Building No.1 Ground Floor: Dr/Nurse Office Examination-No.3 Soiled /Utility/Bed Processing-No.4
Building No.1 Ground Floor: Dr/Nurse Office Examination-No.3 Soiled /Utility/Bed Processing-No.4
1 GROUND FLOOR
Water Closet De-Ionized Wash Basin/Sink Lavatory Bath Tub Shower Tray Janitor Wash Basin/Kitchen/Clinical Sink Washing Machine
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total
Toilet No. 1 10 5 50 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 5 10 4 3 3 0
Dr/Nurse Office
Examination-No.3 5 0 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 7 14 4 3 3 0
Soiled /Utility/Bed
Processing-No.4 5 0 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 8 16 4 3 3 0
Bath- No. 16 5 15 75 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 15 30 5 0 2 1.5 1.5 30 60 4 3 3 0
Patient Bath No17 10 1 10 2 2 0 2 1.5 1.5 0 4 3 3 1 4 2 1.5 1.5 1 2 5 0 2 1.5 1.5 1 2 4 3 3 0
5 0 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 3 6 4 3 3 0
Clean Utility No24
5 0 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 2 1 2 4 3 3 0
Janitor 5 0 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 1 5 2 1.5 1.5 0 4 3 3 0
135 0 0 4 32 5 110 0
BUILDING NO.1 FIRST FLOOR
Water Closet De-Ionized Wash Basin/Sink Lavatory Bath Tub Shower Tray Janitor Wash Basin/Kitchen/Clinical Sink Washing Machine
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total
Toilet No. 1 10 5 50 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 5 10 4 3 3 0
Dr/Nurse Office
Examination-No.3 5 0 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 8 16 4 3 3 0
Nurses Lounge-
No.4 5 0 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 2 4 4 3 3 0
5 0 2 2 0 2 1.5 1.5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 1 2 4 3 3 0
Soiled Utility- No6
2 2 1 2
Total Janitor - 1 No
286
Bed Processing-No.27 - 1 No
Patients bath 33 - 1 No (Public)
Total Janitor - 1 No
288
589
BUILDING NO.2 BASEMENT FLOOR
Water Closet De-Ionized Wash Basin/Sink Urinal Bath Tub Shower Tray Hose Bib Wash Basin/Kitchen/Clinical Sink SCRUB
Room Name FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total
Toilet No. 20 10 1 10 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 1 2 5 0 2 1.5 1.5 1 2 2 1.5 1.5 0
Toilet No.36 10 6 60 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 6 12 2 1.5 1.5 0
House Keep/Staff
Lockers Toilet No.37
10 1 10 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 1 2 5 0 2 1.5 1.5 3 6 2 1.5 1.5 0
Dr/Treat/ Examination
/Gully-No.3
5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 16 32 2 1.5 1.5 0
Soiled Utility/Service
Area/Rec-No.4 5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 10 20 2 1.5 1.5 0
Toilet No. 9 10 4 40 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 2 4 2 1.5 1.5 0
Endoscopy No.10 10 2 20 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 4 8 2 1.5 1.5 0
Industrial
Processing No.11 5 0 2 2 2 4 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 2 4 2 1.5 1.5 0
Male/Female
Change Rm No.21 5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 2 4 5 0 2 1.5 1.5 0 0 2 1.5 1.5 0
Male/Female Staff
Change Rm 10 2 20 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 2 4 5 0 2 1.5 1.5 2 4 2 1.5 1.5 0
Janitor 5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 3 15 2 1.5 1.5 0 2 1.5 1.5 0 Total
140 4 0 0 8 15 84 0 251
BUILDING NO.2 FIRST FLOOR
Water Closet De-Ionized Wash Basin/Sink Urinal Bath Tub Shower Tray Janitor Wash Basin/Kitchen/Clinical Sink SCRUB
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total
Toilet No. 1 10 6 60 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 6 12 2 1.5 1.5 0
Toilet/Shower 10 2 20 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 2 4 5 0 2 1.5 1.5 0 2 1.5 1.5 0
Nursery/Control/ Solid
utility /Holding/LDR-
No.3 5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 20 40 2 1.5 1.5 0
Examination/
Recovery - 4 5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 4 8 2 1.5 1.5 0
5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 1 2 2 1.5 1.5 0
Soiled Utility- No6 5 5 0 2 2 1 2 2
Soiled Utility/ 5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 2 4 2 1.5 1.5 0
Holding- No 6 A 5 5 0 2 2 1 1 2 2
Bath No.16 5 9 45 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 18 36 5 0 2 1.5 1.5 9 18 2 1.5 1.5 0
Toilet No.20 10 1 10 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 1 2 5 0 2 1.5 1.5 1 2 2 1.5 1.5 0
Change No.43 10 2 20 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 2 4 5 0 2 1.5 1.5 4 8 2 1.5 1.5 0
Connection for
SCRUB & Soiled
Holding 5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 1 2 2 1.5 1.5 1 2
Janitor 5 0 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 2 10 2 1.5 1.5 0 2 1.5 1.5 0 Total
155 0 0 0 46 10 100 2 313
BUILDING NO.2 ROOF FLOOR
Bib Tap De-Ionized Wash Basin/Sinkt Urinal Bath Tub Shower Tray Janitor Wash Basin/Kitchen/Clinical Sink SCRUB
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity Total
Roof Floor 5 3 15 2 2 0 5 5 0 4 3 3 0 2 1.5 1.5 0 5 0 2 1.5 1.5 0 2 1.5 1.5 0 Total
15 0 0 0 0 0 0 0 15
810
Toilet No. 20 - 1 No (Public)
Toilet No.36 - 6 Nos (Public)
Janitor - 3 Nos
Anaesth. Cleaning
No.14 5 0 2 2 1 2 5 5
Processing & for
further Distribution
as per med.
Equipment No.19 5 0 2 2 6 12 5 5
Chnge Room
No.20 10 2 20 2 2 0 5 5
Shower No.21 5 0 2 2 0 5 5
Toilet No.44 10 2 20 2 2 0 5 5
Water Point for
Sink No.3 5 0 2 2 0 5 5
Janitor 5 0 2 2 0 5 5
65 16
BUILDING NO.1 ROOF FLOOR
Bib Tap De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Roof Floor 5 3 15 2 2 0 5 5
15 0
Urinal Bath Tub Shower Tray Janitor
Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 2 4 5 0
0 4 3 3 0 2 1.5 1.5 3 6 5 0
0 4 3 3 0 2 1.5 1.5 1 2 5 0
0 4 3 3 0 2 2 1 2 5 0
0 4 3 3 0 2 1.5 1.5 0 5 1 5
0 0 14 5
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 2 4 5 0
0 4 3 3 0 2 1.5 1.5 1 2 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 4 20
0 0 6 20
331
aleToilet No.1- 4Nos (Public)
ation-No.4 - 1 No
ty No.6 - 1 Nos
mination No 42 - 1 No
y Shower - 1 No
1 - 2 Nos (Public)
1 - 1 No(Private)
44 - 1 No(Public)
Anaesth Work
Room No.15 5 0 2 2 1 2 5 5
Soild Utility No.4 5 0 2 2 0 5 5
Change No.23 10 2 20 2 2 0 5 5
SCRUB No.25 5 0 2 2 0 5 5
SCRUB No.26 5 0 2 2 0 5 5
Soiled Holding/
Frozen Section
No.3 5 0 2 2 0 5 5
30 2
BUILDING NO.1 ROOF FLOOR
Bib Tap De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Roof Floor 5 3 15 2 2 0 5 5
15 0
Urinal Bath Tub Shower Tray Janitor
Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
5 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 1 5
5 0 0 5
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 2 4 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 1 5
0 4 3 3 0 2 1.5 1.5 0 5 0
0 0 4 5
320
aleToilet No.1- 6Nos(Public)
8 - 1 No(Public)
9 - 3 Nos(Public)
No.18 - 2 Nos
ding - 1 No.
1 - 1 No(Public)
Assembling/ Drug
Preparation/ Special
Collection area No.3
5 0 2 2 0 5 5
Toilet No.9 A 10 2 20 2 2 0 5 5
Toilet No.13 10 2 20 2 2 0 5 5
Hystology/Biochemi
stry/future
connection No.14 5 0 2 2 5 10 5 5
Cytology/Soiled
Holding No.15 5 0 2 2 2 4 5 5
Janitor 5 0 2 2 0 5 5
70 14
BUILDING NO.5 & 6 FIRST FLOOR
Water Closet De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Clinic/Administratio
n/ Office/EDP No.3 5 0 2 2 0 5 5
Female Toilet No.9 10 2 20 2 2 0 5 5
Female Toilet No13 10 2 20 2 2 0 5 5
Male Toilet No.28 10 1 10 2 2 0 5 5 2
Ablutiom No.30 5 0 2 2 0 5 5
Male Toilet No.31 10 2 20 2 2 0 5 5
Janitor 5 0 2 2 0 5 5
70 0
BUILDING NO.5 & 6 ROOF FLOOR
Bib Tap De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Roof Floor 5 3 15 2 2 0 5 5
15 0
Urinal Bath Tub Shower Tray Janitor
Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 2 10
0 0 0 10
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
10 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 1 5
10 0 0 5
Hystology/Biochemistry/future connection
2 1.5 1.5 5 10 2 1.5 1.5 0 No.14 - 5 Nos
314
aleToilet No.1- 3Nos(Public)
Biochemistry/future connection
Nos
5 0 2 2 0 5 5
Soiled Utility No.6A
Janitor 5 0 2 2 0 5 5
60 0
BUILDING NO.5 & 6 ROOF FLOOR
Bib Tap De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Roof Floor 5 3 15 2 2 0 5 5
15 0
Urinal Bath Tub Shower Tray Janitor
Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 1 5
0 0 0 5
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 0
0 4 3 3 0 2 1.5 1.5 0 5 1 5
0 0 0 5
314
aleToilet No.1- 6Nos(Public)
9 - 1 No(Public)
y No.4 - 1 No
ding No.6 - 1 No
ty No.6A - 1 No
BUILDING NO. 9 GATE HOUSEGROUND FLOOR
Water Closet De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Toilet No.35 5 1 5 2 2 0 5 5
5 0
BUILDING NO. 10 GATE HOUSE GROUND FLOOR
Water Closet De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Toilet No.34 10 2 20 2 2 0 5 5 1
20 0
BUILDING NO. 14-MOSQUE GROUND FLOOR
Water Closet De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Ablution No.40 5 0 2 2 0 5 5
Toilet No.41 10 2 20 2 2 0 5 5
20 0
BUILDING NO. 15-GATE HOUSE GROUND FLOOR
Water Closet De-Ionized Wash Basin/Sink Urinal
Room Name
FU Quantity Total FU CW HW Quantity Total FU CW HW Quantity
Toilet No.35 10 1 10 4 3 3 0 5 5 1
10 0
Urinal Bath Tub Shower Tray Janitor
Total FU CW HW Quantity Total FU CW HW Quantity Total FU Quantity Total
0 4 3 3 0 2 1.5 1.5 0 5 0
0 0 0 0
111
Cold Water Only
35 - 1 No (Private)
41 - 1 No (Public)
35 - 1 No (Public)
SUMMARY
SL.NO BUILDING FU
1 BUILDING NO.1 589
2 BUILDING NO.2 810
3 BUILDING NO.3 331
4 BUILDING NO.4 320
5 BUILDING NO.5&6 314
6 BUILDING NO.11 40
7 BUILDING NO.13 314
8 BUILDING NO.9+10+14+15 111
TOTAL FU 2829
TOTAL FLOW IN GPM 300
TOTAL FLOW IN L/S 18.92706