You are on page 1of 26

A.

Site Identification

B. Start of Construction

C. Forming and Concrete Filling, CHB Laying

D. Electrical & Plumbing Installation (Ground Floor)

E. Start of Construction (2nd Floor)

F. Forming and Concrete Filling, CHB Laying

G. Roof Works

H. Electrical & Plumbing Installation (2nd Floor)

I. Finishing
Works

Site Visit
Site Cleaning
Staking and Batter boards

Excavation
Delivery of Material ( Ground Floor)
Cutting And Assembling of Steel Reinforcement

Forming of column, Pouring of Footings and Columns


Footing and Column Form Removal
CHB Laying and Back Filling
Beams and Slab Forms,Pouring of Beams and Slabs
Beams and Slab Form Removal

Intallation of Electrical Works


Installation of Plumbing and Drainage System

delivery of Materials (2nd Floor)


Forming of Stairs, Pouring of Stairs
Stair Form Removal
Plastering and Tile Works (Ground Floor)

Column Forming and Column Pouring


Column Form Removal
CHB Laying
Beam Forming and Beam Pouring
Beams Form Removal

Roof Framing and Roof Sheet Laying

Intallation of Electrical Works (2nd Floor)


Installation of Plumbing and Drainage System (2nd Floor)

Plastering and Tile Works (2nd Floor )


Painting of Walls and Varnishing ( Ground nd 2nd Floor)
Finishing and Over all Cleaning
Work Description

Site Visitation
Site Cleaning
Preliminary Delivery Materials
Staking and Batter Boards
Excavation
Cutting and Assembling Steel Reinforcement
Dummy (1)
Forming of Columns
Pouring for Footing and Columns
Removal of Forms
CHB Laying and Backfilling
Installation of Electrical works and Plumbing Drainage and water Supply
Ground Plastering and Tile Works
Secondary Delivery of Materials
Cutting and Assembling Steel Reinforcement
Dummy (2)
Forming of Beams and Slab
Pouring of Beams and Slab, Various Pipe Installations
Removal of Forms, CHB Laying
Installation of Electrical works and Plumbing Drainage and water Supply
Forming and Steel Reinforcement for Stairway
Construction of Stairways
Roof Framing and Roof Sheet Laying
Doors and Windows Intallation
Plastering and Tile Works for 2nd Floor
Painting and Varnishing
Final Finishing and Over all Cleaning
Dummy(3)
Duration (Day) Activity Start Finish

1 1--2 04-Jan-21 04-Jan-21


2 2--3 04-Jan-21 05-Jan-21
4 2--4 05-Jan-21 08-Jan-21
2 3--5 08-Jan-21 09-Jan-21
7 4--5 09-Jan-21 16-Jan-21
10 5--6 16-Jan-21 27-Jan-21
0 6--8 27-Jan-21 27-Jan-21
4 5--7 27-Jan-21 30-Jan-21
2 7--8 30-Jan-21 01-Feb-21
1 8--9 01-Feb-21 01-Feb-21
14 9--10 01-Feb-21 16-Feb-21
7 9--11 16-Feb-21 23-Feb-21
10 11--12 23-Feb-21 05-Mar-21
4 11--13 05-Mar-21 09-Mar-21
8 13--14 09-Mar-21 17-Mar-21
0 12--14 17-Mar-21 17-Mar-21
4 14--15 17-Mar-21 20-Mar-21
2 15--16 20-Mar-21 22-Mar-21
14 16--17 22-Mar-21 08-Apr-21
7 17--18 08-Apr-21 15-Apr-21
10 18--19 15-Apr-21 26-Apr-21
10 18--20 26-Apr-21 07-May-21
14 19--21 07-May-21 22-May-21
7 20--21 22-May-21 29-May-21
10 21--22 29-May-21 08-Jun-21
21 21--23 08-Jun-21 03-Jul-21
3 23--24 03-Jul-21 06-Jul-21
0 22--24 06-Jul-21 06-Jul-21
Start Finish 4 5 6 7 8 9 10
M T W Th F S S

DAY 1 DAY 1
DAY 2 DAY 3
DAY 3 DAY 6
DAY 6 DAY 7
DAY 7 DAY 13
DAY 13 DAY 22
DAY 22 DAY 22
DAY 22 DAY 25
DAY 25 DAY 26
DAY 26 DAY 26
DAY 26 DAY 39
DAY 39 DAY 45
DAY 45 DAY 54
DAY 54 DAY 57
DAY 57 DAY 64
DAY 64 DAY 64
DAY 64 DAY 65
DAY 65 DAY 66
DAY 66 DAY 79
DAY 79 DAY 85
DAY 85 DAY 94
DAY 94 DAY 103
DAY 103 DAY 116
DAY 116 DAY 122
DAY 122 DAY 131
DAY 131 DAY 151
DAY 151 DAY 153
DAY 153 DAY 153
JANUARY
11 12 13 14 15 16 17 18 19 20
M T W Th F S S M T W
21 22 23 24 25 26 27 28 29 30
Th F S S M T W Th F S
31 1 2 3 4 5 6 7 8 9
S M T W Th F S S M T
February
10 11 12 13 14 15 16 17 18 19
W Th F S S M T W Th F
20 21 22 23 24 25 26 27 28 1
S S M T W Th F S S M
2 3 4 5 6 7 8 9 10 11
T W Th F S S M T W Th
March
12 13 14 15 16 17 18 19 20 21
F S S M T W Th F S S
22 23 24 25 26 27 28 29 30 31
M T W Th F S S M T W
1 2 3 4 5 6 7 8 9 10
Th F S S M T W Th F S
April
11 12 13 14 15 16 17 18 19 20
S M T W Th F S S M T
21 22 23 24 25 26 27 28 29 30
W TH F S S M T W Th F
1 2 3 4 5 6 7 8 9 10
S S M T W TH F S S M
May
11 12 13 14 15 16 17 18 19 20
T W TH F S S M T W TH
21 22 23 24 25 26 27 28 29 30
F S S M T W TH F S S
31 1 2 3 4 5 6 7 8 9
M T W TH F S S M T W
June
10 11 12 13 14 15 16 17 18 19
TH F S S M T W TH F S
20 21 22 23 24 25 26 27 28 29
S M T W TH F S S M T
30 1 2 3 4 5 6 7 8 9
W TH F S S M T W TH F
JULY
10 11 12 13 14 15 16 17 18 19
S S M T W TH F S S M
20 21 22 23 24 25 26 27 28 29
T W TH F S S M T W TH
30 31
F S

You might also like