500 Parapet Walls & Columns, Reinf, Formwork & concrete casting 5d 02/Feb/15 07/Feb/15 54d 02/Feb/15 07/Feb/15, Parapet
520 Steel reinf, formwork & Concrete casting for Base fo Chiller & Water Tank 5d 02/Feb/15 07/Feb/15 54d 02/Feb/15 07/Feb/15, Steel rein
521 Anchor Bolts for Track of Craddle 5d 02/Feb/15 07/Feb/15 54d 02/Feb/15 07/Feb/15, Anchor B
ROOF INSULATION & WATERPROFING WORK 5d 08/Feb/15 12/Feb/15 54d 12/Feb/15, ROOF I
528 Roof insulation and waterproofing System 5d 08/Feb/15 12/Feb/15 54d 08/Feb/15 12/Feb/15, Roof ins
529 500x500x500mm thick tile loosely laid 5d 08/Feb/15 12/Feb/15 54d 08/Feb/15 12/Feb/15, 500x500
EMBEDDED MEP (SUPERSTRUCTURE) 140d 11/Aug/14 20/Jan/15 64d 20/Jan/15, EMBEDDE
MEP 2 Embedded Conduits in Concrete Work 140d 11/Aug/14 20/Jan/15 64d 11/Aug/14 20/Jan/15, Embedded
ROUGH FINISHES INTERNAL 209d 02/Aug/14 01/Apr/15 13d 01/Apr/15, RO
BASEMENT NO 02 (2B) 24d 02/Aug/14 28/Aug/14 138d 28/Aug/14, BASEMENT NO 02 (2B)
530 Masonary Work 12d 02/Aug/14 14/Aug/14 32d 02/Aug/14 14/Aug/14, Masonary Work
540 Plastering Work 12d 05/Aug/14 18/Aug/14 32d 05/Aug/14 18/Aug/14, Plastering Work
541 Floor Screed and Water proofing at Wet Areas 7d 14/Aug/14 21/Aug/14 115d 14/Aug/14 21/Aug/14, Floor Screed and Water proo
550 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 23/Aug/14 28/Aug/14 126d 23/Aug/14 28/Aug/14, Flooring Work & Threshold(G
555 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 24/Aug/14 28/Aug/14 138d 24/Aug/14 28/Aug/14, Wall finishes & Skirting ( Gla
BASEMENT NO 01 (1B) 24d 21/Aug/14 17/Sep/14 126d 17/Sep/14, BASEMENT NO 01 (1B)
560 Masonary Work 12d 21/Aug/14 03/Sep/14 27d 21/Aug/14 03/Sep/14, Masonary Work
570 Plastering Work 12d 25/Aug/14 07/Sep/14 27d 25/Aug/14 07/Sep/14, Plastering Work
571 Floor Screed and Water proofing at Wet Areas 7d 03/Sep/14 10/Sep/14 105d 03/Sep/14 10/Sep/14, Floor Screed and Water pr
580 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 11/Sep/14 17/Sep/14 115d 11/Sep/14 17/Sep/14, Flooring Work & Threshol
585 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 13/Sep/14 17/Sep/14 126d 13/Sep/14 17/Sep/14, Wall finishes & Skirting ( G
LOWER GROUND (LG) 26d 13/Sep/14 12/Oct/14 110d 12/Oct/14, LOWER GROUND (LG)
590 Masonary Work 12d 13/Sep/14 25/Sep/14 32d 13/Sep/14 25/Sep/14, Masonary Work
600 Plastering Work 12d 16/Sep/14 29/Sep/14 32d 16/Sep/14 29/Sep/14, Plastering Work

Remaining Level of Effort Critical Remaining W... Page 3 of 13 STAMP


Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
601 Floor Screed and Water proofing at Wet Areas 7d 28/Sep/14 05/Oct/14 91d 28/Sep/14 05/Oct/14, Floor Screed and Water
610 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 06/Oct/14 12/Oct/14 100d 06/Oct/14 12/Oct/14, Flooring Work & Thres
615 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 07/Oct/14 12/Oct/14 110d 07/Oct/14 12/Oct/14, Wall finishes & Skirting
GROUND FLOOR (GF) 24d 02/Oct/14 29/Oct/14 100d 29/Oct/14, GROUND FLOOR (GF)
620 Masonary Work 12d 02/Oct/14 15/Oct/14 27d 02/Oct/14 15/Oct/14, Masonary Work
630 Plastering Work 12d 06/Oct/14 19/Oct/14 27d 06/Oct/14 19/Oct/14, Plastering Work
631 Floor Screed and Water proofing at Wet Areas 7d 15/Oct/14 22/Oct/14 83d 15/Oct/14 22/Oct/14, Floor Screed and Wat
640 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 23/Oct/14 29/Oct/14 91d 23/Oct/14 29/Oct/14, Flooring Work & Thre
645 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 25/Oct/14 29/Oct/14 100d 25/Oct/14 29/Oct/14, Wall finishes & Skirtin
MEZZANINE FLOOR (MF) 24d 22/Oct/14 18/Nov/14 88d 18/Nov/14, MEZZANINE FLO
650 Masonary Work 12d 22/Oct/14 04/Nov/14 22d 22/Oct/14 04/Nov/14, Masonary Work
660 Plastering Work 12d 26/Oct/14 08/Nov/14 22d 26/Oct/14 08/Nov/14, Plastering Work
661 Floor Screed and Water proofing at Wet Areas 7d 04/Nov/14 11/Nov/14 73d 04/Nov/14 11/Nov/14, Floor Screed and W
670 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 12/Nov/14 18/Nov/14 80d 12/Nov/14 18/Nov/14, Flooring Work & T
675 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 13/Nov/14 18/Nov/14 88d 13/Nov/14 18/Nov/14, Wall finishes & Sk
1ST FLOOR (1F) 24d 08/Nov/14 04/Dec/14 79d 04/Dec/14, 1ST FLOOR (1F)
680 Masonary Work 12d 08/Nov/14 20/Nov/14 20d 08/Nov/14 20/Nov/14, Masonary Work
690 Plastering Work 12d 11/Nov/14 24/Nov/14 20d 11/Nov/14 24/Nov/14, Plastering Work
691 Floor Screed and Water proofing at Wet Areas 7d 20/Nov/14 27/Nov/14 66d 20/Nov/14 27/Nov/14, Floor Screed and
700 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 29/Nov/14 04/Dec/14 72d 29/Nov/14 04/Dec/14, Flooring Work &
705 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 30/Nov/14 04/Dec/14 79d 30/Nov/14 04/Dec/14, Wall finishes & S
2ND FLOOR (2F) 24d 27/Nov/14 24/Dec/14 67d 24/Dec/14, 2ND FLOOR (2F)
710 Masonary Work 12d 27/Nov/14 10/Dec/14 15d 27/Nov/14 10/Dec/14, Masonary Work
720 Plastering Work 12d 01/Dec/14 14/Dec/14 15d 01/Dec/14 14/Dec/14, Plastering Work
721 Floor Screed and Water proofing at Wet Areas 7d 10/Dec/14 17/Dec/14 56d 10/Dec/14 17/Dec/14, Floor Screed a
730 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 18/Dec/14 24/Dec/14 61d 18/Dec/14 24/Dec/14, Flooring Work
735 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 20/Dec/14 24/Dec/14 67d 20/Dec/14 24/Dec/14, Wall finishes &
3RD FLOOR (3F) 24d 17/Dec/14 13/Jan/15 55d 13/Jan/15, 3RD FLOOR (3F)
740 Masonary Work 12d 17/Dec/14 30/Dec/14 10d 17/Dec/14 30/Dec/14, Masonary Work
750 Plastering Work 12d 21/Dec/14 03/Jan/15 10d 21/Dec/14 03/Jan/15, Plastering Work
751 Floor Screed and Water proofing at Wet Areas 7d 30/Dec/14 06/Jan/15 46d 30/Dec/14 06/Jan/15, Floor Screed
760 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 07/Jan/15 13/Jan/15 50d 07/Jan/15 13/Jan/15, Flooring Wo
765 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 08/Jan/15 13/Jan/15 55d 08/Jan/15 13/Jan/15, Wall finishes
4TH FLOOR (4F) 24d 06/Jan/15 02/Feb/15 43d 02/Feb/15, 4TH FLOOR (4F)
770 Masonary Work 12d 06/Jan/15 19/Jan/15 5d 06/Jan/15 19/Jan/15, Masonary Work
780 Plastering Work 12d 10/Jan/15 22/Jan/15 5d 10/Jan/15 22/Jan/15, Plastering Work
781 Floor Screed and Water proofing at Wet Areas 7d 19/Jan/15 26/Jan/15 36d 19/Jan/15 26/Jan/15, Floor Scre
790 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 27/Jan/15 02/Feb/15 39d 27/Jan/15 02/Feb/15, Flooring W
795 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 28/Jan/15 02/Feb/15 43d 28/Jan/15 02/Feb/15, Wall finis
5TH FLOOR (5F) 24d 26/Jan/15 22/Feb/15 31d 22/Feb/15, 5TH F

Remaining Level of Effort Critical Remaining W... Page 4 of 13 STAMP


Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
800 Masonary Work 12d 26/Jan/15 08/Feb/15 0d 26/Jan/15 08/Feb/15, Masonary Work
810 Plastering Work 12d 29/Jan/15 11/Feb/15 0d 29/Jan/15 11/Feb/15, Plastering Work
811 Floor Screed and Water proofing at Wet Areas 7d 08/Feb/15 15/Feb/15 26d 08/Feb/15 15/Feb/15, Floor S
820 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 16/Feb/15 22/Feb/15 28d 16/Feb/15 22/Feb/15, Floorin
825 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 17/Feb/15 22/Feb/15 31d 17/Feb/15 22/Feb/15, Wall fin
6TH FLOOR (6F) 24d 09/Feb/15 08/Mar/15 24d 08/Mar/15, 6TH
830 Masonary Work 12d 09/Feb/15 22/Feb/15 0d 09/Feb/15 22/Feb/15, Mason
840 Plastering Work 10d 15/Feb/15 25/Feb/15 0d 15/Feb/15 25/Feb/15, Plaste
841 Floor Screed and Water proofing at Wet Areas 7d 22/Feb/15 01/Mar/15 21d 22/Feb/15 01/Mar/15, Floor
850 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 02/Mar/15 08/Mar/15 22d 02/Mar/15 08/Mar/15, Floor
855 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 03/Mar/15 08/Mar/15 24d 03/Mar/15 08/Mar/15, Wall
7TH FLOOR (7F) 24d 23/Feb/15 22/Mar/15 17d 22/Mar/15, 7TH
860 Masonary Work 12d 23/Feb/15 08/Mar/15 4d 23/Feb/15 08/Mar/15, Maso
870 Plastering Work 9d 02/Mar/15 11/Mar/15 5d 02/Mar/15 11/Mar/15, Plast
871 Floor Screed and Water proofing at Wet Areas 7d 08/Mar/15 15/Mar/15 16d 08/Mar/15 15/Mar/15, Floo
890 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 16/Mar/15 22/Mar/15 16d 16/Mar/15 22/Mar/15, Flo
895 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 17/Mar/15 22/Mar/15 17d 17/Mar/15 22/Mar/15, Wa
ROOF FLOOR 21d 09/Mar/15 01/Apr/15 13d 01/Apr/15, RO
900 Masonary Work 12d 09/Mar/15 22/Mar/15 4d 09/Mar/15 22/Mar/15, Ma
910 Plastering Work 10d 15/Mar/15 25/Mar/15 4d 15/Mar/15 25/Mar/15, Pla
920 Flooring Work & Threshold(Granite, Granitti Ceramic & Staturio Marble) 6d 26/Mar/15 01/Apr/15 13d 26/Mar/15 01/Apr/15, Flo
925 Wall finishes & Skirting ( Glazed Ceramic Tile & Staturio Marble) 5d 28/Mar/15 01/Apr/15 13d 28/Mar/15 01/Apr/15, W
FINAL FINISHES INTERNAL 207d 19/Aug/14 16/Apr/15 0d 16/Apr/15, F
BASEMENT NO 02 (2B) 29d 19/Aug/14 21/Sep/14 46d 21/Sep/14, BASEMENT NO 02 (2B)
930 Paint Work 8d 19/Aug/14 27/Aug/14 36d 19/Aug/14 27/Aug/14, Paint Work
940 Metal Works 5d 25/Aug/14 30/Aug/14 38d 25/Aug/14 30/Aug/14, Metal Works
945 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 31/Aug/14 08/Sep/14 38d 31/Aug/14 08/Sep/14, False Ceiling Work (60 X 60
946 Bulk Head Gypsum Board 5d 06/Sep/14 10/Sep/14 39d 06/Sep/14 10/Sep/14, Bulk Head Gypsum Board
947 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & 7d 06/Sep/14 13/Sep/14 39d 06/Sep/14 13/Sep/14, Staircase finishing (Balustr
Landing)
950 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 07/Sep/14 20/Sep/14 46d 07/Sep/14 20/Sep/14, Wood & Plastic Work(Kitc
955 Doors & Windows (Wood & Alluminium) 12d 08/Sep/14 21/Sep/14 46d 08/Sep/14 21/Sep/14, Doors & Windows (Wood
BASEMENT NO 01 (1B) 43d 08/Sep/14 27/Oct/14 27d 27/Oct/14, BASEMENT NO 01 (1B)
960 Paint Work 10d 08/Sep/14 18/Sep/14 27d 08/Sep/14 18/Sep/14, Paint Work
970 Metal Works 5d 16/Sep/14 21/Sep/14 27d 16/Sep/14 21/Sep/14, Metal Works
975 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 22/Sep/14 30/Sep/14 27d 22/Sep/14 30/Sep/14, False Ceiling Work (60 X
976 Bulk Head Gypsum Board 5d 28/Sep/14 02/Oct/14 27d 28/Sep/14 02/Oct/14, Bulk Head Gypsum Board
977 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 28/Sep/14 11/Oct/14 27d 28/Sep/14 11/Oct/14, Staircase finishing (Balu
980 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 13/Oct/14 26/Oct/14 27d 13/Oct/14 26/Oct/14, Wood & Plastic Work
985 Doors & Windows (Wood & Alluminium) 12d 14/Oct/14 27/Oct/14 27d 14/Oct/14 27/Oct/14, Doors & Windows (W

Remaining Level of Effort Critical Remaining W... Page 5 of 13 STAMP


Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
LOWER GROUND (LG) 36d 30/Sep/14 10/Nov/14 27d 10/Nov/14, LOWER GROUND (LG)
1000 Paint Work 10d 30/Sep/14 11/Oct/14 32d 30/Sep/14 11/Oct/14, Paint Work
1003 Metal Works 5d 08/Oct/14 13/Oct/14 32d 08/Oct/14 13/Oct/14, Metal Works
1005 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 14/Oct/14 22/Oct/14 32d 14/Oct/14 22/Oct/14, False Ceiling Work (6
1006 Bulk Head Gypsum Board 5d 20/Oct/14 25/Oct/14 32d 20/Oct/14 25/Oct/14, Bulk Head Gypsum Board
1007 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 20/Oct/14 02/Nov/14 32d 20/Oct/14 02/Nov/14, Staircase finishing (B
1010 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 27/Oct/14 09/Nov/14 27d 27/Oct/14 09/Nov/14, Wood & Plastic Wo
1015 Doors & Windows (Wood & Alluminium) 12d 28/Oct/14 10/Nov/14 27d 28/Oct/14 10/Nov/14, Doors & Windows (
GROUND FLOOR (GF) 31d 20/Oct/14 24/Nov/14 27d 24/Nov/14, GROUND FLOOR (GF)
1020 Paint Work 10d 20/Oct/14 30/Oct/14 27d 20/Oct/14 30/Oct/14, Paint Work
1030 Metal Works 5d 28/Oct/14 02/Nov/14 27d 28/Oct/14 02/Nov/14, Metal Works
1035 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 03/Nov/14 11/Nov/14 27d 03/Nov/14 11/Nov/14, False Ceiling Work
1036 Bulk Head Gypsum Board 5d 09/Nov/14 13/Nov/14 27d 09/Nov/14 13/Nov/14, Bulk Head Gypsum Board
1037 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 09/Nov/14 22/Nov/14 27d 09/Nov/14 22/Nov/14, Staircase finishing
1040 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 10/Nov/14 23/Nov/14 27d 10/Nov/14 23/Nov/14, Wood & Plastic W
1045 Doors & Windows (Wood & Alluminium) 12d 11/Nov/14 24/Nov/14 27d 11/Nov/14 24/Nov/14, Doors & Windows
MEZZANINE FLOOR (MF) 31d 09/Nov/14 14/Dec/14 22d 14/Dec/14, MEZZANINE F
1050 Paint Work 10d 09/Nov/14 19/Nov/14 22d 09/Nov/14 19/Nov/14, Paint Work
1060 Metal Works 5d 17/Nov/14 22/Nov/14 22d 17/Nov/14 22/Nov/14, Metal Works
1065 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 23/Nov/14 01/Dec/14 22d 23/Nov/14 01/Dec/14, False Ceiling Wo
1066 Bulk Head Gypsum Board 5d 29/Nov/14 03/Dec/14 22d 29/Nov/14 03/Dec/14, Bulk Head Gyps
1067 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 29/Nov/14 11/Dec/14 22d 29/Nov/14 11/Dec/14, Staircase finish
1070 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 30/Nov/14 13/Dec/14 22d 30/Nov/14 13/Dec/14, Wood & Plastic
1075 Doors & Windows (Wood & Alluminium) 12d 01/Dec/14 14/Dec/14 22d 01/Dec/14 14/Dec/14, Doors & Windo
1ST FLOOR (1F) 31d 25/Nov/14 30/Dec/14 20d 30/Dec/14, 1ST FLOOR (1F)
1080 Paint Work 10d 25/Nov/14 06/Dec/14 20d 25/Nov/14 06/Dec/14, Paint Work
1090 Metal Works 5d 03/Dec/14 08/Dec/14 20d 03/Dec/14 08/Dec/14, Metal Works
1095 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 09/Dec/14 17/Dec/14 20d 09/Dec/14 17/Dec/14, False Ceiling W
1096 Bulk Head Gypsum Board 5d 15/Dec/14 20/Dec/14 20d 15/Dec/14 20/Dec/14, Bulk Head Gyp
1097 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 15/Dec/14 28/Dec/14 20d 15/Dec/14 28/Dec/14, Staircase finis
1100 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 16/Dec/14 29/Dec/14 20d 16/Dec/14 29/Dec/14, Wood & Plas
1105 Doors & Windows (Wood & Alluminium) 12d 17/Dec/14 30/Dec/14 20d 17/Dec/14 30/Dec/14, Doors & Win
2ND FLOOR (2F) 31d 15/Dec/14 19/Jan/15 15d 19/Jan/15, 2ND FLOOR (2F)
1110 Paint Work 10d 15/Dec/14 25/Dec/14 15d 15/Dec/14 25/Dec/14, Paint Work
1120 Metal Works 5d 23/Dec/14 28/Dec/14 15d 23/Dec/14 28/Dec/14, Metal Works
1125 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 29/Dec/14 06/Jan/15 15d 29/Dec/14 06/Jan/15, False Ceiling
1126 Bulk Head Gypsum Board 5d 04/Jan/15 08/Jan/15 15d 04/Jan/15 08/Jan/15, Bulk Head G
1127 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 04/Jan/15 17/Jan/15 15d 04/Jan/15 17/Jan/15, Staircase fi
1130 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 05/Jan/15 18/Jan/15 15d 05/Jan/15 18/Jan/15, Wood & Pla
1135 Doors & Windows (Wood & Alluminium) 12d 06/Jan/15 19/Jan/15 15d 06/Jan/15 19/Jan/15, Doors & W

Remaining Level of Effort Critical Remaining W... Page 6 of 13 STAMP


Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
3RD FLOOR (3F) 31d 04/Jan/15 08/Feb/15 10d 08/Feb/15, 3RD FLO
1140 Paint Work 10d 04/Jan/15 14/Jan/15 10d 04/Jan/15 14/Jan/15, Paint Work
1150 Metal Works 5d 12/Jan/15 17/Jan/15 10d 12/Jan/15 17/Jan/15, Metal Works
1155 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 18/Jan/15 26/Jan/15 10d 18/Jan/15 26/Jan/15, False Ceil
1156 Bulk Head Gypsum Board 5d 24/Jan/15 28/Jan/15 10d 24/Jan/15 28/Jan/15, Bulk Head
1157 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 24/Jan/15 05/Feb/15 10d 24/Jan/15 05/Feb/15, Staircase
1160 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 25/Jan/15 07/Feb/15 10d 25/Jan/15 07/Feb/15, Wood &
1165 Doors & Windows (Wood & Alluminium) 12d 26/Jan/15 08/Feb/15 10d 26/Jan/15 08/Feb/15, Doors &
4TH FLOOR (4F) 31d 24/Jan/15 28/Feb/15 5d 28/Feb/15, 4TH F
1170 Paint Work 10d 24/Jan/15 03/Feb/15 5d 24/Jan/15 03/Feb/15, Paint Work
1180 Metal Works 5d 01/Feb/15 05/Feb/15 5d 01/Feb/15 05/Feb/15, Metal Works
1185 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 07/Feb/15 15/Feb/15 5d 07/Feb/15 15/Feb/15, False C
1186 Bulk Head Gypsum Board 5d 12/Feb/15 17/Feb/15 5d 12/Feb/15 17/Feb/15, Bulk He
1187 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 12/Feb/15 25/Feb/15 5d 12/Feb/15 25/Feb/15, Stairca
1190 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 14/Feb/15 26/Feb/15 5d 14/Feb/15 26/Feb/15, Wood
1195 Doors & Windows (Wood & Alluminium) 12d 15/Feb/15 28/Feb/15 5d 15/Feb/15 28/Feb/15, Doors
5TH FLOOR (5F) 31d 12/Feb/15 19/Mar/15 0d 19/Mar/15, 5TH
1200 Paint Work 10d 12/Feb/15 23/Feb/15 0d 12/Feb/15 23/Feb/15, Paint Work
1210 Metal Works 5d 21/Feb/15 25/Feb/15 0d 21/Feb/15 25/Feb/15, Metal Works
1215 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 26/Feb/15 07/Mar/15 0d 26/Feb/15 07/Mar/15, False
1216 Bulk Head Gypsum Board 5d 04/Mar/15 09/Mar/15 0d 04/Mar/15 09/Mar/15, Bulk
1217 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 04/Mar/15 17/Mar/15 0d 04/Mar/15 17/Mar/15, Stai
1220 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 05/Mar/15 18/Mar/15 0d 05/Mar/15 18/Mar/15, Wo
1225 Doors & Windows (Wood & Alluminium) 12d 07/Mar/15 19/Mar/15 0d 07/Mar/15 19/Mar/15, Doo
6TH FLOOR (6F) 31d 26/Feb/15 02/Apr/15 0d 02/Apr/15, 6T
1230 Paint Work 10d 26/Feb/15 09/Mar/15 0d 26/Feb/15 09/Mar/15, Paint Work
1240 Metal Works 5d 07/Mar/15 11/Mar/15 0d 07/Mar/15 11/Mar/15, Metal Works
1245 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 8d 12/Mar/15 21/Mar/15 0d 12/Mar/15 21/Mar/15, Fal
1246 Bulk Head Gypsum Board 5d 18/Mar/15 23/Mar/15 0d 18/Mar/15 23/Mar/15, Bu
1247 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 12d 18/Mar/15 31/Mar/15 0d 18/Mar/15 31/Mar/15, St
1250 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 12d 19/Mar/15 01/Apr/15 0d 19/Mar/15 01/Apr/15, W
1255 Doors & Windows (Wood & Alluminium) 12d 21/Mar/15 02/Apr/15 0d 21/Mar/15 02/Apr/15, Do
7TH FLOOR (7F) 25d 12/Mar/15 09/Apr/15 0d 09/Apr/15, 7
1260 Paint Work 8d 12/Mar/15 21/Mar/15 5d 12/Mar/15 21/Mar/15, Paint Work
1270 Metal Works 4d 19/Mar/15 23/Mar/15 5d 19/Mar/15 23/Mar/15, Me
1275 False Ceiling Work (60 X 60cm Gypsum,Aluminum Tiles) 5d 24/Mar/15 29/Mar/15 5d 24/Mar/15 29/Mar/15, Fa
1276 Bulk Head Gypsum Board 5d 26/Mar/15 31/Mar/15 5d 26/Mar/15 31/Mar/15, Bu
1277 Staircase finishing (Balustrades,Handrails & Marble for Tread, Riser & Landing) 5d 01/Apr/15 06/Apr/15 0d 01/Apr/15 06/Apr/15, S
1280 Wood & Plastic Work(Kitchen,wall & Base Cabinets) 6d 02/Apr/15 08/Apr/15 0d 02/Apr/15 08/Apr/15, W
1285 Doors & Windows (Wood & Alluminium) 6d 04/Apr/15 09/Apr/15 0d 04/Apr/15 09/Apr/15, D

Remaining Level of Effort Critical Remaining W... Page 7 of 13 STAMP


Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
ROOF FLOOR 19d 26/Mar/15 16/Apr/15 0d 16/Apr/15, R
1290 Paint Work 5d 26/Mar/15 31/Mar/15 4d 26/Mar/15 31/Mar/15, Paint Work
1300 Metal Works 4d 30/Mar/15 02/Apr/15 10d 30/Mar/15 02/Apr/15, M
1305 Doors & Windows (Wood & Alluminium) 6d 11/Apr/15 16/Apr/15 0d 11/Apr/15 16/Apr/15, D
EXTERNAL FINISHES 62d 13/Dec/14 22/Feb/15 46d 22/Feb/15, EXTER
Parking Area & Side Walk 30d 15/Dec/14 18/Jan/15 76d 18/Jan/15, Parking Are
1320 Parking Area & Side Walk 10d 15/Dec/14 25/Dec/14 46d 15/Dec/14 25/Dec/14, Parking Area
1322 Asphalt Work / Pavement Reinstatement 10d 27/Dec/14 06/Jan/15 76d 27/Dec/14 06/Jan/15, Asphalt Work
1324 Interlock & Curb Stone Pavement 10d 07/Jan/15 18/Jan/15 76d 07/Jan/15 18/Jan/15, Interlock &
Elevation Finishing Work 62d 13/Dec/14 22/Feb/15 46d 22/Feb/15, Elevati
1330 Facade damp-proofing behind cladding 60d 15/Dec/14 22/Feb/15 46d 15/Dec/14 22/Feb/15, Facad
1331 4mm thick aluminum Composite fire rated Cladding 52d 13/Dec/14 11/Feb/15 56d 13/Dec/14 11/Feb/15, 4mm thi
1332 Aluminum Windows and Glazed Curtain Walls 42d 18/Dec/14 05/Feb/15 61d 18/Dec/14 05/Feb/15, Aluminum
1333 Mirror Finish Stainless Steel Circular Columns 20d 13/Jan/15 05/Feb/15 61d 13/Jan/15 05/Feb/15, Mirror Fi
CONVEYING SYSTEM 47d 01/Dec/14 24/Jan/15 71d 24/Jan/15, CONVEYI

PASSENGER LIFTS 47d 01/Dec/14 24/Jan/15 71d 24/Jan/15, PASSENG


ALL FLOORS 47d 01/Dec/14 24/Jan/15 71d 24/Jan/15, ALL FLOORS
PL.1 Gondola/ Scaffolding Installation 7d 01/Dec/14 08/Dec/14 71d 01/Dec/14 08/Dec/14, Gondola/ Scaffo
PL.11 Guide Rail Installation 2d 09/Dec/14 10/Dec/14 71d 09/Dec/14 10/Dec/14, Guide Rail Installation
PL.21 Entrance & Door Installation 5d 11/Dec/14 16/Dec/14 71d 11/Dec/14 16/Dec/14, Entrance & Do
PL.31 Pit Equipment Installation 5d 17/Dec/14 22/Dec/14 71d 17/Dec/14 22/Dec/14, Pit Equipment
PL.41 Conduits & Troughs Fixings 3d 23/Dec/14 25/Dec/14 71d 23/Dec/14 25/Dec/14, Conduits & Tr
PL.51 Fascia Plates Fixing 5d 27/Dec/14 31/Dec/14 71d 27/Dec/14 31/Dec/14, Fascia Plates Fixing
PL.61 Machine Room Equipment Installation 5d 01/Jan/15 06/Jan/15 71d 01/Jan/15 06/Jan/15, Machine Roo
PL.71 Cabinet Assembly & Wiring 5d 07/Jan/15 12/Jan/15 71d 07/Jan/15 12/Jan/15, Cabinet Ass
PL.81 Testing & Adjustment 5d 13/Jan/15 18/Jan/15 71d 13/Jan/15 18/Jan/15, Testing & A
PL.91 Cabin Finishes 5d 19/Jan/15 24/Jan/15 71d 19/Jan/15 24/Jan/15, Cabin Finishes
CAR LIFTS 41d 01/Dec/14 17/Jan/15 77d 17/Jan/15, CAR LIFTS
BASEMENT FLOORS 41d 01/Dec/14 17/Jan/15 77d 17/Jan/15, BASEMENT
CL.1 Gondola/ Scaffolding Installation 5d 01/Dec/14 06/Dec/14 77d 01/Dec/14 06/Dec/14, Gondola/ Scaffo
CL.11 Guide Rail Installation 2d 07/Dec/14 08/Dec/14 77d 07/Dec/14 08/Dec/14, Guide Rail Installation
CL.21 Entrance & Door Installation 5d 09/Dec/14 14/Dec/14 77d 09/Dec/14 14/Dec/14, Entrance & Doo
CL.31 Pit Equipment Installation 5d 15/Dec/14 20/Dec/14 77d 15/Dec/14 20/Dec/14, Pit Equipment
CL.41 Conduits & Troughs Fixings 3d 21/Dec/14 23/Dec/14 77d 21/Dec/14 23/Dec/14, Conduits & Tr
CL.51 Fascia Plates Fixing 5d 24/Dec/14 29/Dec/14 77d 24/Dec/14 29/Dec/14, Fascia Plates Fixing
CL.61 Machine Room Equipment Installation 5d 30/Dec/14 04/Jan/15 77d 30/Dec/14 04/Jan/15, Machine Roo
CL.71 Cabinet Assembly & Wiring 3d 05/Jan/15 07/Jan/15 77d 05/Jan/15 07/Jan/15, Cabinet Asse
CL.81 Testing & Adjustment 5d 08/Jan/15 13/Jan/15 77d 08/Jan/15 13/Jan/15, Testing & Ad
CL.91 Cabin Finishes 3d 14/Jan/15 17/Jan/15 77d 14/Jan/15 17/Jan/15, Cabin Finishes

Remaining Level of Effort Critical Remaining W... Page 8 of 13 STAMP


Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
CRADLE SYSTEM 10d 13/Jan/15 24/Jan/15 71d 24/Jan/15, CRADLE SYSTEM
1360 Installation of Galvanized UB Tracks 5d 13/Jan/15 18/Jan/15 71d 13/Jan/15 18/Jan/15, Installation
1365 Installation of Powered Cradle (Tr olley) 240kg 5d 19/Jan/15 24/Jan/15 71d 19/Jan/15 24/Jan/15, Installation
GARBAGE DISPOSAL SYSTEM 40d 15/Jan/15 02/Mar/15 39d 02/Mar/15, GARB
GDS-10 Garbage Disposal Chute 40d 15/Jan/15 02/Mar/15 39d 15/Jan/15 02/Mar/15, Garba
MEP WORKS 208d 02/Aug/14 31/Mar/15 4d 31/Mar/15, M

MECHANICAL / HVAC 208d 02/Aug/14 31/Mar/15 4d 31/Mar/15, M


BASEMENT NO 02 (2B) 23d 02/Aug/14 27/Aug/14 189d 27/Aug/14, BASEMENT NO 02 (2B)
2000 Mechanical/HVAC First Fix 18d 02/Aug/14 21/Aug/14 194d 02/Aug/14 21/Aug/14, Mechanical/HVAC First Fix
2010 Mechanical/HVAC Final Fix 20d 05/Aug/14 27/Aug/14 189d 05/Aug/14 27/Aug/14, Mechanical/HVAC Final Fix
BASEMENT NO 01 (1B) 25d 21/Aug/14 18/Sep/14 170d 18/Sep/14, BASEMENT NO 01 (1B)
2020 Mechanical/HVAC First Fix 18d 21/Aug/14 10/Sep/14 177d 21/Aug/14 10/Sep/14, Mechanical/HVAC First Fix
2030 Mechanical/HVAC Final Fix 20d 27/Aug/14 18/Sep/14 170d 27/Aug/14 18/Sep/14, Mechanical/HVAC Final Fix
LOWER GROUND (LG) 25d 13/Sep/14 11/Oct/14 151d 11/Oct/14, LOWER GROUND (LG)
2040 Mechanical/HVAC First Fix 18d 13/Sep/14 02/Oct/14 158d 13/Sep/14 02/Oct/14, Mechanical/HVAC First Fix
2050 Mechanical/HVAC Final Fix 20d 18/Sep/14 11/Oct/14 151d 18/Sep/14 11/Oct/14, Mechanical/HVAC Final Fix
GROUND FLOOR (GF) 25d 02/Oct/14 30/Oct/14 134d 30/Oct/14, GROUND FLOOR (GF)
2060 Mechanical/HVAC First Fix 18d 02/Oct/14 22/Oct/14 141d 02/Oct/14 22/Oct/14, Mechanical/HVAC First Fix
2070 Mechanical/HVAC Final Fix 20d 08/Oct/14 30/Oct/14 134d 08/Oct/14 30/Oct/14, Mechanical/HVAC Final Fix
MEZZANINE FLOOR (MF) 25d 22/Oct/14 19/Nov/14 117d 19/Nov/14, MEZZANINE FLO
2080 Mechanical/HVAC First Fix 18d 22/Oct/14 11/Nov/14 124d 22/Oct/14 11/Nov/14, Mechanical/HVAC First Fix
2090 Mechanical/HVAC Final Fix 20d 28/Oct/14 19/Nov/14 117d 28/Oct/14 19/Nov/14, Mechanical/HVAC Final Fix
1ST FLOOR (1F) 25d 08/Nov/14 06/Dec/14 103d 06/Dec/14, 1ST FLOOR (1F)
2100 Mechanical/HVAC First Fix 18d 08/Nov/14 27/Nov/14 110d 08/Nov/14 27/Nov/14, Mechanical/HVAC
2110 Mechanical/HVAC Final Fix 20d 13/Nov/14 06/Dec/14 103d 13/Nov/14 06/Dec/14, Mechanical/HVA
2ND FLOOR (2F) 25d 27/Nov/14 25/Dec/14 86d 25/Dec/14, 2ND FLOOR (2F)
2120 Mechanical/HVAC First Fix 18d 27/Nov/14 17/Dec/14 93d 27/Nov/14 17/Dec/14, Mechanical/HV
2130 Mechanical/HVAC Final Fix 20d 03/Dec/14 25/Dec/14 86d 03/Dec/14 25/Dec/14, Mechanical/H
3RD FLOOR (3F) 25d 17/Dec/14 14/Jan/15 69d 14/Jan/15, 3RD FLOOR (3F)
2140 Mechanical/HVAC First Fix 18d 17/Dec/14 06/Jan/15 76d 17/Dec/14 06/Jan/15, Mechanical/H
2150 Mechanical/HVAC Final Fix 20d 23/Dec/14 14/Jan/15 69d 23/Dec/14 14/Jan/15, Mechanical
4TH FLOOR (4F) 25d 06/Jan/15 03/Feb/15 52d 03/Feb/15, 4TH FLO
2160 Mechanical/HVAC First Fix 18d 06/Jan/15 26/Jan/15 59d 06/Jan/15 26/Jan/15, Mechanica
2170 Mechanical/HVAC Final Fix 20d 12/Jan/15 03/Feb/15 52d 12/Jan/15 03/Feb/15, Mechanic
5TH FLOOR (5F) 25d 26/Jan/15 23/Feb/15 35d 23/Feb/15, 5TH F
2180 Mechanical/HVAC First Fix 18d 26/Jan/15 15/Feb/15 42d 26/Jan/15 15/Feb/15, Mechan
2190 Mechanical/HVAC Final Fix 20d 01/Feb/15 23/Feb/15 35d 01/Feb/15 23/Feb/15, Mecha
6TH FLOOR (6F) 25d 09/Feb/15 09/Mar/15 23d 09/Mar/15, 6TH
2200 Mechanical/HVAC First Fix 18d 09/Feb/15 01/Mar/15 30d 09/Feb/15 01/Mar/15, Mech
2210 Mechanical/HVAC Final Fix 18d 17/Feb/15 09/Mar/15 23d 17/Feb/15 09/Mar/15, Mech

Remaining Level of Effort Critical Remaining W... Page 9 of 13 STAMP


Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
7TH FLOOR (7F) 23d 23/Feb/15 21/Mar/15 13d 21/Mar/15, 7TH
2220 Mechanical/HVAC First Fix 18d 23/Feb/15 15/Mar/15 18d 23/Feb/15 15/Mar/15, Mec
2230 Mechanical/HVAC Final Fix 18d 01/Mar/15 21/Mar/15 13d 01/Mar/15 21/Mar/15, Me
ROOF FLOOR 20d 09/Mar/15 31/Mar/15 4d 31/Mar/15, RO
2240 Mechanical/HVAC First Fix 18d 09/Mar/15 29/Mar/15 6d 09/Mar/15 29/Mar/15, Me
2250 Mechanical/HVAC Final Fix 18d 11/Mar/15 31/Mar/15 4d 11/Mar/15 31/Mar/15, M
ELECTRICAL 208d 02/Aug/14 31/Mar/15 4d 31/Mar/15, EL
BASEMENT NO 02 (2B) 23d 02/Aug/14 27/Aug/14 189d 27/Aug/14, BASEMENT NO 02 (2B)
3000 Electrical First Fix 20d 02/Aug/14 24/Aug/14 192d 02/Aug/14 24/Aug/14, Electrical First Fix
3010 Electrical Final Fix 21d 04/Aug/14 27/Aug/14 189d 04/Aug/14 27/Aug/14, Electrical Final Fix
BASEMENT NO 01 (1B) 25d 21/Aug/14 18/Sep/14 170d 18/Sep/14, BASEMENT NO 01 (1B)
3020 Electrical First Fix 20d 21/Aug/14 13/Sep/14 175d 21/Aug/14 13/Sep/14, Electrical First Fix
3030 Electrical Final Fix 21d 26/Aug/14 18/Sep/14 170d 26/Aug/14 18/Sep/14, Electrical Final Fix
LOWER GROUND (LG) 25d 13/Sep/14 11/Oct/14 151d 11/Oct/14, LOWER GROUND (LG)
3040 Electrical First Fix 20d 13/Sep/14 05/Oct/14 156d 13/Sep/14 05/Oct/14, Electrical First Fix
3050 Electrical Final Fix 21d 17/Sep/14 11/Oct/14 151d 17/Sep/14 11/Oct/14, Electrical Final Fix
GROUND FLOOR (GF) 25d 02/Oct/14 30/Oct/14 134d 30/Oct/14, GROUND FLOOR (GF)
3060 Electrical First Fix 20d 02/Oct/14 25/Oct/14 139d 02/Oct/14 25/Oct/14, Electrical First Fix
3070 Electrical Final Fix 21d 07/Oct/14 30/Oct/14 134d 07/Oct/14 30/Oct/14, Electrical Final Fix
MEZZANINE FLOOR (MF) 25d 22/Oct/14 19/Nov/14 117d 19/Nov/14, MEZZANINE FLO
3080 Electrical First Fix 20d 22/Oct/14 13/Nov/14 122d 22/Oct/14 13/Nov/14, Electrical First Fix
3090 Electrical Final Fix 21d 27/Oct/14 19/Nov/14 117d 27/Oct/14 19/Nov/14, Electrical Final Fix
1ST FLOOR (1F) 25d 08/Nov/14 06/Dec/14 103d 06/Dec/14, 1ST FLOOR (1F)
3100 Electrical First Fix 20d 08/Nov/14 30/Nov/14 108d 08/Nov/14 30/Nov/14, Electrical First Fix
3110 Electrical Final Fix 21d 12/Nov/14 06/Dec/14 103d 12/Nov/14 06/Dec/14, Electrical Final Fix
2ND FLOOR (2F) 25d 27/Nov/14 25/Dec/14 86d 25/Dec/14, 2ND FLOOR (2F)
3120 Electrical First Fix 20d 27/Nov/14 20/Dec/14 91d 27/Nov/14 20/Dec/14, Electrical First Fix
3130 Electrical Final Fix 21d 02/Dec/14 25/Dec/14 86d 02/Dec/14 25/Dec/14, Electrical Final Fix
3RD FLOOR (3F) 25d 17/Dec/14 14/Jan/15 69d 14/Jan/15, 3RD FLOOR (3F)
3140 Electrical First Fix 20d 17/Dec/14 08/Jan/15 74d 17/Dec/14 08/Jan/15, Electrical First Fix
3150 Electrical Final Fix 21d 22/Dec/14 14/Jan/15 69d 22/Dec/14 14/Jan/15, Electrical Final Fix
4TH FLOOR (4F) 25d 06/Jan/15 03/Feb/15 52d 03/Feb/15, 4TH FLO
3160 Electrical First Fix 20d 06/Jan/15 28/Jan/15 57d 06/Jan/15 28/Jan/15, Electrical First Fix
3170 Electrical Final Fix 21d 11/Jan/15 03/Feb/15 52d 11/Jan/15 03/Feb/15, Electrical Final Fix
5TH FLOOR (5F) 25d 26/Jan/15 23/Feb/15 35d 23/Feb/15, 5TH F
3180 Electrical First Fix 20d 26/Jan/15 17/Feb/15 40d 26/Jan/15 17/Feb/15, Electric
3190 Electrical Final Fix 21d 31/Jan/15 23/Feb/15 35d 31/Jan/15 23/Feb/15, Electri
6TH FLOOR (6F) 25d 09/Feb/15 09/Mar/15 23d 09/Mar/15, 6TH
3200 Electrical First Fix 20d 09/Feb/15 03/Mar/15 28d 09/Feb/15 03/Mar/15, Electr
3210 Electrical Final Fix 21d 14/Feb/15 09/Mar/15 23d 14/Feb/15 09/Mar/15, Elect
7TH FLOOR (7F) 23d 23/Feb/15 21/Mar/15 13d 21/Mar/15, 7TH
Remaining Level of Effort Critical Remaining W... Page 10 of 13 STAMP
Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
3220 Electrical First Fix 20d 23/Feb/15 17/Mar/15 16d 23/Feb/15 17/Mar/15, Elec
3230 Electrical Final Fix 21d 25/Feb/15 21/Mar/15 13d 25/Feb/15 21/Mar/15, Ele
ROOF FLOOR 21d 08/Mar/15 31/Mar/15 4d 31/Mar/15, RO
3240 Electrical First Fix 20d 09/Mar/15 31/Mar/15 4d 09/Mar/15 31/Mar/15, El
3250 Electrical Final Fix 21d 08/Mar/15 31/Mar/15 4d 08/Mar/15 31/Mar/15, El
PLUMBING 208d 02/Aug/14 31/Mar/15 4d 31/Mar/15, PLUMBING
BASEMENT NO 02 (2B) 25d 02/Aug/14 30/Aug/14 187d 30/Aug/14, BASEMENT NO 02 (2B)
4000 Plumbing & Drainage First Fix 25d 02/Aug/14 30/Aug/14 187d 02/Aug/14 30/Aug/14, Plumbing & Drainage First Fix
4010 Plumbing & Drainage Final Fix 20d 05/Aug/14 27/Aug/14 189d 05/Aug/14 27/Aug/14, Plumbing & Drainage Final Fix
BASEMENT NO 01 (1B) 25d 21/Aug/14 18/Sep/14 170d 18/Sep/14, BASEMENT NO 01 (1B)
4020 Plumbing & Drainage First Fix 25d 21/Aug/14 18/Sep/14 170d 21/Aug/14 18/Sep/14, Plumbing & Drainage First Fix
4030 Plumbing & Drainage Final Fix 20d 27/Aug/14 18/Sep/14 170d 27/Aug/14 18/Sep/14, Plumbing & Drainage Final Fix
LOWER GROUND (LG) 25d 13/Sep/14 11/Oct/14 151d 11/Oct/14, LOWER GROUND (LG)
4040 Plumbing & Drainage First Fix 25d 13/Sep/14 11/Oct/14 151d 13/Sep/14 11/Oct/14, Plumbing & Drainage First Fix
4050 Plumbing & Drainage Final Fix 20d 18/Sep/14 11/Oct/14 151d 18/Sep/14 11/Oct/14, Plumbing & Drainage Final Fix
GROUND FLOOR (GF) 25d 02/Oct/14 30/Oct/14 134d 30/Oct/14, GROUND FLOOR (GF)
4060 Plumbing & Drainage First Fix 25d 02/Oct/14 30/Oct/14 134d 02/Oct/14 30/Oct/14, Plumbing & Drainage First Fix
4070 Plumbing & Drainage Final Fix 20d 08/Oct/14 30/Oct/14 134d 08/Oct/14 30/Oct/14, Plumbing & Drainage Final Fix
MEZZANINE FLOOR (MF) 25d 22/Oct/14 19/Nov/14 117d 19/Nov/14, MEZZANINE FLO
4080 Plumbing & Drainage First Fix 25d 22/Oct/14 19/Nov/14 117d 22/Oct/14 19/Nov/14, Plumbing & Draina
4090 Plumbing & Drainage Final Fix 20d 28/Oct/14 19/Nov/14 117d 28/Oct/14 19/Nov/14, Plumbing & Draina
1ST FLOOR (1F) 25d 08/Nov/14 06/Dec/14 103d 06/Dec/14, 1ST FLOOR (1F)
4100 Plumbing & Drainage First Fix 18d 08/Nov/14 27/Nov/14 110d 08/Nov/14 27/Nov/14, Plumbing & Drain
4110 Plumbing & Drainage Final Fix 20d 13/Nov/14 06/Dec/14 103d 13/Nov/14 06/Dec/14, Plumbing & Drai
2ND FLOOR (2F) 25d 27/Nov/14 25/Dec/14 86d 25/Dec/14, 2ND FLOOR (2F)
4120 Plumbing & Drainage First Fix 18d 27/Nov/14 17/Dec/14 93d 27/Nov/14 17/Dec/14, Plumbing & Dra
4130 Plumbing & Drainage Final Fix 20d 03/Dec/14 25/Dec/14 86d 03/Dec/14 25/Dec/14, Plumbing & D
3RD FLOOR (3F) 25d 17/Dec/14 14/Jan/15 69d 14/Jan/15, 3RD FLOOR (3F)
4140 Plumbing & Drainage First Fix 18d 17/Dec/14 06/Jan/15 76d 17/Dec/14 06/Jan/15, Plumbing & D
4150 Plumbing & Drainage Final Fix 20d 23/Dec/14 14/Jan/15 69d 23/Dec/14 14/Jan/15, Plumbing &
4TH FLOOR (4F) 25d 06/Jan/15 03/Feb/15 52d 03/Feb/15, 4TH FLO
4160 Plumbing & Drainage First Fix 18d 06/Jan/15 26/Jan/15 59d 06/Jan/15 26/Jan/15, Plumbing &
4170 Plumbing & Drainage Final Fix 20d 12/Jan/15 03/Feb/15 52d 12/Jan/15 03/Feb/15, Plumbing
5TH FLOOR (5F) 25d 26/Jan/15 23/Feb/15 35d 23/Feb/15, 5TH F
4180 Plumbing & Drainage First Fix 18d 26/Jan/15 15/Feb/15 42d 26/Jan/15 15/Feb/15, Plumbin
4190 Plumbing & Drainage Final Fix 20d 01/Feb/15 23/Feb/15 35d 01/Feb/15 23/Feb/15, Plumb
6TH FLOOR (6F) 25d 09/Feb/15 09/Mar/15 23d 09/Mar/15, 6TH
4200 Plumbing & Drainage First Fix 18d 09/Feb/15 01/Mar/15 30d 09/Feb/15 01/Mar/15, Plumb
4210 Plumbing & Drainage Final Fix 20d 15/Feb/15 09/Mar/15 23d 15/Feb/15 09/Mar/15, Plum
7TH FLOOR (7F) 23d 23/Feb/15 21/Mar/15 13d 21/Mar/15, 7TH
4220 Plumbing & Drainage First Fix 18d 23/Feb/15 15/Mar/15 18d 23/Feb/15 15/Mar/15, Plum
Remaining Level of Effort Critical Remaining W... Page 11 of 13 STAMP
Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
4230 Plumbing & Drainage Final Fix 20d 26/Feb/15 21/Mar/15 13d 26/Feb/15 21/Mar/15, Plu
ROOF FLOOR 20d 09/Mar/15 31/Mar/15 4d 31/Mar/15, RO
4240 Plumbing & Drainage First Fix 18d 09/Mar/15 29/Mar/15 6d 09/Mar/15 29/Mar/15, Plu
4250 Plumbing & Drainage Final Fix 20d 09/Mar/15 31/Mar/15 4d 09/Mar/15 31/Mar/15, Pl
FIRE FIGHTING 208d 02/Aug/14 31/Mar/15 4d 31/Mar/15, FI
BASEMENT NO 02 (2B) 23d 02/Aug/14 27/Aug/14 189d 27/Aug/14, BASEMENT NO 02 (2B)
5000 Fire Fighting First Fix 15d 02/Aug/14 18/Aug/14 197d 02/Aug/14 18/Aug/14, Fire Fighting First Fix
5010 Fire Fighting Final Fix 20d 05/Aug/14 27/Aug/14 189d 05/Aug/14 27/Aug/14, Fire Fighting Final Fix
BASEMENT NO 01 (1B) 25d 21/Aug/14 18/Sep/14 170d 18/Sep/14, BASEMENT NO 01 (1B)
5020 Fire Fighting First Fix 15d 21/Aug/14 07/Sep/14 180d 21/Aug/14 07/Sep/14, Fire Fighting First Fix
5030 Fire Fighting Final Fix 20d 27/Aug/14 18/Sep/14 170d 27/Aug/14 18/Sep/14, Fire Fighting Final Fix
LOWER GROUND (LG) 25d 13/Sep/14 11/Oct/14 151d 11/Oct/14, LOWER GROUND (LG)
5040 Fire Fighting First Fix 15d 13/Sep/14 29/Sep/14 161d 13/Sep/14 29/Sep/14, Fire Fighting First Fix
5050 Fire Fighting Final Fix 20d 18/Sep/14 11/Oct/14 151d 18/Sep/14 11/Oct/14, Fire Fighting Final Fix
GROUND FLOOR (GF) 25d 02/Oct/14 30/Oct/14 134d 30/Oct/14, GROUND FLOOR (GF)
5060 Fire Fighting First Fix 15d 02/Oct/14 19/Oct/14 144d 02/Oct/14 19/Oct/14, Fire Fighting First Fix
5070 Fire Fighting Final Fix 20d 08/Oct/14 30/Oct/14 134d 08/Oct/14 30/Oct/14, Fire Fighting Final Fix
MEZZANINE FLOOR (MF) 25d 22/Oct/14 19/Nov/14 117d 19/Nov/14, MEZZANINE FLO
5080 Fire Fighting First Fix 15d 22/Oct/14 08/Nov/14 127d 22/Oct/14 08/Nov/14, Fire Fighting First Fix
5090 Fire Fighting Final Fix 20d 28/Oct/14 19/Nov/14 117d 28/Oct/14 19/Nov/14, Fire Fighting Final Fix
1ST FLOOR (1F) 25d 08/Nov/14 06/Dec/14 103d 06/Dec/14, 1ST FLOOR (1F)
5100 Fire Fighting First Fix 15d 08/Nov/14 24/Nov/14 113d 08/Nov/14 24/Nov/14, Fire Fighting First Fix
5110 Fire Fighting Final Fix 20d 13/Nov/14 06/Dec/14 103d 13/Nov/14 06/Dec/14, Fire Fighting Final Fix
2ND FLOOR (2F) 25d 27/Nov/14 25/Dec/14 86d 25/Dec/14, 2ND FLOOR (2F)
5120 Fire Fighting First Fix 15d 27/Nov/14 14/Dec/14 96d 27/Nov/14 14/Dec/14, Fire Fighting First Fix
5130 Fire Fighting Final Fix 20d 03/Dec/14 25/Dec/14 86d 03/Dec/14 25/Dec/14, Fire Fighting Final Fix
3RD FLOOR (3F) 25d 17/Dec/14 14/Jan/15 69d 14/Jan/15, 3RD FLOOR (3F)
5140 Fire Fighting First Fix 15d 17/Dec/14 03/Jan/15 79d 17/Dec/14 03/Jan/15, Fire Fighting First Fix
5150 Fire Fighting Final Fix 20d 23/Dec/14 14/Jan/15 69d 23/Dec/14 14/Jan/15, Fire Fighting
4TH FLOOR (4F) 25d 06/Jan/15 03/Feb/15 52d 03/Feb/15, 4TH FLO
5160 Fire Fighting First Fix 15d 06/Jan/15 22/Jan/15 62d 06/Jan/15 22/Jan/15, Fire Fightin
5170 Fire Fighting Final Fix 20d 12/Jan/15 03/Feb/15 52d 12/Jan/15 03/Feb/15, Fire Figh
5TH FLOOR (5F) 25d 26/Jan/15 23/Feb/15 35d 23/Feb/15, 5TH F
5180 Fire Fighting First Fix 15d 26/Jan/15 11/Feb/15 45d 26/Jan/15 11/Feb/15, Fire Figh
5190 Fire Fighting Final Fix 20d 01/Feb/15 23/Feb/15 35d 01/Feb/15 23/Feb/15, Fire Fi
6TH FLOOR (6F) 25d 09/Feb/15 09/Mar/15 23d 09/Mar/15, 6TH
5200 Fire Fighting First Fix 15d 09/Feb/15 25/Feb/15 33d 09/Feb/15 25/Feb/15, Fire F
5210 Fire Fighting Final Fix 20d 15/Feb/15 09/Mar/15 23d 15/Feb/15 09/Mar/15, Fire
7TH FLOOR (7F) 23d 23/Feb/15 21/Mar/15 13d 21/Mar/15, 7TH
5220 Fire Fighting First Fix 15d 23/Feb/15 11/Mar/15 21d 23/Feb/15 11/Mar/15, Fire
5230 Fire Fighting Final Fix 20d 26/Feb/15 21/Mar/15 13d 26/Feb/15 21/Mar/15, Fire
Remaining Level of Effort Critical Remaining W... Page 12 of 13 STAMP
Actual Work Milestone
Remaining Work Summary
COMMERCIAL BUILDING, ME-9 / C-128 ABU BASELINE PROGRAM
DHABI
Activity ID Activity Name Original Start Finish Total 2013 2014 2015
Duration Float
J Jul A S O N D J F M A M J Jul A S O N D J F M A M J Jul
ROOF FLOOR 20d 09/Mar/15 31/Mar/15 4d 31/Mar/15, RO
5240 Fire Fighting First Fix 15d 09/Mar/15 25/Mar/15 9d 09/Mar/15 25/Mar/15, Fir
5250 Fire Fighting Final Fix 20d 09/Mar/15 31/Mar/15 4d 09/Mar/15 31/Mar/15, Fi
TESTING AND COMMISSIONING 10d 01/Apr/15 12/Apr/15 4d 12/Apr/15, T
1370 Mechanical / HVAC Work Commissioning 10d 01/Apr/15 12/Apr/15 4d 01/Apr/15 12/Apr/15, M
1380 Electrical Work Commissioning 10d 01/Apr/15 12/Apr/15 4d 01/Apr/15 12/Apr/15, E
1390 Plumbing Work Commissioning 10d 01/Apr/15 12/Apr/15 4d 01/Apr/15 12/Apr/15, P
1395 Fire Fighting Work Commissioning 10d 01/Apr/15 12/Apr/15 4d 01/Apr/15 12/Apr/15, F
CLOSE OUT AND HANDING OVER 54d 12/Feb/15 16/Apr/15 0d 16/Apr/15, C
1400 Final Finished Closeout 0d 16/Apr/15 0d Final Finish
1410 Mechanical / HVAC Work Closeout 0d 12/Apr/15 4d Mechanical
1420 Electrical Work Closeout 0d 12/Apr/15 4d Electrical W
1430 Plumbing Work Closeout 0d 12/Apr/15 4d Plumbing W
1440 Fire Fighting Work Closeout 0d 12/Apr/15 4d Fire Fighting
1450 Conveying System Closeout 0d 12/Feb/15 54d Conveying System
1460 Garbage Disposal Work Close out 0d 02/Mar/15 39d Garbage Disposa

Remaining Level of Effort Critical Remaining W... Page 13 of 13 STAMP