No.

Pekerjaan Area Waktu Durasi Waktu Keterangan

1 Pasang Outlet L-1 Lantai - 1 23 - November 1 Hari


2 Pasang Outlet L-2 Lantai - 2 24 - November 1 Hari
3 Pasang Outlet L-3 Lantai - 3 25 - November 1 Hari
4 Pasang Outlet L-4 Lantai - 4 26 - November 1 Hari
5 Pasang Outlet L-5 Lantai - 5 27 - November 1 Hari
6 Pasang Outlet L-6 Lantai - Atap 28 - November 1 Hari

7 Pasang Lampu L-1 Lantai - 1 26 - 27 November 2 Hari Lembur


8 Pasang Lampu L-2 Lantai - 2 16 - 17 November 2 Hari Lembur
9 Pasang Lampu L-3 Lantai - 3 18 - 19 November 2 Hari Lembur
10 Pasang Lampu L-4 Lantai - 4 20 - 21 November 2 Hari Lembur
11 Pasang Lampu L-5 Lantai - 5 22 - 23 November 2 Hari Lembur
12 Pasang Lampu L-6 Lantai - Atap 24 - 25 November 2 Hari Lembur

13 Pasang Panel L-1 Lantai - 1 Ok


14 Pasang Panel L-2 Lantai - 2 Ok
15 Pasang Panel L-3 Lantai - 3 Ok
16 Pasang Panel L-4 Lantai - 4 Ok
17 Pasang Panel L-5 Lantai - 5 Ok
18 Pasang Panel L-6 Lantai - Atap Ok

19 Tarik Kabel Feeder L-1 Lantai - 1 18 - 20 November 3 Hari


20 Tarik Kabel Feeder L-2 Lantai - 2 18 - 20 November 3 Hari
21 Tarik Kabel Feeder L-3 Lantai - 3 18 - 20 November 3 Hari
22 Tarik Kabel Feeder L-4 Lantai - 4 18 - 20 November 3 Hari
23 Tarik Kabel Feeder L-5 Lantai - 5 18 - 20 November 3 Hari
24 Tarik Kabel Feeder L-6 Lantai - Atap 18 - 20 November 3 Hari

25 Terminasi L-1 Lantai - 1 20 - 22 November 3 Hari


26 Terminasi L-2 Lantai - 2 20 - 22 November 3 Hari
27 Terminasi L-3 Lantai - 3 20 - 22 November 3 Hari
28 Terminasi L-4 Lantai - 4 20 - 22 November 3 Hari
29 Terminasi L-5 Lantai - 5 20 - 22 November 3 Hari
30 Terminasi L-6 Lantai - Atap 20 - 22 November 3 Hari

31 Power AC Cassate L-1 Lantai - 1 19 November 1 Hari


32 Power AC Cassate L-2 Lantai - 2 18 November 1 Hari
33 Power AC Cassate L-3 Lantai - 3 17 November 1 Hari
34 Power AC Cassate L-4 Lantai - 4 Ok
35 Power AC Cassate L-5 Lantai - 5 Ok

36 Grounding + Tiang Petir Lantai - Atap 17 - 18 November 2 Hari