PERT/CPM

Activity Description Predecessors Estimated Time


A Site Clearing 1 day
B Mobilization A 1 day
C Layout B 1 day
D Excavation B 4 days
E Grading Areas C,D 2 days
F Formworks C,D 5 days
G Concrete Pouring C,D 3 days
H Wall Footing E,F,G 2 days
I CHB Layout H 15 days
J Column H 5 days
K Beam J 7 days
L Wall Construction I,K 7 days
M Roofing I,K 6 days
N Plastering I,L 14 days
O Ceiling M 5 days
P Tile Works M 10 days
Q Painting L 22 days
R Windows and Doors O,P,Q 5 days
S Fixtures R 4 days
T Furnitures S 3 days