You are on page 1of 12

Computers and Structures 125 (2013) 11–22

Contents lists available at SciVerse ScienceDirect

Computers and Structures


journal homepage: www.elsevier.com/locate/compstruc

Time-dependent analysis of cable domes using a modified dynamic


relaxation method and creep theory
Stanislav Kmet ⇑, Marek Mojdis
Technical University of Kosice, Faculty of Civil Engineering, Institute of Structural Engineering, Vysokoskolska 4, Kosice, Slovakia

a r t i c l e i n f o a b s t r a c t

Article history: The stiffness of cable domes is conditioned by their states of prestress. The decrease of prestress due to
Received 18 December 2012 creep of cables determines the serviceability and load bearing capacity of the cable dome. In this paper, a
Accepted 20 April 2013 modified dynamic relaxation method for a time-dependent non-linear static analysis of cable domes
Available online 26 May 2013
based on the application of creep theory is presented. Creep constitutive equations in logarithmic forms
are directly used for the adjustment of cable lengths. The applicability of the modified dynamic relaxation
Keywords: method to this type of structures composed of steel and synthetic cables and struts with a finite element
Dynamic relaxation method
idealisation is demonstrated.
Time-dependent analysis
Cable domes
Ó 2013 Elsevier Ltd. All rights reserved.
Steel cable
Synthetic cable
Creep

1. Introduction dome could fail. That is why a time-dependent structural analysis


in order to verify the required prestress level of the structure antic-
Cable domes are lightweight spatial pre-stressed structures that ipated during its design lifetime is needed.
are increasingly investigated as structural solutions for large-span Yuan and Dong [5] proposed the concept of feasible integral
roof systems. The cable dome structures first proposed by Geiger prestress modes considering the inherent geometric symmetry of
et al. [1] have been developed in recent years due to their innova- cable domes. However, the proposed concept is effective only for
tive forms, lightweight and deployability [2]. They belong to a class domes with a single integral prestress mode, and cannot be applied
of pre-stressed pin-jointed systems that cannot be stable without to a dome with multiple feasible integral prestress modes. There-
introducing prestresses to some members [3]. fore, authors in [6] established a general method to determine
Yuan and Dong [4] present a good insight into the behaviour of the distribution of initial prestresses for different types of cable
cable domes through nonlinear analysis and optimum design. domes.
Introducing a prestress is very important to a cable dome, because Experiences with a number of cable structures constructed of
it has no initial rigidity prior to prestress. The stiffness of cable do- steel wire ropes or synthetic fibre ropes have shown that their pos-
mes is conditioned by their states of prestress. The level of pre- sible failure is characterised by the time-dependent changes in the
stress will not only affect the geometric configuration, but also tension stiffness and consequently by excessive deflections of
determine the serviceability and load bearing capacity of the cable structures due to the increments of cable member lengths sub-
dome. In other words, the prestress should provide the dome en- jected to creep [7]. Thus it is necessary to be precise in prediction
ough stiffness to assure that all cables will not slacken under an ap- of creep strains as the size of creep strains can significantly influ-
plied external load. Additionally, the lower the prestress level is, ences total deformations of cables and consequently, the actual
the better the design is because high prestress levels will lead to behaviour of cable structures, too. Therefore an improvement in
large forces acting back on the boundary ring, which increases the prediction of time-dependent behaviour of cable domes due
the difficulty of construction and decreases the economical effi- to creep effects is the scope of the present paper in which we de-
ciency of such structures. scribe a possible application of a modified dynamic relaxation
If cables slacken or struts become overstressed at a certain pre- method as an effective tool for the time-dependent analysis of
stress level or a certain action effects (i.e. certain load case), the these types of structures.
Parallel-lay ropes, made from synthetic materials, are increas-
ingly being used for structural applications as pre-stressing ten-
⇑ Corresponding author. Tel.: +421 55 602 2121; fax: +421 55 6332748. dons and tension members in the civil engineering industry.
E-mail address: stanislav.kmet@tuke.sk (S. Kmet). Parallel-lay aramid ropes have been identified as an attractive

0045-7949/$ - see front matter Ó 2013 Elsevier Ltd. All rights reserved.
http://dx.doi.org/10.1016/j.compstruc.2013.04.019
12 S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22

material for use in pre-stressed concrete structures and cable this type of structures composed of steel and synthetic cables and
stayed and suspension cable structures. It is clear that for the anal- struts with a finite element idealisation is demonstrated.
ysis and reliability assessment of these structures, an accurate pre-
diction of material rheological properties is highly desirable, as 2. Formulation of the modified dynamic relaxation method
long-term pre-stressing is required and variable load effects are ex- suitable for time-dependent analyses
pected. The ability to predict the creep of the ropes under varying
stresses is therefore very important, since the ropes are made from The dynamic relaxation method is an iterative pseudo-dynamic
materials which exhibit rheological behaviour [8–10]. technique for tracing the motion of a structure from the time of
The dynamic relaxation method proposed by Day [11] is an ex- loading to when it reaches a position of equilibrium arising from
plicit iterative method for the static solution of structural-mechan- the effects of damping [19].
ics problems [12]. The method is very popular and has been The dynamic relaxation method is an attractive approach for
improved and applied by many researchers to solve a variety of the design of pre-stressed cable domes because both form-finding
engineering tasks. The dynamic relaxation method has been re- and analysis can be carried out within a single analytical
searched and applied by Barnes [13,14], Lewis et al. [15], Wakefield framework.
[16], Topping and Khan [17], Lewis [18], Topping and Ivanyi [19], This section describes an overview of the basic governing equa-
Domer et al. [20], Douthe and Baverel [21], Rezaiee-Pajand et al. tions of this method with proposing the necessary modifications to
[22] and others. The mathematical basis of the method was dis- the dynamic relaxation algorithm when applied to a time-depen-
cussed by Papadrakakis [23] and Underwood [12]. Lewis et al. dent analysis of cable domes that are idealised using finite
[15] analysed the non-linear static response of pretensioned cable elements.
roofs using a non-linear energy approach. Dynamic relaxation pre-
sents itself as an attractive approach to the design of prestressed 2.1. Governing equations
cable networks because both form-finding and analysis can be car-
ried out within a relatively single analytical framework. The tech- At any time t the residual force Rtix in the x coordinate direction
nique traces the fictitious motion of the structure from the point of at node i, as the difference between external and internal forces in
loading to the final steady equilibrium state (minimum energy) the corresponding direction, is expressed as
through the use of D’Alembert’s principle [24]. Furthermore,
Barnes [13,14] showed that dynamic relaxation is particularly effi- Rtix ¼ Mix v_ tix þ C ix v tix ð1Þ
cient for form-finding and analysis of tension structures. where Mix is the fictitious mass at node i in the x direction, Cix is the
Wood [25] presented a simple technique for controlling mesh viscous damping factor for node i in the x direction, v tix is the veloc-
distortion during the form-finding of membranes when using dy- ity at time t in the x direction at node i and v_ tix is the acceleration at
namic relaxation. Han and Lee [26] studied the stabilizing process time t in the x direction at node i. The governing equations of the
of unstable structures by applying the dynamic relaxation method. dynamic relaxation method are presented for a system with one de-
Lee et al. [27] used the simple explicit cylindrical arc-length meth- gree of freedom.
od to trace the post-buckling equilibrium path of the structures by Due to damping, nodal velocities and accelerations decay to
combining the dynamic relaxation method with the kinetic damp- zero as the solution is approached. The static equilibrium is thus
ing technique. Rezaiee-Pajand and Sarafrazi [28] proposed an alter- attained and the residual forces come to zero.
native procedure for the common dynamic relaxation method, Let us introduce into Eq. (1) time s which characterises current
which can be applied to the dynamic problems. Alamatian [29] parameters of the structure depending on the creep strain incre-
presented a new formulation for the fictitious mass of the dynamic ments in the cable members at the investigated discrete times sk
relaxation method with kinetic damping. Zhang et al. [30] pre- for k ¼ 1; 2; . . . ; K and consequently, Eq. (1) is rewritten as
sented the form-finding of non-regular tensegrity structures with
a numerical approach based on the dynamic relaxation method Rtix ðsk Þ ¼ M ix ðsk Þv_ tix ðsk Þ þ C ix ðsk Þv tix ðsk Þ ð2Þ
with kinetic damping. New tensegrity configurations that exhibit Individual terms in Eq. (2) are expressed as time-dependent on cur-
more intricate and creative forms can be obtained by this method. rent creep strain increments of cables, hence on current cable
A review of computational methods for tension structures can lengths at investigated times sk while time t characterises the time
be found in [19]. When the dynamic relaxation method is used, of the iteration process.
the static problem is transformed into a pseudo-dynamic one by In the dynamic relaxation method, the maximum kinetic energy
introducing fictitious inertia and damping terms in the equation peak through the calculation of consecutive nodal velocities at
of motion. Dynamic relaxation traces the motion of each node of each time increment is chosen as a new reference state. The anal-
a structure until, due to artificial damping, the structure comes ysis traces the behaviour of the structure at a series of points in
to rest in static equilibrium. One of the advantages of this method time t; t þ Dt; t þ 2Dt; . . . etc. By considering that the nodal velocity
is that the global stiffness matrix is not needed and hence, the varies linearly with time and the acceleration is assumed constant
method is particularly suitable for problems with material and over the time step Dt (small time interval) Eq. (2) can be re-ar-
geometrical nonlinearities. Bel Hadj Ali et al. [31] presented a mod- ranged to give the recurrence equation for the nodal velocity at
ified dynamic relaxation algorithm for static analysis and form- the new time step (t + Dt/2) from the velocity of the previous time
finding of clustered tensegrity structures. Kadkhodayan et al. [32] step (t  Dt/2)
developed an improved dynamic relaxation method by introducing  
a modified fictitious time increment. M ix ðsk Þ=Dt  C ix ðsk Þ=2
v ixtþDt=2 ðsk Þ ¼ v ixtDt=2 ðsk Þ
In this paper, a modified dynamic relaxation method for a time- M ix ðsk Þ=Dt þ C ix ðsk Þ=2
 
dependent non-linear static analysis of cable domes based on the 1
application of creep theory is presented. The method is extended þ Rtix ðsk Þ ð3Þ
Mix ðsk Þ=Dt þ C ix ðsk Þ=2
to directly analyse rheological changes of cable domes due to creep
effects of cables. Creep constitutive equations in logarithmic forms, The velocities given by Eq. (3) are then used to predict the new
for the adjustment of cable lengths, are used directly. The applica- coordinates (the current geometry) at times t + Dt and sk are given
bility of the modified dynamic relaxation with kinetic damping to by
S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22 13

Fig. 1. Typical creep curves (creep strains ec(sk) versus time sk) of the ropes: (a) parallel-lay aramid ropes and (b) spiral strand ropes.

chosen value of the time increment Dt convergence usually may


Table 1 be assured by using fictitious masses defined at time sk in the fol-
The coefficients a(r), b(r) and c(r) for the required stress levels of the
logarithmic-exponential creep constitutive equation of the steel cable.
lowing form

% rult a(r) b(r) c(r) k Dt 2


(%) () () () Mix ðsk Þ ¼ Six ðsk Þ ð7Þ
2
25 0.226 3257.647 0.000862
30 0.280 2511.556 0.00413 where k is the convergence parameter which is constant for the
35 0.337 1999.831 0.00833 whole structure and Six(sk) is the maximum axial stiffness of the i
40 0.397 1621.747 0.0135 node in the x direction at time sk. So called ‘‘nodal stiffness’’ is asso-
45 0.460 1322.790 0.0196 ciated with the stiffness of members n ¼ 1; 2; . . . ; N connected to
50 0.527 1065.143 0.0267
55 0.757 1339.503 0.0620
node i. For cable or strut members stiffness Stix ðsk Þ at times t and
60 1.021 1866.129 0.1030 sk is defined as
!
X
N
E n An T tn ðsk Þ
Stix ð k Þ
s ¼ 0
þ t ð8Þ
tþDt=2 ln ðs0 Þ ln ð sk Þ
xitþDt ðsk Þ ¼ xti ðsk Þ þ Dt:v ix ðsk Þ ð4Þ n¼1
inode

0 0
Following these updated coordinates (Eq. (4)) the new length may where En An =ln ðs0 Þ is the elastic stiffness (ln ðs0 Þ corresponds to the
t
be calculated at times t + Dt and sk, and the current internal force initial unstrained length of the member) and T tn ðsk Þ=ln ðsk Þ is the
t
T ntþDt ðsk Þ in link element n, such as a cable or strut, is determined geometric stiffness. T n ðsk Þ is the current force in the member n
t
as follows and ln ðsk Þ is the current length of the member at times t and sk.
The number of parameters can be reduced with the use of ki-
En An  tþDt 0
 netic damping in the dynamic relaxation method which does not
T ntþDt ðsk Þ ¼ T 0n ðs0 Þ þ 0
l n ð s k Þ  ln ð s0 Þ ð5Þ require a viscous damping term and only the time increment and
ln ðs0 Þ
the fictitious nodal masses need be determined. The method of ki-
0 tþDt
where ln ðs0 Þ is the initial length of element, ln ðsk Þ is the current netic damping has been found to be stable and rapidly convergent
length of element at times t + Dt and sk, T 0n ðs0 Þ is the initial pre- when dealing with large displacements [23,17,14].
stress in the element, En is the elastic modulus of element n and When kinetic damping is employed, the viscous damping terms
An is the cross sectional area of element n. If T ntþDt ðsk Þ < 0 for the Cix(sk) in Eq. (3) are no longer needed. The velocity at node i at time
cable element, the force is compressive so T ntþDt ðsk Þ must be set step t + Dt/2 is written as
tþDt
equal to zero. Note, that current lengths ln ðsk Þ of the correspond- Dt
ing cable element (wire or synthetic cable) at discrete times sk, for v ixtþDt=2 ðsk Þ ¼ v ixtDt=2 ðsk Þ þ Rt ð sk Þ ð9Þ
M ix ðsk Þ ix
k ¼ 1; 2; . . . ; K, can be calculated according to Eqs. (15) and (17) as
will be defined in the next sections. Substituting Eqs. (7) into (9) the velocity then takes the form
The residual forces can thus be calculated at times t + Dt and sk.
For any node i, the residual force in x -direction Rix tþDt
ðsk Þ is calcu- 2Rtix ðsk Þ
v ixtþDt=2 ðsk Þ ¼ v ixtDt=2 ðsk Þ þ ð10Þ
lated as the sum of the external force Fext,ix and the x -component kDtSix ðsk Þ
of the resultant force induced by the contributions of the N mem- The kinetic energy at the time increment t + Dt/2 can be ex-
bers meeting at node i. Hence, the x -component of the residual pressed as
force at node i where member n connects node i to node j is given by
X
I
1
X
N tþDt
xj;n tþDt
ðsk Þ  xi;n ðsk Þ U ktþDt=2 ðsk Þ ¼ M ix ðsk Þðv ixtþDt=2 ðsk ÞÞ2 ð11Þ
RixtþDt ðsk Þ ¼ F ext;ix þ T ntþDt ðsk Þ ð6Þ i¼1
2
tþDt
n¼1 s
ln ð k Þ
If the current kinetic energy U ktþDt=2 ðsk Þ is found to be less than the
inode

Generally convergence and numerical stability of the solution previous value, an energy peak has been passed. Velocities are then
may be achieved by reducing the time interval or increasing the set to zero and nodal coordinates are set to xitDt=2 ðsk Þ when the en-
fictitious masses [19]. According to Barnes [14], for an arbitrarily ergy peak is assumed to have occurred. When the analysis is re-
14 S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22

Fig. 2. Layout, geometry and designation of members and nodes of the investigated cable dome: (a) sectional view, (b) axonometric view and (c) ground plan.

started the velocities at the midpoint of the first time step are given
by

Rtix ðsk Þ
v ixtþDt=2 ðsk Þ ¼ ð12Þ
kDtSix ðsk Þ

where the residual forces Rtix ðsk Þ are recalculated from the xt  Dt/
2
(sk) displacement position [19]. The process repeats until the
structure reaches a stable equilibrium state according to the speci-
fied criteria for residual forces and kinetic energy. Convergence is
assumed when the kinetic energy of the structure is smaller than
a defined value Uke

U k ð sk Þ 6 U ke ð13Þ
Fig. 3. Comparison of vertical deflections of 1–4 selected nodes of a cable dome
obtained by means of a proposed computational model based on the dynamic
relaxation method with those obtained by the closed-form solution according to and the residual forces of all the degrees of freedom are less than a
[35]. prescribed tolerance.
S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22 15

3. Description of the time-dependent computational model

A time-dependent computational model of geometrically non-


linear and materially linear pre-stressed cable domes with rheo-
logical properties is presented based on the application of the mod-
ified dynamic relaxation method and creep theory. The model with
a finite element idealisation of the cable domes was implemented
into the DDRMsau software developed by the authors. The software
was created in the MATLAB numerical computing environment
[33,34].
The pre-processor of input data and the graphical environment
that displays the results are part of the program. Graphical repre-
sentation of initial and resultant forms of the analysed structures,
overview of their deformations and internal forces through quanti-
tative colour schemes are outputs of the program.

3.1. Finite element modelling

Two-node rectilinear spatial elements with three degrees of


freedom at each node (displacements in the nodal x, y and z direc-
tions) marked as CABLE, STRUT and TRUSS elements in the
DDRMsau library were used for the analyses of cable domes. These
elements were used to model the tension cables and compressed
struts of cable domes. A CABLE or STRUT is a three-dimensional
spar element having the unique feature of a stiffness resulting in
a uniaxial tension-only or compression-only element, respectively.
TRUSS is both a tension and compression element. With the ten-
sion-only option, the stiffness is removed if the element goes into
compression (simulating a slack cable). This feature is useful for
cable applications where the entire cable is modelled with one ele-
Fig. 4. Comparison of internal forces obtained by (a) developed DDRMsau software ment. As in a pin-jointed structure, no bending stiffness is included
with those obtained by (b) the geometrically non-linear finite element method in either the tension-only or the compression-only element. Large
when ANSYS software is used. deflection capabilities are available for these elements. The mate-

Fig. 5. Courses of axial forces N(sk) in the individual members of the cable dome with steel cables at investigated times sk: (a) ridge cables, (b) diagonal cables, (c) cable hoops
and (d) struts.
16 S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22

Fig. 6. Courses of vertical displacements w(sk) of 1–4 selected nodes of the cable dome with steel cables at investigated times sk: (a) displacements only due to creep (without
initial displacements at time s0) and (b) comprehensive displacements (sum of initial displacements at time s0 and displacements due to creep at times sk).

Fig. 7. Courses of axial forces N(sk) in the individual members of the cable dome with synthetic cables at investigated times sk: (a) ridge cables, (b) diagonal cables, (c) cable
hoops and (d) struts.

rial model for the cables and struts is characterised by a linear geometry of a loaded structure analysed at initial time s0 is taken
relationship between stresses and strains (material linearity), as the reference configuration. The model enables the continuous
hence Hooke’s law is valid for their behaviour in the elastic transfer of the current structural behaviour data during the re-
range. quired time period.
Boundary conditions are imposed by assigning large masses to In the present computational model, explicit forms of creep
fixed joints at the supports of the structure. constitutive equations for cables considered in this study are used
and incorporated into the developed computational program.

3.2. Time-dependent analysis


3.3. Creep prediction and time-dependent length determination of
For the time-dependent analysis of the cable dome, the time do- cables
main is divided into a discrete number of time steps sk for
k ¼ 1; 2; . . . ; K. At each time increment sk, the structure is analysed In order to perform a time-dependent behaviour analysis of the
under the external applied load and current imposed geometry, pre-stressed cable dome under long-term loads, special attention is
specified by the cable lengths which originate from the creep con- focused in this section on the characterisation of creep properties
stitutive properties of the cables. In this approach, the deformed and on the determination of time-dependent lengths of the cables
S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22 17

Fig. 8. Courses of vertical displacements w(sk) of 1–4 selected nodes of the cable dome with synthetic cables at investigated times sk: (a) displacements only due to creep
(without initial displacements at time s0) and (b) comprehensive displacements (sum of initial displacements at time s0 and displacements due to creep at times sk).

Fig. 9. Comparison of axial forces N(sk) and comprehensive vertical displacements w(sk) in selected members and nodes of the dome formed from steel and synthetic cables
at investigated times sk: (a) ridge cable 1, (b) diagonal cable 5, (c) cable hoop 9, (d) strut 14 and (e) node 1.

used in this study. Steel spiral strand ropes and synthetic parallel- 3.3.1. Synthetic cables
lay aramid ropes are applied as structural tension members of the The creep tests of parallel-lay aramid ropes were carried out by
dome in further analyses. For that purpose, the creep constitutive Guimarães and Burgoyne [8] at Imperial College in London. The
equations of these cables are briefly described. specimens tested under constant load were 30000 N Type G Parafil
18 S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22

Fig. 10. Variation of typical characteristics of the dome formed from synthetic cables during the iteration process at investigated times sk: (a) kinetic energy of the node 1 and
(b) residual forces in the node 1.

ropes with a cross-sectional area of the yarn in the core of of 16.0 mm. The pre-tensioning load of the initially pre-stretched
15.28 mm2. The pre-tensioning load of the specimens was 60% of specimens with cross-sectional area of 148.1 mm2 was 70% of the
the nominal breaking load of the ropes. The creep constitutive nominal breaking load of the ropes. The creep constitutive equa-
equation for the determination of the creep strains ec(sk) at the tion for the determination of the creep strains ec(sk) at the investi-
investigated time sk was obtained in the following logarithmic gated time sk was obtained in the following logarithmic-
form exponential form
 
ec ðsk Þ ¼ bðrÞ:106 log10 ðsk Þ ð14Þ ec ðsk Þ ¼ ðaðrÞ þ cðrÞlnsk Þ 1  ebðrÞsk ð16Þ
where the creep coefficient b(r) (creep rate parameter) depends on
where the creep coefficients a(r), b(r) and c(r) depend on the stress
the stress level r(s0). The units of time into Eq. (14) is necessarily in
level r(s0). These coefficients are for individual stress levels ex-
seconds, thus the resultant ec(sk) is dimensionless
pressed as a percentage of the characteristic value of the ultimate
(e.g.1 day = 86400 s). The creep coefficients have the values
tensile strength of the rope ru = 1370 N mm2 given in Table 1.
b(r) = 74; 91; 104 and 121 according to the stress levels corre-
The units of time sk of the constitutive equation are expressed in
sponding to 35%; 43.7%; 57.3% and 63.1% of the characteristic value
days, thus the resultant ec(sk) is dimensionless. Typical creep curves
of the ultimate tensile strength of the rope ru = 2200 N mm2,
(creep strains ec(sk) versus time sk) of the spiral strand ropes are
respectively. Typical creep curves (creep strains ec(sk) versus time
shown in Fig. 1b.
sk) of the parallel-lay aramid ropes are shown in Fig. 1a. Thus, a current length of the steel cable lc(sk) at time sk is ex-
Consequently, the change of an initial length of the synthetic
pressed in the form
cable member lc(s0) at time s0 into a current length lc(sk) at time
sk due to creep strain increments is expressed in the form lc ðsk Þ ¼ lðs0 Þð1 þ ec ðsk ÞÞ
   
lc ðsk Þ ¼ lc ðs0 Þð1 þ ec ðsk ÞÞ ¼ lc ðs0 Þ 1 þ bðrÞ:106 log10 ðsk Þ : ð15Þ ¼ lðs0 Þ 1 þ ðaðrÞ þ cðrÞlnsk Þð1  ebðrÞsk Þ : ð17Þ

3.3.2. Wire cables 4. Numerical applications and discussions of results


The creep tests of steel wire ropes were carried out by Kmet and
Holickova [10] at the Technical University of Kosice. The specimens In this section, numerical examples are presented and discussed
tested under constant load were spiral strand ropes with a con- in order to show the efficiency of the proposed dynamic relaxation
struction 19 wires per strand with 12 outer wires and a diameter procedure in predicting the time-dependent nonlinear response of
S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22 19

Fig. 11. Variation of typical characteristics of the dome formed from synthetic cables during the iteration process at investigated times sk: (a) axial forces in the cable 1 and
(b) vertical positions of the node 1.

cable domes. The pre-programmed dynamic relaxation algorithm responses obtained by individual approaches. A comparison of
is first verified through the analysis of a cable dome in which creep internal forces obtained by the developed DDRMsau software with
effects are not considered. those obtained by the geometrically non-linear finite element
method when the ANSYS software [36] is used, is shown in
4.1. Validation of the computational model Fig. 4. Results confirmed a very good agreement between individ-
ual approaches.
In order to verify the accuracy of the computational model and
the computer program developed in this study, solutions have 4.2. Time-dependent analysis of the cable dome
been generated for the structure previously examined by Wang
et al. [35]. Authors in [35] proposed a simple analytical approach The problem is to investigate the response variation, i.e. the var-
for the analysis of Geiger domes with a circular ground plan. iation of internal forces {F(sk)} and associated displacements
The structure analysed is a Geiger dome with a circular ground- {w(sk)} of a cable dome at times s = 1; 10; 102; 103 and 104 days
plan and a diameter of 100.0 m as is shown in Fig. 2. A Geiger dome due to the creep of cables against those obtained at the initial time
with an inner hoop is composed of 272 members, as are radial ridge s0 = 0 days (reference response without creep effects) when the
cables, radial diagonal cables, cable hoops and struts. There are 64 vertical uniformly distributed load q = 1.0 N mm2 is applied over
struts and 208 cables in this dome. The division number of the the entire span of the structure.
dome in the circular direction is 16. The number of unconstrained The time-dependent analysis of cable domes by means of the
nodes is 128. The initial geometry, prestress, member properties, modified dynamic relaxation method can be accomplished accord-
and loading conditions used in this study are the same as those used ing to the following process:
previously by Wang et al. [35]. The Young’s modulus of cables and
struts are Ec = 190000 N mm2 and Es = 206000 N mm2, respec- (1) Perform the form-finding of the structure and define the ini-
tively. Layout and geometry as well as the designation of members tial prestress;
and nodes of the investigated cable dome are shown in Fig. 2. (2) Analyse the static behaviour of the dome subjected to an
A comparison of the obtained vertical deflections of the selected external load q at initial time s0 with the creep of the cables
nodes of the cable dome when the closed-form solution according ignored;
to [35] and proposed computational model based on the dynamic (3) Determine the stresses r(s0) in the cable members obtained
relaxation method are applied is shown in Fig. 3. The largest differ- on the basis of a static analysis of the dome at initial time s0
ence is 1.27%, which indicates a very good agreement between the and assign to them the corresponding creep constitutive
20 S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22

Fig. 12. Variation of nodal vertical positions z of the dome formed from synthetic cables during the iteration process at investigated times sk: (a) node 1, (b) node 2, (c) node 3
and (d) node 4.

equations ec(sk) (Eqs. (14), (16)) with relevant coefficients for pre-stresses in the members are arbitrarily specified. As, the dome
adjustment of the cable lengths Lc(sk) due to corresponding is not in equilibrium, the structure is set into motion by unbal-
creep strain increments (Eqs. (15), (17)); anced internal forces. Unbalanced forces and displacements are
(4) Perform the time-dependent analysis of the dome subjected computed using the dynamic relaxation method until the dome
to an external load q with the current parameters at the reaches a steady initial equilibrium state according to a specified
investigated times sk and check if the dome has enough stiff- maximum tolerance (the residuals of all the degrees of freedom
ness. If not, go back to (1) and redesign the initial pre-stress are less than104 kN). Otherwise, the obtained internal forces are
level. taken as the initial values of pre-stressing forces of the dome for
the further time-dependent static analyses at the initial time s0
In the examples, 60% of the characteristic value of the ultimate (creep of cables is ignored) and at the times sk = 1; 10; 100; 1000
tensile strength ru = 1370 N mm2 and ru = 2200 N mm2, are and 10000 days, when creep of the steel and synthetic cables is
considered as the allowable stress of steel cables and synthetic considered.
cables, respectively. The cross-sectional area of the synthetic cables Plots of axial forces N(sk) in the individual members of the
is given by the expression dome (as are ridge cables, diagonal cables, cable hoops and struts)
formed from steel and synthetic cables at investigated times sk are
X
n
shown in Figs. 5 and 7. Plots of vertical displacements w(sk) of se-
Ac ¼ Ai ¼ nAi ¼ n15:28 mm2 ð18Þ
i¼1
lected nodes 1–4 of the dome formed from steel and synthetic
cables at investigated times sk are shown in Figs. 6 and 8.
where n is the number of the parallel fibres, with cross-sectional Figs. 6a and 8a show displacements only due to creep without ini-
areas of 15.28 mm2, from which the cable is constructed. The tial displacements at time s0. Figs. 6b and 8b illustrate comprehen-
cross-sectional area of the steel cables is Ac = n148.1 mm2, where sive displacements as a sum of initial displacements at time s0 and
n is the number of the parallel spiral strand ropes with cross-sec- increments of displacements due to the creep of the cables at times
tional areas of 148.1 mm2 of which the cable is composed. The mod- sk. From the figures it is clear that internal forces decrease signifi-
ulus of elasticity of steel cables and synthetic cables is cantly as the structure gradually begins to slacken and vertical
Ec = 150000 N mm2 and Ec = 130000 N mm2, respectively [37]. deflections increase with time.
The dome is subjected to a uniform vertical load with a magnitude Comparisons of axial forces N(sk) and comprehensive vertical
of q = 1.0 kN m2. displacements w(sk) in selected members (cables and struts) and
In all applications, i.e. in form-finding and in static analyses at nodes of the dome formed from steel and synthetic cables at inves-
the investigated times s0 and sk we use the dynamic relaxation tigated times sk are shown in Fig. 9. From the comparisons shown
method with kinetic damping based on the calculation of a se- in Fig. 9a–d it can be seen that there are only small differences be-
quence of decreasing kinetic energy peaks with the following tween axial forces in steel and synthetic cables at the initial time s0
parameters: the time step Dt = 1 s, the convergence parameter (creep is ignored). Significant differences are visible in Fig. 9e at the
k ¼ 2 constant for the whole structure and a maximum residual initial time s0 between nodal vertical displacements of a structure
force of the structure equal to 104 kN. formed from steel and synthetic cables due to the different modu-
The form-finding process starts from an initial specified lus of elasticity of individual materials. On the other hand, due to
geometry of the dome as is shown in Fig. 2. At the same time, constructions of cables (spiral and parallel-lay form of wires and/
S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22 21

or fibres), an influence of creep on the variation of axial forces and proposed modified dynamic relaxation method can be used for this
vertical displacements is in the case of parallel-lay synthetic cables purpose since it provides time-dependent control of the forces in
less than those in the case of steel spiral cables. The largest de- structural members and nodal displacements (deflections) of the
crease of axial forces at time s = 10000 days in comparison with structure. The method provides the designer effective ways for
those at the initial time s0 is 36.5% for steel ridge cables, 31.5% guiding the evolution of the system by an appropriate and rational
for steel diagonal cables and 34.2% for steel cable hoops. The larg- choice of its initial stiffness.
est decrease of axial forces at time s = 10000 days in comparison As a natural extension of this research, verification of the meth-
with those at the initial time s0 is 16.4% for synthetic ridge cables, od by a comparison with the results obtained by tests of a time-
13.6% for synthetic diagonal cables and 19.1% for synthetic cable dependent behaviour of selected cable dome models awaits further
hoops. The maximal decrease of compressed axial forces in the attention.
struts of the dome formed from steel cables represents 27.8% and
for the dome formed from synthetic cables 11.8%. Acknowledgement
The largest increase of vertical displacements at time
s = 10000 days in comparison with those at initial time s0 is This work is part of Research Project No. 1/0321/12, partially
39.8% for the dome formed from steel cables and 8.5% for the dome founded by the Scientific Grant Agency of the Ministry of Education
formed from synthetic cables. of the Slovak Republic and the Slovak Academy of Sciences. The
Variations of typical characteristics of the dome formed from present research has been carried out within the project: Centre
synthetic cables during the iteration process at investigated times of excellent integrated research for progressive building structures,
sk as are kinetic energy of the node 1, residual forces in the node 1, materials and technologies, supported by European Union Struc-
axial forces in the cable 1 and vertical positions of the node 1 are tural funds.
shown in Figs. 10 and 11. It is clear that the first time loaded cable
dome at the initial time s0 converges to the solution at a slower References
rate than the loaded slack dome at the investigated times sk. Vari-
ations of nodal vertical positions z of the dome formed from syn- [1] Geiger DH, Stefaniuk A, Chen D. The design and construction of two cable
thetic cables during the iteration process at investigated times sk domes for the Korean Olympics. In: Proceedings of the IASS international
symposium on shells, membranes and space frames, vol. 2. Osaka, Japan: 1986.
are shown in Fig. 12. p. 265–72.
For cables exposed to creep strain increments, the initial stiff- [2] Chi Tran H, Lee J. Advanced form-finding of cable-strut structures. Int J Solids
ness will alter due to time-dependent changes of the cables’ Struct 2010;47(14–15):1785–94.
[3] Pellegrino S. A class of tensegrity domes. Int J Space Struct 1992;7(2):127–42.
lengths which are sequentially introduced into the system. At the
[4] Yuan XF, Dong SL. Nonlinear analysis and optimum design of cable domes. Eng
same time, stresses in some or all the members of the cable dome Struct 2002;24(7):965–77.
are arbitrarily redistributed. Consequently, the system cannot [5] Yuan XF, Dong SL. Integral feasible prestress of cable dome. Comput Struct
maintain equilibrium and the structure is set into motion by the 2003;8:2011–9.
[6] Yuan XF, Chen LM, Dong SL. Prestress design of cable domes with new forms.
unbalanced internal forces. The displacements are computed using Int J Solids Struct 2007;44:2773–82.
the dynamic relaxation method based on calculating a sequence of [7] Kmet S, Tomko M, Brda J. Time-dependent analysis and simulation-based
decreasing energy peaks, thereby permitting the structure to reach reliability assessment of suspended cable with rheological properties. Adv Eng
Software 2007;38:561–75.
the steady equilibrium sate at the investigated time. Apart from [8] Guimarães GB, Burgoyne CJ. Creep behaviour of parallel-lay aramid rope. J
particular cases (an initial slackening) or chance situations, maxi- Mater Sci 1992;27:2473–89.
mal unbalanced forces in the time-dependent analysis are not as [9] Kmet S. Non-linear rheology of tension structural element under single and
variable loading history, part I: theoretical derivations. Struct Eng Mech Int J
large as in the analysis of the structure under an imposed external 2004;18:565–89.
load at the initial state. Hence, less time and fewer iterations as [10] Kmet S, Holickova L. Non-linear rheology of tension structural element under
well as kinetic energy peaks are needed until the required degree single and variable loading history, part II: creep of steel rope - examples and
parametrical study. Struct Eng Mech Int J 2004;18:591–607.
of convergence is achieved. [11] Day AS. An introduction to dynamic relaxation. The Engineer
Results confirmed a physical relevance of the proposed theoret- 1965;219:218–21.
ical approach. [12] Underwood P. Dynamic relaxation. In: Belytschko T, Hughes TJR, editors.
Computational Methods for Transient Analysis. Amsterdam: Elsevier; 1983. p.
245–56.
[13] Barnes M. Form and stress engineering of tension structures. Struct Eng Rev
5. Conclusions 1994;6(3–4):175–202.
[14] Barnes MR. Form finding and analysis of tension structures by dynamic
relaxation. Int J Space Struct 1999;14:89–104.
In this paper, a time-dependent computational model of the [15] Lewis WJ, Jones MS, Rushton KR. Dynamic relaxation analysis of the non-linear
geometrically non-linear and materially linear pre-stressed cable static response of pretensioned cable roofs. Comput Struct
domes with rheologic properties, based on the application of the 1984;18(6):989–97.
[16] Wakefield DS. Engineering analysis of tension structures: theory and practice.
modified dynamic relaxation method and creep theory was devel- Eng Struct 1999;21(8):680–90.
oped. Applications were presented to illustrate the time-depen- [17] Topping BHV, Khan AI. Parallel computation schemes for dynamic relaxation.
dent behaviour of cable domes and to demonstrate the efficiency Eng Comput 1994;11(6):513–48.
[18] Lewis WJ. Tension structures: form and behaviour. London: Thomas Telford;
of the proposed method. 2003.
Results obtained from two numerical examples confirmed [19] Topping BHV, Ivanyi P. Computer aided design of cable membrane
physical relevance of the proposed theoretical approach. structures. Kippen, Stirlingshire, Scotland: Saxe-Coburg Publications; 2007.
[20] Domer B, Fest E, Lalit V, Smith IFC. Combining dynamic relaxation method
The stiffness of cable domes is conditioned by their states of with artificial neural networks to enhance simulation of tensegrity structures.
prestress. The decrease of prestress due to creep of cables can ASCE J Struct Eng 2003;129(5):672–81.
cause failure and a loss of reliability of cable domes during their [21] Douthe C, Baverel O. Design of nexorades or reciprocal frame systems with the
dynamic relaxation method. Comput Struct 2009;87(21–22):1296–307.
working life. This time-dependent computational model is deemed
[22] Rezaiee-Pajand M, Kadkhodayan M, Alamatian J, Zhang LC. A new method of
useful due to its pragmatic ability to predict the time-dependent fictitious viscous damping determination for the dynamic relaxation method.
behaviour of prestressed cable domes. This approach can increase Comput Struct 2011;89:783–94.
the reliability and enhance the performance of cable domes. [23] Papadrakakis M. A method for the automatic evaluation of the dynamic
relaxation parameters. Comput Methods Appl Mech Eng 1981;25(1):35–48.
There is a growing need for numerical methods devoted to [24] Kwan ASK. A new approach to geometric nonlinearity of cable structures.
time-dependent analysis of prestressed cable structures. The Comput Struct 1998;67(4):243–52.
22 S. Kmet, M. Mojdis / Computers and Structures 125 (2013) 11–22

[25] Wood RD. A simple technique for controlling element distortion in dynamic [32] Kadkhodayan M, Alamatian J, Turvey GJ. A new fictitious time for the dynamic
relaxation form-finding of tension membranes. Comput Struct 2002;80(27– relaxation (DXDR) method. Int J Numer Methods Eng 2008;74(6):996–1018.
30):2115–20. [33] MATLAB Documentation. Optimization Toolbox User’s Guide, Version 3.1. The
[26] Han SE, Lee KS. A study of the stabilizing process of unstable structures by MathWorks Inc., Natick, MA, USA. 2006.
dynamic relaxation method. Comput Struct 2003;81(17):1677–88. [34] Mojdis M. Analysis of adaptive cable domes. PhD. Thesis, Technical University
[27] Lee KS, Han SE, Park T. A simple explicit arc-length method using the dynamic of Kosice, Slovakia, 2011.
relaxation method with kinetic damping. Comput Struct 2011;89(1– [35] Wang Z, Yuan X, Dong S. Simple approach for force finding analysis of circular
2):216–33. Geiger domes with consideration of self-weight. J Struct Steel Res
[28] Rezaiee-Pajand M, Sarafrazi SR. Nonlinear dynamic structural analysis using 2010;66:317–22.
dynamic relaxation with zero damping. Comput Struct 2011;89(12– [36] ANSYS, Inc. Release documentation of Ansys 11.0, Southpointe, 275
14):1274–85. Technology Drive, Canonsburg, 2005.
[29] Alamatian J. A new formulation for fictitious mass of the dynamic relaxation [37] Eurocode 3. Design of Steel Structures. Part 1.11 Design of Structures with
method with kinetic damping. Comput Struct 2012;90–91:42–54. Tension Components. CEN, Brussels, 2006.
[30] Zhang L, Maurin B, Motro R. Form-finding of nonregular tensegrity systems.
ASCE J Struct Eng 2006;132(9):1435–40.
[31] Bel Hadj Ali N, Rhode-Barbarigos L, Smith IFC. Analysis of clustered tensegrity
structures using a modified dynamic relaxation algorithm. Int J Solids Struct
2011;48(5):637–47.

You might also like