BIAYA PERALATAN

PROYEK : Percut -Sei Tuan

NO KODE JENIS ALAT ANALISA BEBAN WAKTU


SATUAN JUMLAH
URUT BEBAN URAIAN BEBAN BELI SEWA OP. COST/BBM PERBAIKAN SUKU CADANG JUMLAH ( BULAN )
1 2 3 4 5 6 7 8 9 10 11=7 s.d 10 3

610.4 PERALATAN RINGAN


1 Air Compressor 175 Cfm unit 1 - 4,500,000 - 350,000 - - 3
2 Baby Walls unit - - - - - - - 3
3 Bar Bender unit - - 2,500,000 50,000 200,000 - 2,750,000 3
4 Bar Cutter unit - - 2,500,000 50,000 200,000 - 2,750,000 3
5 Concrete mixer (beton molen) unit - - 1,500,000 - 200,000 - - 3
6 Concrete Vibrator (Engine) unit - - 2,000,000 - 200,000 - - 3
7 Concrete Vibrator (Electric) unit - - 2,000,000 50,000 200,000 - 2,250,000 3
8 Concrete Cutter unit - - 2,000,000 - 260,000 - - 3
9 Container unit 1 20,000,000 - - - - - 3
10 Genset 150 KVA unit - - 15,000,000 1,771,200 500,000 400,000 17,671,200 3
11 Genset 40 KVA / Penerangan unit 1 - 2,500,000 442,800 250,000 - 3,192,800 3
12 Gerobak cor unit 5 250,000 - - - - - 3
13 Hammer Drill (Chiping) unit 1 - 1,500,000 - 225,000 - 1,725,000 3
14 Jack Hammer unit 1 - 1,500,000 - 225,000 - 1,725,000 3
15 Kendaraan roda 2 (sepeda motor) unit 2 - 1,500,000 540,000 50,000 62,500 2,152,500 3
Kendaraan roda 4 (Mini Bus) : 3
16 - SUV (sekelas CRV 2.4) u/GS unit 1 - 6,000,000 2,700,000 500,000 - 9,200,000 3
17 - Double Cabin, u/Site Manager unit - - 6,000,000 2,700,000 500,000 - 9,200,000 3
18 - Inova tipe E, u/Manager unit 1 - 5,500,000 2,700,000 500,000 - 8,700,000 3
19 - Kijang minibus operasional unit 1 - 5,000,000 2,700,000 500,000 - 8,200,000 3
20 - Kendaraan roda 4 pickup unit - - 6,000,000 2,700,000 500,000 - 9,200,000 3
21 Lampu rotary bh 3 750,000 - - - - - 3
22 Lampu sorot bh 4 400,000 - - - - - 3
23 Kabel lampu penerangan m' 3,000 10,500 - - - - - 3
24 Mesin Las unit 1 - 3,500,000 1,800,000 - - 5,300,000 3
25 Stamper unit - - 3,000,000 900,000 - - 3,900,000 3
26 Submersible pump unit 1 - 5,000,000 900,000 - - 5,900,000 3
27 Tangki air unit 2 5,000,000 - - - - - 3
28 Truck tangki air unit - - - - - - - 3
29 Truck Colt Diesel / Flat bed truck unit 1 - - - 750,000 - 750,000 3
30 Truck Crane unit - - 22,500,000 - - - 22,500,000 3

JUMLAH
JUMLAH
BIAYA
3=(5x6)+(5x11x12)

-
-
-
-
-
-
-
-
20,000,000
-
9,578,400
1,250,000
-
-
12,915,000
-
27,600,000
-
26,100,000
24,600,000
-
-
-
-
15,900,000
-
-
10,000,000
-
-
-

137,943,400
610.5 50000 PERSIAPAN DAN PENYELESAIAN
1 51000 Mobilisasi & Demobilisasi Alat 15,500,000
1 Air Compressor 175 Cfm 1 unit x Rp 500,000 500,000
2 Baby Walls - unit x Rp - -
3 Bar Bender - unit x Rp - -
4 Bar Cutter - unit x Rp - -
5 Concrete mixer (beton molen) - unit x Rp - -
6 Concrete Vibrator (Engine) - unit x Rp - -
7 Concrete Vibrator (Electric) - unit x Rp - -
8 Concrete Cutter - unit x Rp - -
9 Genset 150 KVA - unit x Rp 500,000 -
10 Genset 40 KVA / Penerangan 1 unit x Rp 500,000 500,000
11 Gerobak cor 5 unit x Rp - -
12 Hammer Drill (Chiping) 1 unit x Rp - -
13 Jack Hammer 1 unit x Rp - -
14 Kendaraan roda 2 (sepeda motor) - unit x Rp - -
15 Kendaraan roda 4 (Pick Up) - unit x Rp - -
16 Kendaraan roda 4 (Mini Bus) - unit x Rp - -
17 Lampu rotary - bh x Rp - -
18 Lampu sorot - bh x Rp - -
19 Mesin Las 1 unit x Rp 1,000,000 1,000,000
20 Stamper - unit x Rp - -
21 Submersible pump 1 unit x Rp 500,000 500,000
22 Tangki air 2 unit x Rp 1,000,000 2,000,000
23 Truck tangki air - unit x Rp - -
24 Truck Colt Diesel 1 unit x Rp 1,000,000 1,000,000
25 Container 1 unit x Rp 10,000,000 10,000,000

2 52000 Mob & Demob Tenaga Kerja 10,500,000


1 Tukang 20 org x Rp 150,000 3,000,000
2 Pekerja 50 org x Rp 150,000 7,500,000

3 53000 Pembebasan Tanah / Ganti Rugi Tanaman -


1 Ganti rugi tanaman, dll - Ls x Rp - -

4 54000 Pembongkaran Bangunan Lama -


1 Pembongkaran bangunan lama - Ls x Rp - -

5 55000 Bangunan Penunjang 315,550,000


a Kantor Kontraktor :
1 Sewa tanah untuk Kantor Kontraktor - m2 x Rp - - prelim
2 Kantor Kontraktor ( Sewa ) 1 Ls x 1 - x Rp - -
3 Pagar keliling base camp - m' x Rp 125,000 -
4 Penyambungan & Instalasi listrik - Ls x Rp 30,000,000 -
5 Penyambungan & Instalasi telpon - Ls x Rp - -
6 Penyambungan & Instalasi air bersih - Ls x Rp 15,000,000 -
7 Rekening listrik 3 bln x Rp 5,000,000 15,000,000
8 Rekening telpon 3 bln x Rp 4,000,000 12,000,000
9 Biaya voucher/pulsa komunikasi 10 org x 3 bln x Rp 100,000 3,000,000
10 Rekening air bersih 3 bln x Rp 1,500,000 4,500,000
b Stock yard ( on site )
1 Sewa tanah untuk Stock yard - m2 x Rp - -
2 Bangunan Gudang Material + Alat - m2 x Rp 500,000 -
3 Barak kerja 200 m2 x Rp 500,000 100,000,000
4 Pagar keliling stock yard - m' x Rp 125,000 -
5 Penyambungan & Instalasi listrik 1 Ls x Rp 15,000,000 15,000,000
6 Penyambungan & Instalasi air bersih 1 Ls x Rp 10,000,000 10,000,000
7 Rekening listrik 3 bln x Rp 2,500,000 7,500,000
8 Rekening air bersih 3 bln x Rp 1,500,000 4,500,000
c Perlengkapan Kantor :
1 AC 1 bh x Rp 2,500,000 2,500,000
2 Biaya perawatan + service AC 3 bln x 1 bh x Rp 25,000 75,000
3 Exhaust fan 2 bh x Rp 750,000 1,500,000
4 Lemari es 1 bh x Rp 2,000,000 2,000,000
5 Dispenser 1 bh x Rp 1,000,000 1,000,000
6 Meja tulis + kursi 5 set x Rp 1,000,000 5,000,000
7 Meja rapat + kursi 2 set x Rp 5,000,000 10,000,000
8 Meja + kursi tamu 3 set x Rp 2,000,000 6,000,000
9 Lemari arsip 1 bh x Rp 500,000 500,000
10 Filing Cabinet 2 bh x Rp 1,000,000 2,000,000
11 Brankas 1 bh x Rp 5,000,000 5,000,000
12 White board 1 bh x Rp 300,000 300,000
13 Mesin ketik 1 bh x Rp 750,000 750,000
14 Mesin Fotocopy - bh x Rp 40,000,000 -
15 Mesin Faximile 1 bh x Rp 3,000,000 3,000,000
16 Komputer (laptop) 3 set x Rp 8,000,000 24,000,000
17 Komputer (desktop) 2 set x Rp 5,000,000 10,000,000
18 Printer 1 bh x Rp 1,500,000 1,500,000
19 Hardisk external 2 bh x Rp 1,000,000 2,000,000
20 Flash disk 3 bh x Rp 100,000 300,000
21 CD 4 box x Rp 150,000 600,000
22 Plotter - bh x Rp 25,000,000 -
23 Kalkulator 2 bh x Rp 300,000 600,000
24 Kamera digital 1 bh x Rp 3,500,000 3,500,000
25 Handycam 1 bh x Rp 7,500,000 7,500,000
26 LCD Proyektor 1 bh x Rp 10,000,000 10,000,000
27 Rak gambar 1 bh x Rp 2,500,000 2,500,000
28 Televisi 21" 1 bh x Rp 1,500,000 1,500,000
29 Alat kantor lainnya - Ls x Rp - -

d Mess Karyawan :
1 Sewa tanah untuk Mess Karyawan - m2 x Rp - -
2 Sewa Mess Karyawan 1 bh x 1 th x Rp 20,000,000 20,000,000
3 Pagar keliling mess karyawan - bh x - Ls x Rp - -
4 Pembuatan, sekat, pembersihan, dll - bh x 1 Ls x Rp 1,000,000 -
5 Instalasi air bersih - bh x - Ls x Rp - -
6 Rekening listrik 1 bh x 3 bln x Rp 1,000,000 3,000,000
7 Rekening air bersih 1 bh x 3 bln x Rp 550,000 1,650,000

e Perlengkapan Mess :
1 Tempat tidur 4 bh x Rp 350,000 1,400,000
2 Kasur + bantal + sprei 4 bh x Rp 450,000 1,800,000
3 Lemari kayu 4 bh x Rp 250,000 1,000,000
4 Karpet 50 m2 x Rp 20,000 1,000,000
5 Meja + kursi tamu 1 set x Rp 1,500,000 1,500,000
6 Perlengkapan dapur 1 set x Rp 2,000,000 2,000,000
7 Televisi 21" 1 bh x Rp 1,500,000 1,500,000
8 AC 1 bh x Rp 2,500,000 2,500,000
9 Biaya perawatan + service AC 3 bln x 1 bh x Rp 25,000 75,000
10 Lemari es 1 bh x Rp 2,000,000 2,000,000
11 Dispencer 1 bh x Rp 1,000,000 1,000,000

6 56000 Perlengkapan Kerja 64,250,000


1 Handy Talky (HT) - bh x Rp 2,000,000 -
2 Battery cass - bh x Rp 400,000 -
3 SSB / All band 1 bh x Rp 5,000,000 5,000,000
4 Radio rig 4 bh x Rp 3,500,000 14,000,000
5 Biaya servis alat komunikasi - bh x Rp 750,000 -
6 Ijin radio - Ls x Rp 15,000,000 -
7 Sepatu lapangan 10 bh x Rp 125,000 1,250,000
8 Topi lapangan 10 bh x Rp 50,000 500,000
9 Jas hujan 50 bh x Rp 50,000 2,500,000
10 Sarung tangan 50 bh x Rp 35,000 1,750,000
11 Masker 30 bh x Rp 75,000 2,250,000
12 Safety Belt 10 bh x Rp 75,000 750,000
13 Rompi reflector 10 bh x Rp 75,000 750,000
14 Seragam karyawan - stel x Rp - -
15 Seragam Security + sepatu 40 stel x Rp 475,000 19,000,000
16 Senter + baterry 20 bh x Rp 75,000 1,500,000
17 Terpal plastik 2,000 m2 x Rp 5,000 10,000,000
18 Jaring Pengaman 1,000 m2 x Rp 5,000 5,000,000

7 57000 Pengukuran & Penyelidikan Tanah 11,250,000


1 Total Station + bak ukur (sewa) - bh x - bln x Rp - - prelim
2 Waterpass (beli) - bh x Rp - - prelim
3 Meteran 50 m 3 bh x Rp 750,000 2,250,000
4 Meteran 5 m 5 bh x Rp 50,000 250,000
5 Waterpass aluminium 5 bh x Rp 250,000 1,250,000
6 Service & kalibrasi alat ukur - bh x Rp - -
7 Alat ukur bantu (pilox, kain, kayu, palu, dll) 3 bln x Rp 2,500,000 7,500,000

8 58000 Laboratorium ( double di prelimineries ) 6,100,000


1 Material laboratorium (pasir otawa, dll) 3 bln x Rp 200,000 600,000
2 Test kepadatan timbunan 3 bln x Rp 500,000 1,500,000
3 Test perkerasan agregate 3 bln x Rp 500,000 1,500,000
4 Test beton 3 bln x Rp 250,000 750,000
5 Test besi 5 kali x Rp 350,000 1,750,000
6 Test aspal - bln x Rp 100,000 -

9 59000 Pembersihan Lapangan Kerja ( lihat di DKH Bab 2.01 ) -


1 Pembersihan lapangan kerja - Ls x Rp - -

10 59010 Pemeliharaan Hasil Kerja 660,650,000


1 Biaya PHO & FHO rincian terlampir 142,000,000
2 Biaya pemeliharaan pekerjaan rincian terlampir 518,650,000

11 59020 Biaya lain-lain 104,000,000


1 Koordinasi termin - bln x Rp - -
2 Transport, Lembur Konsultan & Pengawas 4 org x 13 bln x Rp 2,000,000 104,000,000

12 59030 Pengadaan kendaraan operasional -


1 Kendaraan roda 2 (sepeda motor) - unit x Rp - -
2 SUV (sekelas CRV 2.4) u/GS - unit x Rp - -
3 Double Cabin, u/Site Manager - unit x Rp - -
4 Inova tipe E, u/Manager - unit x Rp - -
5 Kendaraan roda 4 (Pick Up) - unit x Rp - -

6 Penjualan kendaraan operasional (buy back) - x Rp - -

JUMLAH 1,187,800,000
RINCIAN BIAYA PEMELIHARAAN ( Seksi 2 )

NO. URAIAN ANALISA B

A. Gaji Pegawai
1 General Superintendent - org x
2 Contract Adm. Manager - org x
3 Staf Contract Adm. & Cost control - org x
4 Drafter ( Highway & Structure ) - org x
5 Staf Akuntasi dan Pajak - org x
6 Pelaksana Struktur - org x
7 Pelaksana Perkerasan 1 org x
8 Pelaksana Pek. Lain-lain - org x
9 Driver - org x
10 Tenaga keamanan - org x
11 Tenaga harian 1 org x

B. Kendaraan Operasional
1 Station / Pick up 1 unit x
2 Sepeda Motor - unit x

C. Penanganan pekerjaan
1 Pekerjaan tanah ( sewa 3 bulan @ 200 jam kerja )
- Bulldozer - unit x
- Excavator 1 unit x
- Vibro Roller 1 unit x
- Dumptruck 1 unit x
- Tangki Air - unit x
- Borrow material - unit x

2 Pekerjaan Drainase
- RCP
- Bronjong
- Beton
- Pasangan mortar saluran

3 Pekerjaan Aspal ( AC-WC )


4 Pekerjaan rigid pavement
5 Pekerjaan PJU / Kelistrikan
6 Pekerjaan Landscape
7 Perambuan, Marka jalan
8 Pekerjaan lain-lain

D. Lain - lain
1 Sewa kantor 1 bh x
2 Sewa Gudang - bh x
3 Rek. Listrik 1 bh x
4 Rek. Telpon 1 bh x
5 Biaya voucher/pulsa komunikasi 5 org x
6 Biaya administrasi (kertas, dll) 1 bh x
7 Biaya makan karyawan 4 org x

RINCIAN BIAYA PHO & FHO

NO. URAIAN ANALISA B

A. PHO
1 Rapat & pemeriksaan lapangan 1
2 Rapat & pemeriksaan lapangan 2
3 Dokumen PHO ( cetak dan copy )
4 Souvenir PHO
5 Biaya akomodasi, dll

B. FHO
1 Rapat & pemeriksaan lapangan 1
2 Rapat & pemeriksaan lapangan 2
3 Dokumen FHO ( cetak dan copy )
4 Souvenir FHO
5 Biaya akomodasi, dll
ANALISA BEBAN SUB TOTAL TOTAL

114,000,000
- bln x - -
- bln x - -
- bln x - -
- bln x - -
- bln x - -
19 bln x 5,000,000 -
19 bln x 5,000,000 95,000,000
- bln x - -
- bln x - -
- bln x - -
19 bln x 1,000,000 19,000,000

174,800,000
19 bln x 9,200,000 174,800,000 BBM + spare part
19 bln x 2,152,500 - BBM + spare part

201,500,000

- jam x - -
100 jam x 265,000 26,500,000
100 jam x 250,000 25,000,000
100 jam x 150,000 15,000,000
- jam x - -
- m3 x - -

- m' x - -
- m3 x - -
- m3 x - -
50 m3 x 300,000 15,000,000

- ton x 700,000 -
300 m2 x 250,000 75,000,000
1 Ls x 15,000,000 15,000,000
1 Ls x 15,000,000 15,000,000
- Ls x 15,000,000 - Hilang & rusak
1 Ls x 15,000,000 15,000,000

28,350,000
3 bln x 2,500,000 7,500,000
- bln x - -
3 bln x 1,500,000 4,500,000
3 bln x 2,500,000 7,500,000
3 bln x 200,000 3,000,000
3 bln x 750,000 2,250,000
3 bln x 300,000 3,600,000

JUMLAH 518,650,000

ANALISA BEBAN SUB TOTAL TOTAL

58,500,000
1 Ls x 25,000,000 25,000,000
1 Ls x 25,000,000 25,000,000
5 set x 200,000 1,000,000
5 Ls x 1,000,000 5,000,000
1 Ls x 2,500,000 2,500,000

83,500,000
1 Ls x 25,000,000 25,000,000
1 Ls x 50,000,000 50,000,000
5 set x 200,000 1,000,000
5 Ls x 1,000,000 5,000,000
1 Ls x 2,500,000 2,500,000

JUMLAH 142,000,000
BIAYA ADMINISTRASI UMUM (BAU)
PROYEK : Tol Semarang - Bawen Seksi 2

NO KODE
URAIAN BEBAN
URUT BEBAN
1 2 3

610.6 60000 BIAYA ADMINISTRASI PROYEK


1 61000 Gaji + Lembur Karyawan
1 Gaji Karyawan Terlampir
2 Lembur karyawan Terlampir
3 THR Karyawan Terlampir
4 Pesangon karyawan harian Terlampir
5 PPh (2%) Terlampir

2 62000 Administrasi Kantor


1 Kertas kalkir / kertas gambar
2 Alat Tulis Kantor, kertas A4, A3, dll
3 Biaya perawatan & service Fotocopy
4 Tinta / toner fotocopy
5 Formulir / cetakan
6 Komputer suplies
7 Tinta printer & tinta plotter
8 Koran / majalah
9 Biaya meterai 50

3 63000 Jamuan Tamu


1 Biaya jamuan tamu
2 Biaya jamuan untuk rapat
3 Jamuan Direksi

4 64000 EKBM (untuk kendaraan proyek)


1 EKBM

5 65000 Beban tender


1 Biaya kontrak

6 66000 Beban Peresmian / Upacara


1 Biaya selamatan

7 67000 Asuransi
1 Asuransi pekerjaan (CAR)
2 Asuransi tenaga kerja
3 Biaya keselamatan (spanduk, panflet, dll)
4 Biaya PPPK & pengobatan karyawan

8 68000 Perjalanan Dinas


1 GS (1 bulan 2 kali pp) 1
2 Manager (1 bulan 1 kali pp) 1
3 Staff Proyek (1 bulan 1 kali pp) 1
9 69000 Biaya Dokumentasi
1 Biaya cetak foto 30
2 Album foto 3
3 Biaya dokumentasi (foto udara, dll)

10 69010 Biaya Akomodasi


1 Biaya makan karyawan 37
2 Biaya makan Konsultan & Pengawas 4
3 Biaya makan & minum lembur 19
4 Air minum, gula, kopi, dll 1

11 69020 Pajak Daerah / Ijin Bangunan


1 Retribusi gal. gol C
2 Iuran kemasyarakatan
3 Koordinasi aparat keamanan (Satpol PP, patroli, dll)
4 Biaya perijinan daerah
ANALISA BEBAN SUB TOTAL

4 5

Terlampir 328,950,000
Terlampir 57,237,500
Terlampir -
Terlampir 36,150,000
Terlampir -

1,000 Lbr x Rp 7,500 7,500,000


3 bln x Rp 4,000,000 12,000,000
3 bln x Rp 1,500,000 4,500,000
3 bln x Rp 1,000,000 3,000,000
3 bln x Rp 1,000,000 3,000,000
3 bln x Rp 1,000,000 3,000,000
3 bln x Rp 1,500,000 4,500,000
3 bln x Rp 250,000 750,000
lbr x 3 bln x Rp 6,500 975,000

3 bln x Rp 5,000,000 15,000,000


3 bln x Rp 2,500,000 7,500,000
3 bln x Rp 5,000,000 15,000,000

1 ls x Rp 25,000,000 25,000,000

4 ls x Rp 30,000,000 120,000,000

0.100% x Rp - -
0.075% x Rp - -
1 bln x Rp 2,500,000 2,500,000
1 bln x Rp 7,500,000 7,500,000

org x 3 kali x Rp 750,000 2,250,000


org x 3 kali x Rp 400,000 1,200,000
org x 3 kali x Rp 250,000 750,000
lbr x 3 bln x Rp 2,000 180,000
bh x 3 bln x Rp 75,000 675,000
1 Ls x Rp 25,000,000 25,000,000

org x 3 bln x Rp 300,000 33,300,000


org x 3 bln x Rp 300,000 3,600,000
org x 3 bln x Rp 150,000 8,550,000
Ls x 3 bln x Rp 5,000,000 15,000,000

- m3 x Rp 1,500 -
3 bln x Rp 5,000,000 15,000,000
3 bln x Rp 10,000,000 30,000,000
- Ls x Rp - -

JUMLAH
TOTAL

422,337,500

39,225,000

37,500,000

25,000,000

120,000,000

10,000,000

4,200,000
25,855,000

60,450,000

45,000,000

789,567,500
PERHITUNGAN GAJI & LEMBUR KARYAWAN
JUMLAH
NO. URAIAN JUMLAH BULAN
PERSONIL
GAJI LEMBUR
1 2 3 4 5

A GAJI & LEMBUR :


1 General Superintendent 1 3 2
Deputy General Superintent 0 3 2
2 Commercial Manager 0 3 2
3 Staf Akuntasi dan Pajak 0 3 2
4 Staf Bagian Umum 0 3 2
5 Staf Bagian Kasir 1 3 2
6 Driver 2 3 2
7 Tenaga keamanan 3 3 2

8 Contract Adm. Manager / Measurement 0 3 2


9 Project Control Supervisor 1 3 2
10 Scheduler / Planner 1 3 2
11 Staf Contract Adm. & Cost control 1 3 2
12 Quantity Surveyor 1 3 2
13 Dokumentasi 0 3 2

14 Quality Control Manager 1 3 2


15 Pelaksana K3LM 0 3 2
16 Staf K3LM ( Adm. & tenaga medis ) 0 3 2
17 Staf Quality Control 1 3 2
18 Pembantu QC 1 3 2

19 Engineering Manager 1 3 2
20 Highway Engineer 0 3 2
21 Structure Engineer 0 3 2
22 Geodetic Engineer 1 3 2
23 System analysis 0 3 2
23 Drafter ( Highway & Structure ) 1 3 2
24 Surveyor 1 3 6
25 Pembantu Surveyor 1 3 6

26 Proc & Equipment Manager 1 3 2


27 Staf Logistik ( Administrasi ) 1 3 2
28 Staf Peralatan (administrasi) 0 3 2
29 Staf Gudang 1 3 2
30 Mekanik 1 3 2
31 Pembantu mekanik 1 3 2
32 Checker 1 3 2
33 Oilman 1 3 2

34 Earthwork & Pavement Manager 0 3 2


35 Pelaksana Tanah 1 3 2
36 Pelaksana Perkerasan 1 3 2
37 Pembantu Pelaksana 2 3 2
3
38 Drainage & Toll Gate Manager 0 3 2
39 Pelaksana Drainase 1 3 2
40 Pelaksana pek. Lain-lain 1 3 2
41 Pelaksana Gerbang Tol 0 3 2
42 Pelaksana ME & Rambu 0 3 2
43 Pembantu Pelaksana 2 3 2

44 Structure Manager 0 3 2
45 Pelaksana Jembatan 1 3 2
46 Pelaksana Upper pass dan box 1 3 2
47 Pembantu Pelaksana 1 3 2

SUB TOTAL A 37

B THR
1 THR ( 1 kali ) 0
SUB TOTAL B

C PESANGON
1 Pesangon PHL & Honorer 0
SUB TOTAL C
D PPh
1 PPh 0
SUB TOTAL D
TOTAL

CATATAN :
Personil tersebut diatas belum termasuk :
■ Flagman
■ Harian lapangan
percut

HARGA SATUAN JUMLAH BIAYA


GAJI LEMBUR JUMLAH GAJI LEMBUR
6 7 8=6+7 9=4x6 10=5x7

8,000,000 2,800,000 10,800,000 24,000,000 5,600,000


8,000,000 2,800,000 10,800,000 - -
5,000,000 1,250,000 6,250,000 - -
3,000,000 750,000 3,750,000 - -
2,500,000 625,000 3,125,000 - -
2,500,000 625,000 3,125,000 7,500,000 1,250,000
1,200,000 300,000 1,500,000 7,200,000 1,200,000
1,200,000 300,000 1,500,000 10,800,000 1,800,000

5,000,000 1,250,000 6,250,000 - -


3,000,000 750,000 3,750,000 9,000,000 1,500,000
3,000,000 750,000 3,750,000 9,000,000 1,500,000
3,000,000 750,000 3,750,000 9,000,000 1,500,000
2,500,000 625,000 3,125,000 7,500,000 1,250,000
1,750,000 437,500 2,187,500 - -
-
5,000,000 1,250,000 6,250,000 15,000,000 2,500,000
5,000,000 1,250,000 6,250,000 - -
1,750,000 437,500 2,187,500 - -
2,500,000 625,000 3,125,000 7,500,000 1,250,000
1,000,000 250,000 1,250,000 3,000,000 500,000
-
6,000,000 1,500,000 7,500,000 18,000,000 3,000,000
5,000,000 1,250,000 6,250,000 - -
5,000,000 1,250,000 6,250,000 - -
5,000,000 1,250,000 6,250,000 15,000,000 2,500,000
5,000,000 1,250,000 6,250,000 - -
2,000,000 500,000 2,500,000 6,000,000 1,000,000
2,000,000 500,000 2,500,000 6,000,000 3,000,000
1,000,000 250,000 1,250,000 3,000,000 1,500,000
-
5,000,000 1,250,000 6,250,000 15,000,000 2,500,000
3,000,000 750,000 3,750,000 9,000,000 1,500,000
3,000,000 750,000 3,750,000 - -
1,500,000 375,000 1,875,000 4,500,000 750,000
1,750,000 437,500 2,187,500 5,250,000 875,000
1,200,000 300,000 1,500,000 3,600,000 600,000
1,200,000 300,000 1,500,000 3,600,000 600,000
1,000,000 250,000 1,250,000 3,000,000 500,000
-
6,000,000 1,500,000 7,500,000 - -
5,000,000 1,250,000 6,250,000 15,000,000 2,500,000
5,000,000 1,250,000 6,250,000 15,000,000 2,500,000
2,500,000 625,000 3,125,000 15,000,000 2,500,000
-
6,000,000 1,500,000 7,500,000 - -
5,000,000 1,250,000 6,250,000 15,000,000 2,500,000
5,000,000 1,250,000 6,250,000 15,000,000 2,500,000
5,000,000 1,250,000 6,250,000 - -
5,000,000 1,250,000 6,250,000 - -
2,500,000 625,000 3,125,000 15,000,000 1,875,000
-
6,000,000 1,500,000 7,500,000 - -
5,000,000 1,250,000 6,250,000 15,000,000 1,875,000
5,000,000 1,250,000 6,250,000 15,000,000 1,875,000
2,500,000 625,000 3,125,000 7,500,000 937,500

179,050,000 46,362,500 225,412,500 328,950,000 57,237,500


AH BIAYA KETERANGAN
JUMLAH
11=9+10 12

29,600,000 8,000,000.00 2,800,000.00


- - -
- - -
- - -
- - -
8,750,000 2,500,000.00 625,000.00
8,400,000 2,400,000.00 600,000.00 2,400,000.00
12,600,000 3,600,000.00 900,000.00 3,600,000.00

- - -
10,500,000 3,000,000.00 750,000.00
10,500,000 3,000,000.00 750,000.00
10,500,000 3,000,000.00 750,000.00
8,750,000 2,500,000.00 625,000.00 2,500,000.00
- - - -
- -
17,500,000 5,000,000.00 1,250,000.00
- - -
- - -
8,750,000 2,500,000.00 625,000.00 2,500,000.00
3,500,000 1,000,000.00 250,000.00 1,000,000.00
- -
21,000,000 6,000,000.00 1,500,000.00
- - -
- - -
17,500,000 5,000,000.00 1,250,000.00
- - -
7,000,000 2,000,000.00 500,000.00 2,000,000.00
9,000,000 2,000,000.00 500,000.00 2,000,000.00
4,500,000 1,000,000.00 250,000.00 1,000,000.00
- -
17,500,000 5,000,000.00 1,250,000.00
10,500,000 3,000,000.00 750,000.00
- - -
5,250,000 1,500,000.00 375,000.00 1,500,000.00
6,125,000 1,750,000.00 437,500.00 1,750,000.00
4,200,000 1,200,000.00 300,000.00 1,200,000.00
4,200,000 1,200,000.00 300,000.00 1,200,000.00
3,500,000 1,000,000.00 250,000.00 1,000,000.00
- -
- - -
17,500,000 5,000,000.00 1,250,000.00
17,500,000 5,000,000.00 1,250,000.00
17,500,000 5,000,000.00 1,250,000.00 5,000,000.00
- -
- - -
17,500,000 5,000,000.00 1,250,000.00
17,500,000 5,000,000.00 1,250,000.00
- - -
- - -
16,875,000 5,000,000.00 1,250,000.00 5,000,000.00
- -
- - -
16,875,000 5,000,000.00 1,250,000.00
16,875,000 5,000,000.00 1,250,000.00
8,437,500 2,500,000.00 625,000.00 2,500,000.00

386,187,500 109,650,000.00 28,212,500.00 36,150,000.00

36,150,000
36,150,000

-
-
422,337,500
1
2

3
4

5
6

7
8
9

9
10
11
12
13
14

15

16
BIAYA PEMASARAN
PROYEK : Percut

NO KODE
URAIAN BEBAN ANALISA BEBAN
URUT BEBAN
1 2 3 4

610.7 BIAYA PEMASARAN


1 71000 Pengurusan Proyek :
a. Pengurusan UM 1 x
b. Pengurusan Termin 3 x
c. Pengurusan Retensi 1 x

2 72000 Pengembangan Perusahaan

3 73000 Contingencies :
ANALISA BEBAN SUB TOTAL TOTAL

4 5 6

42,500,000.00
10,000,000.00 10,000,000.00
7,500,000.00 22,500,000.00
10,000,000.00 10,000,000.00

JUMLAH 42,500,000
MASTER ANGGARAN PELAKSANAAN ( M.A.P )
Pembangunan Jalan Tol Semarang - Solo
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

JUMLAH ESTIMASI
NO URAIAN BIAYA ( %) KETERANGAN
( Rp )

I REALCOST DATA PROYEK


a. Lokasi : Kota Semarang
1 #REF! #REF! #REF! b. Pemilik : PT. Jasa Marga
2 #REF! #REF! #REF! c. Perencana :
3 #REF! #REF! #REF! d. Waktu Pelaksanaan : 395 hari kalender
4 #REF! #REF! #REF! e. Masa Pemeliharaan : 1,095 hari kalender
5 #REF! #REF! #REF! f. Sifat Tender : Tender Terbatas
6 #REF! #REF! #REF! g. Sumber Dana :
7 #REF! #REF! #REF! h. Volume Pekerjaan : 4.950 kilometer
8 #REF! #REF! #REF!
9 #REF! #REF! #REF! KONDISI PENAWARAN
10 #REF! #REF! #REF! a. Uang Muka :
11 #REF! - 0.00% b. Pembayaran :
12 #REF! #REF! #REF! c. Denda :
13 #REF! #REF! #REF! d. Retensi :
14 #REF! - 0.00% e. Jaminan Pelaksanaan :
15 #REF! - 0.00% f. Pemasukan SPH :
16 #REF! #REF! #REF!

JUMLAH REAL COST #REF! #REF!


OVERHEAD :
II INDIRECT COST a. BAU - Pusat : #REF!
1 610.04 - Peralatan 137,943,400.00 #REF! b. BAU - Divisi : #REF!
2 610.05 - Pers / Penyelesaian 1,187,800,000.00 #REF! c. Penyusutan : #REF!
3 610.06 - BAU Proyek 789,567,500.00 #REF! d. Bunga Bank : #REF!
4 610.07 - Rupa - Rupa 42,500,000.00 #REF!
5 610.08 - B a n k #REF! #REF! Jumlah OVERHEAD : #REF!

JUMLAH INDIRECT COST #REF! #REF!


TOTAL DIRECT COST / BK #REF! #REF! LAIN LAIN :
e. Resiko : 0.00%
III INFORMASI - PAGU 342,671,000,000.00 Err:508 g. Pph : 0.00%
f. Pemasaran : #REF!
g. KMK : #REF!
IV ESTIMASI / ALTERNATIF UNTUK PENAWARAN Jumlah OVERHEAD : #REF!
Apabila Mark Up, dengan rencana :

( % ) TERHADAP
RENCANA KEPUTUSAN
OH PPH
LABA LABA
TOTAL PU ( Rp ) BK / PU
PENAWARAN TERMASUK PPN O-
BERSIH KOTOR 10%
(%) E MANAJEMEN

1 #REF! 3.00% 0.50% #REF! #REF! #REF! #REF! #REF!


2 #REF! 3.00% 1.00% #REF! #REF! #REF! #REF! #REF!
3 #REF! 3.00% 1.50% #REF! #REF! #REF! #REF! #REF!
4 #REF! 3.00% 2.00% #REF! #REF! #REF! #REF! #REF!
5 #REF! 3.00% 2.50% #REF! #REF! #REF! #REF! #REF!
6 #REF! 3.00% 3.00% #REF! #REF! #REF! #REF! #REF!
7 #REF! 3.00% 3.50% #REF! #REF! #REF! #REF! #REF!
8 #REF! 3.00% 4.00% #REF! #REF! #REF! #REF! #REF!
9 #REF! 3.00% 4.50% #REF! #REF! #REF! #REF! #REF!
10 #REF! 3.00% 5.00% #REF! #REF! #REF! #REF! #REF!
11 #REF! 3.00% 5.50% #REF! #REF! #REF! #REF! #REF!
12 #REF! 3.00% 6.00% #REF! #REF! #REF! #REF! #REF!
13 #REF! 3.00% 6.50% #REF! #REF! #REF! #REF! #REF!
CATATAN : Jakarta, 13 Nop 08
Material Disupplai TLKJ Disetujui Divisi Sipil
- BETON
- GIRDER
- BESI

Ir. I Gusti Ngurah Putra, MM Ir. Desy Arryani, MM


Dir - III Kepala

02/24/202104:35:58
REKAPITULASI DAFTAR KUANTITAS DAN HARGA

REVISI RENCANA TEKNIK AKHIR JALAN TOL SEMARANG SOLO TAHAP I


RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3 + 3+525 - STA. 8+475

JUMLAH HARGA
NO URAIAN PENAWARAN
( Rp )

BAB 1 UMUM #REF!


BAB 2 PEMBERSIHAN TEMPAT KERJA #REF!
BAB 3 PEMBONGKARAN #REF!
BAB 4 PEKERJAAN TANAH #REF!
BAB 5 GALIAN STRUKTUR #REF!
BAB 6 DRAINASE #REF!
BAB 7 SUBGRADE #REF!
BAB 8 LAPIS PONDASI AGREGAT #REF!
BAB 9 PERKERASAN #REF!
BAB 10 STRUKTUR BETON #REF!
BAB 11 PEKERJAAN BAJA STRUKTURAL -
BAB 12 PEKERJAAN LAIN-LAIN #REF!
BAB 13 PENCAHAYAAN, LAMPU LALU LINTAS #REF!
BAB 14 PEKERJAAN PLAZA TOL -
BAB 15 PENGALIHAN DAN PERLINDUNGAN UTILITAS YANG ADA -
BAB 16 PEKERJAAN FASILITAS TOL DAN KANTOR GERBANG TOL #REF!

(A) JUMLAH HARGA PENAWARAN #REF!


(B) PAJAK PERTAMBAHAN NILAI ( PPN ) = 10% x ( A ) #REF!
(C) JUMLAH TOTAL HARGA PENAWARAN = A + B #REF!

Terbilang :

Tanda Tangan : Atas Nama :

Jabatan : Tanggal :
DAFTAR KUANTITAS DAN HARGA

K AKHIR JALAN TOL SEMARANG SOLO TAHAP I


BAWEN SEKSI II GEDAWANG - SUSUKAN
3 + 3+525 - STA. 8+475

JUMLAH HARGA
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

BAB 1 UMUM

1.19 Pemeliharaan dan Perlindungan Lalu Lintas lump sum #REF! 1.00 #REF!
1.20 (1) Laboratorium lump sum #REF! 1.00 #REF!
1.20 (2) Mobilisasi ( yang tidak tercakup pada 1.20(1) ) lump sum #REF! 1.00 #REF!
1.26 Pekerjaan dan Penanganan Aliran Air yang Sudah Ada lump sum #REF! 1.00 #REF!

TOTAL HARGA PENAWARAN UNTUK BAB 1 #REF!


( Pindahkan ke Rekapitulasi )
BAB 2 PEMBERSIHAN TEMPAT KERJA

2.01 Pembersihan Tempat Kerja m2 #REF! 253,478.52 #REF!

TOTAL HARGA PENAWARAN UNTUK BAB 2 #REF!


( Pindahkan ke Rekapitulasi )
BAB 3 PEMBONGKARAN

3.01 (1) Pembongkaran Pasangan Batu atau Struktur Beton m3 #REF! 817.57 #REF!
3.01 (2) Pembongkaran Kerb m1 #REF! 50.00 #REF!
3.01 (3) Pembongkaran Perkerasan Jalan Aspal atau Beton m2 #REF! 2,998.77 #REF!
3.01 (4) Pembongkaran Rambu Lalu Lintas buah #REF! 2.00 #REF!
3.01 (5) Pembongkaran Guardrail m' #REF! 40.00 #REF!

TOTAL HARGA PENAWARAN UNTUK BAB 3 #REF!


( Pindahkan ke Rekapitulasi )
BAB 4 PEKERJAAN TANAH

4.03 (1) Galian Biasa untuk Timbunan m3 #REF! 1,542,493.11 #REF!


4.03 (1) b Galian Biasa untuk Timbunan Diluar Proyek Seksi 2 m3 #REF! - #REF!
4.03 (2) Galian Biasa untuk Dibuang m3 #REF! 178,510.34 #REF!
4.04 Galian Batu ( Rock Excavation ) m3 - -
4.05 (1) Borrow Material m3 #REF! 879,686.34 #REF!
4.05 (2) Borrow Material asal proyek Seksi II m3 - - -
4.08 (1) Free - Draining Material m3 #REF! - #REF!
4.08 (2) Fabric Mat m3 - - -
4.09 Urugan Material Berbutir ( Granular Backfill ) m3 #REF! 1,274.14 #REF!
4.10 Urugan Rembesan ( Permeable Backfill ) m3 #REF! - #REF!
4.11 (1) Drainase Pasir Vertikal m1 - - -
4.11 (2) Drainase Pasir Horisontal m3 - - -
4.12 Pasangan Batu Kosong ( Blinding Stone ) m3 #REF! 75.93 #REF!
4.13 Urugan Batuan Untuk Shear Key m3 - - -

TOTAL HARGA PENAWARAN UNTUK BAB 4 #REF!


( Pindahkan ke Rekapitulasi )
BAB 5 GALIAN STRUKTUR

5.01 (1) Penggalian Struktur sampai kedalaman tidak lebih dari 2 m m3 #REF! 9,166.42 #REF!
5.01 (2) Penggalian Struktur sampai kedalaman lebih dari 2 m, tapi tidak lebih dari 4 m m3 #REF! 5,519.78 #REF!
5.01 (3) Penggalian Struktur sampai kedalaman lebih dari 4 m m3 #REF! 5,318.09 #REF!
5.01 (4) Tambahan biaya galian pada tempat yang mengandung air tanah m3 #REF! - #REF!
5.01 (5) Tambahan biaya galian di atas 5.01 (1) sampai 5.01 (4) untuk galian m3 #REF! - #REF!
dalam batuan

TOTAL HARGA PENAWARAN UNTUK BAB 5 #REF!


( Pindahkan ke Rekapitulasi )

Page 30 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

BAB 6 DRAINASE

6.05 (1) Pipa Gorong-gorong Beton Tak Bertulang, dia. 40 cm m1 #REF! 2,427.62 #REF!
6.05 (2) Pipa Gorong-gorong Beton Bertulang, dia. 40 cm, Tipe A m1 - -
6.05 (3) Pipa Gorong-gorong Beton Bertulang, dia. 40 cm, Tipe B m1 - -
6.05 (4) Pipa Gorong-gorong Beton Bertulang, dia. 50 cm, Tipe A m1 - -
6.05 (5) Pipa Gorong-gorong Beton Bertulang, dia. 50 cm, Tipe B m1 - -
6.05 (6) Pipa Gorong-gorong Beton Bertulang, dia. 60 cm, Tipe A m1 #REF! 105.27 #REF!
6.05 (7) Pipa Gorong-gorong Beton Bertulang, dia. 60 cm, Tipe B m1 #REF! 55.48 #REF!
6.05 (8) Pipa Gorong-gorong Beton Bertulang, dia. 80 cm, Tipe A m1 - -
6.05 (9) Pipa Gorong-gorong Beton Bertulang, dia. 80 cm, Tipe B m1 - -
6.05 (10) Pipa Gorong-gorong Beton Bertulang, dia. 100 cm, Tipe A m1 #REF! 434.97 #REF!
6.05 (11) Pipa Gorong-gorong Beton Bertulang, dia. 100 cm, Tipe B m1 - -
6.05 (12) Pipa Gorong-gorong Beton Bertulang, dia. 120 cm, Tipe A m1 - -
6.05 (13) Pipa Gorong-gorong Beton Bertulang, dia. 120 cm, Tipe B m1 - -
6.05 (14) Pipa Gorong-gorong Beton Bertulang, dia. 40 cm, Tipe A m1 - -
6.05 (15) Pipa Gorong-gorong Beton Bertulang, dia. 40 cm, Tipe B m1 - -
6.05 (16) Pipa Gorong-gorong Beton Bertulang, dia. 60 cm, Tipe A m1 - -
6.05 (17) Pipa Gorong-gorong Beton Bertulang, dia. 60 cm, Tipe B m1 - -
6.05 (18) Pipa Gorong-gorong Beton Bertulang, dia. 80 cm, Tipe A m1 - -
6.05 (19) Pipa Gorong-gorong Beton Bertulang, dia. 80 cm, Tipe B m1 - -
6.05 (20) Pipa Gorong-gorong Beton Bertulang, 2 dia. 100 cm, Tipe C m1 #REF! 226.98 #REF!
6.05 (21) Pipa Gorong-gorong Beton Bertulang, 2 dia. 100 cm, Tipe D m1 - -
6.06 (1a) Saluran, Tipe DS - 1 m1 #REF! 190.00 #REF!
6.06 (1) Saluran, Tipe DS - 3 m1 #REF! 668.00 #REF!
6.06 (2) Saluran, Tipe DS - 3A m1 #REF! - #REF!
6.06 (2a) Saluran, Tipe DS - 3B m1 #REF! 5.00 #REF!
6.06 (3) Saluran, Tipe DS - 8 m1 #REF! 10,731.00 #REF!
6.06 (4) Saluran Beton dan Penutup, Tipe DC - 1 buah #REF! 190.00 #REF!
6.06 (5) Saluran Beton dan Penutup, Tipe DC - 2 buah -
6.06 (6) Saluran Beton dan Penutup, Tipe DC - 3 buah -
6.06 (7) Saluran Beton dan Penutup, Tipe DC - 4 buah -
6.06 (8) Saluran Beton dan Penutup, Tipe DC - 5 buah #REF! 14.00 #REF!
6.06 (9) Saluran Beton dan Penutup, Tipe DC - 6 buah -
6.06 (10) Saluran Beton dan Penutup, Tipe DC - 7 buah -
6.06 (11) Saluran Beton dan Penutup, Tipe DC - 8 buah -
6.06 (12) Saluran Beton dan Penutup, Tipe DC - 9 buah -
6.06 (13) Saluran Beton dan Penutup, Tipe DC - 10 buah -
6.06 (14) Saluran Beton dan Penutup, Tipe DC - 11 buah -
6.06 (15) Saluran Beton dan Penutup, Tipe DC - 12 buah -
6.06 (16) Saluran Beton dan Penutup, Tipe DC - 13 buah -
6.06 (17) Saluran Beton dan Penutup, Tipe DC - 14 buah -
6.06 (18) Saluran Beton dan Penutup, Tipe DC - 15 buah -
6.06 (19) Saluran Beton dan Penutup, Tipe DC - 16 buah -
6.06 (20) Saluran Beton dan Penutup, Tipe DC - 17 buah -
6.06 (21) Saluran Beton dan Penutup, Tipe DC - 18 buah -
6.06 (22) Saluran Beton dan Penutup, Tipe DC - 19 buah -
6.06 (23) Saluran Beton dan Penutup, Tipe DC - 20 buah -
6.06 (24) Saluran Beton dan Penutup, Tipe DC - 21 buah -
6.06 (25) Inlet Drain, Tipe DI-1 buah #REF! 7.00 #REF!
6.06 (26) Inlet Drain, Tipe DI-2 buah - -
6.06 (27) Inlet Drain, Tipe DI-3 buah #REF! 3.00 #REF!
6.06 (28) Inlet Drain, Tipe DI-4 buah -
6.06 (29) Inlet Drain, Tipe DI-5 buah -
6.06 (30) Inlet Drain, Tipe DI-6 buah -
6.06 (31) Inlet Drain, Tipe DI-7 buah -

Page 31 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

6.06 (32) Outlet Drain, Tipe DO-1 buah #REF! 7.00 #REF!
6.06 (33) Outlet Drain, Tipe DO-2 buah - -
6.06 (34) Outlet Drain, Tipe DO-3 buah #REF! 3.00 #REF!
6.06 (35) Outlet Drain, Tipe DO-4 buah -
6.06 (36) Outlet Drain, Tipe DO-5 buah -
6.06 (37) Outlet Drain, Tipe DO-6 buah -
6.06 (38) Outlet Drain, Tipe DO-7 buah -
6.06 (39) Outlet Drain, Tipe DO-8 buah -
6.07 (1) Selokan Pasangan Batu Mortar ( Mortared Rubble ), Tipe DS-2 m1 - -
6.07 (2) Selokan Pasangan Batu Mortar ( Mortared Rubble ), Tipe DS-4 m1 #REF! 2,264.00 #REF!
6.07 (3) Selokan Pasangan Batu Mortar ( Mortared Rubble ), Tipe DS-5 m1 #REF! 4,652.00 #REF!
6.07 (4) Selokan Pasangan Batu Mortar ( Mortared Rubble ), Tipe DS-6 m1 - -
6.07 (5) Selokan Pasangan Batu Mortar ( Mortared Rubble ), Tipe DS-7 m1 - -
6.07 (6) Selokan Pasangan Batu Mortar ( Mortared Rubble ), Tipe DS-9 m1 - -
6.07 (7) Pasangan Batu Mortar ( Mortared Rubble ), Tipe DS-10 m1 #REF! 460.90 #REF!
6.07 (8) Bangunan Terjun Tegak m3 - -
Pasangan Batu Kali Untuk Inlet & Outlet pada Box Culvert / Wing Wall dan
6.07 (9) m3 #REF! 3,109.24 #REF!
gorong - .gorong
6.07 (10) Pasangan Batu Kosong ( Grouted RipRap ) m3 - -
6.08 (1) Pipa Drainase, dia. 15 cm, dengan perlengkapan sambungan dan penyangga m1 #REF! 143.00 #REF!
6.08 (2) Pipa Drainase, dia. 20 cm, dengan perlengkapan sambungan dan penyangga m1 #REF! 1,110.98 #REF!
6.08 (3) Deck Drain beserta asessorisnya, Tipe 1 buah #REF! 286.00 #REF!
6.08 (4) Deck Drain beserta asessorisnya, Tipe 2 buah - -
6.09 (1) Bahan Porous untuk Penimbunan atau Bahan Penyaring ( Filter ) m3 #REF! 3,317.08 #REF!
6.09 (2) Anyaman Filter Plastik ( Geotextile ) m2 - -
Pipa Berlubang Banyak (Perforated Pipe) untuk Pekerjaan Drainase Bawah
6.09 (3) a m 1
#REF! 7,524.75 #REF!
Permukaan Ø 6 Inch
Pipa Berlubang Banyak (Perforated Pipe) untuk Kolektor Pengumpul
6.09 (3) b m1 #REF! 288.00 #REF!
Sumber Air Ø 4 Inch
6.09 (4) Geotextile Non Woven m2 #REF! 20,325.57 #REF!

TOTAL HARGA PENAWARAN UNTUK BAB 6 #REF!


( Pindahkan ke Rekapitulasi )
BAB 7 SUBGRADE

7.01 Persiapan Tanah Dasar m2 #REF! 131,373.00 #REF!

TOTAL HARGA PENAWARAN UNTUK BAB 7 #REF!


( Pindahkan ke Rekapitulasi )
BAB 8 LAPIS PONDASI AGREGAT (SUBBASE)

8.01 (1) Lapis Pondasi Agregat Kelas A m3 #REF! 462.00 #REF!


8.01 (2) Lapis Pondasi Agregat Kelas B m3 #REF! 14,530.68 #REF!

TOTAL HARGA PENAWARAN UNTUK BAB 8 #REF!


( Pindahkan ke Rekapitulasi )
BAB 9 PERKERASAN

9.02 Pengerukan Perkerasan Lama ( Scarify Old Pavement ) m2 - -


9.03 Penambahan perkerasan existing m2 #REF! - #REF!
9.04 Bitumen Lapis Resap Pengikat ( Prime Coat ) kg #REF! 67,825.15 #REF!
9.05 Bitumen Lapis Pengikat (Tack Coat ) kg #REF! 5,948.26 #REF!
9.06 Seal coat ( grade RC-250 ) m2 - - -
9.07 (1) Asphalt Treated Base Course ton #REF! 9,163.03 #REF!
9.07 (2) Asphalt Concrete Binder Course ton #REF! 346.00 #REF!
9.07 (3) Asphalt Concrete Wearing Course ton #REF! 1,398.36 #REF!

Page 32 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

9.07 (4) Semen Aspal ton #REF! 611.03 #REF!


9.08 (1) Perkerasan Beton ( t = 31 cm ) m2 #REF! 70,008.00 #REF!
9.08 (2) Perkerasan Beton ( t = 31 cm ), Double Wire Mesh m2 #REF! - #REF!
9.08 (3) Perkerasan Beton ( t = 31 cm ), Single Wire Mesh m2 #REF! - #REF!
9.08 (4) Lapis Beton Semen Pondasi Bawah (Cement Treated Sus Base / CTSB) m3 #REF! - #REF!
9.09 (1) Lean Concrete ( t = 10 cm ) m2 #REF! 88,084.00 #REF!
9.09 (2) Sand Bedding ( t = 6 cm ) m2 - - -

TOTAL HARGA PENAWARAN UNTUK BAB 9 #REF!


( Pindahkan ke Rekapitulasi )
BAB 10 STRUKTUR BETON

10.01 (1) Beton Kelas A - 1 m3 - - -


10.01 (2) Beton Kelas A - 2 m3 - - -
10.01 (3) Beton Kelas A - 3 m3 - - -
10.01 (4) Beton Kelas B - 1 m3 #REF! 5,230.66 #REF!
10.01 (5) Beton Kelas B - 2 m3 - - -
10.01 (6) Beton Kelas B - 3 m3 - - -
10.01 (7) Beton Kelas C - 1 m3 #REF! 7,686.42 #REF!
10.01 (8) Beton Kelas C - 2 m3 #REF! 786.66 #REF!
10.01 (9) Beton Kelas D m3 #REF! 34.28 #REF!
10.01 (10) Beton Kelas E m3 #REF! 875.80 #REF!
10.01 (11) Asphaltic Joint Filter, tebal 20 cm m2 - - -
10.01 (12) Beton Kelas B - B m3 #REF! 9,726.64 #REF!
10.02 (1) Batang Baja Tulangan Polos kg #REF! 980.66 #REF!
10.02 (2) Batang Baja Tulangan Ulir kg #REF! 3,432,539.17 #REF!
10.02(3) Anchor Bar + Anchor Cap dia 32 mm ( Fix &Move ) & Accessories buah #REF! 293.00 #REF!
10.02(4) Anchor Bar + Anchor Cap dia 25 mm ( Fix &Move ) & Accessories buah #REF! 92.00 #REF!
10.03 (1) a Pengadaan dan Pemasangan P.C.I Girder, bentang 16,00 m buah #REF! 12.00 #REF!
10.03 (1) b Pengadaan dan Pemasangan P.C.C Girder, bentang 16,00 m buah #REF! 8.00 #REF!
10.03 (2) a Pengadaan dan Pemasangan P.C.I Girder, bentang 20,00 m buah #REF! - #REF!
10.03 (2) b Pengadaan dan Pemasangan P.C.C Girder, bentang 20,00 m buah - - -
10.03 (3) a Pengadaan dan Pemasangan P.C.I Girder, bentang 25.00 m buah #REF! 6.00 #REF!
10.03 (3) b Pengadaan dan Pemasangan P.C.C Girder, bentang 25.00 m buah #REF! 4.00 #REF!
10.03 (4) a Pengadaan dan Pemasangan P.C.I Girder, bentang 30.6 m buah #REF! 14.00 #REF!
10.03 (4) b Pengadaan dan Pemasangan P.C.C Girder, bentang 30.6 m buah #REF! 8.00 #REF!
10.03 (4) c Pengadaan dan Pemasangan P.C.I Girder, bentang 35 m buah #REF! - #REF!
10.03 (5) a Pengadaan dan Pemasangan P.C.I Girder, bentang 38,00 m buah #REF! - #REF!
10.03 (5) b Pengadaan dan Pemasangan P.C.C Girder, bentang 38,00 m buah - - -
10.03 (6) a Pengadaan dan Pemasangan P.C.I Girder, bentang 40,00 m buah #REF! 3.00 #REF!
10.03 (6) b Pengadaan dan Pemasangan P.C.C Girder, bentang 40.00 m buah #REF! 2.00 #REF!
10.03 (6) c Pengadaan P.C.I Girder, bentang 40,60 m untuk Jembatan Banyumanik I buah #REF! 120.00 #REF!
10.03 (6) d Lounching P.C.I Girder, bentang 40,60 m untuk Jembatan Banyumanik I dan buah #REF! 120.00 #REF!
10.03 (7) Plat Precetak ( Concrete Plate ) m2 #REF! 7,525.61 #REF!
10.04.(1) Penyediaan tiang pancang mini ( mini pile ) precast, 25 cm x 25 cm m1 #REF! 7,695.00 #REF!
10.04.(2) Pemancangan tiang pancang mini ( mini pile ) precast, 25 cm x 25 cm m1 #REF! 7,695.00 #REF!
Penyediaan & Pemancangan tiang pancang mini ( mini pile ) precast untuk
10.04.(3) m1 #REF! 48.00 #REF!
test 25 cm x 25 cm
10.04 (4) Penyediaan tiang pancang beton bertulang precast, 35 cm x 35 cm m 1
#REF! - #REF!
10.04 (5) Pemancangan tiang pancang beton bertulang precast, 35 cm x 35 cm m1 #REF! - #REF!
Penyediaan & Pemancangan tiang pancang beton bertulang precast untuk
10.04 (6) m1 #REF! - #REF!
test 35 cm x 35 cm
10.05 (1) Penyediaan Tiang Pancang Beton Bulat Pretensioned, dia 50 cm m1 #REF! 7,850.00 #REF!
10.05 (2) Pemancangan Tiang Pancang Beton Bulat Pretensioned, dia 50 cm m1 #REF! 7,850.00 #REF!
Penyediaan & Pemancangan Tiang Pancang Beton Bulat Pretensioned, Pile
10.05 (3) m 1
#REF! 90.00 #REF!
Test, dia 50 cm

Page 33 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

10.05 (4) Penyediaan Tiang Pancang Beton Bulat Pretensioned, dia 60 cm m1 #REF! - #REF!
10.05 (5) Pemancangan Tiang Pancang Beton Bulat Pretensioned, dia 60 cm m1 #REF! - #REF!
Penyediaan & Pemancangan Tiang Pancang Beton Bulat Pretensioned, Pile
10.05 (6) m1 #REF! - #REF!
Test, dia 60 cm
10.05 (7) Pengeboran awal untuk tiang pancang ( dry preboring ) m1 #REF! - #REF!
10.06 (1) Penyediaan tiang pancang baja di 50 cm, T=9 cm m1 #REF! - #REF!
10.06 (2) Pemancangan tiang pancang baja ukuran dia. 50 cm m1 -
10.07 (1) Tiang bor beton cast-in-place, dia. 50 cm m1 - -
10.07 (2) Tiang bor beton cast-in-place, dia. 60 cm m1 - -
10.07 (3) Tiang bor beton cast-in-place, dia. 80 cm m1 - -
10.07 (4) Tiang bor beton cast-in-place, dia. 100 cm m1 #REF! - #REF!
10.07 (5) Tiang bor beton cast-in-place, dia. 120 cm m1 #REF! 3,275.00 #REF!
10.07 (6) Tiang bor beton cast-in-place, dia. 150 cm m1 #REF! - #REF!
10.07 (7) Tiang bor beton cast-in-place, dia. 180 cm m1 #REF! - #REF!
10.07 (8) Tiang bor beton cast-in-place, dia. 200 cm m1 #REF! - #REF!
10.07 (9) Tiang bor beton cast-in-place, dia. 240 cm m1 #REF! - #REF!
10.07 (10) Tes pembebanan, 2,5 kali beban perencanaan buah - - -
10.07 (10) a Tes pembebanan, 2 kali beban perencanaan secara Statis buah #REF! 2.00 #REF!
10.07 (10) b Tes pembebanan tiang, secara Dinamis buah #REF! 11.00 #REF!
10.07 (11) Tiang Bor Baja Diameter 100 cm m1 -
10.07 (12) Portal baja WF kg -
10.08 Pemboran percobaan m1 -
10.09 (1) Sambungan Ekspansi (Expansion Joint), tipe A m1 #REF! 96.00 #REF!
10.09 (2) Sambungan Ekspansi (Expansion Joint), tipe B m1 #REF! - #REF!
10.09 (3) Sambungan Ekspansi (Expansion Joint), tipe C1 ( celah = 2 cm ) m1 #REF! - #REF!
10.09 (4) Sambungan Ekspansi (Expansion Joint), tipe C2 ( celah = 3 cm ) m1 #REF! - #REF!
10.09 (5) Sambungan Ekspansi (Expansion Joint), tipe C3 ( celah = 4 cm ) m1 #REF! - #REF!
10.09 (6) Sambungan Ekspansi (Expansion Joint), tipe C4 ( celah = 5 cm ) m1 #REF! - #REF!
10.09 (7) Sambungan Ekspansi (Expansion Joint), tipe D m1 #REF! - #REF!
10.09 (8) Sambungan Ekspansi (Expansion Joint), tipe E m1 #REF! - #REF!
10.09 (9) Modular Expantion Joint 3 Seals m1 #REF! 75.60 #REF!
10.09 (10) Modular Expantion Joint 1 Seals m1 #REF! - #REF!
10.09 (11) Rubber Expansion Joint Type Fixed 20 m1 #REF! 75.60 #REF!
10.09 (12) Rubber Expansion Joint Type Fixed 50 m1 #REF! - #REF!
10.09 (13) Rubber Expansion Joint Type Fixed 100 m1 - -
10.10 (1) Metal Bearing Shoe, type A buah #REF! - #REF!
10.10 (1) a Metal Bearing Shoe, type B buah #REF! 36.00 #REF!
10.10 (1) b Metal Bearing Shoe, type C buah #REF! - #REF!
10.10 (1) c Metal Bearing Shoe, type D buah #REF! - #REF!
10.10 (1) d Metal Bearing Shoe, type E buah #REF! - #REF!
10.10 (1) f Metal Bearing Shoe, type F, type Fixed buah #REF! - #REF!
10.10 (2) Bearing Pad dengan asesori ukuran (300 x 300 x 30 mm) buah #REF! - #REF!
10.10 (3) Bearing Pad dengan asesori ukuran (300 x 350 x 36 mm) buah #REF! 40.00 #REF!
10.10 (4) Bearing Pad dengan asesori ukuran (300 x 350 x 39 mm) buah #REF! - #REF!
10.10 (5) Bearing Pad dengan asesori ukuran (400 x 350 x 39 mm) buah #REF! 54.00 #REF!
10.10 (5) a Bearing Pad dengan asesori ukuran (400 x 350 x 39 mm) + taper plate buah #REF! - #REF!
10.10 (6) Bearing Pad dengan asesori ukuran (450 x 400 x 35 mm) buah #REF! - #REF!
10.10 (7) Bearing Pad dengan asesori ukuran (200 x 200 x 20 mm) buah #REF! - #REF!
10.10 (8) Bearing Pad dengan asesori ukuran (400 x 400 x 39 mm) buah #REF! 20.00 #REF!
10.10 (9) Bearing Pad dengan asesori ukuran (400 x 400 x 40 mm) buah #REF! - #REF!
10.10 (10) Bearing Pad dengan asesori ukuran (450 x 400 x 52 mm) buah #REF! 72.00 #REF!
10.10 (10) a Bearing Pad dengan asesori ukuran (450 x 400 x 52 mm) + taper plate buah #REF! - #REF!
10.10 (11) Bearing Pad dengan asesori ukuran (500 x 450 x 54 mm) buah #REF! - #REF!
10.10 (13) Rubber Sheet m2 -

Page 34 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

10.11 Sheet Pile / Turap Beton m1 - - -

TOTAL HARGA PENAWARAN UNTUK BAB 10 #REF!


( Pindahkan ke Rekapitulasi )
BAB 11 PEKERJAAN BAJA STRUKTURAL

11.01(01) Penyediaan Bahan Baja Jembatan ton - - -


11.01(02) Pabrikasi Bahan Baja Jembatan ton - - -
11.01(03) Penyetelan Bahan Baja Jembatan ton - - -
11.02(01) Pekerjaan Baja Struktur untuk Fasilitas Tol kg - - -
11.02(02) Erection kg - - -

TOTAL HARGA PENAWARAN UNTUK BAB 11 -


( Pindahkan ke Rekapitulasi )
BAB 12 PEKERJAAN LAIN-LAIN

12.01 (1) Pohon ( Lansekap lingkungan Jalan ) buah - - -


12.01 (2) Semak / Perdu Lumpsump -
12.01 (3) Solid Sodding m2 #REF! 250,947.00 #REF!
12.01 (4) Strip Sodding m2 -
12.02 (1) Pasangan Batu Kali untuk Retaining Wall m2 #REF! - #REF!
12.04 (1) Deliniator tipe A buah #REF! - #REF!
12.04 (2) Deliniator tipe B buah #REF! - #REF!
12.05 (1) Guardrail, tipe A m1 #REF! 4,254.00 #REF!
12.05 (2) End Section Guardrail buah #REF! 30.00 #REF!
12.05 (3) Chainlink fence m1 #REF! 429.80 #REF!
12.05 (4) Railing fence m1 #REF! - #REF!
12.06 (1) Rambu Pengaturan dan Peringatan, Tipe A-1 buah #REF! 11.00 #REF!
12.06 (2) Rambu Pengaturan dan Peringatan, Tipe A-2 buah #REF! 12.00 #REF!
12.06 (3) Rambu Pengaturan dan Peringatan, Tipe B-1 buah - - -
12.06 (4) Rambu Pengaturan dan Peringatan, Tipe B-2 buah - - -
12.06 (5) Rambu Pengaturan dan Peringatan, Tipe C buah #REF! 27.00 #REF!
12.07 (1) Rambu Petunjuk, Peringatan dan Larangan Tipe A-1 buah #REF! 11.00 #REF!
12.07 (2) Rambu Petunjuk, Peringatan dan Larangan Tipe A-2 buah #REF! 3.00 #REF!
12.07 (3) Rambu Petunjuk, Peringatan dan Larangan Tipe A-3 buah #REF! 8.00 #REF!
12.07 (4) Rambu Petunjuk, Peringatan dan Larangan Tipe A-4 buah - - -
12.07 (5) Rambu Petunjuk, Peringatan dan Larangan Tipe A-5 buah - - -
12.07 (6) Rambu Petunjuk, Peringatan dan Larangan Tipe B-1 buah - - -
12.07 (7) Rambu Petunjuk, Peringatan dan Larangan Tipe B-2 buah - - -
12.07 (8) Rambu Petunjuk, Peringatan dan Larangan Tipe C buah - - -
12.08 (1) Marka Jalan Tipe 1 m2 #REF! 3,632.92 #REF!
12.08 (2) Marka Jalan Tipe 2 m2 #REF! - #REF!
12.08 (3) Rumble Strips m2 #REF! - #REF!
12.09 (1) Guide Post, Tipe A buah #REF! 288.00 #REF!
12.09 (2) Guide Post, Tipe B buah #REF! 554.00 #REF!
12.09 (3) Patok Damija, Tipe A buah - - -
12.09 (4) Patok Damija, Tipe B buah - - -
12.09 (5) Kilometer Post buah #REF! 26.00 #REF!
12.10 (1) Concrete Barrier, tipe-A m1 #REF! 4,598.00 #REF!
12.10 (2) Concrete Barrier, tipe-B m1 #REF! 358.00 #REF!
12.10 (3) Concrete Barrier, tipe-C m1 - - -
12.10 (4) Concrete Barrier, tipe-D m1 - - -
12.11 (1) Kerb Beton, Tipe-A m1 #REF! 774.47 #REF!
12.11 (2) Kerb Beton, Tipe-B m1 #REF! - #REF!
12.12 (1) Pagar ROW, Tipe 1 ( Panel Beton ) m1 #REF! 3,951.00 #REF!
12.12 (2) Pagar ROW, Tipe 2 ( Kawat Berduri ) m1 #REF! 5,765.00 #REF!

Page 35 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

12.12 (3) Pagar ROW, Tipe 3 ( BRC ) m1 #REF! - #REF!


12.13 (1) Blok Beton Perlindungan Lereng / Talud m2 #REF! 1,077.20 #REF!
12.14 Jalur Penyelamat Lumpsump #REF! 3.00 #REF!
12.15 Paving Blok Natural ( ukuran 21 x 10,5 x 8 cm ), K350 m3 #REF! 222.60 #REF!

TOTAL HARGA PENAWARAN UNTUK BAB 12 #REF!


( Pindahkan ke Rekapitulasi )
BAB 13 PENCAHAYAAN LAMPU LALU LINTAS
DAN PEKERJAAN LISTRIK

Lampu Penerangan Jalan, Tinggi 13 m (1 x HPS 250 watt), Armatur Type


13.01(1) buah #REF! - #REF!
SPP 668
Lampu Penerangan Jalan, Tinggi 13 m (1 x HPS 150 watt), Armatur Type
13.01(2) buah #REF! - #REF!
SPP 668
Lampu Penerangan Jalan, Tinggi 13 m (2 x HPS 150 watt), Armatur Type
13.01(3) buah - - -
SPP 668
Lampu Penerangan Jalan, Tinggi 13 m (2 x HPS 250 watt), Armatur Type
13.01(3) a buah - - -
SPP 668
Lampu Penerangan Jalan, Tinggi 13 m (2 x HPS 400 watt), Armatur Type
13.01(4) buah - - -
SPP 668
Lampu Penerangan Jalan, Tinggi 13 m (1 x HPS 400 watt), Armatur Type
13.01(4) a buah - - -
SPP 668
13.01(5) Lampu Penerangan Jalan, Tinggi 20 m ( 2 x HPS 1000 watt ) buah - - -
13.01(5) a Lampu Sorot, Tinggi 14 m (3 x HPS-T 3 x 250 watt), Rumah Type SMF 330 buah #REF! - #REF!
13.01(5) b Lampu Sorot, Tinggi 14 m (3 x HPS-T 3 x 400 watt), Rumah Type SMF 330 buah - - -
Lampu Hight Mast, Tinggi 30 m (4 x HPS-T 1000 watt), Rumah Lampu
13.01(5) c buah - - -
Type MVP 057
Lampu Hight Mast, Tinggi 35 m (4 x HPS-T 1000 watt) Rumah Lampu Type
13.01(5) d buah - - -
MVP 057
13.01(5) e Lampu Bawah Jembatan Lips-T 150 W type SRX 509 buah - - -
13.01(6) Kabel NYFGBY 2C - 4 mm2 m1 - - -
13.01(7) Kabel NYFGBY 2C - 6 mm2 m1 - - -
13.01(8) Kabel NYFGBY 2C - 10 mm2 m1 - - -
13.01(9) Kabel NYFGBY 3C - 4 mm2 m1 - - -
13.01(10) Kabel NYFGBY 3C - 10 mm2 m1 - - -
13.01(11) Kabel NYFGBY 3C - 16 mm2 m1 - - -
13.01(12) Kabel NYFGBY 4C - 4 mm2 m1 - - -
13.01(13) Kabel NYFGBY 4C - 10 mm2 m1 #REF! - #REF!
13.01(14) Kabel NYFGBY 4C - 16 mm2 m1 #REF! - #REF!
13.01(15) Kabel NYFGBY 4C - 25 mm2 m1 #REF! - #REF!
13.01(16) Kabel NYFGBY 4C - 35 mm2 m1 - - -
13.01(16) a Kabel NYFGBY 4C - 70 mm2 m1 - - -
13.01(16) b Kabel NYFGBY 4C - 95 mm2 m1 #REF! - #REF!
13.01(17) Kabel NYY/NYM 2 x 2,5 mm2 m1 - - -
13.01(18) Kabel NYY/NYM 2 x 10 mm2 m1 - - -
13.01(19) Kabel NYAF 240 x 1½ mm2 m1 - - -
13.01(19).a Kabel BC 10 mm m1 - - -
13.01(19).b Kabel BC 25 mm m1 - - -
13.01(20) Kabel Tray ( L = 40 cm ) m1 - - -
13.01(21) Panel PJU - I m1 - - -
13.01(22) Panel PJU - II m1 - - -
13.01(23) Grounding Panel PJU buah - - -
13.01(24) Grounding Tiang Lampu PJU buah - - -
13.01(25) Lampu Merkuri 50 watt buah - - -
13.01(26) Instalasi Penangkal Petir Gerbang Tol buah - - -
13.01(26).a Penangkal Petir Lampu High Mast, Grounding & Asesoris buah - - -
13.01(27) Panel Tol Gate unit - - -

Page 36 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

13.01(28) Grounding Panel Tol Gate buah - - -


13.01(29) Lampu TL 1 x 20 watt buah - - -
13.01(30) Saklar buah - - -
13.01(31) Stop Kontak Pompa Isap buah - - -
13.01(32) Pipa PVC Ø ½" m1 - - -
13.01(33) Instalasi dan Asesoris titik - - -
13.01(34) Pompa Isap 250 Watt, 220 Volt, 50 Hz unit - - -
13.01(35) Instalasi Pompa dan Asesoris unit - - -
13.01(36) Pipa PVC Ø 4" m1 #REF! 266.81 #REF!
13.01(37) Pipa PVC Ø 6" m1 #REF! 2,183.94 #REF!
13.01(38) Pipa PVC Ø 8" m1 #REF! 245.43 #REF!
13.01(39) Pipa Galvanish Diameter 6" ( 2 Jalur ) m1 - - -
13.01(40) Panel Meter PLN unit - - -
13.01(41) Kabel BC 4 x 70 mm m1 - - -
13.01(42) Kabel BC 4 x 95 mm m1 - - -
13.01(43) Manhole Listrik buah - - -
13.01(44) Panel Kontrol Pengendali Lalu Lintas buah - - -
13.01(45) Lampu Pengendali Lalu Lintas Type 1 buah - - -
13.01(46) Lampu Pengendali Lalu Lintas Type 2 buah - - -
13.01(47) Penyambungan daya Ke PLN 52.6 KVA Ls - - -
13.02 (1) Pelindung Kabel m1 - - -
13.02 (2) Rak Kabel ( Cable Tray ) m1 - - -
13.02 (3) Galian Kabel m1 - - -

TOTAL HARGA PENAWARAN UNTUK BAB 13 #REF!


( Pindahkan ke Rekapitulasi )
BAB 14 PLAZA TOL

14.01(1) Pulau Tol Tipe A


14.01(1).1 Beton Kelas B m3 - - -
14.01(1).2 Beton Kelas E m3 - - -
14.01(1).3 Pekerjaan Penulangan kg - - -
14.01(1).4 Lantai Screed Floor Hardener m2 - - -
14.01(1).5 Kerb Beton, Tipe A m' - - -

14.01(2) Pulau Tol Tipe B


14.01(2).1 Beton Kelas B m3 - - -
14.01(2).2 Beton Kelas E m3 - - -
14.01(2).3 Pembesian Pulau kg - - -
14.01(2).4 Lantai Screed Floor Hardener m2 - - -
14.01(2).5 Kerb Beton, Tipe A m1 - - -
14.01(2).6 Tangga Keramik 20x20 cm, Spesi 1:3, setara Roman KW.1 m2 - - -
14.01(2).7 Staimoising Keramik 7x20 cm , Spesi 1:3 setara Roman KW.1 m1 - - -
14.01(2).8 Hand Rail Carbon Steel Ø 1/2" dicat kg - - -
14.01(2).9 Tiang Railing Carbon Steel Ø 1" dicat kg - - -
14.01(2).10 Beton Class C-1untuk Tangga m3 - - -
14.01(2).11 Pembesian Tangga kg - - -

14.01(3) Pulau Tol Tipe C


14.01(3).1 Beton Kelas B m3 - - -
14.01(3).2 Beton Kelas E m3 - - -
14.01(3).3 Pembesian Pulau kg - - -
14.01(3).4 Lantai Screed Floor Hardener m2 - - -
14.01(3).5 Kerb Beton, Tipe A m1 - - -
14.01(3).6 Boot Ruang KSPT & Keamanan buah - - -

Page 37 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

14.01(4) Pulau Tol Tipe D


14.01(4).1 Beton Kelas B m3 - - -
14.01(4).2 Beton Kelas E m3 - - -
14.01(4).3 Pembesian Pulau kg - - -
14.01(4).4 Lantai Screed Floor Hardener m2 - - -
14.01(4).5 Kerb Beton, Tipe A m1 - - -
14.01(4).6 Booth Toilet buah - - -

14.01(4). A Pulau Tol Tipe E


14.01(4).a.1 Beton Kelas B m3 - - -
14.01(4).a.2 Beton Kelas E m3 - - -
14.01(4).a.3 Pembesian Pulau kg - - -
14.01(4).a.4 Lantai Screed Floor Hardener m2 - - -
14.01(4).a.5 Kerb Beton, Tipe A m1 - - -

14.01(4).B Pulau Tol Tipe F


14.01(1).b.1 Beton Kelas B m3 - - -
14.01(1).b.2 Beton Kelas E m3 - - -
14.01(1).b.3 Pembesian Pulau m3 - - -
14.01(1).b.4 Lantai Screed Floor Hardener m3 - - -
14.01(1).b.5 Kerb Beton, Tipe A m3 - - -

14.01(5) Atap Gerbang Tol


14.01 (5).1 Pipa Air Hujan & pipa Electrical PVC Ø 6" m1 - - -
14.01 (5).2 Roof Drain Ø 6" buah - - -
14.01 (5).3 Talang Air Plat Metal m2 - - -
14.01 (5).4 Cat Walk Baja Strip Rangka Besi Siku L.50.50.5 m1 - - -
14.01 (5).5 Trekstang, dudukan gording dan ikatan angin kg - - -
14.01 (5).6 Besi Siku L 50.50.5 kg - - -
14.01 (5).7 Penggantung cat walk pipa besi dia 2" m1 - - -
14.01 (5).8 Atap Metal Trimdek m2 - - -
14.01 (5).8.a Atap Metal setara Decra m2 - - -
14.01 (5).8.b Plafon Alumunium Strip m2 - - -
14.01 (5).8.c Jalusi Alumunium 94.97 x 92.8 x 1,5 mm m1 - - -
14.01 (5).9 Nok Metal Trimdek m1 - - -
14.01 (5).9.a Nok Metal setara Decra m1 - - -
14.01 (5).10 Listplank Alumunium Cladding setara Alucubond m2 -
14.01 (5).11 Sun Shading Poly Carbonat, Rangka Pipa Besi Ø 100 mm (lengkap) m1 - - -
14.01 (5).12 Tangga Cat Walkpipa Besi Ø 2" buah - - -
14.01 (5).13 Cat Besi setara ICI m2 - - -
14.01 (5).14 Cat Kolom ( Cat Interior ) m2 - - -
14.01 (5).15 Cat Listplank Luar ( Cat Exterior ) m2 -
14.01 (5).16 Cat Listplank dalam dan Plafond ( Cat Interior ) m2 -
14.01 (5).17 Lampu LLA ( Optic Lamp ) buah - - -
14.01 (5).18 Lampu TCW 2 x 36 watt type TKO buah - - -
14.01 (5).19 Lampu TL 2 x 20 watt type TKO buah - - -
14.01 (5).20 Instalasi penerangan & stop kontak titik - - -
14.01 (5).21 Stop Kontak buah - - -
14.01 (5).22 Stop kontak AC buah - - -
14.01 (5).23 Saklar tunggal 1 pase 10 A buah - - -
14.01 (5).24 Pipa Galvanish dia 2" (air bersih) m1 - - -
14.01 (5).25 Pipa Galvanish dia 1/2" (air bersih) m1 - - -
14.01 (5).26 Kran air bersih buah - - -
14.01 (5).27 Galian Kabel m1 - - -
14.01 (5).28 Galian Pipa m1 - - -
14.01 (5).29 Kabel NYFGBY 4 x 120 mm2 (dari panel distribusi ke panel gerbang tol) m1 - - -

Page 38 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

14.01 (5).30 Kabel NYFGBY 4 x 10 mm2 m1 - - -


14.01 (5).31 Rambu Nama Gerbang tol buah - - -
14.01 (5).32 Rambu Lebar Jalur buah - - -
14.01 (5).33 Rambu Batas Ketinggian buah - - -
14.01 (5).34 Rambu Petunjuk Tanda Ambil Tiket buah - - -
14.01 (5).35 Rambu Petunjuk Tanda Bayar Tol buah - - -
14.01 (5).36 Rambu Petunjuk Tanda Tarif Tol buah - - -
14.01 (5).37 Rambu Larangan Menaikkan Menurunkan Penumpang buah - - -
14.01 (5).38 Reflektor diatas Bumper Blok buah - - -
14.01 (5).39 Rambu Stop buah - - -
14.01 (5).40 Panel Gerbang Tol buah - - -
14.01 (5).40.a Panel Gardu Tol buah - - -
14.01 (5).41 Panel Besi dia 8" ( pelindung gardu ) m1 - - -
14.01 (5).42 Manhole Drainase buah - - -
14.01 (5).43 Manhole Elektrikal buah - - -
14.01 (5).44 Pipa PVC 4" m1 - - -
14.01 (5).44.a Pipa PVC 2" m1 - - -
14.01 (5).44.b Buis Beton Ø 30 Cm m1 - - -
14.01 (5).45 Tabung Pemadam Kebakaran kap 6 kg buah - - -
14.01 (5).46 Instalasi Penangkal Petir unit - - -
14.01 (5).47 Selasar m1 -
14.01 (5).48 Galian Tanah Pondasi Kolom Gerbang Tol m3 - - -
14.01 (5).49 Urugan Kembali Pondasi Kolom Gerbang Tol m3 - - -
14.01 (5).50 Pasir Urug Bawah Pondasi Kolom Gerbang Tol m3 - - -
14.01 (5).51 Beton Kelas E Bawah Pondasi Kolom Gerbang Tol m3 - - -
14.01 (5).52 Beton Kelas C Pondasi Kolom Gerbang Tol m3 - - -
14.01 (5).53 Pembesian Pondasi Kolom Gerbang Tol kg - - -

14.01(6) Gardu Tol


14.01(6) Gardu Tol buah - - -

14.01 (7) Tunnel


A Pekerjaan Tanah
14.01 (7).1 Galian Pondasi m3 - - -
14.01 (7).2 Urugan Pondasi m3 - - -
14.01 (7).3 Pasir Urug m3 - - -

B Pekerjan Struktur
14.01 (7).4 Penyediaan Tiang Pancang Beton Bertulang Precast, 25x25 cm m1 - - -
14.01 (7).5 Pemancangan Tiang Pancang Betin Bertulang Precast, 25x25 cm m1 - - -
Penyedian dan Pemancangan Tiang Pancang Beton Bertulang Precast untuk
14.01 (7).6 m 1
- - -
Test, 25x25 cm
14.01 (7).7 Lantai Kerja Beton Klass E m3 - - -
14.01 (7).8 Beton Klass C-1 m3 - - -
14.01 (7).9 Pekerjaan Penulangan kg - - -

C Pekerjaan Dinding
14.01 (7).10 Dinding Pasangan bata 1:4 m2 - - -

D Pekerjaan Kusen
14.01 (7).11 Kusen Pintu Karbon Steel Ø 2" m2 - - -

E Pekerjaan Lantai
14.01 (7).12 Lantai Keramik 20x20 cm Spesi Ex AM 40, Setara roman KW 1 m2 - - -
14.01 (7).13 Lantai Keramik 30x30 cm Spesi Ex AM 40, Setara roman KW 1 m2 - - -
14.01 (7).14 Stairnoising Keramik 7/20 m2 - - -

Page 39 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

14.01 (7).15 Lantai Koral Sikat m2 - - -

F Pekerjaan Pengecatan
14.01 (7).16 Cat Dinding Setara ICI ( Interior ) m2 - - -
14.01 (7).17 Cat Besi Setara ICI m2 - - -

G Pekerjaan Instalasi Listrik


14.01 (7).18 Panel Tunnel unit - - -
14.01 (7).19 Kabel NYFGBY 4 x 10 mm2 m1 - - -
14.01 (7).20 Lampu TL 20 Watt buah - - -
14.01 (7).21 Saklar buah - - -
14.01 (7).22 Stop Kontak buah - - -
14.01 (7).23 Pompa Sum Plt 250 W dan Instalasi unit - - -
14.01 (7).24 Instalasi Lampu dan Stop Kontak titik - - -
14.01 (7).25 Kabel Tray W=40 cm m1 - - -

H Pekerjaan Lain - Lain


14.01 (7).26 Box Fire Extinghuiser, Frame Alumunium Kaca 6 mm buah - - -
14.01 (7).27 Fire Extinghuiser, Kap 6 kg buah - - -
14.01 (7).28 Railing Carbon Steel Ø 2" dicat kg - - -
14.01 (7).29 Railing Carbon Steel Ø 1" dicat kg - - -
14.01 (7).30 Glass Blok buah - - -

TOTAL HARGA PENAWARAN UNTUK BAB 14 -


( Pindahkan ke Rekapitulasi )
BAB 15 PENGALIHAN DAN PERLINDUNGAN UTILITAS YANG ADA

15.1 Provisional Sum untuk Pengalihan dan Perlindungan Utilitas Yang Ada sum - - -

TOTAL HARGA PENAWARAN UNTUK BAB 15 -


( Pindahkan ke Rekapitulasi )
BAB 16 PEKERJAAN FASILITAS TOL DAN KANTOR GERBANG TOL

16.01 (1) BANGUNAN FASILITAS TOL


A. Pekerjaan Tanah
16.01 (1).1 Galian Pondasi m3 - - -
16.01 (1).2 Urugan pondasi m3 - - -
16.01 (1).3 Pengurugan Peninggian Peil pada Lantai m3 - - -
16.01 (1).4 Pasir Urug m3 - - -

B. Pekerjaan Pondasi dan Beton Struktur


16.01 (1).5 Pasangan Batu Kosong m3 - - -
16.01 (1).6 Pasangan Batu Kali 1:4 m3 - - -
16.01 (1).7 Pasangan Roolag Batu Bata 1:3 m3 - - -
16.01 (1).8 Kolom Balok ( Beton Kelas C ) m3 - - -
16.01 (1).9 Beton kelas D ( Beton non Struktur Fasilitas Tol ) m3 - - -
16.01 (1).10 Lantai Kerja, Beton Kelas E m3 - - -
16.01 (1).11 Pekerjaan Penulangan kilogram - - -

C. Pekerjaan Dinding
16.01 (1).12 Dinding Batu Bata Spesi 1 : 3 m2 - - -
16.01 (1).13 Dinding Batu Bata Spesi 1 : 4 m2 - - -
16.01 (1).14 Dinding Keramik 20/20 cm, Spesi 1 : 3 Produk Roman KW-1 m2 - - -
16.01 (1).15 Dinding Batu Alam / Tempel ( Andesit ) m2 - - -
16.01 (1).16 Dinding Partisi Gypsum 12 mm PR-1 m2 - - -
16.01 (1).17 Dinding Partisi Gypsum 12 mm PR-2 m2 - - -

Page 40 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

16.01 (1).18 Dinding Partisi Gypsum 12 mm PR-3 m2 - - -


16.01 (1).19 Dinding Partisi Gypsum 12 mm PR-4 m2 - - -
16.01 (1).19.a Dinding Partisi Gypsum 12 mm PR-5 m2 - - -
16.01 (1).19.b Dinding Partisi Gypsum 12 mm PR-6 m2 - - -
16.01 (1).19.c Dinding Partisi Gypsum 12 mm PR-7 m2 - - -
16.01 (1).19.d Dinding Partisi Gypsum 12 mm PR-8 m2 - - -
16.01 (1).19.e Dinding Partisi Gypsum 12 mm PR-9 m2 - - -
16.01 (1).19.f Dinding Partisi Gypsum 12 mm PR-10 m2 - - -
16.01 (1).19.g Dinding Partisi Gypsum 12 mm PR-11 m2 - - -
16.01 (1).19.h Dinding Partisi Gypsum 12 mm PR-12 m2 - - -
16.01 (1).19.i Dinding Partisi Gypsum 12 mm PR-13 m2 - - -
16.01 (1).19.j Dinding Partisi Gypsum 12 mm PR-14 m2 - - -
16.01 (1).19.k Dinding Partisi Gypsum 12 mm PR-15 m2 - - -
16.01 (1).19.l Dinding Partisi Gypsum 12 mm PR-16 m2 - - -
16.01 (1).19.m Dinding Partisi Gypsum 12 mm PR-17 m2 - - -
16.01 (1).19.n Dinding Partisi Gypsum 12 mm PR-18 m2 - - -
16.01 (1).19.o Dinding Partisi Gypsum 12 mm PR-19 m2 - - -
16.01 (1).19.p Dinding Partisi Gypsum 12 mm PR-20 m2 - - -
16.01 (1).19.q Dinding Partisi Gypsum 12 mm PR-21 m2 - - -
16.01 (1).20 Plesteran Dinding Spesi 1 : 3 m2 - - -
16.01 (1).20.a Plesteran Dinding Groove Segitiga Spesi 1 : 3 m2 - - -
16.01 (1).21 Plesteran Dinding Spesi 1 : 4 m2 - - -

D. Pekerjaan Atap dan Plafond


16.01 (1).22 Kuda-kuda rangka baja 2L 50x50x5 kilogram - - -
16.01 (1).23 Gording Light Lip Channel kilogram - - -
16.01 (1).24 Trekstang, Dudukan gording, dan ikatan angin kilogram - - -
16.01 (1).24.a Usuk Besi Hollow 50x50x1.6 mm dan Reng Besi Hollow 30x30x1.6 mm kilogram - - -
16.01 (1).24.b Plywood 6 mm dan Alumunium Foil dibawah Reng m2 - - -
16.01 (1).25 Atap Genteng Metal setara Decra m2 - - -
16.01 (1).26 Nok Genteng Metal setara Decra m1 - - -
16.01 (1).27 List Plank GRC Rangka Kayu Kamper 5/7 m1 - - -
16.01 (1).28 Roof Drain 4" buah - - -
16.01 (1).29 Pipa Talang PVC 4" m1 - - -
16.01 (1).30 Talang Papan Kayu Kamper Flashing Metal m2 - - -
16.01 (1).31 Atap Dak Beton Kelas C m3 - - -
16.01 (1).32 Pembesian Plat Atap kilogram - - -
16.01 (1).33 Plafond Gypsum Tahan Api m2 - - -
16.01 (1).33.a Plafond Acoustic 600x600 Rangka Alumunium m2 - - -
16.01 (1).33.b Plafond Gypsum 9 mm Rangka Besi Hollow 40x40 m2 - - -
16.01 (1).34 Plafond GRC Board m2 - - -
16.01 (1).35 List Plafond Alumunium meter - - -
16.01 (1).36 List Plafon Kayu 5/5 cm, setara Kamper Samarinda meter - - -
16.01 (1).37 Plafond Beton Expose m2 - - -
16.01 (1).38 Water Proofing m2 - - -

E. Pekerjaan Kusen, Pintu dan Jendela


16.01 (1).39 Kusen Tipe PJ-1, Kusen Alumunium, Pintu Panel Kaca Bening 6 mm bh - - -
16.01 (1).40 Kusen Tipe P-1, Kusen Alumunium, Pintu Panel Kaca Bening 6 mm bh - - -
16.01 (1).41 Kusen Tipe P-2, Kusen Alumunium, Pintu Dobel Teakwood Kaca Bening 6 mm bh - - -
16.01 (1).42 Kusen Tipe P-3, Kusen dan Pintu PVC, lebar 80 cm bh - - -
16.01 (1).42.a Kusen Tipe P-4, Kusen dan Pintu PVC, lebar 70 cm bh - - -
16.01 (1).43 Kusen Tipe J-1, Kusen Alumunium, Jendela Kaca Bening 6 mm bh - - -
16.01 (1).44 Kusen Tipe J-2, Kusen Alumunium, Jendela Kaca Bening 6 mm bh - - -
16.01 (1).45 Kusen Tipe J-3, Kusen Alumunium, Kaca Bening 6 mm bh - - -
16.01 (1).46 Kusen Tipe BV-1, Kusen Alumunium, Jendela Kaca Bening 6 mm bh - - -

Page 41 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

16.01 (1).47 Kusen Tipe BV-2, Kusen Alumunium, Kaca Bening 6 mm bh - - -


16.01 (1).48 Kusen Tipe BV-3, Kusen Alumunium, Kaca Bening 6 mm bh - - -
16.01 (1).48.a Kusen Tipe BV-4, Kusen Alumunium, Kaca Bening 6 mm bh - - -

F. Pekerjaan Lantai
16.01 (1).49 Pasir Urug Lantai 10 cm m3 - - -
16.01 (1).50 Sub Lantai Beton Kelas D; t = 5 cm m3 - - -
16.01 (1).50.a Lantai Koral Sikat Selasar m3 - - -
16.01 (1).51 Lantai Keramik 20/20 cm, Spesi Ex. AM 40, setara Roman KW-1 m2 - - -
16.01 (1).52 Lantai Keramik 30/30 cm, Ex. AM 40, setara Roman KW-1 m2 - - -
16.01 (1).53 Plint Keramik 10/30 cm, Spesi Ex. AM 40 setara Roman KW-1 meter - - -
16.01 (1).54 Stairnosing Keramik 5/20 cm, Spesi Ex AM 40 setara Roman KW-1 meter - - -
16.01 (1).55 Meja Beton Lapis Keramik untuk Pantry meter - - -

G. Sanitasi
16.01 (1).56 Kloset Jongkok, setara Toto CW 420J/SW 420 JP buah - - -
16.01 (1).57 Washtafel, setaraToto ZW 661EJ buah - - -
16.01 (1).58 Bak Mandi Fiber Glass ( lokal ) buah - - -
16.01 (1).59 Kran Air, setara Toto T23 B13 buah - - -
16.01 (1).60 Floor Drain, setara Toto TX 1B buah - - -
16.01 (1).61 Kitchen Zink, Diethelm buah - - -
16.01 (1).62 Kaca Cermin 70 x 80 cm, t = 5 mm buah - - -
16.01 (1).63 Clean Out dia 4" buah - - -
16.01 (1).64 Urinor setara Toto U57 M buah - - -
16.01 (1).65 Sekat setaraToto A100 buah - - -

H. Pekerjaan Drainase
16.01 (1).64 Drainase Saluran Terbuka ½ dia 8" m' - - -
16.01 (1).64.a Saluran Tipe DS-3 m' - - -
16.01 (1).64.b Saluran Tipe DS-3C m' - - -
16.01 (1).64.c Saluran Tipe DS-3D m' - - -
16.01 (1).64.d Saluran Tipe DS-10 m' - - -

I. Pekerjaan Pengecatan
16.01 (1).65 Cat Dinding setara ICI - Emulsion ( exterior ) m2 - - -
16.01 (1).66 Cat Dinding setara ICI - Emulsion ( interior ) m2 - - -
16.01 (1).67 Cat Plafond setara ICI - Emulsion m2 - - -
16.01 (1).68 Cat List Plafond setara ICI ( teras & teritisan ) m2 - - -
16.01 (1).69 Cat Kusen Kayu setara ICI m2 - - -
16.01 (1).69.a Cat Kusen Kayu Melamine m2 - - -
16.01 (1).70 Cat Rangka Atap setara ICI m2 - - -
16.01 (1).71 Cat Listplank setara ICI m2 - - -
16.01 (1).72 Cat Besi setara ICI m2 - - -
-
J. Pekerjaan Instalasi Listrik -
16.01 (1).73 Panel Kantor Gerbang Tol unit - - -
16.01 (1).74 Lampu TL 1 x 36 watt, Tki buah - - -
16.01 (1).74.a Lampu TL 2 x 36 watt, Tki buah - - -
16.01 (1).74.b Lampu TL 3 x 36 watt, Tki buah - - -
16.01 (1).75 Lampu TL Bulat 20 watt buah - - -
16.01 (1).75.a Lampu TL 20 watt buah - - -
16.01 (1).76 Lampu Down Light PCL 22 watt buah - - -
16.01 (1).77 Saklar Seri (MK) 250 Volt, 10 Amp buah - - -
16.01 (1).78 Saklar Tunggal (MK) 250 Volt, 6 Amp buah - - -
16.01 (1).79 Stop Kontak buah - - -
16.01 (1).80 Stop Kontak AC buah - - -

Page 42 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

16.01 (1).81 AC Split 1 PK buah - - -


16.01 (1).82 Kabel NYFGBY 4 x 25 mm2 m1 - - -
16.01 (1).83 Instalasi Penerangan ( dengan kabel NYM 4 x 2.5 mm2 ) titik - - -
16.01 (1).84 Instalasi Stop Kontak ( dengan kabel NYM 4 x 4 mm2 ) titik - - -
16.01 (1).85 Exhoust Fan, Kap 200 cfm, Sp.01 ( tipe shtter ) 8" buah - - -
16.01 (1).86 Instalasi Listrik untuk AC titik - - -
16.01 (1).87 Instalasi Listrik untuk Ex. Fan unit - - -
16.01 (1).88 Instalasi Penangkal Petir buah - - -
16.01 (1).89 Galian Kabel m1 - - -

K. Pekerjaan Plambing
16.01 (1).90 Pipa air bersih, Gip Medium kelas dia 2 ½" m1 - - -
16.01 (1).91 Pipa air bersih, PVC dia 2" m1 - - -
16.01 (1).92 Pipa air bersih, Gip Medium kelas dia 1" m1 - - -
16.01 (1).93 Pipa air bersih, Gip Medium kelas dia 3/4" m1 - - -
16.01 (1).94 Pipa air bersih, PVC dia ½" m1 - - -
16.01 (1).95 Pipa air kotor, PVC kelas AW dia 4" m1 - - -
16.01 (1).96 Pipa air kotor, PVC kelas AW dia 3" m1 - - -
16.01 (1).97 Pipa air kotor, PVC kelas AW dia 2" m1 - - -
16.01 (1).98 Pipa air bekas, PVC kelas AW dia 3" m1 - - -
16.01 (1).99 Pipa air bekas, PVC kelas AW dia 2" m1 - - -
16.01 (1).100 Clean Out dia 4" m1 - - -
16.01 (1).101 Pipa Ventilasi PVC kelas AW dia 1" m1 - - -
16.01 (1).102 Pipa Ventilasi PVC kelas AW dia 1¼" m1 - - -
16.01 (1).103 Septik Tank, Kap 3 m3 unit - - -
16.01 (1).104 Resapan, Kap 3 m3 unit - - -
16.01 (1).105 Fire Extinguisher, Kap 6 kg buah - - -

16.01 (1) RUMAH GENERATOR


A. Pekerjaan Tanah
16.01 (2).1 Galian Pondasi m3 - - -
16.01 (2).2 Urugan Pondasi m3 - - -
16.01 (2).3 Pengurugan Peninggian Peil pada Lantai m3 - - -
16.01 (2).4 Pasir Urug m3 - - -

B. Pekerjaan Struktur
16.01 (2).5 Pasangan Batu Kosong m3 - - -
16.01 (2).6 Pasangan Batu Kali 1:3 m3 - - -
16.01 (2).7 Beton kelas C ( Beton Struktur Fasilitas Tol ) m3 - - -
16.01 (2).8 Beton kelas D ( Beton Fasilitas Tol ) m3 - - -
16.01 (2).9 Lantai Kerja ( Beton Kelas E ) m3 - - -
16.01 (2).10 Pekerjaan Penulangan kilogram - - -

C. Pekerjaan Dinding
16.01 (2).11 Dinding Batu Bata Spesi 1 : 3 m2 - - -
16.01 (2).12 Dinding Batu Bata Spesi 1 : 4 m2 - - -
16.01 (2).13 Dinding Batu Alam / Tempel ( Andesit ) m2 - - -
16.01 (2).14 Plesteran Dinding Spesi 1 : 3 m2 - - -
16.01 (2).14.a Plesteran Dinding Groove Segitiga Spesi 1 : 5 m2 - - -
16.01 (2).15 Plesteran Dinding Spesi 1 : 4 m2 - - -

D. Pekerjaan Atap dan Plafond


16.01 (2).16 Atap Beton kelas C m3 - - -
16.01 (2).17 Pembesian Plat Atap kilogram - - -
16.01 (2).18 Water Proofing m2 - - -
16.01 (2).19 Roof Drain 4 " buah - - -

Page 43 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

16.01 (2).20 Pipa Talang PVC 4" m1 - - -

E. Pekerjaan Kusen, Pintu dan Jendela


16.01 (2).21 Kusen Pintu Stainless Steel. Pintu Besi buah - - -
16.01 (2).22 Lubang Radiator buah - - -

F. Pekerjaan Lantai
16.01 (2).23 Pasir Urug Lantai 10 cm m3 - - -
16.01 (2).23.a Lantai Kerja Beton Kelas E m3 - - -
16.01 (2).24 Pekerjaan Lantai ( Beton Kelas C ) m3 - - -
16.01 (2).25 Pekerjaan Koral Sikat Berpola m3 - - -
16.01 (2).26 Pekerjaan Screed Lapis Floor Hardener m2 - - -
16.01 (2).26.a Pekerjaan Penulangan kg - - -
16.01 (2).26.b Plat Bordes buah - - -
16.01 (2).26.c Peredam Bantalan Ls - - -

G. Pekerjaan Pengecatan
16.01 (2).27 Cat Dinding setara ICI - Emulsion ( exterior ) m2 - - -
16.01 (2).28 Cat Dinding setara ICI - Emulsion ( interior ) m2 - - -
16.01 (2).29 Cat Kayu setara ICI m2 - - -
16.01 (2).30 Cat Besi setara ICI m2 - - -

H. Pekerjaan Instalasi Listrik


16.01 (2).31 Generator 350 KVA ( Silent Type ) buah - - -
16.01 (2).32 Tangki Harian 500 Liter, termasuk pemipaan buah - - -
16.01 (2).33 Panel Distribusi buah - - -
16.01 (2).34 Panel AMF buah - - -
16.01 (2).34.a Panel Rumah Genset buah - - -
16.01 (2).35 Lampu TL 1 x 40 watt buah - - -
16.01 (2).36 Lampu TL Bu;at 20 watt buah - - -
16.01 (2).36.a Lampu Taman Mercury 50 W, Tinggi 2 m buah - - -
16.01 (2).36.b Lampu Parkir HPS-T 1x150 W, Tinggi 13 m buah - - -
16.01 (2).37 Instalasi Penerangan dengan Kabel NYM 4 x 2,5 mm2 titik - - -
16.01 (2).38 Kabel NYFGBY 4 x 10 mm2 m1 - - -
16.01 (2).39 Kabel NYY 4 x 300 mm2 ( PLN - Panel AMF - Panel Distribusi ) m1 - - -
16.01 (2).39.a Kabel NYM 4 x 16 mm2 ( Panel Distribusi - Panel R Genset ) m1 - - -
16.01 (2).40 Saklar Tunggal / double buah - - -
16.01 (2).41 Stop kontak buah - - -
16.01 (2).42 Instalasi Stop Kontak titik - - -
16.01 (2).43 Exhaust Fan Kap. 605 CFM, Tipe Suttert 12" buah - - -
16.01 (2).44 Instalasi Listrik untuk Exhaust Fan titik - - -
16.01 (2).45 Fire Extinguisher, Kap 20 kg buah - - -
16.01 (2).46 Galian Kabel m1 - - -

16.01 (3) PEKERJAAN MENARA AIR DAN SUMUR DANGKAL


16.01 (3).1 Ground Tank Kapasitas 5.20 m3 buah - - -
16.01 (3).2 Sumur Dangkal kedalaman 24 meter buah - - -
16.01 (3).3 Rumah dan Kedudukan Pompa buah - - -
16.01 (3).4 Pompa Air 500 Watt, 220 Volt, 50 Hz, Kap. 1.1 l/det buah - - -
16.01 (3).5 Pompa Air 250 Watt, 220 Volt, 50 Hz, Kap. 0,55 l/det buah - - -
16.01 (3).6 Instalasi Kabel NYFGBY 3 X 4 mm2 meter - - -
16.01 (3).7 Tangki Air, Fibre Glass, kap 2000 liter buah - - -
16.01 (3).7.a Tangki Air, Fibre Glass, kap 3500 liter buah - - -
16.01 (3).8 Gate Valve dia 1½" buah - - -
16.01 (3).9 Gate Valve dia 1" buah - - -
16.01 (3).9.a Gate Valve dia 2" buah - - -

Page 44 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

16.01 (3).9.b Gate Valve dia 3" buah - - -


16.01 (3).10 Pelampung buah - - -
16.01 (3).11 Pipa Air Bersih Gip Medium Class 2 ½" m1 - - -
16.01 (3).12 Pipa Air Bersih Gip Medium Class 2" m1 - - -
16.01 (3).13 Pipa Air Bersih Gip Medium Class 1" m1 - - -
16.01 (3).14 Pipa Air Bersih Gip Medium Class ½" m1 - - -
16.01 (3).14.a Pipa Air Bersih, PVC 3" m1 - - -
16.01 (3).15 Pipa Air Bersih, PVC 2 ½" m1 - - -
16.01 (3).16 Pipa Air Bersih, PVC 2" m1 - - -
16.01 (3).17 Pipa Air Bersih, PVC 1 ¼" m1 - - -
16.01 (3).18 Pipa Air Bersih, PVC 1" m1 - - -
16.01 (3).18.a Pipa Air Bersih, PVC ½" m1 - - -
16.01 (3).19 Galian Pipa m' - - -
16.01 (3).20 Kran Air dia ½" Toto buah - - -
16.01 (3).21 Instalasi Penangkal Petir unit - - -

16.01 (4) JALAN LINGKUNGAN , PARKIR KENDARAAN


16.01 (4).1 Paving Block Natural ( ukuran 21 x 10,5 x 8 cm ), K 350 m2 #REF! 424.40 #REF!
16.01 (4).2 Paving Block Natural ( ukuran 21 x 10,5 x 6 cm ), K 225 m2 - - -
16.01 (4).3 Lantai Beton Sikat Berpola m2 - - -
16.01 (4).4 Sand Bedding t = 5 cm m2 - - -
16.01 (4).4.a Agregat Klas B m3 - - -
16.01 (4).4.b Kerb Beton Type A m1 - - -
16.01 (4).4.c Kerb Beton Type B m1 - - -

16.01 (5) RUMAH API


16.01 (5).1 Rumah Api unit - - -
16.01 (5).2 Fire Extinguiser ( termasuk Trolley, tabung dan isinya ) kap. 150 kg unit - - -

16.01 (6) TIANG BENDERA


16.01 (6).1 Tiang Bendera unit - - -
16.01 (6).2 Umbul-Umbul unit - - -

16.01 (7) TEMPAT SAMPAH


16.01 (7).1 Tempat Sampah unit - - -

16.01 (8) RUMAH DINAS


A. Pekerjaan Tanah
16.01 (8).1 Galian Pondasi m3 - - -
16.01 (8).2 Urugan pondasi m3 - - -
16.01 (8).3 Pengurugan Peninggian Peil pada Lantai m3 - - -
16.01 (8).4 Pasir Urug m3 - - -

B. Pekerjaan Pondasi dan Beton Struktur


16.01 (8).5 Pasangan Batu Kosong m3 - - -
16.01 (8).6 Pasangan Batu Kali 1:4 m3 - - -
16.01 (8).7 Pasangan Roolag Batu Bata 1:3 m3 - - -
16.01 (8).8 Kolom Balok ( Beton Kelas C ) m3 - - -
16.01 (8).9 Beton kelas D ( Beton non Struktur Fasilitas Tol ) m3 - - -
16.01 (8).10 Lantai Kerja, Beton Kelas E m3 - - -
16.01 (8).11 Pekerjaan Penulangan kilogram - - -

C. Pekerjaan Dinding
16.01 (8).12 Dinding Batu Bata Spesi 1 : 3 m2 - - -
16.01 (8).13 Dinding Batu Bata Spesi 1 : 4 m2 - - -
16.01 (8).14 Dinding Keramik 20/20 cm, Spesi 1:3 Produk Keramik KW-1 m2 - - -

Page 45 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

16.01 (8).15 Dinding Batu Alam / Tempel ( Andesit ) m2 - - -


16.01 (8).16 Plesteran Dinding Spesi 1 : 3 m2 - - -
16.01 (8).17 Plesteran Dinding Groove Segitiga Spesi 1 : 3 m2 - - -
16.01 (8).18 Plesteran Dinding Spesi 1 : 4 m2 - - -

D. Pekerjaan Atap dan Plafond


16.01 (8).19 Kuda-kuda Rangka Kayu Kamper Samarinda m3 - - -
16.01 (8).20 Balok Bubung dan Gording Kayu Kamper Samarinda m3 - - -
16.01 (8).21 Usuk dan Reng Kayu Kamper Samarinda m3 - - -
16.01 (8).22 Atap Genteng Keramik m2 - - -
16.01 (8).23 Nok Genteng Keramik m1 - - -
16.01 (8).24 List Plank Papan Kamper Samarinda m1 - - -
16.01 (8).25 Atap Polycarbonate Twinlite t=5 mm m2 - - -
16.01 (8).26 Rangka Atap Polycarbonate, Pipa Besi Ø 3" kilogram - - -
16.01 (8).27 Roof Drain 4" buah - - -
16.01 (8).28 Pipa Talang PVC 4" m1 - - -
16.01 (8).29 Atap Dak Beton Kelas C m3 - - -
16.01 (8).30 Pembesian Plat Atap kilogram - - -
16.01 (8).31 Plafond Multipleks 6 mm m2 - - -
16.01 (8).32 List Plafond Cornice meter - - -
16.01 (8).33 Plafond Beton Expose m2 - - -

E. Pekerjaan Kusen, Pintu dan Jendela


16.01 (8).34 Kusen Tipe PJ-1, Kayu Kamper Samarinda Kaca Bening 6 mm buah - - -
16.01 (8).35 Kusen Tipe P-1, Kayu Kamper Samarinda buah - - -
16.01 (8).36 Kusen Tipe P-2, Kayu Kamper Samarinda buah - - -
16.01 (8).37 Kusen Tipe J-1, Kayu Kamper Samarinda, Jendela Kaca Bening 4 mm buah - - -
16.01 (8).38 Kusen Tipe J-2, Kayu Kamper Samarinda, Jendela Kaca Bening 4 mm buah - - -
16.01 (8).39 Kusen Tipe BV-1, Kayu Kamper Samarinda buah - - -

F. Pekerjaan Lantai
16.01 (8).40 Pasir Urug Lantai 10 cm m3 - - -
16.01 (8).41 Sub Lantai Beton Kelas D; t = 5 cm m3 - - -
16.01 (8).42 Lantai Koral Sikat Selasar m3 - - -
16.01 (8).43 Lantai Keramik 20/20 cm, Spesi Ex. AM 40, setara Roman KW-1 m2 - - -
16.01 (8).44 Lantai Keramik 30/30 cm, Ex. AM 40, setara Roman KW-1 m2 - - -
16.01 (8).45 Meja Beton Lapis Keramik untuk Pantry meter - - -

G. Sanitasi
16.01 (8).46 Kloset Jongkok, setara Toto CW 420J/SW 420 JP buah - - -
16.01 (8).47 Washtafel, setara Toto L 230 buah - - -
16.01 (8).48 Bak Air Fiber Glass ( lokal ) buah - - -
16.01 (8).49 Kran Air, setara Toto atau San Ei buah - - -
16.01 (8).50 Floor Drain, setara Toto TX 1B buah - - -
16.01 (8).51 Kitchen Zink, Diethelm buah - - -

H. Pekerjaan Drainase
16.01 (8).52 Drainase Saluran Terbuka ½ dia 20 cm dengan buis beton m1 - - -

I. Pekerjaan Pengecatan
16.01 (8).53 Cat Dinding setara ICI - Emulsion ( exterior ) m2 - - -
16.01 (8).54 Cat Dinding setara ICI - Emulsion ( interior ) m2 - - -
16.01 (8).55 Cat Plafond setara ICI - Emulsion m2 - - -
16.01 (8).56 Cat Kusen Kayu setara ICI m2 - - -
16.01 (8).57 Cat Rangka Atap setara ICI m2 - - -
16.01 (8).58 Cat Listplank Kayu setara ICI m2 - - -

Page 46 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

16.01 (8).59 Cat Besi setara ICI m2 - - -

J. Pekerjaan Instalasi Listrik


16.01 (8).60 Panel Kantor Rumah Dinas unit - - -
16.01 (8).61 Lampu TL 1 x 36 watt, Tki buah - - -
16.01 (8).62 Lampu TL Bulat 20 watt buah - - -
16.01 (8).63 Saklar Seri (MK) 250 Volt, 10 Amp buah - - -
16.01 (8).64 Saklar Tunggal (MK) 250 Volt, 6 Amp buah - - -
16.01 (8).65 Stop Kontak buah - - -
16.01 (8).66 Stop Kontak AC buah - - -
16.01 (8).67 AC Split 1/2 PK buah - - -
16.01 (8).68 Kabel NYFGBY 4 x 10 mm2 m1 - - -
16.01 (8).69 Instalasi Penerangan ( dengan kabel NYM 4 x 2.5 mm2 ) titik - - -
16.01 (8).70 Instalasi Stop Kontak ( dengan kabel NYM 4 x 2.5 mm2 ) titik - - -
16.01 (8).71 Instalasi Stop Kontak AC ( dengan kabel NYM 4 x 4 mm2 ) titik - - -
16.01 (8).72 Instalasi Listrik untuk AC titik - - -

K. Pekerjaan Plambing
16.01 (8).73 Pipa air bersih, Gip Medium kelas dia 2 ½" m1 - - -
16.01 (8).74 Pipa air bersih, PVC dia 2" m1 - - -
16.01 (8).75 Pipa air bersih, Gip Medium kelas dia 1" m1 - - -
16.01 (8).76 Pipa air bersih, Gip Medium kelas dia 3/4" m1 - - -
16.01 (8).77 Pipa air bersih, PVC dia ½" m1 - - -
16.01 (8).78 Pipa air kotor, PVC kelas AW dia 4" m1 - - -
16.01 (8).79 Pipa air kotor, PVC kelas AW dia 3" m1 - - -
16.01 (8).80 Pipa air kotor, PVC kelas AW dia 2" m1 - - -
16.01 (8).81 Pipa air bekas, PVC kelas AW dia 3" m1 - - -
16.01 (8).82 Pipa air bekas, PVC kelas AW dia 2" m1 - - -
16.01 (8).83 Clean Out dia 4" m1 - - -
16.01 (8).84 Pipa Ventilasi PVC kelas AW dia 1" m1 - - -
16.01 (8).85 Pipa Ventilasi PVC kelas AW dia 1¼" m1 - - -
16.01 (8).86 Septik Tank, Kap 3 m3 unit - - -
16.01 (8).87 Resapan, Kap 3 m3 unit - - -

16.5 Pekerjaan Penanaman dan Perawatan Tanaman Fastol


16. (07) 1 Adam hawa Rumpun/pot - - -
16. (07) 2 Anggrek tanah Rumpun/pot - - -
16. (07) 3 Arachis pintoi Rumpun/pot - - -
16. (07) 4 Aren Pohon - - -
16. (07) 5 Asam Jawa Pohon - - -
16. (07) 6 Bakung Air Mancur Rumpun/pot - - -
16. (07) 7 Belimbing Manis Pohon - - -
16. (07) 8 Belimbing Wuluh Pohon - - -
16. (07) 9 Vougenville Pohon - - -
16. (07) 10 Bungur Pohon - - -
16. (07) 11 Cemara gunung Pohon - - -
16. (07) 12 Cengkeh Pohon - - -
16. (07) 13 Delima merah Pohon - - -
16. (07) 14 Delima putih Pohon - - -
16. (07) 15 Flamboyant Pohon - - -
16. (07) 16 Gardenia Rumpun/pot - - -
16. (07) 17 Golden Pohon - - -
16. (07) 18 Iris Rumpun/pot - - -
16. (07) 19 Jambu biji merah Pohon - - -
16. (07) 20 Kamboja kuning Pohon - - -
16. (07) 21 Kantil Pohon - - -

Page 47 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG BAWEN SEKSI II GEDAWANG - SUSUKAN
STA. 3+525 - STA. 8+475

MATA HARGA KUANTITAS JUMLAH


PEMBA- URAIAN SATUAN SATUAN TOTAL HARGA
YARAN ( Rupiah ) ( Rupiah )
a b c d e f=dxe

16. (07) 22 Kapuk Pohon - - -


16. (07) 23 Kayu manis Pohon - - -
16. (07) 24 Kembang sepatu Rumpun/pot - - -
16. (07) 25 Kenanga Pohon - - -
16. (07) 26 Kirai payung Pohon - - -
16. (07) 27 Klengkeng Pohon - - -
16. (07) 28 Lantana Rumpun/pot - - -
16. (07) 29 Lili Orange Rumpun/pot - - -
16. (07) 30 Lili paris putih Rumpun/pot - - -
16. (07) 31 Nepholepis exaltata Rumpun/pot - - -
16. (07) 32 Rambutan Pohon - - -
16. (07) 33 Rumput Paitan M2 - - -
16. (07) 34 Salam Pohon - - -
16. (07) 35 Sansiviera ( pedang-pedangan ) Rumpun/pot - - -
16. (07) 36 Sphathypylum walisii Rumpun/pot - - -
16. (07) 37 Tabebuiya Pohon - - -
16. (07) 38 Trengguli Pohon - - -
16. (07) 39 Zypharanthes ( Kembang Coklat Putih ) Rumpun/pot - - -

TOTAL HARGA PENAWARAN UNTUK BAB 16 #REF!


( Pindahkan ke Rekapitulasi )

Page 48 of 60
PEMBANGUNAN JALAN TOL SEMARANG - SOLO TAHAP I
RUAS SEMARANG - BAWEN SEKSI II : GEDAWANG- PENGGARON
STA 3 + 525 - STA 8 +475

B U L A N K E:
ITEM NO. DESCRIPTION UNIT QUANTITY START FINISH START PEKERJAAN MULAI DURASI MULAI DURASI HARGA SATUAN TOTAL BOBOT %
1 2 3 4 5 6 7 8 9 10 11 12 13
BAB 1 UMUM
1.19 Pemeliharaan dan Perlindungan Lalu Lintas Lump Sum #REF! 1/1/2009 8:00 1/25/2010 17:00 1/1/2009 7:00 1 13 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
1.20(1) Laboraturium Lump Sum #REF! 1/1/2009 8:00 2/14/2009 17:00 1/1/2009 7:00 1 1 #REF! #REF! #REF! #REF! - - - - - - - - - - - -
1.20(2) Mobilisasi (yang tidak tercakup pada 1.20(1) Lump Sum #REF! 1/1/2009 8:00 3/31/2009 17:00 1/1/2009 7:00 1 3 #REF! #REF! #REF! #REF! #REF! #REF!
1.26 Pekerjaan dan Penanganan Aliran Air yang sudah ada Lump Sum #REF! 1/1/2009 8:00 11/26/2009 17:00 1/1/2009 7:00 1 11 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - -
BAB 2 PEMBERSIHAN TEMPAT KERJA - - - - - - - - - - - - -
2.01 Pembersihan tempat Kerja m2 253,478.52 1/15/2009 8:00 3/20/2009 17:00 1/1/2009 7:00 1 2 #REF! #REF! #REF! #REF! #REF! - - - - - - - - - - -
BAB 3 PEMBONGKARAN - - - - - - - - - - - - -
3.01(1) Pembongkaran Pasangan Batu atau Struktur Beton m3 817.57 1/22/2009 8:00 2/20/2009 17:00 1/1/2009 7:00 1 1 #REF! #REF! #REF! #REF! - - - - - - - - - - - -
3.01(2) Pembongkaran Kerb m' 50.00 1/22/2009 8:00 1/26/2009 17:00 1/1/2009 7:00 1 1 #REF! #REF! #REF! #REF! - - - - - - - - - - - -
3.01(3) Pembongkaran Perkerasan Jalan Aspal atau Beton m2 2,998.77 1/22/2009 8:00 2/12/2009 17:00 1/1/2009 7:00 1 1 #REF! #REF! #REF! #REF! - - - - - - - - - - - -
3.01(4) Pembongkaran Rambu Lalu Lintas buah 2.00 1/22/2009 8:00 1/28/2009 17:00 1/1/2009 7:00 1 1 #REF! #REF! #REF! #REF! - - - - - - - - - - - -
3.01(5) Pembongkaran Guardraill m' 40.00 1/22/2009 8:00 1/26/2009 17:00 1/1/2009 7:00 1 1 #REF! #REF! #REF! #REF! - - - - - - - - - - - -
BAB 4 PEKERJAAN TANAH - - - - - - - - - - - - -
4.03 (1) Galian Biasa untuk Timbunan m3 1,542,493.11 1/15/2009 8:00 11/10/2009 17:00 1/1/2009 7:00 1 10 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - -
4.03 (2) Galian Biasa untuk Dibuang m3 178,510.34 1/15/2009 8:00 10/16/2009 17:00 1/1/2009 7:00 1 9 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - -
4.05 (1) Borrow Material m3 879,686.34 3/16/2009 8:00 11/10/2009 17:00 1/1/2009 7:00 3 8 #REF! #REF! #REF! - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - -
4.09 Urugan Material Berbutir (Granular Backfill) m3 1,274.14 5/10/2009 8:00 10/1/2009 17:00 1/1/2009 7:00 5 5 #REF! #REF! #REF! - - - - #REF! #REF! #REF! #REF! #REF! - - - -
4.12 Pasangan Batu Kosong (Blinding Stone) m3 75.93 3/11/2009 8:00 4/10/2009 8:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
BAB 5 GALIAN STRUKTUR - - - - - - - - - - - - -
5.01 (1) Penggalian Struktur sampai kedalaman tidak lebih dari 2 m m3 9,166.42 4/4/2009 8:00 7/2/2009 17:00 1/1/2009 7:00 4 3 #REF! #REF! #REF! - - - #REF! #REF! #REF! - - - - - - -
5.01 (2) Penggalian Struktur sampai kedalaman lebih dari 2 m,tapi tidak lebih dari 4 m m3 5,519.78 4/4/2009 8:00 7/2/2009 17:00 1/1/2009 7:00 4 3 #REF! #REF! #REF! - - - #REF! #REF! #REF! - - - - - - -
5.01 (3) Penggalian Struktur sampai kedalaman lebih dari 4 m m3 5,318.09 4/4/2009 8:00 8/1/2009 17:00 1/1/2009 7:00 4 4 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF! - - - - - -
BAB 6 DRAINASE - - - - - - - - - - - - -
6.05 (1) Pipa Gorong-gorong Beton Tak Bertulang, dia. 40 cm m' 2,427.62 2/14/2009 8:00 6/8/2009 17:00 1/1/2009 7:00 2 4 #REF! #REF! #REF! - #REF! #REF! #REF! #REF! - - - - - - - -
6.05 (6) Pipa Gorong-gorong Beton Bertulang, dia. 60 cm, Tipe A m' 105.27 2/21/2009 8:00 3/13/2009 17:00 1/1/2009 7:00 2 1 #REF! #REF! #REF! - #REF! - - - - - - - - - - -
6.05 (7) Pipa Gorong-gorong Beton Bertulang, dia. 60 cm, Tipe B m' 55.48 3/14/2009 8:00 3/23/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
6.05 (10) Pipa Gorong-gorong Beton Bertulang, dia. 100 cm, Tipe A m' 434.97 2/14/2009 8:00 6/2/2009 17:00 1/1/2009 7:00 2 4 #REF! #REF! #REF! - #REF! #REF! #REF! #REF! - - - - - - - -
6.05 (20) Pipa Gorong-gorong Beton Bertulang, 2 dia. 100 cm, Tipe C m' 226.98 3/24/2009 8:00 5/22/2009 17:00 1/1/2009 7:00 3 2 #REF! #REF! #REF! - - #REF! #REF! - - - - - - - - -
6.06 (1a) Saluran, Tipe DS-1 m' 190.00 2/14/2009 8:00 3/9/2009 17:00 1/1/2009 7:00 2 1 #REF! #REF! #REF! - #REF! - - - - - - - - - - -
6.06 (1) Saluran, Tipe DS-3 m' 668.00 2/14/2009 8:00 5/8/2009 17:00 1/1/2009 7:00 2 3 #REF! #REF! #REF! - #REF! #REF! #REF! - - - - - - - - -
6.06 (2a) Saluran, Tipe DS-3B m' 5.00 5/9/2009 8:00 5/10/2009 17:00 1/1/2009 7:00 5 1 #REF! #REF! #REF! - - - - #REF! - - - - - - - -
6.06 (3) Saluran, Tipe DS-8 m' 10,731.00 2/14/2009 8:00 7/13/2009 17:00 1/1/2009 7:00 2 5 #REF! #REF! #REF! - #REF! #REF! #REF! #REF! #REF! - - - - - - -
6.06 (4) Saluran Beton dan Penutup, Tipe DC - 1 Buah 190.00 3/10/2009 8:00 6/1/2009 17:00 1/1/2009 7:00 3 3 #REF! #REF! #REF! - - #REF! #REF! #REF! - - - - - - - -
6.06 (4) Saluran Beton dan Penutup, Tipe DC - 5 Buah 14.00 6/2/2009 8:00 6/7/2009 17:00 1/1/2009 7:00 6 1 #REF! #REF! #REF! - - - - - #REF! - - - - - - -
6.06 (25) Inlet Drain, Tipe DI - 1 Buah 7.00 3/10/2009 8:00 3/16/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
6.06 (27) Inlet Drain, Tipe DI - 3 Buah 3.00 3/17/2009 8:00 3/18/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
6.06 (32) Outlet Drain, Tipe DO - 1 Buah 7.00 3/19/2009 8:00 3/25/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
6.06 (34) Outlet Drain, Tipe DO - 3 Buah 3.00 3/26/2009 8:00 3/27/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
6.07 (2) Selokan Pasangan Batu Mortar (Mortared Rubble), Tipe DS - 4 m' 2,264.00 3/10/2009 8:00 6/7/2009 17:00 1/1/2009 7:00 3 3 #REF! #REF! #REF! - - #REF! #REF! #REF! - - - - - - - -
6.07 (3) Selokan Pasangan Batu Mortar (Mortared Rubble), Tipe DS - 5 m' 4,652.00 3/10/2009 8:00 7/7/2009 17:00 1/1/2009 7:00 3 4 #REF! #REF! #REF! - - #REF! #REF! #REF! #REF! - - - - - - -
6.07 (7) Selokan Pasangan Batu Mortar (Mortared Rubble), Tipe DS - 10 m' 460.90 3/24/2009 8:00 4/22/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
6.07 (9) Pasangan Batu Kali untuk Inlet & Outlet pada Box Culvert / Wing Wall dan Goro m3 3,109.24 4/23/2009 8:00 6/21/2009 17:00 1/1/2009 7:00 4 2 #REF! #REF! #REF! - - - #REF! #REF! - - - - - - - -
6.08 (1) Pipa Drainase, dia. 15 cm, dengan perlengkapan sambungan dan penyangga m' 143.00 3/24/2009 8:00 3/30/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
6.08 (2) Pipa Drainase, dia. 20 cm, dengan perlengkapan sambungan dan penyangga m' 1,110.98 3/24/2009 8:00 5/22/2009 17:00 1/1/2009 7:00 3 2 #REF! #REF! #REF! - - #REF! #REF! - - - - - - - - -
6.08 (3) Deck Drain beserta asessorisnya, Tipe 1 Buah 286.00 11/21/2009 8:00 11/27/2009 17:00 1/1/2009 7:00 11 1 #REF! #REF! #REF! - - - - - - - - - - #REF! - -
6.09 (1) Bahan Porous untuk Penimbunan atau Bahan Penyaring (Filter) m3 3,317.08 5/10/2009 8:00 6/8/2009 17:00 1/1/2009 7:00 5 1 #REF! #REF! #REF! - - - - #REF! - - - - - - - -
6.09 (3)a Pipa Berlubang Banyak (Perforated Pipe) untuk Pekerjaan Drainase Bawah Perm m' 7,524.75 1/30/2009 8:00 6/8/2009 17:00 1/1/2009 7:00 1 4 #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - - - - - - -
6.09 (3)b Pipa Berlubang Banyak (Perforated Pipe) untuk Kolektor Pengumpul Sumber Air m' 288.00 6/3/2009 8:00 6/8/2009 17:00 1/1/2009 7:00 6 1 #REF! #REF! #REF! - - - - - #REF! - - - - - - -
6.09 (4) Geotekxtile Non Woven m2 20,325.57 1/10/2009 8:00 6/8/2009 17:00 1/1/2009 7:00 1 5 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - - - - - -
BAB 7 SUBGRADE - - - - - - - - - - - - -
7.01 Persiapan Tanah Dasar m2 131,373.00 4/15/2009 8:00 11/10/2009 17:00 1/1/2009 7:00 4 7 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - -
BAB 8 LAPIS PONDASI AGREGAT (SUBBASE) - - - - - - - - - - - - -
80.1 (1) Lapis Pondasi Agregat Kelas A m3 462.00 8/13/2009 8:00 11/30/2009 17:00 1/1/2009 7:00 8 4 #REF! #REF! #REF! - - - - - - - #REF! #REF! #REF! #REF! - -
80.1 (2) Lapis Pondasi Agregat Kelas B m3 14,530.68 6/14/2009 8:00 11/20/2009 17:00 1/1/2009 7:00 6 5 #REF! #REF! #REF! - - - - - #REF! #REF! #REF! #REF! #REF! - - -
BAB 9 PERKERASAN - - - - - - - - - - - - -
9.04 Bitumen Lapis Resap Pengikat (Prime Coat) kg 67,825.15 12/1/2009 8:00 12/14/2009 17:00 1/1/2009 7:00 12 1 #REF! #REF! #REF! - - - - - - - - - - - #REF! -
9.05 Bitumen Lapis Pengikat (tack Coat) kg 5,948.26 12/15/2009 8:00 12/28/2009 17:00 1/1/2009 7:00 12 1 #REF! #REF! #REF! - - - - - - - - - - - #REF! -
9.07 (1) Asphalt Treated Base Course ton 9,163.03 12/1/2009 8:00 12/14/2009 17:00 1/1/2009 7:00 12 1 #REF! #REF! #REF! - - - - - - - - - - - #REF! -
9.07 (2) Asphalt Concrete Binder Course ton 346.00 12/15/2009 8:00 12/20/2009 17:00 1/1/2009 7:00 12 1 #REF! #REF! #REF! - - - - - - - - - - - #REF! -
9.07 (3) Asphalt Concrete Wearing Course ton 1,398.36 12/21/2009 8:00 12/26/2009 17:00 1/1/2009 7:00 12 1 #REF! #REF! #REF! - - - - - - - - - - - #REF! -
9.07 (4) Semen Aspal ton 611.03 12/1/2009 8:00 12/14/2009 17:00 1/1/2009 7:00 12 1 #REF! #REF! #REF! - - - - - - - - - - - #REF! -
9.08 (1) Perkerasan Beton (t=31 cm) m2 70,008.00 4/29/2009 8:00 1/13/2010 17:00 1/1/2009 7:00 4 9 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! -
9.09 (1) Lean Concrete (t=10 cm) m2 88,084.00 4/29/2009 8:00 1/13/2010 17:00 1/1/2009 7:00 4 9 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! -
BAB 10 STRUKTUR BETON - - - - - - - - - - - - -
10.01 (4) Beton Kelas B - 1 m3 5,230.66 4/10/2009 8:00 11/20/2009 17:00 1/1/2009 7:00 4 7 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - -
10.01 (7) Beton Kelas C - 1 m3 7,686.42 4/10/2009 8:00 10/21/2009 17:00 1/1/2009 7:00 4 6 #REF! #REF! #REF! - - - #REF! #REF! #REF! #REF! #REF! #REF! - - - -
10.01 (8) Beton Kelas C - 2 m3 786.66 7/1/2009 8:00 1/11/2010 17:00 1/1/2009 7:00 7 6 #REF! #REF! #REF! - - - - - - #REF! #REF! #REF! #REF! #REF! #REF! -
10.01 (9) Beton Kelas D m3 34.28 2/14/2009 8:00 6/8/2009 17:00 1/1/2009 7:00 2 4 #REF! #REF! #REF! - #REF! #REF! #REF! #REF! - - - - - - - -
10.01 (10) Beton Kelas E m3 875.80 2/14/2009 8:00 6/13/2009 17:00 1/1/2009 7:00 2 4 #REF! #REF! #REF! - #REF! #REF! #REF! #REF! - - - - - - - -
10.01 (12) Beton Kelas B - B m3 9,726.64 4/17/2009 8:00 7/16/2009 17:00 1/1/2009 7:00 4 3 #REF! #REF! #REF! - - - #REF! #REF! #REF! - - - - - - -
10.02 (1) Batang Baja Tulangan Polos kg 980.66 2/14/2009 8:00 9/26/2009 17:00 1/1/2009 7:00 2 7 #REF! #REF! #REF! - #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - - -
10.02 (2) Batang Baja Tulangan Ulir kg #REF! 2/14/2009 8:00 9/26/2009 17:00 1/1/2009 7:00 2 7 #REF! #REF! #REF! - #REF! #REF! #REF! #REF! #REF! #REF! #REF! - - - - -
10.02 (3) Anchor Bar + Anchor Cap dia 32 mm & Accessories (Fix & Move) buah #REF! 5/18/2009 8:00 7/16/2009 17:00 1/1/2009 7:00 5 2 #REF! #REF! #REF! - - - - #REF! #REF! - - - - - - -
10.02 (4) Anchor Bar + Anchor Cap dia 25 mm & Accessories (Fix & Move) buah #REF! 5/18/2009 8:00 7/16/2009 17:00 1/1/2009 7:00 5 2 #REF! #REF! #REF! - - - - #REF! #REF! - - - - - - -
10.03 (1)a Pengadaan dan Pemasangan P.C.I Girder, bentang 16,00 m buah #REF! 6/1/2009 8:00 8/23/2009 17:00 1/1/2009 7:00 6 3 #REF! #REF! #REF! - - - - - #REF! #REF! #REF! - - - - -
10.03 (1)b Pengadaan dan Pemasangan P.C.C Girder, bentang 16,00 m buah #REF! 6/8/2009 8:00 8/2/2009 17:00 1/1/2009 7:00 6 2 #REF! #REF! #REF! - - - - - #REF! #REF! - - - - - -
10.03 (3)a Pengadaan dan Pemasangan P.C.I Girder, bentang 25 m buah 6.00 6/15/2009 8:00 7/26/2009 17:00 1/1/2009 7:00 6 1 #REF! #REF! #REF! - - - - - #REF! - - - - - - -
10.03 (3)b Pengadaan dan Pemasangan P.C.C Girder, bentang 25 m buah 4.00 6/22/2009 8:00 7/12/2009 17:00 1/1/2009 7:00 6 1 #REF! #REF! #REF! - - - - - #REF! - - - - - - -
10.03 (4)a Pengadaan dan Pemasangan P.C.I Girder, bentang 30.6 m buah 14.00 6/15/2009 8:00 9/20/2009 17:00 1/1/2009 7:00 6 3 #REF! #REF! #REF! - - - - - #REF! #REF! #REF! - - - - -
10.03 (4)b Pengadaan dan Pemasangan P.C.C Girder, bentang 30.6 m buah 8.00 6/22/2009 8:00 8/16/2009 17:00 1/1/2009 7:00 6 2 #REF! #REF! #REF! - - - - - #REF! #REF! - - - - - -
10.03 (6)a Pengadaan dan Pemasangan/Ereksi P.C.I Girder, bentang 40 m buah 3.00 8/17/2009 8:00 9/6/2009 17:00 1/1/2009 7:00 8 1 #REF! #REF! #REF! - - - - - - - #REF! - - - - -
10.03 (6)b Pengadaan dan Pemasangan/Ereksi P.C.C Girder, bentang 40 m buah 2.00 8/24/2009 8:00 9/6/2009 17:00 1/1/2009 7:00 8 1 #REF! #REF! #REF! - - - - - - - #REF! - - - - -
10.03 (6) c Pengadaan P.C.I Girder, bentang 40,60 m untuk Jembatan Banyumanik I buah 120.00 6/15/2009 8:00 10/12/2009 17:00 1/1/2009 7:00 6 4 #REF! #REF! #REF! - - - - - #REF! #REF! #REF! #REF! - - - -
10.03 (6) d Lounching P.C.I Girder, bentang 40,60 m untuk Jembatan Banyumanik I dan buah 120.00 7/15/2009 8:00 10/12/2009 17:00 1/1/2009 7:00 7 3 #REF! #REF! #REF! - - - - - - #REF! #REF! #REF! - - - -
10.03 (7) Plat Pracetak (Concrete Plate) m2 7,525.61 7/1/2009 8:00 1/11/2010 17:00 1/1/2009 7:00 7 6 #REF! #REF! #REF! - - - - - - #REF! #REF! #REF! #REF! #REF! #REF! -
10.04 (1) Penyediaan tiang pancang mini (mini pile) Precast,25 x 25 cm m' 7,695.00 3/21/2009 8:00 4/16/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
10.04 (2) Pemancangan tiang pancang mini (mini pile) Precast,25 x 25 cm m' 7,695.00 3/28/2009 8:00 5/20/2009 17:00 1/1/2009 7:00 3 2 #REF! #REF! #REF! - - #REF! #REF! - - - - - - - - -
10.04 (3) Penyediaan dan pemancangan tiang pancang mini (mini pile) Precast untuk test m' 48.00 3/28/2009 8:00 4/1/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
10.05 (1) Penyedian Tiang Pancang Beton Bulat Pretensioned, dia 50 cm m' 7,850.00 3/21/2009 8:00 4/17/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
10.05 (2) Pemancangan Tiang Pancang Beton Bulat Pretensioned, dia 50 cm m' 7,850.00 3/28/2009 8:00 5/21/2009 17:00 1/1/2009 7:00 3 2 #REF! #REF! #REF! - - #REF! #REF! - - - - - - - - -
10.05 (3) Penyediaan & Pemancangan Tiang Pancang Beton Bulat Pretensioned, Pile Test, m' 90.00 3/28/2009 8:00 4/1/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
10.07 (5) Tiang bor beton cast-in-place, dia. 120 cm 3,275.00 3/21/2009 8:00 6/18/2009 17:00 1/1/2009 7:00 3 3 #REF! #REF! #REF! - - #REF! #REF! #REF! - - - - - - - -
10.07 (10) a Tes pembebanan, 2 kali beban perencanaan secara Statis 2.00 3/28/2009 8:00 3/29/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
10.07 (10) b Tes pembebanan tiang, secara Dinamis buah 11.00 3/30/2009 8:00 4/9/2009 17:00 1/1/2009 7:00 3 1 #REF! #REF! #REF! - - #REF! - - - - - - - - - -
10.09 (1) Sambungan Ekpansi (Expansion Joint), Type A m' 96.00 7/28/2009 8:00 11/20/2009 17:00 1/1/2009 7:00 7 4 #REF! #REF! #REF! - - - - - - #REF! #REF! #REF! #REF! - - -
10.09 (9) Modular Expantion Joint 3 Seals m' 75.60 7/28/2009 8:00 11/20/2009 17:00 1/1/2009 7:00 7 4 #REF! #REF! #REF! - - - - - - #REF! #REF! #REF! #REF! - - -
10.09 (11) Rubber Expantion Joint Type Fixed 20 m' 75.60 7/28/2009 8:00 11/20/2009 17:00 1/1/2009 7:00 7 4 #REF! #REF! #REF! - - - - - - #REF! #REF! #REF! #REF! - - -
10.10 (1) a Metal Bearing Shoe, type B buah 36.00 8/13/2009 8:00 11/20/2009 17:00 1/1/2009 7:00 8 3 #REF! #REF! #REF! - - - - - - - #REF! #REF! #REF! - - -
10.10 (3) Bearing Pad dengan asesoris ukuran (300 x 350 x 36 mm) buah 40.00 6/1/2009 8:00 8/23/2009 17:00 1/1/2009 7:00 6 3 #REF! #REF! #REF! - - - - - #REF! #REF! #REF! - - - - -
10.10 (5) Bearing Pad dengan asesoris ukuran (400 x 350 x 39 mm) buah 54.00 6/15/2009 8:00 7/26/2009 17:00 1/1/2009 7:00 6 1 #REF! #REF! #REF! - - - - - #REF! - - - - - - -
10.10 (8) Bearing Pad dengan asesoris ukuran (400 x 400 x 39 mm) buah 20.00 6/15/2009 8:00 9/20/2009 17:00 1/1/2009 7:00 6 3 #REF! #REF! #REF! - - - - - #REF! #REF! #REF! - - - - -
10.10 (10) Bearing Pad dengan asesoris ukuran (450 x 400 x 52 mm) buah 72.00 6/15/2009 8:00 8/13/2009 17:00 1/1/2009 7:00 6 2 #REF! #REF! #REF! - - - - - #REF! #REF! - - - - - -
BAB 12 PEKERJAAN LAIN LAIN - - - - - - - - - - - - -
12.01 (3) Solid Sodding m2 250,947.00 12/27/2009 8:00 1/25/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.05 (1) Guardrail, tipe A m' 4,254.00 12/27/2009 8:00 1/25/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.05 (2) End Section Guardrail buah 30.00 12/27/2009 8:00 1/10/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.05 (4) Railing fence m' 429.80 1/3/2010 8:00 1/9/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.06 (1) Rambu Pengaturan dan Peringatan, Tipe A-1 buah 11.00 1/3/2010 8:00 1/4/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.06 (2) Rambu Pengaturan dan Peringatan, Tipe A-2 buah 12.00 1/3/2010 8:00 1/4/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.06 (5) Rambu Pengaturan dan Peringatan, Tipe C buah 27.00 1/3/2010 8:00 1/5/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.07 (1) Rambu Petunjuk, Peringatan dan Larangan Tipe A - 1 buah 11.00 1/6/2010 8:00 1/7/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.07 (2) Rambu Petunjuk, Peringatan dan Larangan Tipe A - 2 buah 3.00 1/6/2010 8:00 1/6/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.07 (3) Rambu Petunjuk, Peringatan dan Larangan Tipe A - 3 buah 8.00 1/6/2010 8:00 1/6/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.08 (1) Marka Jalan Tipe 1 m2 3,632.92 1/6/2010 8:00 1/18/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.09 (1) Guide Post, tipe A buah 288.00 12/27/2009 8:00 1/2/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.09 (2) Guide Post, tipe B buah 554.00 12/27/2009 8:00 1/2/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.09 (5) Kilometer Post buah 26.00 12/27/2009 8:00 12/29/2009 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.10 (1) Concrete Barrier, Tipe-A m' 4,598.00 12/27/2009 8:00 1/23/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.10 (2) Concrete Barrier, Tipe-B m' 358.00 12/27/2009 8:00 1/23/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.11 (1) Kerb Beton, Tipe-A m' 774.47 12/27/2009 8:00 1/23/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.12 (1) Pagar ROW, Tipe 1 (Panel Beton) m' 3,951.00 12/27/2009 8:00 1/23/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.12 (1) Pagar ROW, Tipe 2 (Kawat Berduri) m' 5,765.00 12/27/2009 8:00 1/23/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.13 (1) Blok Beton Perlindungan Lereng / Talud m2 1,077.20 12/27/2009 8:00 1/23/2010 17:00 1/1/2009 7:00 13 1 #REF! #REF! #REF! - - - - - - - - - - - - #REF!
12.14 Jalur Penyelamat Lumpsump 3.00 12/12/2009 8:00 1/25/2010 17:00 1/1/2009 7:00 12 1 #REF! #REF! #REF! - - - - - - - - - - - #REF! -
12.15 Paving Blok Natural ( ukuran 21 x 10,5 x 8 cm ), K350 m3 222.60 12/26/2009 8:00 1/24/2010 17:00 1/1/2009 7:00 12 1 #REF! #REF! #REF! - - - - - - - - - - - #REF! -
BAB 13 PENCAHAYAAN LAMPU LALU LINTAS DAN PEKERJAAN LISTRIK - - - - - - - - - - - - -
13.01(36) Pipa PVC Ø 4" m' 266.81 11/21/2009 8:00 11/27/2009 17:00 1/1/2009 7:00 11 1 #REF! #REF! #REF! - - - - - - - - - - #REF! - -
13.01(37) Pipa PVC Ø 6 " m' 2,183.94 11/21/2009 8:00 12/4/2009 17:00 1/1/2009 7:00 11 1 #REF! #REF! #REF! - - - - - - - - - - #REF! - -
13.01(38) Pipa PVC Ø 8 " m' 245.43 11/21/2009 8:00 11/27/2009 17:00 1/1/2009 7:00 11 1 #REF! #REF! #REF! - - - - - - - - - - #REF! - -
BAB 16 PEKERJAAN FASILITAS TOL DAN KANTOR GERBANG TOL - - - - - - - - - - - - -
16.01 (4) JALAN LINGKUNGAN, PARKIR KENDARAAN - - - - - - - - - - - - -
16.01 (4).1 Paving block Natural (ukuran 21 x 10,5 x 8 cm), K350 m2 424.40 11/21/2009 8:00 12/10/2009 17:00 1/1/2009 7:00 11 1 #REF! #REF! #REF! - - - - - - - - - - #REF! - -
Jumlah #REF! #REF!
0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
0 #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!

Jakarta, 21 Juli 2008


PT. Waskita Karya (Persero)
Divisi Sipil

Ir. Desi Arryani, MM.


Kepala
uraian qty
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

Pay Item :
No. Pay Item : Lean Concrete & Beton , Class E & D
Lokasi : Saluran Tipe 3 ,Seksi I
0.80
0.15 0.50 0.15

0.60

Beton Klas D

Lean Concrete t= 10 Cm
0.15

0.90

PERHITUNGAN :

LC & BETON SALURAN DS - 3 SEKSI I

DIMENSI
NO. SALURAN JML LUASAN PANJANG LEBAR TINGGI VOLUME KET.
(m²) (m) (m) (m) (m³ / m' )

1 DS - 3 1.00 1.00 0.90 0.10 0.090 Beton


Klas E

2 DS - 3 1.00 0.26 1.00 - - 0.255 Beton


Klas D

TOTAL LC SALURAN TIPE DS -3 BETON KLAS E = 0.090 m³ / m'

TOTAL BETON SALURAN TIPE DS -3 BETON KLAS D = 0.255 m³ / m'

,Kontraktor
Persero PT. Waskita Karya
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

NO. PAY ITEM :


PAY ITEM : Besi Saluran Tipe 3
LOKASI : SEKSI 1 ,Semarang ~ bawen
SKETS :

0.80
0.15 0.50 0.15
D10-200

D10-200

0.60 D13-200

0.15

0.90

NO. SALURAN SATUAN VOLUME KETERANGAN

1 BESI SALURAN DS-3 Kg 18.01


Saluran Tipe 3

Besi D10 = 3,66 Kg

Besi D13 = 14,35 Kg

TOTAL BESIBESI SALURAN DS-3 18.01 Kg/ m'


uraian qty
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

Pay Item :
No. Pay Item : Lean Concrete & Beton , Class E & C
Lokasi : Saluran Tipe 3A ,Seksi I
1.16
Beton Klas C
0.15 0.86 0.15

0.07

0.80 Beton Klas C

Lean Concrete t= 10 Cm
0.20

1.36

PERHITUNGAN :

LC & BETON SALURAN DS - 3A SEKSI I

DIMENSI
NO. SALURAN JML LUASAN PANJANG LEBAR TINGGI VOLUME KET.
(m²) (m) (m) (m) (m³ / m' )
1 DS - 3A 1.00 1.00 1.36 0.10 0.140 Beton
Klas E

2 DS - 3A 1.00 0.492 1.00 - - 0.492 Beton


Klas C

3 DS - 3A 1.00 1.00 0.86 0.07 0.060 Beton tutup


Klas C

TOTAL LC SALURAN TIPE DS -3A BETON KLAS E = 0.140 m³ / m'

TOTAL BETON SALURAN TIPE DS -3A BETON KLAS C = 0.552 m³ / m'

,Kontraktor
Persero PT. Waskita Karya
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

NO. PAY ITEM :


PAY ITEM : Besi Saluran Tipe 3A
LOKASI : SEKSI 1 ,Semarang ~ bawen
SKETS :

0.15 0.86 0.15


D10-200

0.07
D10-200

D13-200
0.80

0.20

1.36

NO. SALURAN SATUAN VOLUME KETERANGAN

1 BESI SALURAN DS-3A Kg 22.52


Sal Tipe 3A

Besi D10 = 4,73 Kg

Besi D13 = 17,78 Kg

TOTAL BESI SALURAN TIPE 3A 22.52 Kg/ m'


uraian qty
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

Pay Item :
No. Pay Item : Lean Concrete & Beton , Class E & C
Lokasi : Saluran Tipe 3B ,Seksi I
0.90
Beton Klas C
0.20 0.50 0.20 Besi siku L 50x50x5 mm

0.07

Besi siku L 70x70x7 mm

Beton Klas C
0.95

Lean Concrete t= 5 Cm
0.20

0.90

PERHITUNGAN :

LC & BETON SALURAN DS - 3B SEKSI I

DIMENSI
NO. SALURAN JML LUASAN PANJANG LEBAR TINGGI VOLUME KET.
(m²) (m) (m) (m) (m³ / m' )
1 DS - 3B 1.00 1.00 0.90 0.10 0.090 Beton
Klas E

2 DS - 3B 1.00 0.507 1.00 - - 0.507 Beton


Klas C

3 DS - 3B 1.00 1.00 0.90 0.07 0.060 Beton tutup


Klas C

TOTAL LC SALURAN TIPE DS -3B BETON KLAS E = 0.090 m³ / m'

TOTAL BETON SALURAN TIPE DS -3B BETON KLAS C = 0.567 m³ / m'

,Kontraktor
Persero PT. Waskita Karya
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

NO. PAY ITEM :


PAY ITEM : Besi Saluran Tipe 3B
LOKASI : SEKSI 1 ,Semarang ~ bawen
SKETS :
0.90

0.20 0.50 0.20 D10-200

0.07
D10-200

D16-200
0.95

0.20

0.90

NO. SALURAN SATUAN VOLUME KETERANGAN

1 BESI SALURAN DS-3B Kg 35.11


Sal Tipe 3B

Besi D10 = 8,79 Kg

Besi D16 = 26,31 Kg

TOTAL BESI SALURAN TIPE 3B 35.11 Kg/ m'


uraian qty
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

Pay Item :
No. Pay Item : Pasir & batu kali
Lokasi : Saluran Tipe 4 ,Seksi I

2.10

0.30 0.50 0.50 0.50 0.30

0.20
1:1 1:1
0.50 Pasir t=5 Cm

Pasangan Batu kali 1 : 3


0.20

Pasir t=5 Cm

PERHITUNGAN :

PASIR & BATU KALI SALURAN DS - 4 SEKSI I

DIMENSI
NO. SALURAN JML LUASAN PANJANG LEBAR TINGGI VOLUME KET.
(m²) (m) (m) (m) (m³ / m' )
1 DS - 4 1.00 0.042 1.00 - - 0.042 Pasir

2 DS - 4 1.00 0.470 1.00 - - 0.470 Batu kali

TOTAL PASIR URUG SALURAN DS-4 = 0.042 m³ / m'

TOTAL BATU KALI SALURAN DS-4 = 0.470 m³ / m'

,Kontraktor
Persero PT. Waskita Karya
uraian qty
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

Pay Item :
No. Pay Item : Pasir & batu kali
Lokasi : Saluran Tipe 5 ,Seksi I

2.85

0.30 0.75 0.75 0.75 0.30

0.20
1:1 1:1
0.75 Pasir t=5 Cm

Pasangan Batu kali 1 : 3


0.20

Pasir t=5 Cm

PERHITUNGAN :

PASIR & BATU KALI SALURAN DS - 5 SEKSI I

DIMENSI
NO. SALURAN JML LUASAN PANJANG LEBAR TINGGI VOLUME KET.
(m²) (m) (m) (m) (m³ / m' )
1 DS - 5 1.00 0.058 1.00 - - 0.058 Pasir

2 DS - 5 1.00 0.570 1.00 - - 0.570 Batu kali

TOTAL PASIR URUG SALURAN DS-5 = 0.058 m³ / m'

TOTAL BATU KALI SALURAN DS-5 = 0.570 m³ / m'

,Kontraktor
Persero PT. Waskita Karya
uraian qty
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

Pay Item :
No. Pay Item : Pasir & beton klas E
Lokasi : Saluran Tipe 8 ,Seksi I

0.20 0.20
Mortar Klas E

Beton Klas E
0.15
Ø 400 1/2

Pasir t=5 Cm

0.05 Buis beton 1/2 Ø 400

PERHITUNGAN :

PASIR & LC SALURAN DS - 8 SEKSI I

DIMENSI
NO. SALURAN JML LUASAN PANJANG LEBAR TINGGI VOLUME KET.
(m²) (m) (m) (m) (m³ / m' )
1 DS - 8 0.016 1.00 - - 0.016 Pasir

2 DS - 8 0.160 1.00 - - 0.160 Beton


Klas E

3 DS - 8 - 1.00 buis beton 1/2 Ø 400 - Buis 1/2 beton

TOTAL PASIR URUG SALURAN DS-8 = 0.016 m³ / m'

TOTAL BETON KLAS E SALURAN DS-8 = 0.160 m³ / m'

,Kontraktor
Persero PT. Waskita Karya
uraian qty
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

Pay Item :
No. Pay Item : sirtu ; beton klas E & beton klas C1
Lokasi : Saluran Tipe DC-1 ,Seksi I

Beton Klas C1

LC Klas E t = 10Cm

Sirtu t=20 Cm

PERHITUNGAN :

SIRTU ; 7 BETON KLAS E ; KLAS C1 SALURAN TIPE DC-1 SEKSI I

DIMENSI
NO. SALURAN JML LUASAN PANJANG LEBAR TINGGI VOLUME KET.
(m²) (m) (m) (m) (m³ / m' )
1 DC - 1 0.200 0.80 - - 0.160 Sirtu

2 DC - 1 0.100 0.80 - - 0.080 Beton


Klas E

3 DC - 1 0.740 0.80 0.592 Beton


Klas C1

TOTAL SIRTU SALURAN DC-1 = 0.160 m³ / m'


TOTAL BETON KLAS E SALURAN DC-1 = 0.080 m³ / m'
TOTAL BETON KLAS C1 SALURAN DC-1 = 0.672 m³ / m'

,Kontraktor
Persero PT. Waskita Karya
PT. JASA MARGA (Persero)
PEMBANGUNAN JALAN TOL SEMARANG - SOLO
RUAS SEMARANG - BAWEN
SEKSI I : TEMBALANG - GEDAWANG ( STA=0+000 s/d 3+525 )

PERHITUNGAN VOLUME

NO. PAY ITEM :


PAY ITEM : Besi Saluran Tipe DC-1
LOKASI : SEKSI 1 ,Semarang ~ bawen
SKETS :

D10-200

D10-200

D16-200

NO. SALURAN SATUAN VOLUME KETERANGAN

1 BESI SALURAN DC-1 Kg 40.75


Sal Tipe DC-1

Besi D10 = 9,71 Kg

Besi D16 = 31,03 Kg

TOTAL BESI SALURAN TIPE DC-1 40.75 Kg/ m'