A Site Clearing 1 day B Mobilization A 1 day C Layout B 1 day D Excavation B 4 days E Grading Areas C,D 2 days F Formworks C,D 5 days G Concrete Pouring C,D 3 days H Wall Footing E,F,G 2 days I CHB Layout H 15 days J Column H 5 days K Beam J 7 days L Wall Construction I,K 7 days M Roofing I,K 6 days N Plastering I,L 14 days O Ceiling M 5 days P Tile Works M 10 days Q Painting L 22 days R Windows and Doors O,P,Q 5 days S Fixtures R 4 days T Furnitures S 3 days