Professional Documents
Culture Documents
Paul Ivanoff
Legal 1: 33684466v7
Overview
• Introduction to Bonds and International
P f
Performance G
Guarantees:
t Ch
Chapter
t 26
• Introduction to Arbitration and ADR, and
ADR on International Projects: Chapters 28
& 29
• Introduction to Lien Legislation: Chapter 30
• Introduction to Risks in Construction:
Chapter 25
1
2021-02-19
2
2021-02-19
Types of Bonds
• Bidd Bond
o d
– Used in tendering situations
– Generally, the principal under the bond is a contractor;
the obligee under the bond is the owner
– Contractor submits bid to owner along with bid bond
– If contractor’s bid is accepted but contractor fails to
enter into contract,, contractor must ppay
y the owner the
difference needed to retain someone else
– If contractor fails to pay the owner, then surety has to
pay the owner under the bid bond
3
2021-02-19
Types of Bonds…
• Performance Bond
– This bond indemnifies the owner (obligee) if the
principal doesn’t perform it’s contractual obligations
– If contractor in default under the contract, owner will
notify surety and demand surety to step in and make
arrangements for the contract to be completed
– If contractor disputes with owner’s claim of default,
resolution of matter could be prolonged
Types of Bonds…
• Labour
abou and
a d Material
ate a Payment
ay e t Bond
o d
– Generally, purpose of Labour and Material Payment
Bond is to guarantee payment to subcontractors and
suppliers of a contractor
– Where contractor fails to pay subcontractor,
subcontractor may pursue a claim against surety under
the Labour and Material Payment Bond
4
2021-02-19
Bonding Relationship
OWNER
BOND
INDEMNITY SURETY
CONTRACTOR (BONDING
AGREEMENT CO )
CO.)
SUB-
CONTRACTOR
Letters of Credit
• More common outside of Canada
• Pursuant to a contract, Contractor delivers letter of
credit for agreed upon amount to owner
• Letter of Credit may be drawn upon if contractor
defaults
• May
M bbe close
l tto a blank
bl k cheque
h
• Usually affect contractor’s credit capacity
• Often referred to as “Performance Guarantees” in
international work
10
5
2021-02-19
Letter of Credit
OWNER
LETTER OF
CREDIT
CONTRACTOR
AGREEMENT
BANK SUB-
CONTRACTOR
11
Guarantee
OWNER
GUARANTEE
PARENT
CONTRACTOR
COMPANY
SUB-
CONTRACTOR
12
6
2021-02-19
13
14
7
2021-02-19
Is Mediation Voluntary?
• Mediations are ggenerally
y voluntary,
y, unless:
– A contract includes a mediation clause
– An action has been commenced in Toronto and is
subject to the Mandatory Mediation Rule
In addition:
• Any party may withdraw at any time without
reason (Rule 11.1).
11 1)
• Unless the parties have agreed otherwise, the
costs of the mediation are shared equally by
the parties (Rule 12.1).
16
8
2021-02-19
18
9
2021-02-19
10
2021-02-19
21
22
11
2021-02-19
Advantages of Mediation
• Interest-based
Interest based resolution
resolution.
– Can result in “Win-Win” situation.
• May facilitate early resolution.
– May save legal costs and time.
• Parties retain a high degree of control.
• Opportunity for each side to explain its
view of the story.
23
12
2021-02-19
25
13
2021-02-19
Is Arbitration voluntary?
• Parties may voluntarily enter into arbitration.
• Parties
P i may bbe required
i d under
d contract to
submit to binding arbitration.
– Under CCDC 2, either party may refer dispute to arbitration.
– Where an arbitration clause exists in a contract, courts will
generally uphold the clause.
Costs
– Under CCDC 40, the costs will be borne by the unsuccessful
party unless
l theh arbitrator
bi considers
id it i appropriate
i to
apportion the costs between parties (Rule 19).
27
28
14
2021-02-19
29
15
2021-02-19
31
32
16
2021-02-19
33
Arbitration Agreements
34
17
2021-02-19
35
18
2021-02-19
• Typically 3 panellists,
panellists one appointed
by each party and the chair appointed
by the two appointees.
• Typically decisions are non-binding.
• Costs shared byy the pparties
37
38
19
2021-02-19
What is a lien?
• Powerful remedy: a charge against the land that
was improved by the construction
• Gives subcontractors and suppliers claim against
owner, even where no privity of contract with the
owner exists
• Created by Statute
• very technical since statute based
39
20
2021-02-19
41
21
2021-02-19
43
• General Examples of
Lienable Services:
– All Basic Construction
Work
– Supply and installation of
Equipment
q p ((If Attached))
– Engineering Services
– Architectural Services
(Since 1997 Amendment)
44
22
2021-02-19
45
23
2021-02-19
47
Substantial Performance
• Two Part Test
1. the work must be ready for the purpose
intended (the “Qualitative Test”)
2. the cost of completing incomplete items and
rectifying known defects must be less than an
amo nt calculated
amount calc lated as:
a) 3% of the first $1,000,000 of Contract Price, plus
b) 2% of the next $1,000,000 of Contract Price, plus
c) 1% of the remainder of the Contract Price
24
2021-02-19
Example
Contract Price = $3,500,000
$3 500 000
Quantitative Calculation:
3% of $1,000,000 = $30,000
2% off $1
$1,000,000
000 000 = $20,000
$20 000
1% of $1,500,000 = $15,000
$65,000
49
50
25
2021-02-19
51
Certificate Published
P blished
for services or materials supplied on or before
the date of substantial performance, the lien of a
contractor expires 60 days after the earlier of,
i publication of the certificate of substantial
i.
performance of the work, and
ii. the date the contract is completed,
abandoned or terminated
52
26
2021-02-19
54
27
2021-02-19
What is a Holdback?
• all ppayers
y on contracts and subcontracts under which a lien
may arise must retain a holdback equal to 10% of the price
of the services and materials
• the holdback must be maintained until all liens which may
be claimed against the holdback have expired or have
otherwise been satisfied in accordance with the legislation
• the holdback obligation applies at all levels within the
construction pyramid
• lien claimants may claim against the holdback through the
lien provisions
55
28
2021-02-19
57
29
2021-02-19
59
Introduction
• Many different Project Delivery Systems
• Determine risk allocation for the Project
• Consider which Project Delivery System matches
the risk profile for the Project and meets the other
requirements
q of the Project
j Participants
p
(examples of risks: Health & Safety issues, ability
to fast track, owner’s level of involvement)
60
30
2021-02-19
• Design-Bid-Build
Design Bid Build (general contractor)
g
• Design-Build
61
Design-Bid-Build
Owner
Subconsultant Subconsultant
Subcontractor Subcontractor
62
31
2021-02-19
63
64
32
2021-02-19
Construction Management
(not at risk)
65
66
33
2021-02-19
67
Design-Build
Owner’s Owner
Consultant
C l
Design-
Builder
Design Subcontractors
Consultant
68
34
2021-02-19
• Conducive to “fast-tracking”
69
70
35
2021-02-19
Conclusion
• Questions
71
36