SAFETY PRECAUTION

STEEL WIRE D24


1 While slinging work, don't operate crane. L=6m 150
9.5T SHACKLE
2 After lift up 30 cm, keep 30 seconds, then start to lift up. (3-3-3 exercises)
3 Before slinging work, check wire rope state and wrap it with inspected tape SUPPORT LIFTING BEAM

150
4 Car driver don't do slinging work 150x150x8 L=3m 9.5T SHACKLE
3T CHAIN BLOCK
5 Monitor must check that nobody stay under heavy load while lifting up. STEEL WIRE D20
6 The men who send signal must discuss the way of sign. L=4m

EQUIPMENT LIST chiller foundation bea

No NAME WEIGHT (KG) TIME


1 CONTAINER 12550 02
DETAIL-1 DE
2 CHILLER 8850 02
3 WATER SUPPLY PUMP 120 01
4 TANK 1200 03 12
SIGNAL MAN
watch man 8
10
09
EXISTING FOUNDATION a
EXISTING FOUNDATION b

DETAIL

11 13

signal man

mh mh

mh mh mh

barricade

CRANE 200T
6
signal man
1
watch man
supervisor
direction
control man
STEEL plate barricade
2 CHILLER
10T FORKLIFT 9560x2260x2460 1000x1000x20
5 7

watch man
TRAILER