Schedule Of Work PT KRN

Field Test Week


1 2 3 4 5 6 7 8 9 10 11 12
Preparation 1 Weeks
Soil Investigation 4 Weeks
Cpt 4 Weeks
Soil Lab 6 Weeks
Factual Report 2 Weeks
Final Report 4 Weeks

1. 1 week after the PO / job certainty, we will visit the site and we will begin preparations with a site survey to prepare a place to access all the requirements for working in the
field and also look for work points in the field of work.
2. Field work will be carried out for 4 weeks or 1 month . The work of the Soil Investigation is done by the wash boring method using 3 Mechines estimates that the work of 1
hole is 4 days.
3. For sondir / cpt test we will use 1 tool with estimated 3 point jobs in 1 day.
.4. For soil lab sample work will be sent partially or periodically a number of quota that allows to be sent from the field.