MASJED SOLEYMAN

PETROCHEMICAL INDUSTRIES
COMPANY Wuhuan Engineering Co. LTD.

MIS FERTILIZER PROJECT (Phase I) Rev 0B


o .
Attachment No. 1: Mechanical Check 1100-OL-PM-PCJ-062
list for Erection of Urea Stripper, T-6501 Page 1 of 2

Attachment No. 1:
Mechanical Check list for Erection of
Urea Stripper, T-6501

0B FOR APPROVAL M. Karimi F. Ramizi M. Fardipour 08/06/2020

0A FOR APPROVAL M. Karimi F. Ramizi M. Fardipour 31/05/2020

Rev. Description DEGND CHEKD APPRD Date

Must not be copied, transmitted to others or used without official permission of PARAVAR Engineering company.
MASJED SOLEYMAN
PETROCHEMICAL INDUSTRIES
COMPANY Wuhuan Engineering Co. LTD.

MIS FERTILIZER PROJECT (Phase I) Rev 0B


o .
Attachment No. 1: Mechanical Check 1100-OL-PM-PCJ-062
list for Erection of Urea Stripper, T-6501 Page 2 of 2

NGST MC
Row

Description Remark
Date Name Date Name
1 Released foundation by Civil (T-6501)
2 Removal of temporary cap of Nozzle No. 11

3 Checking lifting plan for T-6501

4 Checking and preservation of anchor bolts

5 HSE approval for start of erection

6 Installation of Equipment (T-6501)


Scaffolding to access the top and bottom
7
manholes
8 Bolt tensioning to open the manholes
9 Cover removal of top manhole
10 Cover removal of bottom manhole
Air replacement and HSE approval on oxygen
11
concentration (more than 19.5%)
Plumbing of T-6501 according to VD-1219-
12
257E-FAB-006 Installation Manual at site
13 Checking of orientation for T-6501
14 Checking of Elevation for T-6501
Filling and signing of relevant ITP forms by
15
parties