Professional Documents
Culture Documents
Risk Assessment Summary Report On Work Road Crossing at WPA
Risk Assessment Summary Report On Work Road Crossing at WPA
10 05
A JunFeb Issued for Review AUT BHW RJH
2013
Rev Rev Date Description Prepared By Checked By Endorsed By Approved By
Charter For Night Time Works at Site Risk
Assessment Risk Assessment Summary 10 05
Report on Working at Height Risk
BANYU URIP Assessment Summary Report on Work
JunFeb 2013
Rev A
PROJECT Road Crossing at WPA
MPI: Not Classified Page 2 of 35
Revisio
Section Description
n
A All Issued For Internal Review
TABLE OF CONTENTS
1. Executive Summary 4
2. Risk and action items summary 5
3. Individual Scenario 6
Appendices 9
Appendix 1 – Risk Matrix 10
Appendix 2 – Attendance list 11
Appendix 3 – Method Statement 12
1. Executive Summary 4
2. Risk and action items summary 5
3. Individual Scenario 6
Appendices 11
Appendix 1 – Risk Matrix 12
Appendix 2 – Charter 13
Appendix 3 – Attendance list 23
Appendix 4 - Brain Storming (Identify Hazard) 24
TABLE OF FIGURES
1. EXECUTIVE SUMMARY
A Risk Assessment was held in purpose of re-identification the risk possibly occur during work road
crossing working at height in EPC1 Banyu Urip Project. The Risk Assessment covered the EMDC
working at height expectation. The actions were determined to ensure coverage all the expectation
that able to minimize the risks as low as reasonably practicable.
The meeting was held on SundayThursday, 010 4 FebruaryJune 2013 at 1316:330 to 168.00 hrs.
The objectives of this Risk Assessment are to:
Identify hazard and project risk issues associated with the project common activity in working at
height. work road crossing.
Identify mitigations (if any) to achieve acceptable risk.
Propose the mitigation plan to be used for improving the safety working methods for any activity
deal with work road crossingworking at height.
As a result some actions need to be taken to allow risk as low as reasonable practicable
4 1,3 Assign dedicated safety advisor to see the AUT 21 Feb 2013
overall working at height operation
3.
4. INDIVIDUAL SCENARIO
SCENARIO 1
Risk Matrix
A B C D E Legend
I HS = Health &
II HS Safety
III E = Environmental
P= Public
IV F Disruption
F = Financial
Scenario Description:
Worker trapped in collapsed trenchWorkers/ rigger fall from height during steel erection
Potential Causes:
513377731.docRisk a Assessment Working Road Crossing at
WPAWorking at Height
Charter For Night Time Works at Site Risk
Assessment Risk Assessment Summary 10 05
Report on Working at Height Risk
BANYU URIP Assessment Summary Report on Work
JunFeb 2013
Rev A
PROJECT Road Crossing at WPA
MPI: Not Classified Page 8 of 35
Incorrect slopping
Rainy
Poor planning
Ineffective supervision
Risk tolerance is high
Lack of supervision
no training
in experience worker
uncertified lifting equipment and gears and tools
uninspected platform
incorrect PPE
heat environment condition
water not available
Consequences:
Serious Injury
medical treatment
equipment damage
schedule impact
Reputation (media attention)
Fatality / serious injury
Assumed Safeguards
Risk Before
HS= II DI E=E NAN/ P=P NAN/ F=F IV DIII
HS= C = A = A = C
Risk After
HS= II DI E=E P=P F=F IV DIII
NANA NANA
HS= D = = = D
Comments:
No comment
SCENARIO 2
Risk Matrix
A B C D E Legend
I HS = Health &
II HS Safety
III E = Environmental
P= Public
IV F Disruption
F = Financial
Scenario Description:
Worker struck by equipment in the night
Worker struck by dropped tool or material
Potential Causes:
No signalman
No Pre start inspection
Unqualified operator
No barricade to restrict the area
No supervisor in area
Poor planning Risk tolerance is high
Lack of supervision
Lack of training
in experience worker
uncertified lifting equipment
uninspected platform
untethered tools
inappropriate barricading
Consequences:
Serious injury
Medical treatment
Schedule impact
Medical Treatment
First Aid
Damage equipment
Near Miss
Assumed Safeguards
Risk Before
II
HS= E=E NAN/ P=P NAN/ F=F IV
DIII
HS= = A = A = DIVC
C
Action Items Actione
e
Barricade training
Consequences management (disciplinary action)
Risk After
II
HS= E=E P=P F=F IV DIV
DIII NANA NANA
HS= = = = D
D
Comments:
No comment
SCENARIO 3
Risk Matrix
A B C D E Legend
I HS = Health &
II Safety
III E = Environmental
P= Public
IV Disruption
F = Financial
Scenario Description:
Potential Causes:
Unqualified personnel modifying scaffolding
Poor Planning
Lack of barricading
Incomplete scaffold was used
No tie off
Consequences:
Fatality / serious injury
Assumed Safeguards
Inspected scaffolding by competent inspector
Scaffolding is erected by certified personnel
Adequate supervision
Medical check
Proper work planning: PTW and JSA
Safety personnel on site dedicated to area
Correct PPE is available
Proper Barricade and signage
Risk Before
HS= IC E= N/A P= N/A F= III C
Risk After
HS= ID E= NA P= NA F= III D
Comments:
No comment
5.
III Medical Treatment for Potential Short Term Public complaint. Division/Site
Personnel/No Impact Minor Adverse Effect. Isolated impact, one time Between 2 USMD and
on Public local media coverage. 500 USKD, or 2 week
Lost Time Incident delay
(LTI)
Scenario
Worker struck by dropped tool or dropped material
Workers/ rigger fall from height during steel erection
Pipe fitter slipped through open scaffold boards
Method Of Work
Road Crossing
A. Preparation
B. Location
C. Sequence Of Work
D. Traffic Management Plan
A. Preparation
1. Equipment
1.1 Heavy Equipment
- Excavator
- Vibro Compact
2. Material Support
- Pipe Scaffolding + Clem
- U Head
- Jack Base
3. Material
- Wood
513377731.docRisk a Assessment Working Road Crossing at
WPAWorking at Height
Charter For Night Time Works at Site Risk
Assessment Risk Assessment Summary 10 05
Report on Working at Height Risk
BANYU URIP Assessment Summary Report on Work
JunFeb 2013
Rev A
PROJECT Road Crossing at WPA
MPI: Not Classified Page 31 of 35
- Rebar
- Concrete
B. Location
C. Sequence of Work
1. General Sequence
2. Detail Sequence
2.1 Excavation Work
a. Alternative 1
b. Alternative 2
Sequence 1
Install rebar for slab, pedestal pipe sleeper and install embedded, continue to concrete
Sequence 2
Install rebar for wall (h=1.50 m), Install scaffolding, formwork and concrete
Sequence 3
Install Scaffolding, install rebar (h=1 m), formwork with tie rod (support with scaffolding)
Pouring concrete.
Sequence 4
Install scaffolding, formwork, rebar and pouring concrete