M / S NATIONAL RCC WORKS Pvt (Ltd)

CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR


BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
Consuled Beam in 2ND-Floor Slab
Joint 1 ( A to E)
1 Grid A to B (S/Beam) 6 0 1 4 4 5.75 23 - - - 34.5 -
2 Stirrups 3 8" 1 11 11 3.50 38.5 14.4375 - - - -
3 Grid A to B (L/Beam) 6 0 1 8 8 15.00 120 - - - 180 -
4 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
5 Grid B to D 6 0 1 8 8 29.84 238.72 - - - 358.08 -
6 Stirrups 3 8" 1 46 46 4.00 184 69 - - - -
7 Grid D to E 6 0 1 8 8 15.00 120 - - - 180 -
8 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
9 Grid A to E (Front CB1) 6 0 1 8 8 61.91 495.28 - - - 742.92 -
10 Stirrups 3 8" 1 89 89 4.00 356 133.5 - - - -
11 Joint 2 ( E to K)
12 Grid E to G (S/Beam) 6 0 1 4 4 5.75 23 - - - 34.5 -
13 Stirrups 3 8" 1 11 11 3.50 38.5 14.4375 - - - -
14 Grid E to G (L/Beam) 6 0 1 8 8 15.00 120 - - - 180 -
15 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
16 Grid G to J 6 0 1 8 8 29.84 238.72 - - - 358.08 -
17 Stirrups 3 8" 1 46 46 4.00 184 69 - - - -
18 Grid J to K 6 0 1 8 8 15.00 120 - - - 180 -
19 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
20 Grid E to K (Front CB1) 6 0 1 8 8 61.03 488.24 - - - 732.36 -
21 Stirrups 3 8" 1 89 89 4.00 356 133.5 - - - -
22 Joint 3 ( L to O)
23 Grid L to K (S/Beam) 6 0 1 4 4 5.75 23 - - - 34.5 -
24 Stirrups 3 8" 1 11 11 3.50 38.5 14.4375 - - - -
25 Grid L to K (L/Beam) 6 0 1 8 8 15.00 120 - - - 180 -
26 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
27 Grid K to L 6 0 1 8 8 15.125 121 - - - 181.5 -
28 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
29 Grid M to N 6 0 1 8 8 15.125 121 - - - 181.5 -
30 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
31 Grid N to O (S/Beam) 6 0 1 4 4 5.75 23 - - - 34.5 -
32 Stirrups 3 8" 1 11 11 3.50 38.5 14.4375 - - - -
33 Grid N to O (L/Beam) 6 0 1 8 8 15.00 120 - - - 180 -
34 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
35 Grid L to O (Front CB1) 6 0 1 8 8 71.31 570.48 - - - 855.72 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
36 Stirrups 3 8" 1 104 104 4.00 416 156 - - - -
37 Joint 4 ( O to T)
38 Grid O to T (S/Beam) 6 0 1 4 4 5.75 23 - - - 34.5 -
39 Stirrups 3 8" 1 11 11 3.50 38.5 14.4375 - - - -
40 Grid O to T (L/Beam) 6 0 1 8 8 15.00 120 - - - 180 -
41 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
42 Grid Q to S 6 0 1 8 8 29.840 238.72 - - - 358.08 -
43 Stirrups 3 8" 1 46 46 4.00 184 69 - - - -
44 Grid S to T (S/Beam) 6 0 1 4 4 5.75 23 - - - 34.5 -
45 Stirrups 3 8" 1 11 11 3.50 38.5 14.4375 - - - -
46 Grid S to T (L/Beam) 6 0 1 8 8 15.00 120 - - - 180 -
47 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
48 Grid O to T (Front CB1) 6 0 1 8 8 61.03 488.24 - - - 732.36 -
49 Stirrups 3 8" 1 89 89 4.00 356 133.5 - - - -
50 Joint 5 ( T to U)
51 Grid O to T (S/Beam) 6 0 1 4 4 5.75 23 - - - 34.5 -
52 Stirrups 3 8" 1 11 11 3.50 38.5 14.4375 - - - -
53 Grid O to T (L/Beam) 6 0 1 8 8 15.00 120 - - - 180 -
54 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
55 Grid Q to S 6 0 1 8 8 29.840 238.72 - - - 358.08 -
56 Stirrups 3 8" 1 46 46 4.00 184 69 - - - -
57 Grid S to T (S/Beam) 6 0 1 4 4 5.75 23 - - - 34.5 -
58 Stirrups 3 8" 1 11 11 3.50 38.5 14.4375 - - - -
59 Grid S to T (L/Beam) 6 0 1 8 8 15.00 120 - - - 180 -
60 Stirrups 3 8" 1 24 24 4.00 96 36 - - - -
61 Grid O to T (Front CB1) 6 0 1 8 8 61.03 488.24 - - - 732.36 -
62 Stirrups 3 8" 1 89 89 4.00 356 133.5 - - - -
1 1513.5 7667.04
Total Weight in Lbs 9180.54

Total Weight in Kg 4165.40


123 Total Weight in Ton 4.165
124

125

126

127

128

129

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
130

131

132

133

134

135

136

137

138

139

140

141

142 0 - -
143 Landing 0 4.81 0 - -
144 M-bar 4 6" 1 23 23 12.5 0 - -
145 D-bar 4 10" 1 13 13 0 - -
146 stair form landing to roof 0 - -
147 M-bar 4 6" 1 24 11.25 258.75 - 172.58625

24
148 D-bar 4 10" 1 8 6 78 - 52.026

8
149 0 - -
150 Steel as in stair area (2nd-floor) 0 4.81 115.44 - 76.99848
151 Grid 1-2/L-M 0 12.5 100 - 66.7
152 M-bar 4 5" 1 28 28 0 - -
153 D-bar 4 7" 1 20 20 0 - -
154 0 - -
155 11.5 322 - 214.774
156 11.58 231.6 - 154.4772
157 0.00 737.56
158 STEEL IN SEPTIC TANK (2NO) Total Weight in Lbs 737.56
159 BED Total Weight in Kg 334.65
160 M-BAR 4 6" 2 30 60 Total Weight in Ton 0.335
161 D-BAR 4 6" 2 22 44
162 WALL 0
163 L/SIDE (vertical bar) 4 6" 4 22 88 11 660 - 440.22
164 L/SIDE (horzintal bar) 3 9" 4 12 48 15 660 - 440.22
165 S/SIDE (vertical bar) 4 6" 4 18 72 0 - -
166 S/SIDE (horzintal bar) 3 9" 4 12 48 8.5 748 - 498.916

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
167 M-BAR 4 6" 2 30 60 11.5 552 207 -
168 D-BAR 4 6" 2 22 44 8.5 612 - 408.204
169 SLAB 8.5 408 153 -
170 M-BAR 4 6" 2 25 50 11 660 - 440.22
171 D-BAR 4 6" 2 17 34 15 660 - 440.22
172

173 8.25 412.5 - 275.1375


174 12.25 416.5 - 277.8055
175 360 3220.943
176 Total Weight in Lbs 3580.94 Lbs
177 Total Weight in Kg 1624.75 kg
178 Total Weight in Ton 1.625 Ton
179

180

181

182

183

184

185

186

187

188

189

190

191

192

193

194

195

196

197

198

199

200

201

202

203 Extra bars on Grid 11 P* 0

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
204 Main Bars 6 6" C/C 1 19 19
205 Dist Bars 6 6" C/C 1 17 17
206 Extra bars on Grid 12 F 0 0 - - - 187.11 -
207 Main Bars 6 6" C/C 1 16 16 9.38 178.22 - - - - -
208 Dist Bars 6 6" C/C 1 14 14 10.71 182.07 - - - 223.215 -
209 Extra bars on Grid 12 G 0 0 - - - 227.01 -
210 Main Bars 6 6" C/C 1 19 19 6.47 103.52 - - - - -
211 Dist Bars 6 6" C/C 1 14 14 7.5 105 - - - 184.395 -
212 Extra bars on Grid 12 H 0 0 - - - 187.11 -
213 Main Bars 6 6" C/C 1 23 23 6.47 122.93 - - - - -
214 Dist Bars 6 6" C/C 1 14 14 8.91 124.74 - - - 174.69 -
215 Extra bars on Grid 12 (I) 0 0 - - - 175.875 -
216 Main Bars 6 6" C/C 1 19 19 6.47 148.81 - - - - -
217 Dist Bars 6 6" C/C 1 14 14 10.81 151.34 - - - 213.51 -
218 Extra bars on Grid 12 J 0 0 - - - 221.76 -
219 Main Bars 6 6" C/C 1 18 18 6.47 122.93 - - - - -
220 Dist Bars 6 6" C/C 1 14 14 8.91 124.74 - - - 194.1 -
221 Extra bars on Grid 12 K 0 0 - - - 195.51 -
222 Main Bars 6 6" C/C 1 22 22 6.47 116.46 - - - - -
223 Dist Bars 6 6" C/C 1 14 14 8.375 117.25 - - - 145.575 -
224 Extra bars on Grid 12 L 0 0 - - - 149.625 -
225 Main Bars 6 6" C/C 1 20 20 6.47 142.34 - - - - -
226 Dist Bars 6 6" C/C 1 14 14 10.56 147.84 - - - 174.69 -
227 Extra bars on Grid 12 M 0 0 - - - 174.51 -
228 Main Bars 6 6" C/C 1 15 15 6.47 129.4 - - - - -
229 Dist Bars 6 6" C/C 1 14 14 9.31 130.34 - - - 145.575 -
230 Extra bars on Grid 12 N 0 0 - - - 145.74 -
231 Main Bars 6 6" C/C 1 18 18 6.47 97.05 - - - - -
232 Dist Bars 6 6" C/C 1 14 14 7.125 99.75 - - - 196.605 -
233 Extra bars on Grid 12 O 0 0 - - - 182.91 -
234 Main Bars 6 6" C/C 1 15 15 6.47 116.46 - - - - -
235 Dist Bars 6 6" C/C 1 14 14 8.31 116.34 - - - - -
236 Extra bars on Grid 12 P* 0 0 - - - 71.25 -
237 Main Bars 6 6" C/C 1 17 17 6.47 97.05 - - - 67.05 -
238 Dist Bars 6 6" C/C 1 13 13 6.94 97.16 - - - - -
239 Extra bars on Centers 0 0 - - - 251.085 -
240 Grid (F-G, 11-12) 0 7.71 131.07 - - - 254.79 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
241 Main Bars 6 6" C/C 1 19 19 9.38 121.94 - - - - -
242 Dist Bars 6 6" C/C 1 5 5 0 - - - 251.085 -
243 Grid (G-H, 11-12) 0 0 - - - 254.79 -
244 Main Bars 6 6" C/C 1 19 19 2.5 47.5 - - - - -
245 Dist Bars 6 6" C/C 1 19 19 8.94 44.7 - - - 142.5 -
246 Grid (H-I, 11-12) 0 0 - - - 147.51 -
247 Main Bars 6 6" C/C 1 19 19 8.81 167.39 - - - - -
248 Dist Bars 6 6" C/C 1 19 19 8.94 169.86 - - - 249.375 -
249 Grid (I-J, 11-12) 0 0 - - - 254.79 -
250 Main Bars 6 6" C/C 1 19 19 8.81 167.39 - - - - -
251 Dist Bars 6 6" C/C 1 11 11 8.94 169.86 - - - 235.125 -
252 Grid (J-K, 11-12) 0 0 - - - 241.38 -
253 Main Bars 6 6" C/C 1 19 19 5 95 - - - - -
254 Dist Bars 6 6" C/C 1 19 19 8.94 98.34 - - - 178.125 -
255 Grid (K-L, 11-12) 0 0 - - - 187.74 -
256 Main Bars 6 6" C/C 1 19 19 8.75 166.25 - - - - -
257 Dist Bars 6 6" C/C 1 18 18 8.94 169.86 - - - 178.125 -
258 Grid (L-M, 11-12) 0 0 - - - 187.74 -
259 Main Bars 6 6" C/C 1 19 19 8.25 156.75 - - - - -
260 Dist Bars 6 6" C/C 1 14 14 8.94 160.92 - - - 207.9 -
261 Grid (M-N, 11-12) 0 0 - - - 203.385 -
262 Main Bars 6 6" C/C 1 19 19 6.25 118.75 - - - - -
263 Dist Bars 6 6" C/C 1 14 14 8.94 125.16 - - - 209.79 -
264 Grid (N-O, 11-12)* 0 0 - - - 219.03 -
265 Main Bars 6 6" C/C 1 18 18 6.25 118.75 - - - - -
266 Dist Bars 6 6" C/C 1 13 13 8.94 125.16 - - - 173.28 -
267 Grid (O-P, 11-12)* 0 0 - - - 168.75 -
268 Main Bars 6 6" C/C 1 18 18 7.7 138.6 - - - - -
269 Dist Bars 6 6" C/C 1 14 14 10.43 135.59 - - - 205.77 -
270 Extra bars on Grid 13 F 0 0 - - - 200.475 -
271 Main Bars 6 6" C/C 1 16 16 7.77 139.86 - - - - -
272 Dist Bars 6 6" C/C 1 15 15 10.43 146.02 - - - 249.09 -
273 Extra bars on Grid 13 G 0 0 - - - 243.225 -
274 Main Bars 6 6" C/C 1 19 19 7.22 115.52 - - - - -
275 Dist Bars 6 6" C/C 1 15 15 7.5 112.5 - - - 205.77 -
276 Extra bars on Grid 13 H 0 0 - - - 200.475 -
277 Main Bars 6 6" C/C 1 23 23 7.22 137.18 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
278 Dist Bars 6 6" C/C 1 15 15 8.91 133.65 - - - 205.77 -
279 Extra bars on Grid 13 (I) 0 0 - - - 198.225 -
280 Main Bars 6 6" C/C 1 19 19 7.22 166.06 - - - - -
281 Dist Bars 6 6" C/C 1 15 15 10.81 162.15 - - - 238.26 -
282 Extra bars on Grid 13 J 0 0 - - - 235.575 -
283 Main Bars 6 6" C/C 1 19 19 7.22 137.18 - - - - -
284 Dist Bars 6 6" C/C 1 15 15 8.91 133.65 - - - 216.6 -
285 Extra bars on Grid 13 K 0 0 - - - 208.8 -
286 Main Bars 6 6" C/C 1 22 22 7.22 137.18 - - - - -
287 Dist Bars 6 6" C/C 1 15 15 8.81 132.15 - - - 194.94 -
288 Extra bars on Grid 13 L 0 0 - - - 186.075 -
289 Main Bars 6 6" C/C 1 20 20 7.22 158.84 - - - - -
290 Dist Bars 6 6" C/C 1 15 15 10.47 157.05 - - - 184.11 -
291 Extra bars on Grid 13 M 0 0 - - - 182.8125 -
292 Main Bars 6 6" C/C 1 18 18 7.22 144.4 - - - - -
293 Dist Bars 6 6" C/C 1 15 15 9.28 139.2 - - - 182.07 -
294 Extra bars on Grid 13 N 0 0 - - - 174.96 -
295 Main Bars 6 6" C/C 1 17 17 7.22 129.96 - - - - -
296 Dist Bars 6 6" C/C 1 15 15 8.27 124.05 - - - 160.65 -
297 Extra bars on Grid 13 O* 0 0 - - - 149.58 -
298 Main Bars 6 6" C/C 1 17 17 7.22 122.74 - - - - -
299 Dist Bars 6 6" C/C 1 12 12 8.125 121.875 - - - 300.51 -
300 Extra bars on Grid 13 P* 0 0 - - - 296.25 -
301 Main Bars 6 6" C/C 1 15 15 7.14 121.38 - - - - -
302 Dist Bars 6 6" C/C 1 12 12 9.72 116.64 - - - 309.375 -
303 Extra bars on Grid 15 D 0 0 - - - 312 -
304 Main Bars 6 6" C/C 1 21 21 7.14 107.1 - - - - -
305 Dist Bars 6 6" C/C 1 20 20 8.31 99.72 - - - 294.03 -
306 Extra bars on Grid 15 F 0 0 - - - 296.4 -
307 Main Bars 6 6" C/C 1 22 22 9.54 200.34 - - - - -
308 Dist Bars 6 6" C/C 1 20 20 9.875 197.5 - - - 358.8 -
309 Extra bars on Grid 15 G 0 0 - - - 357.39 -
310 Main Bars 6 6" C/C 1 22 22 9.375 206.25 - - - - -
311 Dist Bars 6 6" C/C 1 19 19 10.4 208 - - - 294.03 -
312 Extra bars on Grid 15 H 0 0 - - - 296.4 -
313 Main Bars 6 6" C/C 1 23 23 8.91 196.02 - - - - -
314 Dist Bars 6 6" C/C 1 22 22 10.4 197.6 - - - 290.73 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
315 Extra bars on Grid 15 (I) 0 0 - - - 296.4 -
316 Main Bars 6 6" C/C 1 22 22 10.4 239.2 - - - - -
317 Dist Bars 6 6" C/C 1 19 19 10.83 238.26 - - - 343.2 -
318 Extra bars on Grid 15 J 0 0 - - - 345.18 -
319 Main Bars 6 6" C/C 1 22 22 8.91 196.02 - - - - -
320 Dist Bars 6 6" C/C 1 19 19 10.4 197.6 - - - 306.24 -
321 Extra bars on Grid 15 K 0 0 - - - 312 -
322 Main Bars 6 6" C/C 1 22 22 8.81 193.82 - - - - -
323 Dist Bars 6 6" C/C 1 22 22 10.4 197.6 - - - 272.91 -
324 Extra bars on Grid 15 L 0 0 - - - 280.8 -
325 Main Bars 6 6" C/C 1 22 22 10.4 228.8 - - - - -
326 Dist Bars 6 6" C/C 1 20 20 10.46 230.12 - - - 235.62 -
327 Extra bars on Grid 15 M 0 0 - - - 234 -
328 Main Bars 6 6" C/C 1 22 22 9.28 204.16 - - - - -
329 Dist Bars 6 6" C/C 1 18 18 10.4 208 - - - 264 -
330 Extra bars on Grid 15 N 0 0 - - - 265.2 -
331 Main Bars 6 6" C/C 1 22 22 8.27 181.94 - - - - -
332 Dist Bars 6 6" C/C 1 15 15 10.4 187.2 - - - 274.23 -
333 Extra bars on Grid 15 N1 0 0 - - - 268.2 -
334 Main Bars 6 6" C/C 1 22 22 7.14 157.08 - - - - -
335 Dist Bars 6 6" C/C 1 17 17 10.4 156 - - - 339.24 -
336 Extra bars on Grid 15 P* 0 0 - - - 350.625 -
337 Main Bars 6 6" C/C 1 22 22 8 176 - - - - -
338 Dist Bars 6 6" C/C 1 15 15 10.4 176.8 - - - 309.375 -
339 Extra bars on Grid 16 D 0 0 - - - 308.4 -
340 Main Bars 6 6" C/C 1 22 22 8.31 182.82 - - - - -
341 Dist Bars 6 6" C/C 1 22 22 11.92 178.8 - - - 294.03 -
342 Extra bars on Grid 16 F 0 0 - - - 292.98 -
343 Main Bars 6 6" C/C 1 22 22 10.28 226.16 - - - - -
344 Dist Bars 6 6" C/C 1 20 20 10.625 233.75 - - - 354.66 -
345 Extra bars on Grid 16 G 0 0 - - - 357.72 -
346 Main Bars 6 6" C/C 1 22 22 9.375 206.25 - - - - -
347 Dist Bars 6 6" C/C 1 19 19 10.28 205.6 - - - 294.03 -
348 Extra bars on Grid 16 H 0 0 - - - 292.98 -
349 Main Bars 6 6" C/C 1 23 23 8.91 196.02 - - - - -
350 Dist Bars 6 6" C/C 1 22 22 10.28 195.32 - - - 290.73 -
351 Extra bars on Grid 16 (I) 0 0 - - - 292.98 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
352 Main Bars 6 6" C/C 1 22 22 10.28 236.44 - - - - -
353 Dist Bars 6 6" C/C 1 19 19 10.84 238.48 - - - 339.24 -
354 Extra bars on Grid 16 J 0 0 - - - 345.18 -
355 Main Bars 6 6" C/C 1 22 22 8.91 196.02 - - - - -
356 Dist Bars 6 6" C/C 1 19 19 10.28 195.32 - - - 306.24 -
357 Extra bars on Grid 16 K 0 0 - - - 308.4 -
358 Main Bars 6 6" C/C 1 22 22 8.81 193.82 - - - - -
359 Dist Bars 6 6" C/C 1 22 22 10.28 195.32 - - - 272.91 -
360 Extra bars on Grid 16 L 0 0 - - - 277.56 -
361 Main Bars 6 6" C/C 1 22 22 10.28 226.16 - - - - -
362 Dist Bars 6 6" C/C 1 20 20 10.46 230.12 - - - 235.62 -
363 Extra bars on Grid 16 M 0 0 - - - 231.3 -
364 Main Bars 6 6" C/C 1 22 22 9.28 204.16 - - - - -
365 Dist Bars 6 6" C/C 1 18 18 10.28 205.6 - - - 264 -
366 Extra bars on Grid 16 N 0 0 - - - 262.14 -
367 Main Bars 6 6" C/C 1 22 22 8.27 181.94 - - - - -
368 Dist Bars 6 6" C/C 1 15 15 10.28 185.04 - - - 274.23 -
369 Extra bars on Grid 16 N1 0 0 - - - 268.2 -
370 Main Bars 6 6" C/C 1 22 22 7.14 157.08 - - - - -
371 Dist Bars 6 6" C/C 1 17 17 10.28 154.2 - - - 75.075 -
372 Extra bars on Grid 16 P* 0 0 - - - 63 -
373 Main Bars 6 6" C/C 1 22 22 8 176 - - - - -
374 Dist Bars 6 6" C/C 1 15 15 10.28 174.76 - - - 75.075 -
375 Extra bars on Grid 13 B1 0 0 - - - 60.69 -
376 Main Bars 6 6" C/C 1 13 13 8.31 182.82 - - - - -
377 Dist Bars 6 6" C/C 1 7 7 11.92 178.8 - - - 75.075 -
378 Extra bars on Grid 13 B2 0 0 - - - 60.69 -
379 Main Bars 6 6" C/C 1 13 13 3.85 50.05 - - - - -
380 Dist Bars 6 6" C/C 1 7 7 6 42 - - - 75.075 -
381 Extra bars on Grid 13 C 0 0 - - - 60.69 -
382 Main Bars 6 6" C/C 1 13 13 3.85 50.05 - - - - -
383 Dist Bars 6 6" C/C 1 7 7 5.78 40.46 - - - 75.075 -
384 Extra bars on Grid 13 C2 0 0 - - - 60.69 -
385 Main Bars 6 6" C/C 1 13 13 3.85 50.05 - - - - -
386 Dist Bars 6 6" C/C 1 7 7 5.78 40.46 - - - 57.75 -
387 Extra bars on Grid 13 D2 0 0 - - - 48.5625 -
388 Main Bars 6 6" C/C 1 13 13 3.85 50.05 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
389 Dist Bars 6 6" C/C 1 7 7 5.78 40.46 - - - 114.48 -
390 Extra bars on Grid 13 E1 0 0 - - - 126.06 -
391 Main Bars 6 6" C/C 1 10 10 3.85 50.05 - - - - -
392 Dist Bars 6 6" C/C 1 7 7 5.78 40.46 - - - 93.015 -
393 Extra bars on Grid 14 A1 0 0 - - - 99.495 -
394 Main Bars 6 6" C/C 1 16 16 3.85 38.5 - - - - -
395 Dist Bars 6 6" C/C 1 11 11 4.625 32.375 - - - 372.06 -
396 Extra bars on Grid 14 B1 0 0 - - - 381.48 -
397 Main Bars 6 6" C/C 1 13 13 4.77 76.32 - - - - -
398 Dist Bars 6 6" C/C 1 11 11 7.64 84.04 - - - - -
399 Extra bars on Grid 14 B2,C1,C2,D2 0 0 - - - 52.8 -
400 Main Bars 6 6" C/C 4 13 52 4.77 62.01 - - - 50.085 -
401 Dist Bars 6 6" C/C 4 11 44 6.03 66.33 - - - - -
402 Extra bars on Centers 0 0 - - - 55.275 -
403 Grid (A1-B1, 13-14) 0 4.77 248.04 - - - 57.24 -
404 Main Bars 6 6" C/C 1 11 11 5.78 254.32 - - - - -
405 Dist Bars 6 6" C/C 1 7 7 0 - - - 240 -
406 Grid (A1-B1, 14-14a) 0 0 - - - 224.7 -
407 Main Bars 6 6" C/C 1 11 11 3.2 35.2 - - - - -
408 Dist Bars 6 6" C/C 1 8 8 4.77 33.39 - - - 251.25 -
409 Grid (B1-E1, 13-14) 0 0 - - - 256.8 -
410 Main Bars 6 6" C/C 5 10 50 3.35 36.85 - - - - -
411 Dist Bars 6 6" C/C 5 7 35 4.77 38.16 - - - 21 -
412 Grid (B1-E1, 14-14a) 0 0 - - - 24 -
413 Main Bars 6 6" C/C 5 10 50 3.2 160 - - - - -
414 Dist Bars 6 6" C/C 5 8 40 4.28 149.8 - - - 24 -
415 Grid (E1-F, 13-14) 0 0 - - - 25.125 -
416 Main Bars 6 6" C/C 1 7 7 3.35 167.5 - - - - -
417 Dist Bars 6 6" C/C 1 5 5 4.28 171.2 - - - 127.5 -
418 Grid (M-N, 13-16) 0 0 - - - 128.535 -
419 Main Bars 6 6" C/C 1 8 8 2 14 - - - - -
420 Dist Bars 6 6" C/C 1 5 5 3.2 16 - - - 142.5 -
421 Grid (F-G, 13-15) 0 0 - - - 149.49 -
422 Main Bars 6 6" C/C 1 17 17 2 16 - - - - -
423 Dist Bars 6 6" C/C 1 11 11 3.35 16.75 - - - 222.015 -
424 Grid (F-G, 15-16) 0 0 - - - 224.91 -
425 Main Bars 6 6" C/C 1 19 19 5 85 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
426 Dist Bars 6 6" C/C 1 11 11 7.79 85.69 - - - 251.37 -
427 Grid (G-H, 13-15) 0 0 - - - 258.21 -
428 Main Bars 6 6" C/C 1 19 19 5 95 - - - - -
429 Dist Bars 6 6" C/C 1 17 17 9.06 99.66 - - - 222.015 -
430 Grid (G-H, 15-16) 0 0 - - - 224.91 -
431 Main Bars 6 6" C/C 1 19 19 7.79 148.01 - - - - -
432 Dist Bars 6 6" C/C 1 19 19 8.82 149.94 - - - 251.37 -
433 Grid (H-I, 13-15) 0 0 - - - 258.21 -
434 Main Bars 6 6" C/C 1 19 19 8.82 167.58 - - - - -
435 Dist Bars 6 6" C/C 1 17 17 9.06 172.14 - - - 127.5 -
436 Grid (H-I, 15-16) 0 0 - - - 128.535 -
437 Main Bars 6 6" C/C 1 19 19 7.79 148.01 - - - - -
438 Dist Bars 6 6" C/C 1 19 19 8.82 149.94 - - - 142.5 -
439 Grid (I-J, 13-15) 0 0 - - - 149.49 -
440 Main Bars 6 6" C/C 1 17 17 8.82 167.58 - - - - -
441 Dist Bars 6 6" C/C 1 11 11 9.06 172.14 - - - 210.33 -
442 Grid (I-J, 15-16) 0 0 - - - 216.24 -
443 Main Bars 6 6" C/C 1 19 19 5 85 - - - - -
444 Dist Bars 6 6" C/C 1 11 11 7.79 85.69 - - - 222.015 -
445 Grid (J-K, 13-15) 0 0 - - - 244.62 -
446 Main Bars 6 6" C/C 1 18 18 5 95 - - - - -
447 Dist Bars 6 6" C/C 1 17 17 9.06 99.66 - - - 210.33 -
448 Grid (J-K, 15-16) 0 0 - - - 211.395 -
449 Main Bars 6 6" C/C 1 19 19 7.79 140.22 - - - - -
450 Dist Bars 6 6" C/C 1 18 18 8.48 144.16 - - - 222.015 -
451 Grid (K-L, 13-15) 0 0 - - - 231.03 -
452 Main Bars 6 6" C/C 1 18 18 7.79 148.01 - - - - -
453 Dist Bars 6 6" C/C 1 17 17 9.06 163.08 - - - 319.77 -
454 Grid (K-L, 15-16) 0 0 - - - 327.18 -
455 Main Bars 6 6" C/C 1 19 19 7.79 140.22 - - - - -
456 Dist Bars 6 6" C/C 1 17 17 8.29 140.93 - - - 357.39 -
457 Grid (L-N, 13-15) 0 0 - - - 380.52 -
458 Main Bars 6 6" C/C 2 17 34 7.79 148.01 - - - - -
459 Dist Bars 6 6" C/C 2 14 28 9.06 154.02 - - - 86.0625 -
460 Grid (L-N, 15-16) 0 0 - - - 93.48 -
461 Main Bars 6 6" C/C 2 19 38 6.27 213.18 - - - - -
462 Dist Bars 6 6" C/C 2 14 28 7.79 218.12 - - - 96.1875 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
463 Grid (N-N1, 13-15) 0 0 - - - 108.72 -
464 Main Bars 6 6" C/C 1 17 17 6.27 238.26 - - - - -
465 Dist Bars 6 6" C/C 1 8 8 9.06 253.68 - - - - -
466 Grid (N-N1, 15-16) 0 0 - - - 945 -
467 Main Bars 6 6" C/C 1 19 19 3.375 57.375 - - - 789.75 -
468 Dist Bars 6 6" C/C 1 8 8 7.79 62.32 - - - 360 -
469 Raft for lift 0 0 - - - 468 -
470 Bottom Bars 0 3.375 64.125 - - - - -
471 Main Bars 6 6" C/C 1 24 24 9.06 72.48 - - - 285 -
472 Dist Bars 6 6" C/C 1 18 18 0 - - - 253.5 -
473 Inside Beams L/W 6 6" C/C 2 12 24 0 - - - - -
474 Inside Beams S/W 6 6" C/C 2 12 24 26.25 630 - - - 468 -
475 Top Bars 0 29.25 526.5 - - - 540 -
476 Main Bars 6 6" C/C 1 19 19 10 240 - - - - -
477 Dist Bars 6 6" C/C 1 13 13 13 312 - - - - -
478 Inner side Vertical Bars 0 0 - - - - -
479 Main Bars L/W 6 6" C/C 2 12 24 10 190 - - - - -
480 Main Bars S/W 6 6" C/C 2 18 36 13 169 - - - - -
481 Dist Bars outer L/w 4 6" C/C 2 6 12 0 - - - - -
482 Dist Bars inner L/w 4 6" C/C 2 6 12 13 312 - - - - -
483 Dist Bars outer S/w 4 6" C/C 2 6 12 10 360 - - - - -
484 Dist Bars inner S/w 4 6" C/C 2 6 12 12.5 150 - 100.05 - - -
485 Dowels for Lift RCC wall 0 10.25 123 - 82.041 - - -
486 Main Bars L/W 4 9" C/C 2 15 30 9.5 114 - 76.038 - - -
487 Dist bars L/W 3 9" C/C 2 10 20 7.25 87 - 58.029 - - -
488 Main Bars S/W 4 9" C/C 2 10 20 0 - - - - -
489 Dist bars S/W 3 9" C/C 2 10 20 10 300 - 200.1 - - -
Dowels for Lift RCC wall up to Ground Floor
490 Center 0 11.25 225 84.375 - - - -
491 Main Bars L/W 4 9" C/C 2 15 30 10 200 - 133.4 - - -
492 Dist bars L/W 3 9" C/C 2 11 22 8.25 165 61.875 - - - -
493 Main Bars S/W 4 9" C/C 2 10 20 0 - - - - -
494 Dist bars S/W 3 9" C/C 2 11 22 13.79 413.7 - 275.9379 - - -
495 Dowels for Stairs 0 11.25 247.5 92.8125 - - - -
496 Between Grid 11-12 0 11.79 235.8 - 157.2786 - - -
497 Main Bars 4 9" C/C 2 11 22 8.25 181.5 68.0625 - - 290.4 -
498 Between Grid 15-16 0 0 - - - 283.6875 -
499 Main Bars 4 9" C/C 2 11 22 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
500 0 6.75 148.5 - 99.0495 - 290.4 -
501 Extra bars on Grid 16-E1 0 0 - - - 283.6875 -
502 Main Bars 6 6" C/C 1 20 20 6.75 148.5 - 99.0495 - - -
503 Dist Bars 6 6" C/C 1 17 17 0 - - - 135 -
504 Extra bars on Grid 17-E1 0 0 - - - 125.1 -
505 Main Bars 6 6" C/C 1 20 20 9.68 193.6 - - - - -
506 Dist Bars 6 6" C/C 1 17 17 11.125 189.125 - - - 162 -
507 Extra bars on Grid 12 -A 0 0 - - - 148.5 -
508 Main Bars 6 6" C/C 1 15 15 9.68 193.6 - - - - -
509 Dist Bars 6 6" C/C 1 10 10 11.125 189.125 - - - 234 -
510 Extra bars on Grid 12 -B 0 0 - - - 208.05 -
511 Main Bars 6 6" C/C 1 18 18 6 90 - - - - -
512 Dist Bars 6 6" C/C 1 10 10 8.34 83.4 - - - 198 -
513 Extra bars on Grid 12 -C 0 0 - - - 183.6 -
514 Main Bars 6 6" C/C 1 26 26 6 108 - - - - -
515 Dist Bars 6 6" C/C 1 10 10 9.9 99 - - - 237.9 -
516 Extra bars on Grid 12 -E 0 0 - - - 226.38 -
517 Main Bars 6 6" C/C 1 22 22 6 156 - - - - -
518 Dist Bars 6 6" C/C 1 10 10 13.87 138.7 - - - 237.9 -
519 Extra bars on Grid 16 -Q 0 0 - - - 226.38 -
520 Main Bars 6 6" C/C 1 20 20 6 132 - - - - -
521 Dist Bars 6 6" C/C 1 14 14 12.24 122.4 - - - - -
522 Extra bars on Grid 17 -Q 0 0 - - - - -
523 Main Bars 6 6" C/C 1 20 20 7.93 158.6 - - - 2594.235 -
524 Dist Bars 6 6" C/C 1 14 14 10.78 150.92 - - - 5876.415 -
525 OPD AND PORCH ( RAFT SCHEDULE ) 0 0 - - - 10898.595 -
526 Bottom Bars 0 7.93 158.6 - - - - -
527 Main Bars 0 10.78 150.92 - - - 15698.25 -
528 Raft 1 6 6" C/C 1 62 62 0 - - - 1234.035 -
529 Raft 2 6 6" C/C 1 79 79 0 - - - 2658.6 -
530 Raft 3 6 6" C/C 1 141 141 0 - - - - -
531 Dist Bars 0 27.895 1729.49 - - - - -
532 Raft A 6 6" C/C 1 75 75 49.59 3917.61 - - - 2454.735 -
533 Raft B 6 6" C/C 1 33 33 51.53 7265.73 - - - 5520.915 -
534 Raft C 6 6" C/C 1 40 40 0 - - - 10264.095 -
535 Top Bars 0 139.54 10465.5 - - - - -
536 Main Bars 0 24.93 822.69 - - - 15023.25 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
537 Raft 1 6 6" C/C 1 62 62 44.31 1772.4 - - - 1159.785 -
538 Raft 2 6 6" C/C 1 79 79 0 - - - 2388.6 -
539 Raft 3 6 6" C/C 1 141 141 0 - - - - -
540 Dist Bars 0 26.395 1636.49 - - - - -
541 Raft A 6 6" C/C 1 75 75 46.59 3680.61 - - - 844.56 -
542 Raft B 6 6" C/C 1 33 33 48.53 6842.73 - - - 818.235 -
543 Raft C 6 6" C/C 1 40 40 0 - - - - -
544 Extra bars on Bottom For Column's 0 133.54 10015.5 - - - 650.4 -
545 Grid 17 / F' 0 23.43 773.19 - - - 626.1 -
546 Main Bars 6 6" C/C 1 36 36 39.81 1592.4 - - - - -
547 Dist Bars 6 6" C/C 1 29 29 0 - - - 530.265 -
548 Grid 17 / J 0 0 - - - 513.15 -
549 Main Bars 6 6" C/C 1 40 40 15.64 563.04 - - - - -
550 Dist Bars 6 6" C/C 1 20 20 18.81 545.49 - - - 476.325 -
551 Grid 17 / K 0 0 - - - 466.5 -
552 Main Bars 6 6" C/C 1 29 29 10.84 433.6 - - - - -
553 Dist Bars 6 6" C/C 1 22 22 20.87 417.4 - - - 349.2 -
554 Grid 17 / L 0 0 - - - 327.42 -
555 Main Bars 6 6" C/C 1 29 29 12.19 353.51 - - - - -
556 Dist Bars 6 6" C/C 1 20 20 15.55 342.1 - - - 337.68 -
557 Grid 17 / M 0 0 - - - 327.42 -
558 Main Bars 6 6" C/C 1 24 24 10.95 317.55 - - - - -
559 Dist Bars 6 6" C/C 1 17 17 15.55 311 - - - 494.4375 -
560 Grid 17 / N 0 0 - - - 486 -
561 Main Bars 6 6" C/C 1 24 24 9.7 232.8 - - - - -
562 Dist Bars 6 6" C/C 1 17 17 12.84 218.28 - - - 768.75 -
563 Grid 17-18 / G' 0 0 - - - 750.03 -
564 Main Bars 6 6" C/C 1 25 25 9.38 225.12 - - - - -
565 Dist Bars 6 6" C/C 1 24 24 12.84 218.28 - - - 576.96 -
566 Grid 17-18 /J 0 0 - - - 566.28 -
567 Main Bars 6 6" C/C 1 41 41 13.185 329.625 - - - - -
568 Dist Bars 6 6" C/C 1 23 23 13.5 324 - - - 470.61 -
569 Grid 17-18 /J' 0 0 - - - 450.765 -
570 Main Bars 6 6" C/C 1 32 32 12.5 512.5 - - - - -
571 Dist Bars 6 6" C/C 1 22 22 21.74 500.02 - - - 470.61 -
572 Grid 17-18 / K' 0 0 - - - 450.765 -
573 Main Bars 6 6" C/C 1 27 27 12.02 384.64 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
574 Dist Bars 6 6" C/C 1 21 21 17.16 377.52 - - - 576.96 -
575 Grid 17-18 / L' 0 0 - - - 566.28 -
576 Main Bars 6 6" C/C 1 27 27 11.62 313.74 - - - - -
577 Dist Bars 6 6" C/C 1 21 21 14.31 300.51 - - - - -
578 Grid 17-18 / M' 0 0 - - - 879.27 -
579 Main Bars 6 6" C/C 1 32 32 11.62 313.74 - - - 825 -
580 Dist Bars 6 6" C/C 1 22 22 14.31 300.51 - - - - -
581 Extra bars For Centers 0 0 - - - 307.5 -
582 Grid 16-17 / F-J 0 12.02 384.64 - - - 298.62 -
583 Main Bars 6 6" C/C 1 53 53 17.16 377.52 - - - - -
584 Dist Bars 6 6" C/C 1 20 20 0 - - - 286.2 -
585 Grid 16-17 / J-K 0 0 - - - 282.03 -
586 Main Bars 6 6" C/C 1 20 20 11.06 586.18 - - - - -
587 Dist Bars 6 6" C/C 1 18 18 27.5 550 - - - 233.1 -
588 Grid 16-17 / K-L 0 0 - - - 232.26 -
589 Main Bars 6 6" C/C 1 20 20 10.25 205 - - - - -
590 Dist Bars 6 6" C/C 1 17 17 11.06 199.08 - - - 233.1 -
591 Grid 16-17 / L-M 0 0 - - - 232.26 -
592 Main Bars 6 6" C/C 1 20 20 9.54 190.8 - - - - -
593 Dist Bars 6 6" C/C 1 14 14 11.06 188.02 - - - 1057.5 -
594 Grid 16-17 / M-N 0 0 - - - 1034.88 -
595 Main Bars 6 6" C/C 1 20 20 7.77 155.4 - - - - -
596 Dist Bars 6 6" C/C 1 14 14 11.06 154.84 - - - 1315.71 -
597 Grid 17-18 / G-J 0 0 - - - 1275 -
598 Main Bars 6 6" C/C 1 47 47 7.77 155.4 - - - - -
599 Dist Bars 6 6" C/C 1 28 28 11.06 154.84 - - - - -
600 Grid 17-18 / J-N 0 0 - - - - 2403
601 Main Bars 6 6" C/C 1 66 66 15 705 - - - - -
602 Dist Bars 6 6" C/C 1 25 25 24.64 689.92 - - - - -
603 BASEMENT Column's Schedule up to Center 0 0 - - - - -
604 C1 0 13.29 877.14 - - - - -
605 Main Bars 8 3 24 72 34 850 - - - - 4672.5
606 Stirrups 3 6" C/C 3 15 45 0 - - - - -
607 Stirrups 3 6" C/C 3 15 45 0 - - - - -
608 Stirrups 3 6" C/C 3 15 45 12.5 900 - - - - -
609 C2 0 7.5 337.5 126.5625 - - - -
610 Main Bars 8 7 20 140 5.33 239.85 89.94375 - - - 12415.5

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
611 Stirrups 3 6" C/C 7 15 105 5.33 239.85 89.94375 - - - -
612 Stirrups 3 6" C/C 7 15 105 0 - - - - -
613 Stirrups 3 6" C/C 7 15 105 12.5 1750 - - - - -
614 C3 0 7.5 787.5 295.3125 - - - -
615 Main Bars 8 31 12 372 5.75 603.75 226.40625 - - - 8811
616 Stirrups 3 6" C/C 31 15 465 5.75 603.75 226.40625 - - - -
617 Stirrups 3 6" C/C 31 15 465 0 - - - - -
618 Stirrups 3 6" C/C 31 15 465 12.5 4650 - - - 1512 -
619 C6 0 7.5 3487.5 1307.8125 - - - -
620 Main Bars 8 11 24 264 5.75 2673.75 1002.65625 - - - -
621 Stirrups 3 4" C/C 11 30 330 5.75 2673.75 1002.65625 - - 1728 -
622 C7 0 0 - - - - -
623 Main Bars 6 7 12 84 12.5 3300 - - - - -
624 Stirrups 3 4" C/C 7 30 210 7.56 2494.8 935.55 - - - -
625 C9 0 0 - - - - 3484.35
626 Main Bars 6 12 8 96 12 1008 - - - - -
627 Stirrups 3 6" C/C 12 15 180 4.42 928.2 348.075 - - - -
Basement Column's Up to Ground
628 Floor Center 0 0 - - - - -
629 C1 0 12 1152 - - - - -
630 Main Bars 8 3 24 72 5.5 990 371.25 - - - 6649.902
631 Stirrups 3 4",6" C/C 3 34 102 0 - - - - -
632 Stirrups 3 4",6" C/C 3 34 102 0 - - - - -
633 Stirrups 3 4",6" C/C 3 34 102 18.125 1305 - - - - -
634 C2 0 7.5 765 286.875 - - - -
635 Main Bars 8 7 20 140 5.33 543.66 203.8725 - - - 17669.7396
636 Stirrups 3 4",6" C/C 7 34 238 5.33 543.66 203.8725 - - - -
637 Stirrups 3 4",6" C/C 7 34 238 0 - - - - -
638 Stirrups 3 4",6" C/C 7 34 238 17.79 2490.6 - - - - -
639 C3 0 7.5 1785 669.375 - - - -
640 Main Bars 8 31 12 372 5.75 1368.5 513.1875 - - - 12539.8152
641 Stirrups 3 4",6" C/C 31 34 1054 5.75 1368.5 513.1875 - - - -
642 Stirrups 3 4",6" C/C 31 34 1054 0 - - - - -
643 Stirrups 3 4",6" C/C 31 34 1054 17.79 6617.88 - - - 2115.54 -
644 C6 0 7.5 7905 2964.375 - - - -
645 Main Bars 8 11 24 264 5.75 6060.5 2272.6875 - - - -
646 Stirrups 3 4" C/C 11 38 418 5.75 6060.5 2272.6875 - - 2417.76 -
647 C7 0 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
648 Main Bars 6 7 12 84 17.79 4696.56 - - - - -
649 Stirrups 3 4" C/C 7 38 266 7.56 3160.08 1185.03 - - - -
650 C9 0 0 - - - - -
651 Main Bars 6 12 8 96 16.79 1410.36 - - - - -
652 Stirrups 3 6" C/C 12 25 300 4.42 1175.72 440.895 - - - -
653 R.C.C Wall 0 0 - - - - -
654 Grid 11 / F-N 0 16.79 1611.84 - - - - -
655 Main Bars 4 9" C/C 2 156 312 5.5 1650 618.75 - - - -
656 Dist Bars 3 9" C/C 2 20 40 0 - - - - -
657 Grid 12 /B- F 0 0 - - - - -
658 Main Bars 4 9" C/C 2 65 130 16.48 5141.76 - 3429.55392 - - -
659 Dist Bars 3 9" C/C 2 20 40 141.42 5656.8 2121.3 - - - -
660 Grid 14 /B1-D 0 0 - - - - -
661 Main Bars 4 9" C/C 2 48 96 16.48 2142.4 - 1428.9808 - - -
662 Dist Bars 3 9" C/C 2 20 40 60.54 2421.6 908.1 - - - -
663 Grid (B1 - B1, 13-14a) 0 0 - - - - -
664 Main Bars 4 9" C/C 2 48 96 16.48 1582.08 - 1055.24736 - - -
665 Dist Bars 3 9" C/C 2 20 40 37.31 1492.4 559.65 - - - -
666 Grid 15-16 /D 0 0 - - - - -
667 Main Bars 4 9" C/C 2 31 62 16.48 1582.08 - 1055.24736 - - -
668 Dist Bars 3 9" C/C 2 20 40 35.17 1406.8 527.55 - - - -
669 Grid D-N1 /16 0 0 - - - - -
670 Main Bars 4 9" C/C 2 176 352 16.48 1021.76 - 681.51392 - - -
671 Dist Bars 3 9" C/C 2 20 40 24.625 985 369.375 - - - -
672 Grid F /11 - 12 0 0 - - - - -
673 Main Bars 4 9" C/C 2 25 50 16.48 5800.96 - 3869.24032 - - -
674 Dist Bars 3 9" C/C 2 20 40 162.54 6501.6 2438.1 - - - -
675 Grid N /11 - 12 0 0 - - - - -
676 Main Bars 4 9" C/C 2 28 56 16.48 824 - 549.608 - - -
677 Dist Bars 3 9" C/C 2 20 40 23.625 945 354.375 - - - -
678 Grid N1 /12 - 16 0 0 - - - - -
679 Main Bars 4 9" C/C 2 57 114 16.48 922.88 - 615.56096 - - -
680 Dist Bars 3 9" C/C 2 20 40 21.875 875 328.125 - - - -
681 Grid N-N1 /12 0 0 - - - - 6654.708
682 Main Bars 4 9" C/C 2 13 26 16.48 1878.72 - 1253.10624 - - -
683 Dist Bars 3 9" C/C 2 20 40 46.375 1855 695.625 - - - -
684 OPD & PORCH Column's Schedule Bed Level = 87.65 0 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
685 C2 0 16.48 428.48 - 285.79616 - - -
686 Main Bars 8 6 20 120 10.75 430 161.25 - - - 665.4708
687 Stirrups 3 4"&6" C/C 6 33 198 0 - - - - -
688 Stirrups 3 4"&6" C/C 6 33 198 0 - - - - -
689 Stirrups 3 4"&6" C/C 6 33 198 20.77 2492.4 - - - - -
690 C3 0 7.5 1485 556.875 - - - -
691 Main Bars 8 1 12 12 5.75 1138.5 426.9375 - - - 1386.3975
692 Stirrups 3 6" C/C 1 31 31 5.75 1138.5 426.9375 - - - -
693 Stirrups 3 4"&6" C/C 1 31 31 0 - - - - -
694 Stirrups 3 4"&6" C/C 1 31 31 20.77 249.24 - - - - 1330.9416
695 C5 0 7.5 232.5 87.1875 - - - -
696 Main Bars 8 1 25 25 5.75 178.25 66.84375 - - - -
697 Stirrups 3 4" C/C 1 49 49 5.75 178.25 66.84375 - - 2243.16 -
698 C6 0 0 - - - - -
699 Main Bars 8 1 24 24 20.77 519.25 - - - - -
700 Stirrups 3 6" C/C 1 33 33 9.14 447.86 167.9475 - - - -
701 C7 0 0 - - - - -
702 Main Bars 6 6 12 72 20.77 498.48 - - - 456.75 -
703 Stirrups 3 6" C/C 6 33 198 7.56 249.48 93.555 - - - -
704 Raft Schedule of Ground Floor 0 0 - - - 983.01 -
705 Bottom Bars 0 20.77 1495.44 - - - - -
706 Grid D to G (1-2) 0 4.42 875.16 328.185 - - 4856.685 -
707 Dist Bars 6 6" C/C 1 7 7 0 - - - - -
708 Grid I to N (1'-2) 0 0 - - - 6048 -
709 Dist Bars 6 6" C/C 1 7 7 0 - - - 30473.625 -
710 Grid D to N ( 1-2 ) 0 43.5 304.5 - - - 7129.6875 -
711 Dist Bars 6 6" C/C 1 19 19 0 - - - 40060.8 -
712 Grid A to N ( 2 -7) 0 93.62 655.34 - - - - -
713 Main Bars 6 6" C/C 1 63 63 0 - - - - -
714 Main Bars 6 6" C/C 1 266 266 170.41 3237.79 - - - 456.75 -
715 Main Bars 6 6" C/C 1 65 65 0 - - - - -
716 Dist Bars 6 6" C/C 1 120 120 64 4032 - - - 983.01 -
717 Top Bars 0 76.375 20315.75 - - - - -
718 Grid D to G (1-2) 0 73.125 4753.125 - - - 4856.685 -
719 Dist Bars 6 6" C/C 1 7 7 222.56 26707.2 - - - - -
720 Grid I to N (1'-2) 0 0 - - - 6048 -
721 Dist Bars 6 6" C/C 1 7 7 0 - - - 30473.625 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
722 Grid D to N ( 1-2 ) 0 43.5 304.5 - - - 7129.6875 -
723 Dist Bars 6 6" C/C 1 19 19 0 - - - 40060.8 -
724 Grid A to N ( 1 -7) 0 93.62 655.34 - - - - -
725 Main Bars 6 6" C/C 1 63 63 0 - - - - -
726 Main Bars 6 6" C/C 1 266 266 170.41 3237.79 - - - 200.61 -
727 Main Bars 6 6" C/C 1 65 65 0 - - - 212.16 -
728 Dist Bars 6 6" C/C 1 120 120 64 4032 - - - - -
729 Extra Bars in Bottom for Column's 0 76.375 20315.75 - - - 291.72 -
730 Extra bars on Grid 1-D 0 73.125 4753.125 - - - 279.72 -
731 Main Bars 6 6" C/C 1 18 18 222.56 26707.2 - - - - -
732 Dist Bars 6 6" C/C 1 16 16 0 - - - 318.24 -
733 Extra bars on Grid 1-E 0 0 - - - 322.11 -
734 Main Bars 6 6" C/C 1 22 22 7.43 133.74 - - - - -
735 Dist Bars 6 6" C/C 1 18 18 8.84 141.44 - - - 295.245 -
736 Extra bars on Grid 1-G 0 0 - - - 307.92 -
737 Main Bars 6 6" C/C 1 24 24 8.84 194.48 - - - - -
738 Dist Bars 6 6" C/C 1 18 18 10.36 186.48 - - - 235.125 -
739 Extra bars on Grid 1'-H 0 0 - - - 238.68 -
740 Main Bars 6 6" C/C 1 27 27 8.84 212.16 - - - - -
741 Dist Bars 6 6" C/C 1 16 16 11.93 214.74 - - - 306.1875 -
742 Extra bars on Grid 1- I 0 0 - - - 310.935 -
743 Main Bars 6 6" C/C 1 19 19 7.29 196.83 - - - - -
744 Dist Bars 6 6" C/C 1 18 18 12.83 205.28 - - - 357.9375 -
745 Extra bars on Grid 1- J 0 0 - - - 360.03 -
746 Main Bars 6 6" C/C 1 23 23 8.25 156.75 - - - - -
747 Dist Bars 6 6" C/C 1 19 19 8.84 159.12 - - - 315.1575 -
748 Extra bars on Grid 1- K 0 0 - - - 310.935 -
749 Main Bars 6 6" C/C 1 23 23 8.875 204.125 - - - - -
750 Dist Bars 6 6" C/C 1 22 22 10.91 207.29 - - - 285.315 -
751 Extra bars on Grid 1- L 0 0 - - - 294.57 -
752 Main Bars 6 6" C/C 1 23 23 10.375 238.625 - - - - -
753 Dist Bars 6 6" C/C 1 19 19 10.91 240.02 - - - 306.705 -
754 Extra bars on Grid 1- M 0 0 - - - 310.935 -
755 Main Bars 6 6" C/C 1 23 23 9.135 210.105 - - - - -
756 Dist Bars 6 6" C/C 1 18 18 10.91 207.29 - - - 246.96 -
757 Extra bars on Grid 1- N 0 0 - - - 260.355 -
758 Main Bars 6 6" C/C 1 23 23 8.27 190.21 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
759 Dist Bars 6 6" C/C 1 19 19 10.91 196.38 - - - 264.915 -
760 Extra bars on Grid 2-A 0 0 - - - 275.67 -
761 Main Bars 6 6" C/C 1 21 21 8.89 204.47 - - - - -
762 Dist Bars 6 6" C/C 1 17 17 10.91 207.29 - - - 398.19 -
763 Extra bars on Grid 2-B 0 0 - - - 389.8125 -
764 Main Bars 6 6" C/C 1 21 21 7.84 164.64 - - - - -
765 Dist Bars 6 6" C/C 1 18 18 10.21 173.57 - - - 394.11 -
766 Extra bars on Grid 2-C 0 0 - - - 391.875 -
767 Main Bars 6 6" C/C 1 26 26 8.41 176.61 - - - - -
768 Dist Bars 6 6" C/C 1 21 21 10.21 183.78 - - - 339.75 -
769 Extra bars on Grid 2-E 0 0 - - - 344.565 -
770 Main Bars 6 6" C/C 1 29 29 10.21 265.46 - - - - -
771 Dist Bars 6 6" C/C 1 19 19 12.375 259.875 - - - 284.625 -
772 Extra bars on Grid 2-G 0 0 - - - 276.42 -
773 Main Bars 6 6" C/C 1 25 25 9.06 262.74 - - - - -
774 Dist Bars 6 6" C/C 1 19 19 13.75 261.25 - - - 253.935 -
775 Extra bars on Grid 2-H 0 0 - - - 258.21 -
776 Main Bars 6 6" C/C 1 23 23 9.06 226.5 - - - - -
777 Dist Bars 6 6" C/C 1 17 17 12.09 229.71 - - - 298.98 -
778 Extra bars on Grid 2-I 0 0 - - - 306.375 -
779 Main Bars 6 6" C/C 1 19 19 8.25 189.75 - - - - -
780 Dist Bars 6 6" C/C 1 19 19 10.84 184.28 - - - 298.98 -
781 Extra bars on Grid 3-J 0 0 - - - 295.6875 -
782 Main Bars 6 6" C/C 1 22 22 8.91 169.29 - - - - -
783 Dist Bars 6 6" C/C 1 19 19 9.06 172.14 - - - 258.21 -
784 Extra bars on Grid 3-K 0 0 - - - 260.3475 -
785 Main Bars 6 6" C/C 1 22 22 9.06 199.32 - - - - -
786 Dist Bars 6 6" C/C 1 19 19 10.75 204.25 - - - 235.695 -
787 Extra bars on Grid 3-L 0 0 - - - 246.645 -
788 Main Bars 6 6" C/C 1 19 19 9.06 199.32 - - - - -
789 Dist Bars 6 6" C/C 1 19 19 10.375 197.125 - - - 253.365 -
790 Extra bars on Grid 3-M 0 0 - - - 246.645 -
791 Main Bars 6 6" C/C 1 19 19 9.06 172.14 - - - - -
792 Dist Bars 6 6" C/C 1 18 18 9.135 173.565 - - - 223.44 -
793 Extra bars on Grid 3-N 0 0 - - - 228.735 -
794 Main Bars 6 6" C/C 1 19 19 8.27 157.13 - - - - -
795 Dist Bars 6 6" C/C 1 18 18 9.135 164.43 - - - 239.685 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
796 Extra bars on Grid 4-A 0 0 - - - 242.19 -
797 Main Bars 6 6" C/C 1 19 19 8.89 168.91 - - - - -
798 Dist Bars 6 6" C/C 1 17 17 9.135 164.43 - - - 349.83 -
799 Extra bars on Grid 4-B 0 0 - - - 352.6875 -
800 Main Bars 6 6" C/C 1 19 19 7.84 148.96 - - - - -
801 Dist Bars 6 6" C/C 1 18 18 8.97 152.49 - - - 376.74 -
802 Extra bars on Grid 4-C 0 0 - - - 391.875 -
803 Main Bars 6 6" C/C 1 26 26 8.41 159.79 - - - - -
804 Dist Bars 6 6" C/C 1 19 19 8.97 161.46 - - - 336.375 -
805 Extra bars on Grid 4-E 0 0 - - - 345.135 -
806 Main Bars 6 6" C/C 1 28 28 8.97 233.22 - - - - -
807 Dist Bars 6 6" C/C 1 19 19 12.375 235.125 - - - 309.465 -
808 Extra bars on Grid 4-G 0 0 - - - 308.655 -
809 Main Bars 6 6" C/C 1 25 25 8.97 251.16 - - - - -
810 Dist Bars 6 6" C/C 1 19 19 13.75 261.25 - - - 255.645 -
811 Extra bars on Grid 4-H 0 0 - - - 253.935 -
812 Main Bars 6 6" C/C 1 23 23 8.97 224.25 - - - - -
813 Dist Bars 6 6" C/C 1 19 19 12.11 230.09 - - - 240.54 -
814 Extra bars on Grid 4-I 0 0 - - - 239.625 -
815 Main Bars 6 6" C/C 1 19 19 8.97 206.31 - - - - -
816 Dist Bars 6 6" C/C 1 19 19 10.83 205.77 - - - 278.52 -
817 Extra bars on Grid 4-J 0 0 - - - 280.125 -
818 Main Bars 6 6" C/C 1 19 19 8.97 170.43 - - - - -
819 Dist Bars 6 6" C/C 1 18 18 8.91 169.29 - - - 240.54 -
820 Extra bars on Grid 4-K 0 0 - - - 246.78 -
821 Main Bars 6 6" C/C 1 22 22 8.44 160.36 - - - - -
822 Dist Bars 6 6" C/C 1 18 18 8.875 159.75 - - - 227.88 -
823 Extra bars on Grid 4-L 0 0 - - - 223.29 -
824 Main Bars 6 6" C/C 1 19 19 8.44 185.68 - - - - -
825 Dist Bars 6 6" C/C 1 18 18 10.375 186.75 - - - 240.54 -
826 Extra bars on Grid 4-M 0 0 - - - 240.03 -
827 Main Bars 6 6" C/C 1 18 18 8.44 160.36 - - - - -
828 Dist Bars 6 6" C/C 1 18 18 9.14 164.52 - - - 223.44 -
829 Extra bars on Grid 4-N 0 0 - - - 230.265 -
830 Main Bars 6 6" C/C 1 19 19 8.44 151.92 - - - - -
831 Dist Bars 6 6" C/C 1 18 18 8.27 148.86 - - - 251.085 -
832 Extra bars on Grid 5-A 0 0 - - - 257.355 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
833 Main Bars 6 6" C/C 1 19 19 8.44 160.36 - - - - -
834 Dist Bars 6 6" C/C 1 17 17 8.89 160.02 - - - 352.17 -
835 Extra bars on Grid 5-B 0 0 - - - 352.6875 -
836 Main Bars 6 6" C/C 1 19 19 7.84 148.96 - - - - -
837 Dist Bars 6 6" C/C 1 19 19 9.03 153.51 - - - 392.805 -
838 Extra bars on Grid 5-C 0 0 - - - 391.875 -
839 Main Bars 6 6" C/C 1 26 26 8.81 167.39 - - - - -
840 Dist Bars 6 6" C/C 1 19 19 9.03 171.57 - - - 338.625 -
841 Extra bars on Grid 5-E 0 0 - - - 345.135 -
842 Main Bars 6 6" C/C 1 29 29 9.03 234.78 - - - - -
843 Dist Bars 6 6" C/C 1 19 19 12.375 235.125 - - - 311.535 -
844 Extra bars on Grid 5-G 0 0 - - - 308.94 -
845 Main Bars 6 6" C/C 1 25 25 9.03 261.87 - - - - -
846 Dist Bars 6 6" C/C 1 19 19 13.75 261.25 - - - 254.22 -
847 Extra bars on Grid 5-H 0 0 - - - 257.355 -
848 Main Bars 6 6" C/C 1 23 23 9.03 225.75 - - - - -
849 Dist Bars 6 6" C/C 1 19 19 12.11 230.09 - - - 252.9375 -
850 Extra bars on Grid 5-I 0 0 - - - 257.355 -
851 Main Bars 6 6" C/C 1 19 19 9.03 207.69 - - - - -
852 Dist Bars 6 6" C/C 1 19 19 10.84 205.96 - - - 297.99 -
853 Extra bars on Grid 6-J 0 0 - - - 295.6875 -
854 Main Bars 6 6" C/C 1 19 19 8.92 169.48 - - - - -
855 Dist Bars 6 6" C/C 1 19 19 9.03 171.57 - - - 257.355 -
856 Extra bars on Grid 6-K 0 0 - - - 260.49 -
857 Main Bars 6 6" C/C 1 22 22 8.875 168.625 - - - - -
858 Dist Bars 6 6" C/C 1 19 19 9.03 171.57 - - - 235.695 -
859 Extra bars on Grid 6-L 0 0 - - - 243.81 -
860 Main Bars 6 6" C/C 1 19 19 9.03 198.66 - - - - -
861 Dist Bars 6 6" C/C 1 19 19 10.375 197.125 - - - 253.365 -
862 Extra bars on Grid 6-M 0 0 - - - 257.355 -
863 Main Bars 6 6" C/C 1 19 19 9.03 171.57 - - - - -
864 Dist Bars 6 6" C/C 1 18 18 9.14 173.66 - - - 261.03 -
865 Extra bars on Grid 6-N 0 0 - - - 262.14 -
866 Main Bars 6 6" C/C 1 19 19 8.27 157.13 - - - - -
867 Dist Bars 6 6" C/C 1 19 19 9.03 162.54 - - - 277.53 -
868 Extra bars on Grid 7-A 0 0 - - - 277.56 -
869 Main Bars 6 6" C/C 1 22 22 8.89 168.91 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
870 Dist Bars 6 6" C/C 1 17 17 9.03 171.57 - - - 400.92 -
871 Extra bars on Grid 7-B 0 0 - - - 408.375 -
872 Main Bars 6 6" C/C 1 22 22 7.91 174.02 - - - - -
873 Dist Bars 6 6" C/C 1 18 18 10.28 174.76 - - - 447.18 -
874 Extra bars on Grid 7-C 0 0 - - - 453.75 -
875 Main Bars 6 6" C/C 1 26 26 8.41 185.02 - - - - -
876 Dist Bars 6 6" C/C 1 22 22 10.28 185.04 - - - 385.5 -
877 Extra bars on Grid 7-E 0 0 - - - 399.63 -
878 Main Bars 6 6" C/C 1 29 29 10.28 267.28 - - - - -
879 Dist Bars 6 6" C/C 1 22 22 12.375 272.25 - - - 354.66 -
880 Extra bars on Grid 7-G 0 0 - - - 357.72 -
881 Main Bars 6 6" C/C 1 25 25 10.28 298.12 - - - - -
882 Dist Bars 6 6" C/C 1 22 22 13.75 302.5 - - - 294.36 -
883 Extra bars on Grid 7-H 0 0 - - - 292.98 -
884 Main Bars 6 6" C/C 1 23 23 10.28 257 - - - - -
885 Dist Bars 6 6" C/C 1 22 22 12.11 266.42 - - - 235.125 -
886 Extra bars on Grid 7-I 0 0 - - - 239.625 -
887 Main Bars 6 6" C/C 1 22 22 10.28 236.44 - - - - -
888 Dist Bars 6 6" C/C 1 19 19 10.84 238.48 - - - 272.25 -
889 Extra bars on Grid 7-J 0 0 - - - 280.125 -
890 Main Bars 6 6" C/C 1 19 19 8.92 196.24 - - - - -
891 Dist Bars 6 6" C/C 1 18 18 10.28 195.32 - - - 235.125 -
892 Extra bars on Grid 7-K 0 0 - - - 246.78 -
893 Main Bars 6 6" C/C 1 22 22 8.25 156.75 - - - - -
894 Dist Bars 6 6" C/C 1 18 18 8.875 159.75 - - - 222.75 -
895 Extra bars on Grid 7-L 0 0 - - - 223.29 -
896 Main Bars 6 6" C/C 1 19 19 8.25 181.5 - - - - -
897 Dist Bars 6 6" C/C 1 18 18 10.375 186.75 - - - 235.125 -
898 Extra bars on Grid 7-M 0 0 - - - 240.03 -
899 Main Bars 6 6" C/C 1 18 18 8.25 156.75 - - - - -
900 Dist Bars 6 6" C/C 1 18 18 9.14 164.52 - - - 39.1875 -
901 Extra bars on Grid 7-N 0 0 - - - 46.71 -
902 Main Bars 6 6" C/C 1 19 19 8.25 148.5 - - - - -
903 Dist Bars 6 6" C/C 1 18 18 8.27 148.86 - - - 186.84 -
904 Extra bars on Grid 1-2/D-E (Top) 0 0 - - - 187.6875 -
905 Main Bars 6 6" C/C 1 11 11 8.25 156.75 - - - - -
906 Dist Bars 6 6" C/C 1 6 6 8.89 160.02 - - - 101.46 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
907 Extra bars on Grid 1-2/E-G 0 0 - - - 106.08 -
908 Main Bars 6 6" C/C 1 24 24 2.375 26.125 - - - - -
909 Dist Bars 6 6" C/C 1 11 11 5.19 31.14 - - - 101.46 -
910 Extra bars on Grid 1'-2/G-H 0 0 - - - 106.08 -
911 Main Bars 6 6" C/C 1 19 19 5.19 124.56 - - - - -
912 Dist Bars 6 6" C/C 1 8 8 11.375 125.125 - - - 479.415 -
913 Extra bars on Grid 1'-2/H-I 0 0 - - - 486.75 -
914 Main Bars 6 6" C/C 1 19 19 3.56 67.64 - - - - -
915 Dist Bars 6 6" C/C 1 8 8 8.84 70.72 - - - 264 -
916 Extra bars on Grid 1-3/I-K 0 0 - - - 262.905 -
917 Main Bars 6 6" C/C 1 31 31 3.56 67.64 - - - - -
918 Dist Bars 6 6" C/C 1 22 22 8.84 70.72 - - - 206.91 -
919 Extra bars on Grid 1-3/K-L 0 0 - - - 216.51 -
920 Main Bars 6 6" C/C 1 22 22 10.31 319.61 - - - - -
921 Dist Bars 6 6" C/C 1 17 17 14.75 324.5 - - - 206.91 -
922 Extra bars on Grid 1-3/L-M 0 0 - - - 216.51 -
923 Main Bars 6 6" C/C 1 22 22 8 176 - - - - -
924 Dist Bars 6 6" C/C 1 14 14 10.31 175.27 - - - 119.415 -
925 Extra bars on Grid 1-2/M-N 0 0 - - - 120.69 -
926 Main Bars 6 6" C/C 1 22 22 6.27 137.94 - - - - -
927 Dist Bars 6 6" C/C 1 14 14 10.31 144.34 - - - 232.875 -
928 Extra bars on Grid 2-4/A-B 0 0 - - - 241.38 -
929 Main Bars 6 6" C/C 1 19 19 6.27 137.94 - - - - -
930 Dist Bars 6 6" C/C 1 9 9 10.31 144.34 - - - 335.25 -
931 Extra bars on Grid 2-4/B-C 0 0 - - - 327.375 -
932 Main Bars 6 6" C/C 1 18 18 4.19 79.61 - - - - -
933 Dist Bars 6 6" C/C 1 18 18 8.94 80.46 - - - 321.84 -
934 Extra bars on Grid 2-4/C-E 0 0 - - - 307.125 -
935 Main Bars 6 6" C/C 1 25 25 8.625 155.25 - - - - -
936 Dist Bars 6 6" C/C 1 18 18 8.94 160.92 - - - 241.38 -
937 Extra bars on Grid 2-4/E-G 0 0 - - - 238.68 -
938 Main Bars 6 6" C/C 1 24 24 8.94 223.5 - - - - -
939 Dist Bars 6 6" C/C 1 18 18 12.125 218.25 - - - 415.71 -
940 Extra bars on Grid 2-4/G-H 0 0 - - - 400.68 -
941 Main Bars 6 6" C/C 1 18 18 8.94 214.56 - - - - -
942 Dist Bars 6 6" C/C 1 18 18 11.375 204.75 - - - 108.585 -
943 Extra bars on Grid 2-4/H-J 0 0 - - - 118.125 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
944 Main Bars 6 6" C/C 1 31 31 8.94 160.92 - - - - -
945 Dist Bars 6 6" C/C 1 18 18 8.84 159.12 - - - 97.155 -
946 Extra bars on Grid 3-4/J-K 0 0 - - - 108 -
947 Main Bars 6 6" C/C 1 19 19 8.94 277.14 - - - - -
948 Dist Bars 6 6" C/C 1 9 9 14.84 267.12 - - - 80.01 -
949 Extra bars on Grid 3-4/K-L 0 0 - - - 84.645 -
950 Main Bars 6 6" C/C 1 17 17 3.81 72.39 - - - - -
951 Dist Bars 6 6" C/C 1 9 9 8.75 78.75 - - - 80.01 -
952 Extra bars on Grid 3-4/L-M 0 0 - - - 84.645 -
953 Main Bars 6 6" C/C 1 14 14 3.81 64.77 - - - - -
954 Dist Bars 6 6" C/C 1 9 9 8 72 - - - 69.135 -
955 Extra bars on Grid 3-4/M-N 0 0 - - - 67.5 -
956 Main Bars 6 6" C/C 1 14 14 3.81 53.34 - - - - -
957 Dist Bars 6 6" C/C 1 9 9 6.27 56.43 - - - 135 -
958 Extra bars on Grid 4-5/A-B 0 0 - - - 142.3125 -
959 Main Bars 6 6" C/C 1 11 11 3.81 53.34 - - - - -
960 Dist Bars 6 6" C/C 1 9 9 6.27 56.43 - - - 187.5 -
961 Extra bars on Grid 4-5/B-C 0 0 - - - 200.0625 -
962 Main Bars 6 6" C/C 1 18 18 4.19 46.09 - - - - -
963 Dist Bars 6 6" C/C 1 11 11 5 45 - - - 180 -
964 Extra bars on Grid 4-5/C-E 0 0 - - - 187.6875 -
965 Main Bars 6 6" C/C 1 25 25 5 90 - - - - -
966 Dist Bars 6 6" C/C 1 11 11 8.625 94.875 - - - 142.5 -
967 Extra bars on Grid 4-5/E-G 0 0 - - - 145.86 -
968 Main Bars 6 6" C/C 1 24 24 5 125 - - - - -
969 Dist Bars 6 6" C/C 1 11 11 12.125 133.375 - - - 142.5 -
970 Extra bars on Grid 4-5/G-H 0 0 - - - 145.86 -
971 Main Bars 6 6" C/C 1 19 19 5 120 - - - - -
972 Dist Bars 6 6" C/C 1 11 11 11.375 125.125 - - - 421.29 -
973 Extra bars on Grid 4-5/H-I 0 0 - - - 420.375 -
974 Main Bars 6 6" C/C 1 19 19 5 95 - - - - -
975 Dist Bars 6 6" C/C 1 11 11 8.84 97.24 - - - 228 -
976 Extra bars on Grid 4-6/I-K 0 0 - - - 231.03 -
977 Main Bars 6 6" C/C 1 31 31 5 95 - - - - -
978 Dist Bars 6 6" C/C 1 19 19 8.84 97.24 - - - 178.695 -
979 Extra bars on Grid 4-6/K-L 0 0 - - - 190.26 -
980 Main Bars 6 6" C/C 1 19 19 9.06 280.86 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
981 Dist Bars 6 6" C/C 1 17 17 14.75 280.25 - - - 178.695 -
982 Extra bars on Grid 4-6/L-M 0 0 - - - 190.26 -
983 Main Bars 6 6" C/C 1 19 19 8 152 - - - - -
984 Dist Bars 6 6" C/C 1 14 14 9.06 154.02 - - - 119.415 -
985 Extra bars on Grid 4-6/M-N 0 0 - - - 122.31 -
986 Main Bars 6 6" C/C 1 19 19 6.27 119.13 - - - - -
987 Dist Bars 6 6" C/C 1 14 14 9.06 126.84 - - - 245.8125 -
988 Extra bars on Grid 5-7/A-B 0 0 - - - 244.62 -
989 Main Bars 6 6" C/C 1 19 19 6.27 119.13 - - - - -
990 Dist Bars 6 6" C/C 1 9 9 9.06 126.84 - - - 339.75 -
991 Extra bars on Grid 5-7/B-C 0 0 - - - 345.5625 -
992 Main Bars 6 6" C/C 1 19 19 4.19 79.61 - - - - -
993 Dist Bars 6 6" C/C 1 18 18 9.06 81.54 - - - 326.16 -
994 Extra bars on Grid 5-7/C-E 0 0 - - - 324.1875 -
995 Main Bars 6 6" C/C 1 25 25 8.625 163.875 - - - - -
996 Dist Bars 6 6" C/C 1 19 19 9.06 163.08 - - - 251.94 -
997 Extra bars on Grid 5-7/E-G 0 0 - - - 258.21 -
998 Main Bars 6 6" C/C 1 24 24 9.06 226.5 - - - - -
999 Dist Bars 6 6" C/C 1 19 19 12.125 230.375 - - - 421.29 -
1000 Extra bars on Grid 5-7/G-H 0 0 - - - 422.94 -
1001 Main Bars 6 6" C/C 1 19 19 9.06 217.44 - - - - -
1002 Dist Bars 6 6" C/C 1 19 19 11.375 216.125 - - - 142.5 -
1003 Extra bars on Grid 5-7/H-J 0 0 - - - 144.375 -
1004 Main Bars 6 6" C/C 1 31 31 8.84 167.96 - - - - -
1005 Dist Bars 6 6" C/C 1 19 19 9.06 172.14 - - - 127.5 -
1006 Extra bars on Grid 6-7/J-K 0 0 - - - 132 -
1007 Main Bars 6 6" C/C 1 19 19 9.06 280.86 - - - - -
1008 Dist Bars 6 6" C/C 1 11 11 14.84 281.96 - - - 105 -
1009 Extra bars on Grid 6-7/K-L 0 0 - - - 103.455 -
1010 Main Bars 6 6" C/C 1 17 17 5 95 - - - - -
1011 Dist Bars 6 6" C/C 1 11 11 8.75 96.25 - - - 105 -
1012 Extra bars on Grid 6-7/L-M 0 0 - - - 103.455 -
1013 Main Bars 6 6" C/C 1 14 14 5 85 - - - - -
1014 Dist Bars 6 6" C/C 1 11 11 8 88 - - - - -
1015 Extra bars on Grid 6-7/M-N 0 0 - - - - -
1016 Main Bars 6 6" C/C 1 14 14 5 70 - - - - -
1017 Dist Bars 6 6" C/C 1 11 11 6.27 68.97 - - - 3138.75 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1018 Column's Schedule 0 0 - - - 7010.01 -
1019
Raft Schedule of Ground Floor
0 5 70 - - - - -
Remained Portion
1020 Bottom Bars 0 6.27 68.97 - - - 1091.25 -
1021 Raft 1 ( 7 - 8 / A - G ) 0 0 - - - 0 -
1022 Main Bars 6 6" C/C 1 180 180 0 - - - - -
1023 Dist Bars 6 6" C/C 1 21 21 0 - - - 3592.125 -
1024 Raft 2 ( 7 - 8 / G - I ) 0 0 - - - 0 -
1025 Main Bars 6 6" C/C 1 60 60 11.625 2092.5 - - - - -
1026 Dist Bars 6 6" C/C 1 25 25 222.54 4673.34 - - - 10096.3125 -
1027 Raft 3 ( 7 - 8 / I - N ) 0 0 - - - 8939.625 -
1028 Main Bars 6 6" C/C 1 206 206 12.125 727.5 - - - - -
1029 Dist Bars 6 6" C/C 1 21 21 0 - - - 9834.75 -
1030 Raft 4 ( 8 - 11 / A - G ) 0 0 - - - 8749.44 -
1031 Main Bars 6 6" C/C 1 193 193 11.625 2394.75 - - - - -
1032 Dist Bars 6 6" C/C 1 62 62 0 - - - 5469.75 -
1033 Raft 5 ( 8 - 11 / I - N ) 0 0 - - - 5507.8125 -
1034 Main Bars 6 6" C/C 1 188 188 34.875 6730.875 - - - - -
1035 Dist Bars 6 6" C/C 1 62 62 96.125 5959.75 - - - - -
1036 Raft 6 ( 11 - 12 / A - G ) 0 0 - - - 3138.75 -
1037 Main Bars 6 6" C/C 1 156 156 34.875 6556.5 - - - 7010.01 -
1038 Dist Bars 6 6" C/C 1 47 47 94.08 5832.96 - - - - -
1039 Top Bars 0 0 - - - 1091.25 -
1040 Raft 1 ( 7 - 8 / A - G ) 0 23.375 3646.5 - - - 0 -
1041 Main Bars 6 6" C/C 1 180 180 78.125 3671.875 - - - - -
1042 Dist Bars 6 6" C/C 1 21 21 0 - - - 3592.125 -
1043 Raft 2 ( 7 - 8 / G - I ) 0 0 - - - 0 -
1044 Main Bars 6 6" C/C 1 60 60 11.625 2092.5 - - - - -
1045 Dist Bars 6 6" C/C 1 25 25 222.54 4673.34 - - - 10096.3125 -
1046 Raft 3 ( 7 - 8 / I - N ) 0 0 - - - 8939.625 -
1047 Main Bars 6 6" C/C 1 206 206 12.125 727.5 - - - - -
1048 Dist Bars 6 6" C/C 1 21 21 0 - - - 9834.75 -
1049 Raft 4 ( 8 - 11 / A - G ) 0 0 - - - 8749.44 -
1050 Main Bars 6 6" C/C 1 193 193 11.625 2394.75 - - - - -
1051 Dist Bars 6 6" C/C 1 62 62 0 - - - 5469.75 -
1052 Raft 5 ( 8 - 11 / I - N ) 0 0 - - - 5507.8125 -
1053 Main Bars 6 6" C/C 1 188 188 34.875 6730.875 - - - - -
1054 Dist Bars 6 6" C/C 1 62 62 96.125 5959.75 - - - 219.9375 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1055 Raft 6 ( 11 - 12 / A - G ) 0 0 - - - 211.68 -
1056 Main Bars 6 6" C/C 1 156 156 34.875 6556.5 - - - - -
1057 Dist Bars 6 6" C/C 1 47 47 94.08 5832.96 - - - 232.875 -
1058 Extra bars on Grid 8-A 0 0 - - - 227.07 -
1059 Main Bars 6 6" C/C 1 17 17 23.375 3646.5 - - - - -
1060 Dist Bars 6 6" C/C 1 18 18 78.125 3671.875 - - - 336.375 -
1061 Extra bars on Grid 8-B 0 0 - - - 334.125 -
1062 Main Bars 6 6" C/C 1 18 18 8.625 146.625 - - - - -
1063 Dist Bars 6 6" C/C 1 18 18 7.84 141.12 - - - 375.1875 -
1064 Extra bars on Grid 8-C 0 0 - - - 371.25 -
1065 Main Bars 6 6" C/C 1 26 26 8.625 155.25 - - - - -
1066 Dist Bars 6 6" C/C 1 18 18 8.41 151.38 - - - 323.4375 -
1067 Extra bars on Grid 8-E 0 0 - - - 326.97 -
1068 Main Bars 6 6" C/C 1 29 29 8.625 224.25 - - - - -
1069 Dist Bars 6 6" C/C 1 18 18 12.375 222.75 - - - 297.5625 -
1070 Extra bars on Grid 8-G 0 0 - - - 292.68 -
1071 Main Bars 6 6" C/C 1 25 25 8.625 250.125 - - - - -
1072 Dist Bars 6 6" C/C 1 18 18 13.75 247.5 - - - 183.54 -
1073 Extra bars on Grid 8-H 0 0 - - - 187.32 -
1074 Main Bars 6 6" C/C 1 23 23 8.625 215.625 - - - - -
1075 Dist Bars 6 6" C/C 1 18 18 12.11 217.98 - - - 242.19 -
1076 Extra bars on Grid 8-I 0 0 - - - 235.125 -
1077 Main Bars 6 6" C/C 1 19 19 8.625 198.375 - - - - -
1078 Dist Bars 6 6" C/C 1 14 14 10.84 195.12 - - - 319.5 -
1079 Extra bars on Grid 9-I 0 0 - - - 331.3125 -
1080 Main Bars 6 6" C/C 1 18 18 6.44 122.36 - - - - -
1081 Dist Bars 6 6" C/C 1 19 19 8.92 124.88 - - - 373.5 -
1082 Extra bars on Grid 9-J 0 0 - - - 383.625 -
1083 Main Bars 6 6" C/C 1 24 24 8.97 161.46 - - - - -
1084 Dist Bars 6 6" C/C 1 19 19 8.25 156.75 - - - 329.04 -
1085 Extra bars on Grid 9-K 0 0 - - - 331.3125 -
1086 Main Bars 6 6" C/C 1 24 24 8.875 213 - - - - -
1087 Dist Bars 6 6" C/C 1 22 22 11.625 220.875 - - - 297.72 -
1088 Extra bars on Grid 9-L 0 0 - - - 313.875 -
1089 Main Bars 6 6" C/C 1 24 24 10.375 249 - - - - -
1090 Dist Bars 6 6" C/C 1 19 19 11.625 255.75 - - - 320.04 -
1091 Extra bars on Grid 9-M 0 0 - - - 331.3125 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1092 Main Bars 6 6" C/C 1 24 24 9.14 219.36 - - - - -
1093 Dist Bars 6 6" C/C 1 18 18 11.625 220.875 - - - 223.44 -
1094 Extra bars on Grid 9-N 0 0 - - - 228.735 -
1095 Main Bars 6 6" C/C 1 24 24 8.27 198.48 - - - - -
1096 Dist Bars 6 6" C/C 1 19 19 11.625 209.25 - - - 255.645 -
1097 Extra bars on Grid 10-A 0 0 - - - 239.685 -
1098 Main Bars 6 6" C/C 1 19 19 8.89 213.36 - - - - -
1099 Dist Bars 6 6" C/C 1 17 17 11.625 220.875 - - - 349.83 -
1100 Extra bars on Grid 10-B 0 0 - - - 352.6875 -
1101 Main Bars 6 6" C/C 1 19 19 7.84 148.96 - - - - -
1102 Dist Bars 6 6" C/C 1 19 19 8.97 152.49 - - - 390.195 -
1103 Extra bars on Grid 10-C 0 0 - - - 391.875 -
1104 Main Bars 6 6" C/C 1 26 26 8.97 170.43 - - - - -
1105 Dist Bars 6 6" C/C 1 19 19 8.41 159.79 - - - 322.92 -
1106 Extra bars on Grid 10-E 0 0 - - - 326.04 -
1107 Main Bars 6 6" C/C 1 29 29 8.97 233.22 - - - - -
1108 Dist Bars 6 6" C/C 1 19 19 12.375 235.125 - - - 223.44 -
1109 Extra bars on Grid 10-G 0 0 - - - 228.735 -
1110 Main Bars 6 6" C/C 1 24 24 8.97 260.13 - - - - -
1111 Dist Bars 6 6" C/C 1 19 19 13.75 261.25 - - - 255.645 -
1112 Extra bars on Grid 11-A 0 0 - - - 239.685 -
1113 Main Bars 6 6" C/C 1 19 19 8.97 215.28 - - - - -
1114 Dist Bars 6 6" C/C 1 17 17 11.44 217.36 - - - 349.83 -
1115 Extra bars on Grid 11-B 0 0 - - - 352.6875 -
1116 Main Bars 6 6" C/C 1 19 19 7.84 148.96 - - - - -
1117 Dist Bars 6 6" C/C 1 19 19 8.97 152.49 - - - 390.195 -
1118 Extra bars on Grid 11-C 0 0 - - - 391.875 -
1119 Main Bars 6 6" C/C 1 26 26 8.97 170.43 - - - - -
1120 Dist Bars 6 6" C/C 1 19 19 8.41 159.79 - - - - -
1121 Extra bars on Grid 11-E 0 0 - - - 62.85 -
1122 Main Bars 6 6" C/C 1 29 29 8.97 233.22 - - - 58.185 -
1123 Dist Bars 6 6" C/C 1 19 19 12.375 235.125 - - - - -
1124 Extra bars on Centers 0 0 - - - 116.37 -
1125 Extra bars on Grid 7-8/A-B 0 8.97 260.13 - - - 129.375 -
1126 Main Bars 6 6" C/C 1 10 10 13.75 261.25 - - - - -
1127 Dist Bars 6 6" C/C 1 9 9 0 - - - 161.625 -
1128 Extra bars on Grid 7-8/B-C 0 0 - - - 181.875 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1129 Main Bars 6 6" C/C 1 18 18 4.19 41.9 - - - - -
1130 Dist Bars 6 6" C/C 1 10 10 4.31 38.79 - - - 155.16 -
1131 Extra bars on Grid 7-8/C-E 0 0 - - - 170.625 -
1132 Main Bars 6 6" C/C 1 25 25 4.31 77.58 - - - - -
1133 Dist Bars 6 6" C/C 1 10 10 8.625 86.25 - - - 122.835 -
1134 Extra bars on Grid 7-8/E-G 0 0 - - - 132.6 -
1135 Main Bars 6 6" C/C 1 24 24 4.31 107.75 - - - - -
1136 Dist Bars 6 6" C/C 1 10 10 12.125 121.25 - - - 122.835 -
1137 Extra bars on Grid 7-8/G-H 0 0 - - - 132.6 -
1138 Main Bars 6 6" C/C 1 19 19 4.31 103.44 - - - - -
1139 Dist Bars 6 6" C/C 1 10 10 11.375 113.75 - - - 157.5 -
1140 Extra bars on Grid 7-8/H-I 0 0 - - - 162.9375 -
1141 Main Bars 6 6" C/C 1 19 19 4.31 81.89 - - - - -
1142 Dist Bars 6 6" C/C 1 10 10 8.84 88.4 - - - 275.625 -
1143 Extra bars on Grid 7-9/I-J 0 0 - - - 281.4375 -
1144 Main Bars 6 6" C/C 1 21 21 4.31 81.89 - - - - -
1145 Dist Bars 6 6" C/C 1 11 11 8.84 88.4 - - - 252 -
1146 Extra bars on Grid 7-9/J-K 0 0 - - - 251.8125 -
1147 Main Bars 6 6" C/C 1 21 21 5 105 - - - - -
1148 Dist Bars 6 6" C/C 1 19 19 9.875 108.625 - - - 197.505 -
1149 Extra bars on Grid 7-9/K-L 0 0 - - - 207.375 -
1150 Main Bars 6 6" C/C 1 21 21 8.75 183.75 - - - - -
1151 Dist Bars 6 6" C/C 1 17 17 9.875 187.625 - - - 197.505 -
1152 Extra bars on Grid 7-9/L-M 0 0 - - - 207.375 -
1153 Main Bars 6 6" C/C 1 21 21 8 168 - - - - -
1154 Dist Bars 6 6" C/C 1 14 14 9.875 167.875 - - - 119.415 -
1155 Extra bars on Grid 7-9/M-N 0 0 - - - 120.69 -
1156 Main Bars 6 6" C/C 1 21 21 6.27 131.67 - - - - -
1157 Dist Bars 6 6" C/C 1 14 14 9.875 138.25 - - - 245.8125 -
1158 Extra bars on Grid 8-10/A-B 0 0 - - - 254.79 -
1159 Main Bars 6 6" C/C 1 19 19 6.27 131.67 - - - - -
1160 Dist Bars 6 6" C/C 1 9 9 9.875 138.25 - - - 335.25 -
1161 Extra bars on Grid 8-10/B-C 0 0 - - - 345.5625 -
1162 Main Bars 6 6" C/C 1 19 19 4.19 79.61 - - - - -
1163 Dist Bars 6 6" C/C 1 19 19 8.94 80.46 - - - 321.84 -
1164 Extra bars on Grid 8-10/C-E 0 0 - - - 324.1875 -
1165 Main Bars 6 6" C/C 1 25 25 8.625 163.875 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1166 Dist Bars 6 6" C/C 1 19 19 8.94 169.86 - - - 69.135 -
1167 Extra bars on Grid 9-10/E-G 0 0 - - - 67.5 -
1168 Main Bars 6 6" C/C 1 24 24 8.94 223.5 - - - - -
1169 Dist Bars 6 6" C/C 1 19 19 12.125 230.375 - - - 113.13 -
1170 Extra bars on Grid 10-11/A-B 0 0 - - - 116.4375 -
1171 Main Bars 6 6" C/C 1 11 11 8.94 214.56 - - - - -
1172 Dist Bars 6 6" C/C 1 9 9 11.375 216.125 - - - 157.125 -
1173 Extra bars on Grid 10-11/B-C 0 0 - - - 163.6875 -
1174 Main Bars 6 6" C/C 1 18 18 4.19 46.09 - - - - -
1175 Dist Bars 6 6" C/C 1 9 9 5 45 - - - 150.84 -
1176 Extra bars on Grid 10-11/C-E 0 0 - - - 153.5625 -
1177 Main Bars 6 6" C/C 1 25 25 4.19 75.42 - - - - -
1178 Dist Bars 6 6" C/C 1 9 9 8.625 77.625 - - - 150 -
1179 Extra bars on Grid 10-11/E-G 0 0 - - - 154.6875 -
1180 Main Bars 6 6" C/C 1 24 24 4.19 104.75 - - - - -
1181 Dist Bars 6 6" C/C 1 9 9 12.125 109.125 - - - 262.5 -
1182 Extra bars on Grid 9-11/I-J 0 0 - - - 267.1875 -
1183 Main Bars 6 6" C/C 1 20 20 4.19 100.56 - - - - -
1184 Dist Bars 6 6" C/C 1 11 11 11.375 102.375 - - - 240 -
1185 Extra bars on Grid 9-11/J-K 0 0 - - - 239.0625 -
1186 Main Bars 6 6" C/C 1 20 20 5 100 - - - - -
1187 Dist Bars 6 6" C/C 1 19 19 9.375 103.125 - - - 188.1 -
1188 Extra bars on Grid 9-11/K-L 0 0 - - - 196.875 -
1189 Main Bars 6 6" C/C 1 20 20 8.75 175 - - - - -
1190 Dist Bars 6 6" C/C 1 17 17 9.375 178.125 - - - 188.1 -
1191 Extra bars on Grid 9-11/L-M 0 0 - - - 196.875 -
1192 Main Bars 6 6" C/C 1 20 20 8 160 - - - - -
1193 Dist Bars 6 6" C/C 1 14 14 9.375 159.375 - - - 119.415 -
1194 Extra bars on Grid 9-11/M-N 0 0 - - - 120.69 -
1195 Main Bars 6 6" C/C 1 20 20 6.27 125.4 - - - - -
1196 Dist Bars 6 6" C/C 1 14 14 9.375 131.25 - - - 245.8125 -
1197 Extra bars on Grid 11-12/A-B 0 0 - - - 241.38 -
1198 Main Bars 6 6" C/C 1 19 19 6.27 125.4 - - - - -
1199 Dist Bars 6 6" C/C 1 9 9 9.375 131.25 - - - 335.25 -
1200 Extra bars on Grid 11-12/B-C 0 0 - - - 345.5625 -
1201 Main Bars 6 6" C/C 1 19 19 4.19 79.61 - - - - -
1202 Dist Bars 6 6" C/C 1 18 18 8.94 80.46 - - - 74.8125 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1203 Extra bars on Grid 11-12/C-E 0 0 - - - 80.46 -
1204 Main Bars 6 6" C/C 1 25 25 8.625 163.875 - - - - -
1205 Dist Bars 6 6" C/C 1 19 19 8.94 160.92 - - - - -
1206 Extra bars on Grid 11-12/E-F 0 0 - - - 2555.4375 -
1207 Main Bars 6 6" C/C 1 19 19 8.94 223.5 - - - 2562 -
1208 Dist Bars 6 6" C/C 1 6 6 12.125 230.375 - - - - -
1209 Porch Raft 0 0 - - - 2555.4375 -
1210 Bottom Bars 0 2.625 49.875 - - - 2562 -
1211 Main Bars 6 6" C/C 1 59 59 8.94 53.64 - - - - -
1212 Dist Bars 6 6" C/C 1 56 56 0 - - - - -
1213 Top Bars 0 0 - - - 1532.52 -
1214 Main Bars 6 6" C/C 1 59 59 28.875 1703.625 - - - 1552.8 -
1215 Dist Bars 6 6" C/C 1 56 56 30.5 1708 - - - - -
1216 Extra bars on Bottom For Column's 0 0 - - - - -
1217 Grid 11 & 12 / O & P 0 28.875 1703.625 - - - 146.25 -
1218 Main Bars 6 6" C/C 4 27 108 30.5 1708 - - - 155.76 -
1219 Dist Bars 6 6" C/C 4 20 80 0 - - - - -
1220 Extra bars For Centers 0 0 - - - 251.25 -
1221 Grid 11-12 / N-O 0 9.46 1021.68 - - - 269.04 -
1222 Main Bars 6 6" C/C 1 20 20 12.94 1035.2 - - - - -
1223 Dist Bars 6 6" C/C 1 11 11 0 - - - - -
1224 Grid 11-12 / O-P 0 0 - - - - 37935.36
1225 Main Bars 6 6" C/C 1 20 20 4.875 97.5 - - - - -
1226 Dist Bars 6 6" C/C 1 19 19 9.44 103.84 - - - - -
1227 Column's Schedule 0 0 - - - - -
1228 C2 0 8.375 167.5 - - - - -
1229 Main Bars 8 37 20 740 9.44 179.36 - - - - 26452.224
1230 Stirrups 3 4"&6" C/C 37 29 1073 0 - - - - -
1231 Stirrups 3 4"&6" C/C 37 29 1073 0 - - - - -
1232 Stirrups 3 4"&6" C/C 37 29 1073 19.2 14208 - - - - -
1233 C3 0 7.5 8047.5 3017.8125 - - - -
1234 Main Bars 8 43 12 516 5.5 5901.5 2213.0625 - - - 615.168
1235 Stirrups 3 4"&6" C/C 43 29 1247 5.5 5901.5 2213.0625 - - - -
1236 Stirrups 3 4"&6" C/C 43 29 1247 0 - - - - -
1237 Stirrups 3 4"&6" C/C 43 29 1247 19.2 9907.2 - - - - -
1238 C4 0 7.5 9352.5 3507.1875 - - 1382.4 -
1239 Main Bars 8 1 12 12 6.5 8105.5 3039.5625 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1240 Stirrups 3 6" C/C 1 29 29 6.5 8105.5 3039.5625 - - - -
1241 Stirrups 3 6" C/C 1 29 29 0 - - - - -
1242 C8 0 19.2 230.4 - - - 1573.2 -
1243 Main Bars 6 4 12 48 6.5 188.5 70.6875 - - 1618.5 -
1244 Stirrups 3 6" C/C 4 29 116 4.67 135.43 50.78625 - - 810 -
1245 Stirrups 3 6" C/C 4 29 116 0 - - - 765 -
1246 MAIN PORTION LIFT RAFT 0 19.2 921.6 - - - - -
1247 Main Bars 6 6" C/C 2 19 38 5.5 638 239.25 - - 641.25 -
1248 Dist Bars 6 6" C/C 2 20 40 4 464 174 - - 637.5 -
1249 Internal Beam L/W 6 6" C/C 4 12 48 0 - - - - -
1250 Internal Beam S/W 6 6" C/C 4 12 48 27.6 1048.8 - - - 530.1 -
1251 Top Bars 0 26.975 1079 - - - 558 -
1252 Main Bars 6 6" C/C 2 19 38 11.25 540 - - - - -
1253 Dist Bars 6 6" C/C 2 20 40 10.625 510 - - - - -
1254 Inner side Vertical bars 0 0 - - - - -
1255 Main Bars L/W 6 6" C/C 2 19 38 11.25 427.5 - - - - -
1256 Main Bars S/W 6 6" C/C 2 20 40 10.625 425 - - - - -
1257 Dist Bars outer L/W 4 6" C/C 4 13 52 0 - - - - -
1258 Dist Bars Inner L/W 4 6" C/C 4 13 52 9.3 353.4 - - - - -
1259 Dist Bars outer S/W 4 6" C/C 4 11 44 9.3 372 - - - - -
1260 Dist Bars Inner S/W 4 6" C/C 4 11 44 11.25 585 - 390.195 - - -
1261 Doels for lift RCC Wall 0 9 468 - 312.156 - - -
1262 main bars L/W 4 9" C/C 4 13 52 10.625 467.5 - 311.8225 - - -
1263 Dist bars L/W 3 9" C/C 4 9 36 8.375 368.5 - 245.7895 - - -
1264 main bars S/W 4 9" C/C 4 11 44 0 - - - - -
1265 Dist bars S/W 3 9" C/C 4 9 36 14.55 756.6 - 504.6522 - - -
1266 DOWELS FOR LIFT ( From B-F to G-F Center) 0 9 324 121.5 - - - -
1267 main bars L/W 4 9" C/C 4 15 60 14.55 640.2 - 427.0134 - - -
1268 Dist bars L/W 3 9" C/C 4 18 72 8.375 301.5 113.0625 - - - 1661.9148
1269 main bars S/W 4 9" C/C 4 10 40 0 - - - - 885.2652
1270 Dist bars S/W 3 9" C/C 4 18 72 23 1380 - 920.46 - - -
Ground Floor Column's ( 1st portion Grid 13-
1271 19/ A-N ) Up to F.F center 0 11.25 810 303.75 - - - -
1272 C1 0 23 920 - 613.64 - - -
1273 Main Bars 8 3 12 36 8.25 594 222.75 - - - -
1274 Main Bars 8 3 12 36 0 - - - - 5539.716
1275 Stirrups upto beam bottom 3 4"&6" C/C 3 21 63 0 - - - - 1967.256
1276 Stirrups 3 4"&6" C/C 3 21 63 17.29 622.44 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1277 Stirrups 3 4"&6" C/C 3 21 63 9.21 331.56 - - - - -
1278 C2 0 7.5 472.5 177.1875 - - - -
1279 Main Bars 8 10 12 120 5.33 335.79 125.92125 - - - -
1280 Main Bars 8 10 8 80 5.33 335.79 125.92125 - - - 8863.5456
1281 Stirrups 3 4"&6" C/C 10 21 210 0 - - - - -
1282 Stirrups 3 4"&6" C/C 10 21 210 17.29 2074.8 - - - - -
1283 Stirrups 3 4"&6" C/C 10 21 210 9.21 736.8 - - - - -
1284 C3 0 7.5 1575 590.625 - - - -
1285 Main Bars 8 16 12 192 5.5 1155 433.125 - - - 1154.1075
1286 Stirrups 3 4"&6" C/C 16 21 336 5.5 1155 433.125 - - - -
1287 Stirrups 3 4"&6" C/C 16 21 336 0 - - - - -
1288 Stirrups 3 4"&6" C/C 16 21 336 17.29 3319.68 - - - - 9232.86
1289 C5 0 7.5 2520 945 - - - 983.628
1290 Main Bars 8 1 25 25 6.5 2184 819 - - - -
1291 Stirrups 3 4" C/C 1 25 25 6.5 2184 819 - - - -
1292 C6 0 0 - - - 2052.54 -
1293 Main Bars 8 10 20 200 17.29 432.25 - - - - -
1294 Main Bars 8 10 4 40 9.14 228.5 85.6875 - - - -
1295 Stirrups 3 4" C/C 10 25 250 0 - - - 864 -
1296 C7 0 17.29 3458 - - - - -
1297 Main Bars 6 7 12 84 9.21 368.4 - - - - -
1298 Stirrups 3 4" C/C 7 25 175 7.56 1890 708.75 - - 2345.76 -
1299 C7 0 0 - - - - -
1300 Main Bars 6 6 12 72 16.29 1368.36 - - - - -
1301 Stirrups 3 4" C/C 6 27 162 4.42 773.5 290.0625 - - - -
1302 C9 0 0 - - - - -
1303 Main Bars 6 12 8 96 8 576 - - - 3849.12 -
1304 Stirrups 3 6" C/C 12 17 204 4.42 716.04 268.515 - - - -
1305 1st Portion of Basement Beams 0 0 - - - - -
1306 LB2 0 16.29 1563.84 - - - - -
1307 Grid 11,12 & 13 (F-N) 0 5.5 1122 420.75 - - 2497.5 -
1308 Main Bars 6 3 6 18 0 - - - - -
1309 Stirrups 3 5" & 8" 3 261 783 0 - - - 472.5 -
1310 LB3 0 0 - - - 472.5 -
1311 Grid 11 - 12 (F,G,H,I,J,K,L,M,N) 0 142.56 2566.08 - - - - -
1312 Main Bars 6 9 8 72 6.08 4760.64 1785.24 - - - -
1313 Main Bars 4 9 2 18 0 - - - 3164.4 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1314 Top extra Bars 6 9 4 36 0 - - - - -
1315 Top extra Bars 6 9 4 36 23.125 1665 - - - - -
1316 Stirrups 3 5" & 8" 9 39 351 23.125 416.25 - 277.63875 - 4207.68 -
1317 Grid 15 & 16 (D-N1) 0 8.75 315 - - - - -
1318 Main Bars 6 2 6 12 8.75 315 - - - 472.5 -
1319 Stirrups 3 5" & 8" 2 318 636 6.08 2134.08 800.28 - - 756 -
1320 Grid 13 - 16 (F,G,H,I,J,K,L,M,N) 0 0 - - - - -
1321 Main Bars 6 9 8 72 175.8 2109.6 - - - - -
1322 Main Bars 4 9 2 18 6.08 3866.88 1450.08 - - 561 -
1323 Top extra Bars 6 9 4 36 0 - - - - -
1324 Top extra Bars 6 9 4 36 38.96 2805.12 - - - 105 -
1325 Stirrups 3 5" & 8" 9 71 639 38.96 701.28 - 467.75376 - 105 -
1326 Grid 15 - 16 (D,N1) 0 8.75 315 - - - - -
1327 Main Bars 6 2 8 16 14 504 - - - - -
1328 Main Bars 4 2 2 4 6.08 3885.12 1456.92 - - - -
1329 Top extra Bars 6 2 4 8 0 - - - 282.45 -
1330 Top extra Bars 6 2 4 8 23.375 374 - - - 24 -
1331 Stirrups 3 5" & 8" 2 39 78 23.375 93.5 - 62.3645 - 28.5 -
1332 RAMP STEEL 0 8.75 70 - - - - -
1333 Grid B,E ( 13 - 15 ) LB 1 0 8.75 70 - - - - -
1334 Main Bars 6 2 5 10 6.08 474.24 177.84 - - 1138.125 -
1335 Top extra Bars 6 2 2 4 0 - - - 24 -
1336 Top extra Bars 6 2 1 2 0 - - - 171 -
1337 Stirrups 3 7" C/C 2 31 62 18.83 188.3 - - - - -
1338 Grid 13 & 14a (A - E' ) 0 4 16 - - - - -
1339 Main Bars 6 2 5 10 9.5 19 - - - 103.425 -
1340 Top extra Bars 6 2 2 4 5.58 345.96 129.735 - - 12 -
1341 Top extra Bars 6 2 6 12 0 - - - 71.25 -
1342 Stirrups 3 7" C/C 2 125 250 75.875 758.75 - - - - -
1343 Grid 14 (A - B ) 0 4 16 - - - - -
1344 Main Bars 6 1 5 5 9.5 114 - - - - -
1345 Top extra Bars 6 1 2 2 5.58 1395 523.125 - - 465.03 -
1346 Top extra Bars 6 1 5 5 0 - - - - -
1347 Stirrups 3 7" C/C 1 109 109 13.79 68.95 - - - - -
1348 Conceled Beams 0 4 8 - - - - -
1349 Grid 14 ( B' - E' ) 0 9.5 47.5 - - - 254.88 -
1350 Main Bars 6 2 3 6 5.58 608.22 228.0825 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1351 Main Bars 4 2 2 4 0 - - - - -
1352 Stirrups 3 9" C/C 2 58 116 0 - - - - -
1353 Grid B', C' D' & E' ( 14 - 15 ) 0 51.67 310.02 - - - 253.8 -
1354 Main Bars 6 6 3 18 51.67 206.68 - 137.85556 - - -
1355 Main Bars 4 6 2 12 3.17 367.72 137.895 - - - -
1356 Stirrups 3 9" C/C 6 10 60 0 - - - - -
1357 Grid B', C' D' & E' ( 13 - 14 ) 0 9.44 169.92 - - - 563.625 -
1358 Main Bars 6 6 3 18 9.44 113.28 - 75.55776 - - -
1359 Main Bars 4 6 2 12 3.17 190.2 71.325 - - 428.625 -
1360 Stirrups 3 9" C/C 6 10 60 0 - - - - -
1361 Ground Floor Porch Plinth Beam 0 9.4 169.2 - - - - -
1362 Wall 1 6 1 6 6 9.4 112.8 - 75.2376 - 1444.5 -
1363 Stirrups 3 6" C/C 1 108 108 3.17 190.2 71.325 - - - -
1364 Wall 2 6 1 6 6 0 - - - 1057.5 -
1365 Stirrups 3 6" C/C 1 87 87 62.625 375.75 - - - - -
1366 Ground Floor OPD Plinth Beam 0 4.5 486 182.25 - - 852.75 -
1367 External wall 6 1 6 6 47.625 285.75 - - - - -
1368 Stirrups 3 6" C/C 1 269 269 4.5 391.5 146.8125 - - 823.5 -
1369 Internal wall 6 1 6 6 0 - - - - -
1370 Stirrups 3 6" C/C 1 213 213 160.5 963 - - - 319.5 -
1371 Internal wall 6 2 6 12 4.5 1210.5 453.9375 - - - -
1372 Stirrups 3 6" C/C 2 86 172 117.5 705 - - - 265.5 -
1373 S/Wall 6 6 6 36 4.5 958.5 359.4375 - - - -
1374 Stirrups 3 6" C/C 6 25 150 47.375 568.5 - - - 407.25 -
1375 S/Wall 6 2 6 12 4.5 774 290.25 - - - -
1376 Stirrups 3 6" C/C 2 26 52 15.25 549 - - - - -
1377 S/Wall 6 2 6 12 4.5 675 253.125 - - 312.75 -
1378 Stirrups 3 6" C/C 2 24 48 17.75 213 - - - - -
1379 S/Wall 6 1 6 6 4.5 234 87.75 - - 409.95 -
1380 Stirrups 3 6" C/C 1 79 79 14.75 177 - - - - -
Ground Floor Main Portion Plinth
1381 Beam 0 4.5 216 81 - - 790.875 -
1382 Grid 1 / D - G 6 1 6 6 45.25 271.5 - - - - -
1383 Stirrups 3 6" C/C 1 60 60 4.5 355.5 133.3125 - - 1189.71 -
1384 Grid 1 / G - I 6 1 6 6 0 - - - - -
1385 Stirrups 3 6" C/C 1 74 74 34.75 208.5 - - - 655.875 -
1386 Grid 1 / I - N 6 1 6 6 4.5 270 101.25 - - - -
1387 Stirrups 3 6" C/C 1 138 138 45.55 273.3 - - - 1951.29 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1388 Grid 2 / A - I 6 1 6 6 4.5 333 124.875 - - - -
1389 Stirrups 3 6" C/C 1 221 221 87.875 527.25 - - - 1189.71 -
1390 Grid 3 / J - N 6 1 6 6 4.5 621 232.875 - - - -
1391 Stirrups 3 6" C/C 1 118 118 132.19 793.14 - - - 655.875 -
1392 Grid 4 / A - N 6 1 6 6 4.5 994.5 372.9375 - - - -
1393 Stirrups 3 6" C/C 1 354 354 72.875 437.25 - - - 5853.87 -
1394 Grid 5 / A - I 6 1 6 6 4.5 531 199.125 - - - -
1395 Stirrups 3 6" C/C 1 221 221 216.81 1300.86 - - - 1189.71 -
1396 Grid 6 / J - N 6 1 6 6 4.5 1593 597.375 - - - -
1397 Stirrups 3 6" C/C 1 118 118 132.19 793.14 - - - 790.875 -
1398 Grid 7,11 & 12 / A - N 6 3 6 18 4.5 994.5 372.9375 - - - -
1399 Stirrups 3 6" C/C 3 354 1062 72.875 437.25 - - - 808.875 -
1400 Grid 8 / A - I 6 1 6 6 4.5 531 199.125 - - - -
1401 Stirrups 3 6" C/C 1 221 221 216.81 3902.58 - - - 208.125 -
1402 Grid 9 / I - N 6 1 6 6 4.5 4779 1792.125 - - - -
1403 Stirrups 3 6" C/C 1 138 138 132.19 793.14 - - - 210.375 -
1404 Grid 10 , 11 & 12 / A - G 6 1 6 6 4.5 994.5 372.9375 - - - -
1405 Stirrups 3 6" C/C 1 146 146 87.875 527.25 - - - 208.125 -
1406 Grid A / 2 - 4 6 1 6 6 4.5 621 232.875 - - - -
1407 Stirrups 3 6" C/C 1 37 37 89.875 539.25 - - - 208.125 -
1408 Grid A / 5 - 7 6 1 6 6 4.5 657 246.375 - - - -
1409 Stirrups 3 6" C/C 1 37 37 23.125 138.75 - - - 1048.5 -
1410 Grid A / 8 - 10 6 1 6 6 4.5 166.5 62.4375 - - - -
1411 Stirrups 3 6" C/C 1 37 37 23.375 140.25 - - - 1044 -
1412 Grid A / 11 - 12 6 1 6 6 4.5 166.5 62.4375 - - - -
1413 Stirrups 3 6" C/C 1 37 37 23.125 138.75 - - - 140.625 -
1414 Grid B & C / 2 - 7 6 2 6 12 4.5 166.5 62.4375 - - - -
1415 Stirrups 3 6" C/C 2 93 186 23.125 138.75 - - - 635.625 -
1416 Grid B & C / 8 - 12 6 2 6 12 4.5 166.5 62.4375 - - - -
1417 Stirrups 3 6" C/C 2 93 186 58.25 699 - - - 522 -
1418 Grid D / 1 - 2 6 1 6 6 4.5 837 313.875 - - - -
1419 Stirrups 3 6" C/C 1 22 22 58 696 - - - 2502 -
1420 Grid E / 1 - 7 6 1 6 6 4.5 837 313.875 - - - -
1421 Stirrups 3 6" C/C 1 113 113 15.625 93.75 - - - 698.625 -
1422 Grid E / 8 - 12 6 1 6 6 4.5 99 37.125 - - - -
1423 Stirrups 3 6" C/C 1 93 93 70.625 423.75 - - - 6255 -
1424 Grid G & I / 1 - 12 6 2 6 12 4.5 508.5 190.6875 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1425 Stirrups 3 6" C/C 2 222 444 58 348 - - - 765 -
1426 Grid H / 1 - 8 6 1 6 6 4.5 418.5 156.9375 - - - -
1427 Stirrups 3 6" C/C 1 125 125 139 1668 - - - 200.25 -
1428 Grid J , K , L , M , & N / 1 - 12 6 5 6 30 4.5 1998 749.25 - - - -
1429 Stirrups 3 6" C/C 5 222 1110 77.625 465.75 - - - 589.5 -
1430 OFF SET PLINTH BEAM 6 20 6 120 4.5 562.5 210.9375 - - - -
1431 Stirrups 3 6" C/C 20 5 100 139 4170 - - - 208.125 -
1432 FOR STAIRS PLINTH BEAM 6 2 6 12 4.5 4995 1873.125 - - - -
1433 Stirrups 3 6" C/C 2 16 32 4.25 510 - - - 178.56 -
1434 PORCH 11, 12 (N - P) 6 2 6 12 4 400 150 - - - -
1435 Stirrups 3 6" C/C 2 52 104 11.125 133.5 - - - - -
1436 PORCH 11 - 12 (P) 6 1 6 6 4.5 144 54 - - - -
1437 Stirrups 3 6" C/C 1 36 36 32.75 393 - - - - -
1438 Ground Floor Dummy Column 6 1 8 8 4.5 468 175.5 - - - -
1439 Stirrups 3 6" C/C 1 23 23 23.125 138.75 - - - - -
1440 1st Portion of Basement Slab 0 4.5 162 60.75 - - - -
1441 Grid F - J ( 11 - 12 ) 0 14.88 119.04 - - - - -
1442 Main Bars 4 8" C/C 1 30 30 4 92 34.5 - - - -
1443 Dist Bars 4 8" C/C 1 97 97 0 - - - - -
1444 Grid K - N ( 11 - 12 ) 0 0 - - - - -
1445 Main Bars 4 8" C/C 1 30 30 67.56 2026.8 - 1351.8756 - - -
1446 Dist Bars 4 8" C/C 1 69 69 21.625 2097.625 - 1399.115875 - - -
1447 Extra Bars 0 0 - - - - -
1448 Grid 11 & 12 ( F - J ) 4 7" C/C 2 103 206 51.92 1557.6 - 1038.9192 - - -
1449 Grid 11 & 12 ( F - J ) Temp 3 12" C/C 4 5 20 21.625 1492.125 - 995.247375 - - -
1450 Grid 11 & 12 ( F - J ) Temp 3 12" C/C 4 5 20 0 - - - - -
1451 Grid 11 & 12 ( K - N ) 4 7" C/C 2 78 156 4.98 1025.88 - 684.26196 - - -
1452 Grid 11 & 12 ( K - N ) Temp 3 12" C/C 2 5 10 7 140 52.5 - - - -
1453 Grid 11 & 12 ( K - N ) Temp 3 12" C/C 2 5 10 8 160 60 - - - -
1454 Grid 11 & 12 ( K - N ) Temp 3 12" C/C 2 5 10 4.98 776.88 - 518.17896 - - -
1455 Grid F, J ( 11 - 12 ) 4 7" C/C 2 34 68 10.08 100.8 37.8 - - - -
1456 Grid F, J ( 11 - 12 ) Temp 3 12" C/C 2 3 6 6.43 64.3 24.1125 - - - -
1457 Grid G, I ( 11 - 12 ) 4 7" C/C 2 34 68 8.2 82 30.75 - - - -
1458 Grid G, I ( 11 - 12 ) Temp 3 12" C/C 2 12 24 3.025 205.7 - 137.2019 - - -
1459 Grid H ( 11 - 12 ) 4 7" C/C 1 34 34 13.625 81.75 30.65625 - - - -
1460 Grid H ( 11 - 12 ) Temp 3 12" C/C 1 15 15 10.97 745.96 - 497.55532 - - -
1461 Grid K ( 11 - 12 ) 4 7" C/C 1 34 34 13.625 327 122.625 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1462 Grid K ( 11 - 12 ) Temp 3 12" C/C 1 6 6 13.54 460.36 - 307.06012 - - -
1463 Grid L ( 11 - 12 ) 4 7" C/C 1 34 34 10.625 159.375 59.765625 - - - -
1464 Grid L ( 11 - 12 ) Temp 3 12" C/C 1 12 12 4.79 162.86 - 108.62762 - - -
1465 Grid M ( 11 - 12 ) 4 7" C/C 1 34 34 10.625 63.75 23.90625 - - - -
1466 Grid M ( 11 - 12 ) Temp 3 12" C/C 1 11 11 11.46 389.64 - 259.88988 - - -
1467 Grid N ( 11 - 12 ) 4 7" C/C 1 34 34 10.625 127.5 47.8125 - - - -
1468 Grid N ( 11 - 12 ) Temp 3 12" C/C 1 5 5 10.11 343.74 - 229.27458 - - -
1469 Stairs in 1st portion 0 10.625 116.875 43.828125 - - - -
1470 Main Bars 4 6" C/C 1 11 11 3.92 133.28 - 88.89776 - - -
1471 Dist Bars 4 9" C/C 1 12 12 10.625 53.125 19.921875 - - - -
1472 Extra bars 4 6" C/C 1 10 10 0 - - - - -
1473 Dist Bars 4 9" C/C 1 3 3 18.42 202.62 - 135.14754 - - -
1474 Landing Extra Bars 4 6" C/C 1 11 11 5.17 62.04 - 41.38068 - - -
1475 Landing Extra Bars 4 6" C/C 1 14 14 6.5 65 - 43.355 - - -
1476 Main Bars 4 6" C/C 1 14 14 5.17 15.51 - 10.34517 - - -
1477 Extra bars 4 6" C/C 1 11 11 8.58 94.38 - 62.95146 - - -
1478 Dist Bars 4 9" C/C 1 14 14 7.33 102.62 - 68.44754 - - -
1479 Main Bars 4 6" C/C 1 10 10 19.83 277.62 - 185.17254 - - -
1480 Dist Bars 4 9" C/C 1 13 13 8.5 93.5 - 62.3645 - - -
1481 Extra bars 4 6" C/C 1 10 10 6.83 95.62 - 63.77854 - - -
1482 Dist Bars 4 9" C/C 1 11 11 9.75 97.5 - 65.0325 - - -
1483 Dowels for G.F stairs 4 6" C/C 2 10 20 5.75 74.75 - 49.85825 - - -
1484 Dist Bars 4 9" C/C 1 9 9 9.25 92.5 - 61.6975 - - -
1485 2nd Portion of Basement Slab 0 5.75 63.25 - 42.18775 - - -
1486 Main Bars 0 9.25 185 - 123.395 - - -
1487 Grid F - N1 ( 13 - 15 ) 4 8" C/C 1 25 25 6 54 - 36.018 - - -
1488 Grid E - N1 ( 15 - 16 ) 4 8" C/C 1 29 29 0 - - - - -
1489 Dist Bars 0 0 - - - - -
1490 Grid 13 - 16 ( E - N1 ) 4 8" C/C 1 175 175 153.94 3848.5 - 2566.9495 - - -
1491 Extra Bars For Slab 0 153.94 4464.26 - 2977.66142 - - -
1492 Grid F ( 13 - 16) 4 7" C/C 1 63 63 0 - - - - -
1493 Grid F ( 13 - 16) Temp 3 12" C/C 1 7 7 39.54 6919.5 - 4615.3065 - - -
1494 Grid G & I (13 - 16) 4 7" C/C 1 63 63 0 - - - - -
1495 Grid G & I (13 - 16) Temp 3 12" C/C 1 12 12 6.25 393.75 - 262.63125 - - -
1496 Grid H (13 - 16) 4 7" C/C 1 63 63 10 70 26.25 - - - -
1497 Grid H (13 - 16) Temp 3 12" C/C 1 15 15 10.97 691.11 - 460.97037 - - -
1498 Grid J (13 - 16) 4 7" C/C 1 63 63 10 120 45 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1499 Grid J (13 - 16) Temp 3 12" C/C 1 12 12 13.53 852.39 - 568.54413 - - -
1500 Grid K (13 - 16) 4 7" C/C 1 63 63 10 150 56.25 - - - -
1501 Grid K (13 - 16) Temp 3 12" C/C 1 14 14 10.74 676.62 - 451.30554 - - -
1502 Grid L (13 - 16) 4 7" C/C 1 63 63 10 120 45 - - - -
1503 Grid L (13 - 16) Temp 3 12" C/C 1 12 12 12.93 814.59 - 543.33153 - - -
1504 Grid M (13 - 16) 4 7" C/C 1 63 63 10 140 52.5 - - - -
1505 Grid M (13 - 16) Temp 3 12" C/C 1 11 11 11.46 721.98 - 481.56066 - - -
1506 Grid N (13 - 16) 4 7" C/C 1 63 63 10 120 45 - - - -
1507 Grid N (13 - 16) Temp 3 12" C/C 1 9 9 10.11 636.93 - 424.83231 - - -
1508 Grid 13 (E - N) 4 7" C/C 1 217 217 10 110 41.25 - - - -
1509 Grid 13 (F - G, I - J) Temp 3 12" C/C 2 6 12 8.18 515.34 - 343.73178 - - -
1510 Grid 13/G - I Temp 3 12" C/C 2 6 12 10 90 33.75 - - - -
1511 Grid 13/ J - K Temp 3 12" C/C 1 6 6 4.67 1013.39 - 675.93113 - - -
1512 Grid 13/ K - L Temp 3 12" C/C 1 6 6 5.58 66.96 25.11 - - - -
1513 Grid 13/ L - N Temp 3 12" C/C 2 6 12 8.14 97.68 36.63 - - - -
1514 Grid 13/ N - N1 Temp 3 12" C/C 1 6 6 8.33 49.98 18.7425 - - - -
1515 Grid 16 (E - N) 4 7" C/C 1 217 217 7.78 46.68 17.505 - - - -
1516 Grid 16 (F - G, I - J) Temp 3 12" C/C 2 6 12 6.43 77.16 28.935 - - - -
1517 Grid 16/G - I Temp 3 12" C/C 2 6 12 4.58 27.48 10.305 - - - -
1518 Grid 16/ J - K Temp 3 12" C/C 1 6 6 5.18 1124.06 - 749.74802 - - -
1519 Grid 16/ K - L Temp 3 12" C/C 1 6 6 5.58 66.96 25.11 - - - -
1520 Grid 16/ L - N Temp 3 12" C/C 2 6 12 8.14 97.68 36.63 - - - -
1521 Grid 16/ N - N1 Temp 3 12" C/C 1 6 6 8.33 49.98 18.7425 - - - -
1522 Grid 15 (E - N) 4 7" C/C 1 217 217 7.78 46.68 17.505 - - - -
1523 Grid 15 (F - G, I - J) Temp 3 12" C/C 2 14 28 6.43 77.16 28.935 - - - -
1524 Grid 15/G - I Temp 3 12" C/C 2 14 28 4.58 27.48 10.305 - - - -
1525 Grid 15/ J - K Temp 3 12" C/C 1 14 14 13 2821 - 1881.607 - - -
1526 Grid 15/ K - L Temp 3 12" C/C 1 14 14 5.58 156.24 58.59 - - - -
1527 Grid 15/ L - N Temp 3 12" C/C 2 14 28 8.14 227.92 85.47 - - - -
1528 Grid 15/ N - N1 Temp 3 12" C/C 1 14 14 8.33 116.62 43.7325 - - - -
1529 RAMP STEEL 0 7.78 108.92 40.845 - - - -
1530 Ramp Slab steel 0 6.43 180.04 67.515 - - - -
1531 Main Bars 4 10" C/C 1 56 56 4.58 64.12 24.045 - - - -
1532 Dist Bars 4 10" C/C 1 9 9 0 - - - - -
1533 Curve 0 0 - - - - -
1534 Main Bars 4 10" C/C 1 12 12 8.4 470.4 - 313.7568 - - -
1535 Dist Bars 4 10" C/C 1 17 17 54.3 488.7 - 325.9629 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1536 Main Bars 4 10" C/C 1 56 56 0 - - - - -
1537 Dist Bars 4 10" C/C 1 9 9 13 156 - 104.052 - - -
1538 Extra bars 0 9.48 161.16 - 107.49372 - - -
1539 // 4 10" C/C 1 9 9 8.1 453.6 - 302.5512 - - -
1540 // 3 12" C/C 1 7 7 54.3 488.7 - 325.9629 - - -
1541 // 4 10" C/C 5 9 45 0 - - - - -
1542 // 3 12" C/C 5 8 40 5.52 49.68 - 33.13656 - - -
1543 // 4 10" C/C 1 9 9 6.91 48.37 18.13875 - - - -
1544 // 3 12" C/C 1 7 7 7.04 316.8 - 211.3056 - - -
1545 // 4 10" C/C 5 9 45 6.91 276.4 103.65 - - - -
1546 // 3 12" C/C 5 8 40 5.52 49.68 - 33.13656 - - -
1547 In Curve 4 10" C/C 1 35 35 6.91 48.37 18.13875 - - - -
1548 Temperature bars 3 12" C/C 1 3 3 7.04 316.8 - 211.3056 - - -
1549 0 6.91 276.4 103.65 - - - -
1550 Basement Stairs 2nd portion 0 2.42 84.7 - 56.4949 - - -
1551 Main Bars 4 6" C/C 1 10 10 8.33 24.99 9.37125 - - - -
1552 Dist Bars 4 9" C/C 1 17 17 0 - - - - -
1553 Extra bars 4 6" C/C 1 10 10 0 - - - - -
1554 Dist Bars 4 9" C/C 1 4 4 18.42 184.2 - 122.8614 - - -
1555 Landing Extra Bars 4 6" C/C 1 10 10 5.17 87.89 - 58.62263 - - -
1556 Landing Extra Bars 4 6" C/C 1 13 13 6.5 65 - 43.355 - - -
1557 Main Bars 4 6" C/C 1 18 18 5.17 20.68 - 13.79356 - - -
1558 Extra bars 4 6" C/C 1 13 13 9.16 91.6 - 61.0972 - - -
1559 Dist Bars 4 9" C/C 1 11 11 21.58 280.54 - 187.12018 - - -
1560 Main Bars 4 6" C/C 1 11 11 6.16 110.88 - 73.95696 - - -
1561 Dist Bars 4 9" C/C 1 11 11 8.5 110.5 - 73.7035 - - -
1562 Extra bars 4 6" C/C 1 10 10 9.75 107.25 - 71.53575 - - -
1563 Dist Bars 4 9" C/C 1 14 14 9.75 107.25 - 71.53575 - - -
1564 Dowels for G.F stairs 4 6" C/C 1 10 10 5.17 56.87 - 37.93229 - - 22158.864
1565 Dist Bars 4 9" C/C 1 6 6 16.58 165.8 - 110.5886 - - 7869.024
1566 FOR STAIRS Dowels 4 2 14 28 5.17 72.38 - 48.27746 - - -
Ground Floor Column's ( 2nd portion Grid 1-
1567 12/ A-P ) Up to F.F Center 0 10 100 - 66.7 - - -
1568 C2 0 5.17 31.02 - 20.69034 - - -
1569 Main Bars 8 40 12 480 5 140 - 93.38 - - -
1570 Main Bars 8 40 8 320 0 - - - - 32130.3528
1571 Stirrups upto beam bottom 3 4"&6" C/C 40 21 840 0 - - - - -
1572 Stirrups 3 4"&6" C/C 40 21 840 17.29 8299.2 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1573 Stirrups 3 4"&6" C/C 40 21 840 9.21 2947.2 - - - - -
1574 C3 0 7.5 6300 2362.5 - - - -
1575 Main Bars 8 58 12 696 5.5 4620 1732.5 - - - 553.9716
1576 Stirrups 3 4"&6" C/C 58 21 1218 5.5 4620 1732.5 - - - -
1577 Stirrups 3 4"&6" C/C 58 21 1218 0 - - - - -
1578 Stirrups 3 4"&6" C/C 58 21 1218 17.29 12033.84 - - - - -
1579 C4 0 7.5 9135 3425.625 - - - 1846.572
1580 Main Bars 8 1 12 12 6.5 7917 2968.875 - - - 196.7256
1581 Stirrups 3 6" C/C 1 17 17 6.5 7917 2968.875 - - - -
1582 Stirrups 3 6" C/C 1 17 17 0 - - - - -
1583 C6 0 17.29 207.48 - - - 423 -
1584 Main Bars 8 2 20 40 6.5 110.5 41.4375 - - - -
1585 Main Bars 8 2 4 8 4.67 79.39 29.77125 - - - -
1586 Stirrups 3 4" C/C 2 25 50 0 - - - - -
1587 C8 0 17.29 691.6 - - - 333.72 -
1588 Main Bars 6 2 12 24 9.21 73.68 - - - - -
1589 Stirrups 3 6" C/C 2 23 46 7.56 378 141.75 - - - -
1590 Stirrups 3 6" C/C 2 23 46 0 - - - - -
1591 C8 0 11.75 282 - - - - -
1592 Main Bars 6 2 12 24 5.5 253 94.875 - - - 1968.5376
1593 Stirrups 3 6" C/C 2 17 34 4 184 69 - - - -
1594 Stirrups 3 6" C/C 2 17 34 0 - - - - 275.01
1595 Porch Beams 0 9.27 222.48 - - - - 80.1
1596 B7 0 5.5 187 70.125 - - - -
1597 Main Bars 8 1 12 12 4 136 51 - - - -
1598 Main Bars 4 1 2 2 0 - - - - -
1599 Extra Bars 8 2 4 8 0 - - - - 1792.3176
1600 Spacer Bars 8 1 24 24 61.44 737.28 - - - - -
1601 Stirrups 3 4" C/C 1 159 159 58.44 116.88 - 77.95896 - - 275.01
1602 Stirrups 3 4" C/C 1 62 62 12.875 103 - - - - 76.7625
1603 B7 0 1.25 30 - - - - -
1604 Main Bars 8 1 12 12 8.58 1364.22 511.5825 - - - -
1605 Main Bars 4 1 2 2 7.33 454.46 170.4225 - - - -
1606 Extra Bars 8 2 4 8 0 - - - - 1355.025
1607 Spacer Bars 8 1 23 23 55.94 671.28 - - - - -
1608 Stirrups 3 4" C/C 1 142 142 52.94 105.88 - 70.62196 - - 348.435
1609 Stirrups 3 4" C/C 1 62 62 12.875 103 - - - - 58.74

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1610 B6 0 1.25 28.75 - - - - -
1611 Main Bars 8 1 10 10 8.58 1218.36 456.885 - - - -
1612 Main Bars 4 1 2 2 7.33 454.46 170.4225 - - - -
1613 Extra Bars 8 2 6 12 0 - - - - 1291.6125
1614 Spacer Bars 8 1 22 22 50.75 507.5 - - - - -
1615 Stirrups 3 4" C/C 1 126 126 47.75 95.5 - 63.6985 - - 284.355
1616 Stirrups 3 4" C/C 1 62 62 10.875 130.5 - - - - 58.74
1617 B5 0 1 22 - - - - -
1618 Main Bars 8 1 10 10 7.08 892.08 334.53 - - - -
1619 Main Bars 4 1 2 2 6 372 139.5 - - - -
1620 Extra Bars 8 2 6 12 0 - - - - 1662.075
1621 Spacer Bars 8 1 22 22 48.375 483.75 - - - - -
1622 Stirrups 3 4" C/C 1 120 120 45.375 90.75 - 60.53025 - - 280.35
1623 Stirrups 3 4" C/C 1 42 42 8.875 106.5 - - - - 252.315
1624 B5 0 1 22 - - - - 48.06
1625 Main Bars 8 1 10 10 7.08 849.6 318.6 - - - -
1626 Main Bars 4 1 2 2 6 252 94.5 - - - -
1627 Extra Bars 8 2 6 12 0 - - - - -
1628 Extra Bars 8 1 6 6 62.25 622.5 - - - 744.375 -
1629 Spacer Bars 8 1 18 18 59.25 118.5 - 79.0395 - - -
1630 Stirrups 3 4" C/C 1 157 157 8.75 105 - - - 144 -
1631 Stirrups 3 4" C/C 1 76 76 15.75 94.5 - - - 126 -
1632 B4 0 1 18 - - - - 53.4
1633 Main Bars 6 1 10 10 7.08 1111.56 416.835 - - - -
1634 Main Bars 4 1 2 2 6 456 171 - - - -
1635 Extra Bars 6 2 6 12 0 - - - 983.745 -
1636 Extra Bars 6 1 6 6 49.625 496.25 - - - - -
1637 Spacer Bars 8 1 20 20 46.625 93.25 - 62.19775 - 63 -
1638 Stirrups 3 4"&6" C/C 1 150 150 8 96 - - - 252 -
1639 B3 0 14 84 - - - - -
1640 Main Bars 6 1 7 7 1 20 - - - - -
1641 Main Bars 4 1 2 2 6.08 912 342 - - - -
1642 Extra Bars 6 2 3 6 0 - - - 856.5 -
1643 Extra Bars 6 4 3 12 93.69 655.83 - - - - -
1644 Stirrups 3 5"&8" C/C 1 161 161 91.19 182.38 - 121.64746 - - -
1645 B3 & B4 U 3 3' C/C 1 38 38 7 42 - - - 251.04 -
1646 CB ( 1 ) 0 14 168 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1647 Main Bars 6 1 8 8 6.08 978.88 367.08 - - - -
1648 Stirrups 3 6" C/C 1 126 126 4 152 57 - - - -
1649 CB ( 2 ) 0 0 - - - - -
1650 Main Bars 6 1 8 8 71.375 571 - - - - -
1651 Stirrups 3 6" C/C 1 38 38 4.25 535.5 200.8125 - - - -
1652 Porch Slab Steel 0 0 - - - - -
1653 Main Bars 4 5" C/C 1 76 76 20.92 167.36 - - - - -
1654 Dist Bars 4 5" C/C 1 46 46 4.25 161.5 60.5625 - - - -
1655 Main Bars 4 5" C/C 1 45 45 0 - - - - -
1656 Main Bars 4 5" C/C 1 33 33 21.92 1665.92 - 1111.16864 - - -
1657 Dist Bars 4 5" C/C 1 44 44 34.42 1583.32 - 1056.07444 - - -
1658 Main Bars 4 5" C/C 1 84 84 21.66 974.7 - 650.1249 - - -
1659 Dist Bars 4 5" C/C 1 63 63 14.33 472.89 - 315.41763 - - -
1660 Dist Bars 4 5" C/C 1 76 76 29.12 1281.28 - 854.61376 - - -
1661 Main Bars 4 5" C/C 1 64 64 21.375 1795.5 - 1197.5985 - - -
1662 Dist Bars 4 5" C/C 1 44 44 36.21 2281.23 - 1521.58041 - - -
1663 Extra Bars 0 20.83 1583.08 - 1055.91436 - - -
1664 Grid 16 / F - J 4 4" C/C 1 188 188 12.375 792 - 528.264 - - -
1665 Grid J / 16 - 17 4 4" C/C 1 58 58 17.2 756.8 - 504.7856 - - -
1666 Grid J / 17 - 18 4 4" C/C 1 31 31 0 - - - - -
1667 Grid 17 & 18 / I - J 4 4" C/C 1 19 19 5.25 987 - 658.329 - - -
1668 Grid 18 - 17 /H - J 4 4" C/C 1 97 97 7.33 425.14 - 283.56838 - - -
1669 Grid H / 16 - 17 4 4" C/C 1 56 56 7.33 227.23 - 151.56241 - - -
1670 Grid H / 17 - 18 4 4" C/C 1 81 81 25 475 - 316.825 - - -
1671 Grid F / 16 - 18 4 4" C/C 1 136 136 9.75 945.75 - 630.81525 - - -
1672 Grid 17 / F - H 4 4" C/C 1 56 56 20.415 1143.24 - 762.54108 - - -
1673 Grid 17 / H - J 4 4" C/C 1 79 79 13.33 1079.73 - 720.17991 - - -
1674 Temperature Bars X-Axis 0 5.25 714 - 476.238 - - -
1675 Grid 16 / F - H 3 12" C/C 1 5 5 13.5 756 - 504.252 - - -
1676 Grid 16 / H - J 3 12" C/C 1 5 5 12.92 1020.68 - 680.79356 - - -
1677 Grid 17 / F' - H 3 12" C/C 1 7 7 0 - - - - -
1678 Grid 17 / H - J 3 12" C/C 1 7 7 16 80 30 - - - -
1679 Grid 18 - 17 / H - J 3 12" C/C 1 9 9 17.42 87.1 32.6625 - - - -
1680 Grid 18 - 17 / H - J 3 12" C/C 1 9 9 18 126 47.25 - - - -
1681 Grid 18 / H - J 3 12" C/C 1 6 6 11 77 28.875 - - - -
1682 Temperature Bars Y-Axis 0 16 144 54 - - - -
1683 Grid F / 16 - 17 3 12" C/C 1 5 5 10 90 33.75 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1684 Grid F / 17 - 18 3 12" C/C 1 18 18 28 168 63 - - - -
1685 Grid H / 16 - 17 3 12" C/C 1 6 6 0 - - - - -
1686 Grid H / 17 - 18 3 12" C/C 1 5 5 12 60 22.5 - - - -
1687 Grid J / 16 - 17 3 12" C/C 1 12 12 11 198 74.25 - - - -
1688 Parapet Wall Steel 0 11 66 24.75 - - - -
1689 Main Bars External 4 6" C/C 1 115 115 18 90 33.75 - - - -
1690 Dist Bars 3 9" C/C 1 8 8 13 156 58.5 - - - -
1691 Main Bars External 4 6" C/C 1 85 85 0 - - - - -
1692 Dist Bars 3 9" C/C 1 8 8 6.5 747.5 - 498.5825 - - -
1693 Main Bars Internal 4 6" C/C 1 115 115 58.15 465.2 174.45 - - - -
1694 Dist Bars 3 9" C/C 1 10 10 6.5 552.5 - 368.5175 - - -
1695 Main Bars Internal 4 6" C/C 1 85 85 43.5 348 130.5 - - 1492.995 -
1696 Dist Bars 3 9" C/C 1 10 10 5.5 632.5 - 421.8775 - 55.125 -
1697 1st Portion Beams 0 58.15 581.5 218.0625 - - 315 -
1698 B3 0 5.5 467.5 - 311.8225 - 130.5 -
1699 Grid 13 / F-N 0 43.5 435 163.125 - - - -
1700 Main Bars 6 1 7 7 0 - - - - -
1701 Extra Bars On Edge 6 2 3 6 0 - - - - -
1702 Extra Bars On Centers 6 5 3 15 0 - - - 3500.49 -
1703 Extra Bars On Centers 6 2 3 6 142.19 995.33 - - - 55.125 -
1704 Stirrups 3 5" & 8 " 1 244 244 6.13 36.75 - - - 72 -
1705 B3 0 14.00 210 - - - 567 -
1706 Grid 15 & 16 / D-N 0 14.50 87 - - - 456.75 -
1707 Main Bars 6 2 7 14 6.08 1483.52 556.32 - - - -
1708 Extra Bars On Edge 6 2 3 6 0 - - - - -
1709 Extra Bars On Edge 6 2 3 6 0 - - - - -
1710 Extra Bars On Centers 6 9 3 27 166.69 2333.66 - - - 769.125 -
1711 Extra Bars On Centers 6 7 3 21 6.13 36.75 - - - 55.125 -
1712 Stirrups 3 5" & 8 " 2 295 590 8.00 48 - - - 63 -
1713 B3 0 14.00 378 - - - 67.5 -
1714 Grid 17 / J-N 0 14.50 304.5 - - - 65.25 -
1715 Main Bars 6 1 7 7 6.08 3587.2 1345.2 - - - -
1716 Extra Bars On Edge 6 2 3 6 0 - - - - -
1717 Extra Bars On Centers 6 1 3 3 0 - - - - -
1718 Extra Bars On Centers 6 1 3 3 73.25 512.75 - - - 204.75 -
1719 Extra Bars On Centers 6 1 3 3 6.13 36.75 - - - 42.75 -
1720 Stirrups 3 5" & 8 " 1 125 125 14.00 42 - - - 54 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1721 B2 0 15.00 45 - - - - -
1722 Grid 15 & 16 /N - N' 0 14.50 43.5 - - - - -
1723 Main Bars 6 2 6 12 6.08 760 285 - - - -
1724 Extra Bars On Edge 6 2 2 4 0 - - - - -
1725 Extra Bars On Edge 6 2 2 4 0 - - - 420.75 -
1726 Stirrups 3 5" & 8 " 1 17 17 11.375 136.5 - - - 85.5 -
1727 Y-AXIS 0 7.125 28.5 - - - - -
1728 B2 0 9.0 36 - - - - -
1729 Grid D & N' / 15-16 0 6.08 103.36 38.76 - - - -
1730 Main Bars 6 2 6 12 0 - - - 2607 -
1731 Extra Bars On Edge 6 4 2 8 0 - - - - -
1732 Stirrups 3 5" & 8 " 2 41 82 0 - - - 513 -
1733 B4 0 23.375 280.5 - - - 594 -
1734 Grid F,G,H & I / 13-16 0 7.125 57 - - - 108 -
1735 Main Bars 6 4 10 40 6.08 498.56 186.96 - - - -
1736 Main Bars 4 4 2 8 0 - - - - -
1737 Extra Bars On Edge 6 8 6 48 0 - - - - -
1738 Extra Bars On Centers 6 4 6 24 43.45 1738 - - - 3024 -
1739 Spacer Bars 6 4 18 72 40.45 323.6 - 215.8412 - - -
1740 Stirrups 3 4"&6" C/C 4 97 388 7.13 342 - - - 192.375 -
1741 B4 0 16.50 396 - - - 137.25 -
1742 Grid J,K,L,M & N / 13-16 0 1.00 72 - - - 1008 -
1743 Main Bars 6 5 10 50 6.08 2359.04 884.64 - - 445.5 -
1744 Main Bars 4 5 2 10 0 - - - 180 -
1745 Extra Bars On Edge 6 3 6 18 0 - - - - -
1746 Extra Bars On Edge 6 2 6 12 40.32 2016 - - - - -
1747 Extra Bars On Centers 6 7 6 42 40.07 400.7 - 267.2669 - - -
1748 Extra Bars On Centers 6 3 6 18 7.13 128.25 - - - 1040.625 -
1749 Spacer Bars 6 4 30 120 7.63 91.5 - - - - -
1750 Stirrups 3 4"&6" C/C 4 97 388 16.00 672 - - - 58.5 -
1751 B4 0 16.50 297 - - - 288 -
1752 Grid J,M & N / 16-17 0 1.00 120 - - - 54 -
1753 Main Bars 6 3 10 30 6.08 2359.04 884.64 - - - -
1754 Main Bars 4 3 2 6 0 - - - - -
1755 Extra Bars On Edge 6 1 6 6 0 - - - - -
1756 Extra Bars On Centers 6 2 6 12 23.13 693.75 - - - 354.375 -
1757 Spacer Bars 6 3 12 36 23.13 138.75 - 92.54625 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1758 Stirrups 3 4"&6" C/C 3 53 159 6.50 39 - - - 63 -
1759 B4 0 16.00 192 - - - 18 -
1760 Grid K / 16-17 0 1.00 36 - - - - -
1761 Main Bars 6 1 10 10 6.08 966.72 362.52 - - - -
1762 Main Bars 4 1 2 2 0 - - - - -
1763 Extra Bars On Edge 6 1 6 6 0 - - - 361.875 -
1764 Spacer Bars 6 1 12 12 23.63 236.25 - - - - -
1765 Stirrups 3 4"&6" C/C 1 52 52 23.63 47.25 - 31.51575 - 67.5 -
1766 B4 0 7.00 42 - - - 18 -
1767 Grid L / 16-17 0 1.00 12 - - - - -
1768 Main Bars 6 1 10 10 6.08 316.16 118.56 - - - -
1769 Main Bars 4 1 2 2 0 - - - - -
1770 Extra Bars On Edge 6 1 6 6 0 - - - 1730.85 -
1771 Spacer Bars 6 1 12 12 24.13 241.25 - - - - -
1772 Stirrups 3 4"&6" C/C 1 51 51 24.13 48.25 - 32.18275 - 1008 -
1773 B4 0 7.50 45 - - - 445.5 -
1774 OPD CURVE 0 1.00 12 - - - 45 -
1775 Main Bars 6 1 10 10 6.08 310.08 116.28 - - - -
1776 Main Bars 4 1 2 2 0 - - - - -
1777 Extra Bars On Centers 6 7 6 42 0 - - - - -
1778 Extra Bars On Centers 6 3 6 18 115.39 1153.9 - - - - 722.769
1779 Spacer Bars 6 1 30 30 112.89 225.78 - 150.59526 - - -
1780 Stirrups 3 4"&6" C/C 1 265 265 16.00 672 - - - - 142.1775
1781 B5 0 16.50 297 - - - - 272.34
1782 Grid J1-K / 17-18 0 1.00 30 - - - - 18.69
1783 Main Bars 8 1 10 10 6.08 1611.2 604.2 - - - -
1784 Main Bars 4 1 2 2 0 - - - - -
1785 Extra Bars 8 1 6 6 0 - - - - -
1786 Extra Bars 8 2 6 12 27.07 270.7 - - - - -
1787 Spacer Bars 8 1 7 7 26.57 53.14 - 35.44438 - - 1005.522
1788 Stirrups 3 4" C/C 1 65 65 8.875 53.25 - - - - -
1789 Stirrups 3 4" C/C 1 38 38 8.50 102 - - - - 142.1775
1790 B5 0 1.00 7 - - - - 144.18
1791 Grid K-L / 17-18 0 7.08 460.2 172.575 - - - 21.36
1792 Main Bars 8 1 10 10 6.00 228 85.5 - - - -
1793 Main Bars 4 1 2 2 0 - - - - -
1794 Extra Bars 8 1 6 6 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1795 Extra Bars 8 1 6 6 37.66 376.6 - - - - -
1796 Spacer Bars 8 1 8 8 37.16 74.32 - 49.57144 - - 947.85
1797 Stirrups 3 4" C/C 1 104 104 8.875 53.25 - - - - -
1798 Stirrups 3 4" C/C 1 38 38 9.00 54 - - - - 142.1775
1799 B5 0 1.00 8 - - - - 128.16
1800 Grid L-M / 17-18 0 7.08 736.32 276.12 - - - 18.69
1801 Main Bars 8 1 10 10 6.00 228 85.5 - - - -
1802 Main Bars 4 1 2 2 0 - - - - -
1803 Extra Bars 8 1 6 6 0 - - - - -
1804 Extra Bars 8 1 6 6 35.50 355 - - - 312.75 -
1805 Spacer Bars 8 1 7 7 35.00 70 - 46.69 - - -
1806 Stirrups 3 4" C/C 1 97 97 8.875 53.25 - - - - -
1807 Stirrups 3 4" C/C 1 38 38 8.00 48 - - - - -
1808 CB1 ( Curve ) 0 1.00 7 - - - 148.5 -
1809 Main Bars 6 1 3 3 7.08 686.76 257.535 - - - -
1810 Main Bars 4 1 2 2 6.00 228 85.5 - - - -
1811 Stirrups 3 9" C/C 1 72 72 0 - - - - -
1812 CB2 ( Paramedics Lounge ) 0 69.50 208.5 - - - 155.25 -
1813 Main Bars 6 1 3 3 68.25 136.5 - 91.0455 - - -
1814 Main Bars 4 1 2 2 3.16 227.52 85.32 - - - -
1815 Stirrups 3 9" C/C 1 32 32 0 - - - - -
1816 CB3 ( Wash & CH: ) 0 33.00 99 - - - 112.5 -
1817 Main Bars 6 1 3 3 33.00 66 - 44.022 - - -
1818 Main Bars 4 1 2 2 3.16 101.12 37.92 - - - -
1819 Stirrups 3 9" C/C 1 42 42 0 - - - - -
1820 CB4 ( Wash & CH: ) 0 34.50 103.5 - - - 131.625 -
1821 Main Bars 6 1 3 3 34.50 69 - 46.023 - - -
1822 Main Bars 4 1 2 2 3.16 132.72 49.77 - - - -
1823 Stirrups 3 9" C/C 1 26 26 0 - - - - -
1824 CB5 ( Nurses Lounge ) 0 25.00 75 - - - 74.25 -
1825 Main Bars 6 1 3 3 25.00 50 - 33.35 - - -
1826 Main Bars 4 1 2 2 3.16 82.16 30.81 - - - -
1827 Stirrups 3 9" C/C 1 32 32 0 - - - - -
1828 CB6 ( Junior Doctor Lounge ) 0 29.25 87.75 - - - 90 -
1829 Main Bars 6 1 3 3 29.25 58.5 - 39.0195 - - -
1830 Main Bars 4 1 2 2 3.16 101.12 37.92 - - - -
1831 Stirrups 3 9" C/C 1 18 18 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1832 CB7 ( O.T Nurse ) 0 16.50 49.5 - - - - -
1833 Main Bars 6 1 3 3 16.50 33 - 22.011 - - -
1834 Main Bars 4 1 2 2 3.16 56.88 21.33 - - - -
1835 Stirrups 3 9" C/C 1 23 23 0 - - - - -
1836 Slab Steel 0 20.00 60 - - - - -
1837 Grid F-I / 13-16 0 20.00 40 - 26.68 - - -
1838 Main Bars 4 8" C/C 1 55 55 3.16 72.68 27.255 - - - -
1839 Dist Bars 4 8" C/C 1 76 76 0 - - - - -
1840 Grid I-J / 13-16 0 0 - - - - -
1841 Main Bars 4 8" C/C 1 55 55 54.31 2987.05 - 1992.36235 - - -
1842 Dist Bars 4 10" C/C 1 14 14 39.46 2998.96 - 2000.30632 - - -
1843 Grid J-N / 13-16 0 0 - - - - -
1844 Main Bars 4 8" C/C 1 55 55 13.50 742.5 - 495.2475 - - -
1845 Dist Bars 4 8" C/C 1 96 96 39.46 552.44 - 368.47748 - - -
1846 Grid N-N1 / 15'-16 0 0 - - - - -
1847 Main Bars 4 7" C/C 1 14 14 69.88 3843.125 - 2563.364375 - - -
1848 Dist Bars 4 8" C/C 1 6 6 39.46 3788.16 - 2526.70272 - - -
1849 Grid J-N / 16-17 0 0 - - - - -
1850 Main Bars 4 8" C/C 1 31 31 8.00 112 - 74.704 - - -
1851 Dist Bars 4 8" C/C 1 98 98 10.13 60.75 - 40.52025 - - -
1852 Curve 0 0 - - - - -
1853 Grid J-K / 17-18 0 70.25 2177.75 - 1452.55925 - - -
1854 Main Bars 4 7" C/C 1 23 23 22.16 2171.68 - 1448.51056 - - -
1855 Dist Bars 4 8" C/C 1 26 26 0 - - - - -
1856 Grid K-L / 17-19 0 0 - - - - -
1857 Main Bars 4 7" C/C 1 57 57 12.94 297.62 - 198.51254 - - -
1858 Dist Bars 4 8" C/C 1 29 29 15.77 410.02 - 273.48334 - - -
1859 Grid L-M / 17-19 0 0 - - - - -
1860 Main Bars 4 7" C/C 1 59 59 17.00 969 - 646.323 - - -
1861 Dist Bars 4 8" C/C 1 24 24 32.00 928 - 618.976 - - -
1862 Grid M-N / 17-19 0 0 - - - - -
1863 Main Bars 4 7" C/C 1 53 53 18.58 1096.22 - 731.17874 - - -
1864 Dist Bars 4 8" C/C 1 21 21 35.63 855 - 570.285 - - -
1865 Extra Bars 0 0 - - - - -
1866 X-AXIS 0 18.54 982.62 - 655.40754 - - -
1867 Grid 13 / F-N 4 7" C/C 1 209 209 29.47 618.87 - 412.78629 - - -
1868 Grid 13 / F-G 3 12" C/C 1 4 4 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1869 Grid 13 / G-H 3 12" C/C 1 4 4 0 - - - - -
1870 Grid 13 / H-I 3 12" C/C 1 4 4 4.75 992.75 - 662.16425 - - -
1871 Grid 13 / I-J 3 12" C/C 1 4 4 6.33 25.336 9.501 - - - -
1872 Grid 13 / J-K 3 12" C/C 1 4 4 9.50 38 14.25 - - - -
1873 Grid 13 / K-L 3 12" C/C 1 4 4 9.58 38.32 14.37 - - - -
1874 Grid 13 / L-M 3 12" C/C 1 4 4 6.00 24 9 - - - -
1875 Grid 13 / M-N 3 12" C/C 1 4 4 8.66 34.64 12.99 - - - -
1876 Grid 15 / F-N 4 7" C/C 1 209 209 8.50 34 12.75 - - - -
1877 Grid 15 / F-G 3 12" C/C 1 13 13 7.58 30.32 11.37 - - - -
1878 Grid 15 / G-H 3 12" C/C 1 13 13 8.25 33 12.375 - - - -
1879 Grid 15 / H-I 3 12" C/C 1 13 13 13.25 2769.25 - 1847.08975 - - -
1880 Grid 15 / I-J 3 12" C/C 1 13 13 6.33 82.342 30.87825 - - - -
1881 Grid 15 / J-K 3 12" C/C 1 13 13 9.50 123.5 46.3125 - - - -
1882 Grid 15 / K-L 3 12" C/C 1 13 13 9.58 124.54 46.7025 - - - -
1883 Grid 15 / L-M 3 12" C/C 1 13 13 6.00 78 29.25 - - - -
1884 Grid 15 / M-N 3 12" C/C 1 13 13 8.66 112.58 42.2175 - - - -
1885 Grid 16 / F-J 4 7" C/C 1 103 103 8.50 110.5 41.4375 - - - -
1886 Grid 16 / F-G 3 12" C/C 1 5 5 7.58 98.54 36.9525 - - - -
1887 Grid 16 / G-H 3 12" C/C 1 5 5 8.25 107.25 40.21875 - - - -
1888 Grid 16 / H-I 3 12" C/C 1 5 5 5.42 558.26 - 372.35942 - - -
1889 Grid 16 / I-J 3 12" C/C 1 5 5 6.33 31.67 11.87625 - - - -
1890 Grid 16 / J-N 4 7" C/C 1 109 109 9.50 47.5 17.8125 - - - -
1891 Grid 16 / J-K 3 12" C/C 1 14 14 9.58 47.9 17.9625 - - - -
1892 Grid 16 / K-L 3 12" C/C 1 14 14 6.00 30 11.25 - - - -
1893 Grid 16 / L-M 3 12" C/C 1 14 14 14.16 1543.44 - 1029.47448 - - -
1894 Grid 16 / M-N 3 12" C/C 1 14 14 8.66 121.24 45.465 - - - -
1895 Grid 17 / J-K 4 6" C/C 1 38 38 8.50 119 44.625 - - - -
1896 Grid 17 / J-K 3 12" C/C 1 13 13 7.58 106.12 39.795 - - - -
1897 Grid 17 / K-L 4 6" C/C 1 36 36 8.25 115.5 43.3125 - - - -
1898 Grid 17 / K-L 3 12" C/C 1 18 18 13.88 527.44 - 351.80248 - - -
1899 Grid 17 / L-M 4 6" C/C 1 28 28 8.66 112.58 42.2175 - - - -
1900 Grid 17 / L-M 3 12" C/C 1 18 18 19.00 684 - 456.228 - - -
1901 Grid 17 / M-N 4 6" C/C 1 28 28 8.50 153 57.375 - - - -
1902 Grid 17 / M-N 3 12" C/C 1 17 17 19.00 532 - 354.844 - - -
1903 Y-AXIS 0 7.58 136.44 51.165 - - - -
1904 Grid F / 13-16 4 7" C/C 1 63 63 18.00 504 - 336.168 - - -
1905 Grid F / 13-15 3 12" C/C 1 4 4 8.25 140.25 52.59375 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1906 Grid F / 15-16 3 12" C/C 1 4 4 0 - - - - -
1907 Grid G / 13-16 4 7" C/C 1 63 63 6.25 393.75 - 262.63125 - - -
1908 Grid G / 13-15 3 12" C/C 1 11 11 10.25 41 15.375 - - - -
1909 Grid G / 15-16 3 12" C/C 1 11 11 11.00 44 16.5 - - - -
1910 Grid H / 13-16 4 7" C/C 1 63 63 10.96 690.48 - 460.55016 - - -
1911 Grid H / 13-15 3 12" C/C 1 14 14 10.25 112.75 42.28125 - - - -
1912 Grid H / 15-16 3 12" C/C 1 14 14 11.00 121 45.375 - - - -
1913 Grid I / 13-16 4 7" C/C 1 63 63 13.54 853.02 - 568.96434 - - -
1914 Grid I / 13-15 3 12" C/C 1 11 11 10.25 143.5 53.8125 - - - -
1915 Grid I / 15-16 3 12" C/C 1 11 11 11.00 154 57.75 - - - -
1916 Grid J / 13-16 4 7" C/C 1 63 63 10.96 690.48 - 460.55016 - - -
1917 Grid J / 13-15 3 12" C/C 1 10 10 10.25 112.75 42.28125 - - - -
1918 Grid J / 15-16 3 12" C/C 1 10 10 11.00 121 45.375 - - - -
1919 Grid K / 13-16 4 7" C/C 1 63 63 10.75 677.25 - 451.72575 - - -
1920 Grid K / 13-15 3 12" C/C 1 12 12 10.25 102.5 38.4375 - - - -
1921 Grid K / 15-16 3 12" C/C 1 12 12 9.00 90 33.75 - - - -
1922 Grid L / 13-16 4 7" C/C 1 63 63 12.93 814.59 - 543.33153 - - -
1923 Grid L / 13-15 3 12" C/C 1 11 11 10.25 123 46.125 - - - -
1924 Grid L / 15-16 3 12" C/C 1 11 11 9.00 108 40.5 - - - -
1925 Grid M / 13-16 4 7" C/C 1 63 63 11.46 721.98 - 481.56066 - - -
1926 Grid M / 13-15 3 12" C/C 1 10 10 10.25 112.75 42.28125 - - - -
1927 Grid M / 15-16 3 12" C/C 1 10 10 9.00 99 37.125 - - - -
1928 Grid N / 13-15' 4 7" C/C 1 56 56 10.12 637.56 - 425.25252 - - -
1929 Grid N / 13-15 3 12" C/C 1 4 4 10.25 102.5 38.4375 - - - -
1930 Grid N / 15'-16 4 7" C/C 1 7 7 9.00 90 33.75 - - - -
1931 Grid N / 15-16 3 12" C/C 1 4 4 8.19 458.64 - 305.91288 - - -
1932 Grid J / 16-17 4 7" C/C 1 35 35 10.25 41 15.375 - - - -
1933 Grid J / 16-17 3 12" C/C 1 4 4 12.85 89.95 - 59.99665 - - -
1934 Grid K / 16-17 4 7" C/C 1 35 35 9.00 36 13.5 - - - -
1935 Grid K /16-17 3 12" C/C 1 12 12 5.04 176.4 - 117.6588 - - -
1936 Grid L / 16-17 4 7" C/C 1 35 35 9.00 36 13.5 - - - -
1937 Grid L /16-17 3 12" C/C 1 11 11 12.93 452.55 - 301.85085 - - -
1938 Grid M / 16-17 4 7" C/C 1 35 35 9.00 108 40.5 - - - -
1939 Grid M / 16-17 3 12" C/C 1 10 10 11.46 401.1 - 267.5337 - - -
1940 Grid N / 16-17 4 7" C/C 1 35 35 9.00 99 37.125 - - - -
1941 Grid N / 16-17 3 12" C/C 1 4 4 10.12 354.2 - 236.2514 - - -
1942 Grid J-K / 17-19 4 6" C/C 1 39 39 9.00 90 33.75 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1943 Grid J / 17-18 3 12" C/C 1 5 5 3.91 136.85 - 91.27895 - - -
1944 Grid K-L / 17-19 4 6" C/C 1 37 37 9.00 36 13.5 - - - -
1945 Grid K /17-18 3 12" C/C 1 4 4 5.66 220.74 - 147.23358 - - -
1946 Grid L-M / 17-19 4 6" C/C 1 40 40 9.00 45 16.875 - - - -
1947 Grid L /17-18 3 12" C/C 1 8 8 8.00 296 - 197.432 - - -
1948 Grid N-M / 17-19 4 6" C/C 1 79 79 13.00 52 19.5 - - - -
1949 Grid M-N / 17-18 3 12" C/C 1 8 8 8.25 330 - 220.11 - - -
1950 Grid k / 17-18 4 6" C/C 1 62 62 12.00 96 36 - - - -
1951 B5 - Grid K - 17-18 3 12" C/C 1 11 11 4.25 335.75 - 223.94525 - - -
1952 Grid L / 17-19 4 6" C/C 1 62 62 16.00 128 48 - - - -
1953 B5 - Grid L - 17-19 3 12" C/C 1 11 11 12.93 801.66 - 534.70722 - - -
1954 Grid M / 17-19 4 6" C/C 1 66 66 10.00 110 41.25 - - - -
1955 B5 - Grid M - 17-19 3 12" C/C 1 10 10 11.46 710.52 - 473.91684 - - -
1956 Steel For projection 0 15.00 165 61.875 - - - -
1957 Main Bars 4 8" C/C 1 28 28 12.08 797.28 - 531.78576 - - -
1958 Dist Bars 3 1 1 1 14.50 145 54.375 - - - -
1959 Main Bars 4 8" C/C 1 34 34 0 - - - - -
1960 Dist Bars 3 1 1 1 1.25 35 - 23.345 - - -
1961 Main Bars 4 8" C/C 2 14 28 17.58 17.58 6.5925 - - - -
1962 Dist Bars 3 2 1 2 1.25 42.5 - 28.3475 - - -
1963 Main Bars 4 8" C/C 2 33 66 22.38 22.375 8.390625 - - - -
1964 Dist Bars 3 2 1 2 1.25 35 - 23.345 - - -
1965 Curve Main Bars 4 8" C/C 1 164 164 9.00 18 6.75 - - - -
1966 Dist Bars 3 1 1 1 1.25 82.5 - 55.0275 - - -
1967 Main Bars 4 8" C/C 1 130 130 22.50 45 16.875 - - 156 -
1968 Dist Bars 3 1 1 1 1.25 205 - 136.735 - - -
1969 Main Bars 4 8" C/C 1 34 34 111.55 111.55 41.83125 - - - -
1970 Dist Bars 3 1 1 1 1.25 162.5 - 108.3875 - - -
1971 For Windows 2' Projection 0 84.44 84.44 31.665 - - - -
1972 Main Bars 6 8 4 32 1.25 42.5 - 28.3475 - 915.9 -
1973 Stirrups 3 6" C/C 8 5 40 22.125 22.125 8.296875 - - 13.875 -
1974 Ramp Beams 0 0 - - - 142.5 -
1975 B1 0 3.25 104 - - - - -
1976 Grid 13 & 15 / B 1 - E1 0 2.170 86.8 32.55 - - - -
1977 Main Bars 6 2 5 10 0 - - - 262.5 -
1978 Extra Bars On Edge 6 2 1 2 0 - - - 42.75 -
1979 Extra Bars On Centers 6 10 1 10 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
1980 Stirrups 3 7" C/C 2 83 166 61.06 610.6 - - - - -
1981 B1 on curve 0 4.63 9.25 - - - 111.5625 -
1982 Main Bars 6 1 5 5 9.50 95 - - - 13.875 -
1983 Extra Bars On Centers 6 3 1 3 5.50 913 342.375 - - - -
1984 Stirrups 3 7" C/C 1 53 53 0 - - - - -
1985 Grid 14 / A1 - B1 0 35.00 175 - - - 333 -
1986 Main Bars 6 1 5 5 9.50 28.5 - - - 27.75 -
1987 Extra Bars On Edge 6 2 1 2 5.50 291.5 109.3125 - - 28.5 -
1988 Stirrups 3 7" C/C 1 19 19 0 - - - - -
1989 Grid B1 & E1 / 13 - 14 a 0 14.88 74.375 - - - - -
1990 Main Bars 6 2 6 12 4.63 9.25 - - - 915.9 -
1991 Extra Bars On Edge 6 4 1 4 5.50 104.5 39.1875 - - - -
1992 Extra Bars On Centers 6 2 1 2 0 - - - - -
1993 Stirrups 3 7" C/C 2 25 50 18.50 222 - - - 580.2 -
1994 ( CB ) on Grid 14 / B1 - E1 0 4.63 18.5 - - - - -
1995 Main Bars 6 2 5 10 9.50 19 - - - - -
1996 Stirrups 3 7" C/C 2 83 166 5.50 275 103.125 - - - -
( CB ) on Grid B2,C1,C2 & D2 / 13 - 14 & 14 -
1997 15 0 0 - - - - -
1998 Main Bars 6 8 5 40 61.06 610.6 - - - - -
1999 Stirrups 3 7" C/C 8 13 104 3.16 524.56 196.71 - - - -
2000 Ramp Slab Steel 0 0 - - - - -
2001 Grid 14 - 14a / B1 - E1 0 9.67 386.8 - - - - -
2002 Main Bars 4 10" C/C 2 61 122 3.16 328.64 123.24 - - - -
2003 Dist Bars 4 10" C/C 2 9 18 0 - - - - -
2004 Curve 0 0 - - - - -
2005 Main Bars 4 10" C/C 2 13 26 8.75 1067.5 - 712.0225 - - -
2006 Dist Bars 4 10" C/C 2 18 36 59.00 1062 - 708.354 - - -
2007 Extra Bars 0 0 - - - - -
2008 On Grid 14a 4 10" C/C 2 61 122 14.125 367.25 - 244.95575 - - -
2009 On Grid B2 , C1 , C2 , E1 4 10" C/C 8 9 72 10.71 385.56 - 257.16852 - - -
2010 On Grid B1 4 10" C/C 4 9 36 0 - - - - -
2011 Extra Bars 0 2.50 305 - 203.435 - - -
2012 On Edges 4 10" C/C 2 29 58 7.50 540 - 360.18 - - -
2013 On Grid 14 4 10" C/C 1 12 12 7.50 270 - 180.09 - - -
2014 Temperatures Bars 0 0 - - - - -
2015 On Grid E1 3 12" C/C 2 3 6 3.33 193.14 - 128.82438 - - -
2016 On Grid E , C2 , C1 , B2 / 14 - 14a 3 12" C/C 8 6 48 5.88 70.5 - 47.0235 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2017 On Grid B1 3 12" C/C 4 3 12 0 - - - - -
2018 on curve external 3 12" C/C 2 2 4 5.00 30 11.25 - - - -
2019 Grid 15 - 16 / E1 - F 0 5.00 240 90 - - - -
2020 Main Bars 4 8" C/C 1 28 28 5.00 60 22.5 - - - -
2021 Dist Bars 4 8" C/C 1 14 14 10.17 40.68 15.255 - - - -
2022 Extra Bars 0 0 - - - 36 -
2023 On Grid E1 4 7" C/C 1 32 32 12.00 336 - 224.112 - - -
2024 On Grid 15 & 16 4 7" C/C 1 15 15 21.29 298.06 - 198.80602 - - -
2025 Stairs in Basement to G.F Grid N - N1 0 0 - - - - -
2026 Beam 0 12.00 384 - 256.128 - - -
2027 Main Bars 6 1 6 6 21.29 319.35 - 213.00645 - - -
2028 Stirrups 3 6" C/C 1 9 9 0 - - - - -
2029 ( Stairs up to landing ) Main Bars 4 7" C/C 1 8 8 0 - - - - -
2030 Dist Bars 3 9" C/C 1 20 20 4.00 24 - - - - -
2031 Extra Bars 4 7" C/C 1 8 8 3.00 27 10.125 - - - -
2032 Dist Bars 3 9" C/C 1 5 5 17.625 141 - 94.047 - - -
2033 Landing 0 4.00 80 30 - - - -
2034 Main Bars T & B 4 7" C/C 2 15 30 4.000 32 - 21.344 - - -
2035 Dist Bars 4 7" C/C 2 8 16 4.000 20 7.5 - - - -
2036 Dist Bars 3 9" C/C 2 5 10 0 - - - - -
2037 ( Stairs up to G.F Slab ) Main Bars 4 7" C/C 1 8 8 7.00 210 - 140.07 - - -
2038 Dist Bars 3 9" C/C 1 20 20 9.33 149.28 - 99.56976 - - -
2039 Stairs in 1st Portion G.F to F.F Grid D - F 0 4.50 45 16.875 - - - -
2040 ( Stairs up to 1st landing ) Main Bars 4 7" C/C 1 10 10 14.375 115 - 76.705 - - -
2041 Dist Bars 3 9" C/C 1 15 15 4.50 90 33.75 - - - -
2042 Dist Bars 3 9" C/C 1 5 5 0 - - - - -
2043 Extra bars 4 7" C/C 1 10 10 16.25 162.5 - 108.3875 - - -
2044 Dist Bars 3 9" C/C 1 5 5 5.25 78.75 29.53125 - - - -
2045 Extra bars 4 7" C/C 1 13 13 5.25 26.25 9.84375 - - - -
2046 Dist Bars 3 9" C/C 1 5 5 10.00 100 - 66.7 - - -
2047 1st Landing - 2nd Landing 0 5.25 26.25 9.84375 - - - -
2048 Main Bars 4 7" C/C 1 13 13 8.00 104 - 69.368 - - -
2049 Dist Bars 3 9" C/C 1 12 12 7.00 35 13.125 - - - -
2050 Extra bars 4 7" C/C 1 13 13 0 - - - - -
2051 Dist Bars 3 9" C/C 1 5 5 19.10 248.3 - 165.6161 - - -
2052 Extra bars 4 7" C/C 1 10 10 7.00 84 31.5 - - - -
2053 Dist Bars 3 9" C/C 1 5 5 9.42 122.46 - 81.68082 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2054 2nd Landing - F.F 4 7" C/C 1 10 10 7.00 35 13.125 - - - -
2055 Dist Bars 3 9" C/C 1 16 16 10.00 100 - 66.7 - - -
2056 Dist Bars 3 9" C/C 1 5 5 5.25 26.25 9.84375 - - - -
2057 Stairs in Ist Portion G.F - F.F Grid N - N1 0 18.58 185.8 - 123.9286 - - -
2058 ( Stairs up to landing ) Main Bars 4 7" C/C 1 8 8 5.25 84 31.5 - - - -
2059 Dist Bars 3 9" C/C 1 20 20 5.25 26.25 9.84375 - - - -
2060 Dist Bars 3 9" C/C 1 5 5 0 - - - - -
2061 Landing 0 17.625 141 - 94.047 - - -
2062 Main Bars T & B 4 7" C/C 2 15 30 4.58 91.6 34.35 - - - -
2063 Dist Bars 4 7" C/C 2 8 16 4.58 22.9 8.5875 - - - -
2064 Dist Bars 3 9" C/C 2 5 10 0 - - - - -
2065 ( Stairs up to 1st Floor ) Main Bars 4 7" C/C 1 8 8 7.00 210 - 140.07 - - -
2066 Dist Bars 3 9" C/C 1 20 20 9.33 149.28 - 99.56976 - - -
2067 Dist Bars 3 9" C/C 1 5 5 4.75 47.5 17.8125 - - - -
2068 Stairs in 2nd Portion G.F to F.F Grid J - K /11 - 12 0 14.625 117 - 78.039 - - -
2069 ( Stairs up to 1st landing ) Main Bars 4 7" C/C 1 11 11 4.58 91.6 34.35 - - - -
2070 Dist Bars 3 9" C/C 1 15 15 4.58 22.9 8.5875 - - - -
2071 Dist Bars 3 9" C/C 1 5 5 0 - - - - -
2072 Landing 0 16.96 186.56 - 124.43552 - - -
2073 Extra Bars 4 7" C/C 1 11 11 6.00 90 33.75 - - - -
2074 Dist Bars 3 9" C/C 1 5 5 6.00 30 11.25 - - - -
2075 Extra Bars 4 7" C/C 1 14 14 0 - - - - -
2076 Dist Bars 3 9" C/C 1 5 5 9.75 107.25 - 71.53575 - - -
2077 1st Landing - 2nd Landing 0 6.00 30 11.25 - - - -
2078 Main Bars 4 7" C/C 1 14 14 9.00 126 - 84.042 - - -
2079 Dist Bars 3 9" C/C 1 12 12 7.66 38.3 14.3625 - - - -
2080 Extra bars 4 7" C/C 1 14 14 0 - - - - -
2081 Dist Bars 3 9" C/C 1 5 5 20.35 284.9 - 190.0283 - - -
2082 Extra bars 4 7" C/C 1 11 11 7.66 91.92 34.47 - - - -
2083 Dist Bars 3 9" C/C 1 5 5 9.00 126 - 84.042 - - -
2084 2nd Landing - F.F 4 7" C/C 1 11 11 7.66 38.3 14.3625 - - 130.5 -
2085 Dist Bars 3 9" C/C 1 15 15 9.75 107.25 - 71.53575 - - -
2086 Dist Bars 3 9" C/C 1 5 5 6.00 30 11.25 - - - -
2087 Stairs in 2nd Portion G.F to F.F Grid G - H & H - I / 5 - 7 0 18.09 198.99 - 132.72633 - - -
2088 Beams 0 6.00 90 33.75 - - - -
2089 Main Bars 6 2 6 12 6.00 30 11.25 - - - -
2090 Stirrups 3 6" C/C 2 14 28 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2091 ( Stairs up to 1st landing ) Main Bars 4 7" C/C 2 13 26 0 - - - - -
2092 Dist Bars 3 9" C/C 2 15 30 7.25 87 - - - - -
2093 Extra Bars 4 7" C/C 2 13 26 4.50 126 47.25 - - - -
2094 Dist Bars 3 9" C/C 2 5 10 15.95 414.7 - 276.6049 - - -
2095 Landing 0 7.25 217.5 81.5625 - - - -
2096 Extra Bars 4 7" C/C 2 13 26 4.75 123.5 - 82.3745 - - -
2097 Dist Bars 3 9" C/C 2 5 10 7.25 72.5 27.1875 - - - -
2098 Extra Bars 4 7" C/C 2 10 20 0 - - - - -
2099 Dist Bars 3 9" C/C 2 5 10 8.75 227.5 - 151.7425 - - -
2100 1st Landing - 2nd Landing 0 7.25 72.5 27.1875 - - - -
2101 Main Bars 4 7" C/C 2 10 20 8.75 175 - 116.725 - - -
2102 Dist Bars 3 9" C/C 2 5 10 5.75 57.5 21.5625 - - - -
2103 Extra bars 4 7" C/C 2 10 20 0 - - - - -
2104 Dist Bars 3 9" C/C 2 5 10 22.85 457 - 304.819 - - -
2105 Extra bars 4 7" C/C 2 10 20 5.75 57.5 21.5625 - - - -
2106 Dist Bars 3 9" C/C 2 5 10 10.25 205 - 136.735 - - -
2107 2nd Landing - F.F 4 7" C/C 2 13 26 5.75 57.5 21.5625 - - - -
2108 Dist Bars 3 9" C/C 2 15 30 10.25 205 - 136.735 - - -
2109 Dist Bars 3 9" C/C 2 5 10 5.75 57.5 21.5625 - - - -
2110 Stairs in 2nd Portion G.F to F.F Grid G - H & H - I / 1 - 2 0 16.18 420.68 - 280.59356 - - -
2111 ( Stairs up to landing ) Main Bars 4 7" C/C 2 8 16 7.25 217.5 81.5625 - - - -
2112 Dist Bars 3 9" C/C 2 20 40 7.25 72.5 27.1875 - - - -
2113 Extra bars 4 7" C/C 2 8 16 0 - - - - -
2114 Dist Bars 3 9" C/C 2 5 10 19.130 306.08 - 204.15536 - - -
2115 Landing 0 4.58 183.2 68.7 - - - -
2116 Main Bars T & B 4 7" C/C 2 8 16 7.25 116 - 77.372 - - -
2117 Extra bars 4 7" C/C 2 8 16 4.58 45.8 17.175 - - - -
2118 Dist Bars 3 9" C/C 2 5 10 0 - - - - -
2119 ( Stairs up to 1st Floor ) Main Bars 4 7" C/C 1 8 8 9.50 152 - 101.384 - - -
2120 Dist Bars 3 9" C/C 2 20 40 7.25 116 - 77.372 - - -
2121 Dist Bars 3 9" C/C 2 5 10 4.58 45.8 17.175 - - - -
2122 Steel For Lifts G.Floor 0 14.625 117 - 78.039 - - -
2123 Lifts 6' x 9' 0 4.58 183.2 68.7 - - - -
2124 Long Walls 0 4.58 45.8 17.175 - - - -
2125 Main Bars 4 9" C/C 8 15 120 0 - - - - -
2126 Dist Bars 3 9" C/C 8 10 80 0 - - - - -
2127 Short Walls 0 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2128 Main Bars 4 9" C/C 8 10 80 15.790 1894.8 - 1263.8316 - - -
2129 Dist Bars 3 9" C/C 8 10 80 11.25 900 337.5 - - - -
2130 Lifts 7'-3" x 6'-7.5" 0 0 - - - - -
2131 Long Walls 0 15.790 1263.2 - 842.5544 - - -
2132 Main Bars 4 9" C/C 8 13 104 8.25 660 247.5 - - - -
2133 Dist Bars 3 9" C/C 8 10 80 0 - - - - -
2134 Short Walls 0 0 - - - - -
2135 Main Bars 4 9" C/C 8 11 88 15.790 1642.16 - 1095.32072 - - -
2136 Dist Bars 3 9" C/C 8 10 80 9.00 720 270 - - - -
2137 Doors Lintel Beam ( Basement ) 0 0 - - - - -
2138 D 0 15.790 1389.52 - 926.80984 - - -
2139 Main Bars 4 9" C/C 2 7 14 8.375 670 251.25 - - - -
2140 Stirrups 3 9" C/C 2 9 18 0 - - - - -
2141 D1 0 0 - - - - -
2142 Main Bars 4 9" C/C 4 7 28 6.5 91 - 60.697 - - -
2143 Stirrups 3 9" C/C 4 8 32 2.5 45 16.875 - - - -
2144 D2 0 0 - - - - -
2145 Main Bars 4 9" C/C 2 7 14 5.5 154 - 102.718 - - -
2146 Stirrups 3 9" C/C 2 7 14 2.5 80 30 - - - -
2147 D3 0 0 - - - 521.25 -
2148 Main Bars 4 9" C/C 3 7 21 4.5 63 - 42.021 - - -
2149 Stirrups 3 9" C/C 3 6 18 2.5 35 13.125 - - 128.25 -
2150 Ground Floor Beams 2nd Portion 0 0 - - - 144 -
2151 Grid 1 / D-G ( B4 ) 0 4 84 - 56.028 - - 21.36
2152 Main Bars 6 1 10 10 2.5 45 16.875 - - - -
2153 Main Bars 4 1 2 2 0 - - - - -
2154 Extra Bars On Edge 6 2 6 12 0 - - - 457.38 -
2155 Extra Bars On Centers 6 1 6 6 34.75 347.5 - - - 55.125 -
2156 Spacer Bars 8 1 8 8 33.25 66.5 - 44.3555 - 65.25 -
2157 Stirrups 3 4" & 6" 1 75 75 7.125 85.5 - - - - -
2158 Grid 1' / G-I ( B3 ) 0 16.00 96 - - - - -
2159 Main Bars 6 1 7 7 1.00 8 - - - 912.1875 -
2160 Extra Bars On Edge 6 2 3 6 6.08 456 171 - - 55.125 -
2161 Extra Bars On Centers 6 1 3 3 0 - - - 252 -
2162 Stirrups 3 5" & 8" 1 72 72 43.56 304.92 - - - - -
2163 Grid 1 / I-N ( B3 ) 0 6.125 36.75 - - - - -
2164 Main Bars 6 1 7 7 14.50 43.5 - - - 2709 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2165 Extra Bars On Edge 6 2 3 6 6.08 437.76 164.16 - - 220.5 -
2166 Extra Bars On Centers 6 4 3 12 0 - - - 504 -
2167 Stirrups 3 5" & 8" 1 155 155 86.875 608.125 - - - 540 -
2168 Grid 2,4,5,7,8,10,11&12 / A-C ( B3 ) 0 6.125 36.75 - - - - -
2169 Main Bars 6 8 7 56 14.00 168 - - - - -
2170 Extra Bars On Edge 6 8 3 24 6.08 942.4 353.4 - - 5827.5 -
2171 Extra Bars On Centers 6 8 3 24 0 - - - - -
2172 Extra Bars On Centers 6 8 3 24 32.25 1806 - - - 283.5 -
2173 Stirrups 3 5" & 8" 8 57 456 6.125 147 - - - 504 -
2174 Grid 2,4,5,7,8,10&11 / C-G ( B4 ) 0 14.00 336 - - - - 242.97
2175 Main Bars 6 7 10 70 15.00 360 - - - - -
2176 Main Bars 4 7 2 14 6.08 2772.48 1039.68 - - - -
2177 Extra Bars On Edge 6 7 3 21 0 - - - 2339.4 -
2178 Extra Bars On Centers 6 7 3 21 55.50 3885 - - - 137.8125 -
2179 Spacer Bars 8 7 13 91 55.00 770 - 513.59 - 337.5 -
2180 Stirrups 3 4" & 6" 7 129 903 9.000 189 - - - 315 -
2181 Grid 2,4,5,7 & 8 / G-I ( B3 ) 0 16.00 336 - - - - -
2182 Main Bars 6 5 7 35 1.00 91 - - - - -
2183 Extra Bars On Edge 6 5 3 15 6.08 5490.24 2058.84 - - 3039.75 -
2184 Extra Bars On Centers 6 5 3 15 0 - - - 220.5 -
2185 Extra Bars On Centers 6 5 3 15 44.56 1559.6 - - - 756 -
2186 Stirrups 3 5" & 8" 5 75 375 6.125 91.875 - - - - -
2187 Grid 3,4,6 & 7 / J-N ( B3 ) 0 15.00 225 - - - - -
2188 Main Bars 6 4 7 28 14.00 210 - - - 912.1875 -
2189 Extra Bars On Edge 6 8 3 24 6.08 2280 855 - - 55.125 -
2190 Extra Bars On Centers 6 12 3 36 0 - - - 252 -
2191 Stirrups 3 5" & 8" 4 131 524 72.38 2026.5 - - - - -
2192 Grid 9 / I-N ( B3 ) 0 6.13 147 - - - - -
2193 Main Bars 6 1 7 7 14.00 504 - - - 280.875 -
2194 Extra Bars On Edge 6 2 3 6 6.08 3185.92 1194.72 - - 63 -
2195 Extra Bars On Centers 6 4 3 12 0 - - - 0 -
2196 Stirrups 3 5" & 8" 1 155 155 86.88 608.125 - - - - -
2197 Grid 12 / E-G ( B3 ) 0 6.13 36.75 - - - - -
2198 Main Bars 6 1 7 7 14.00 168 - - - 2691.99 -
2199 Extra Bars On Edge 6 1 3 3 6.08 942.4 353.4 - - 55.125 -
2200 Extra Bars On Edge 6 0 3 0 0 - - - 882 -
2201 Stirrups 3 5" 1 50 50 26.750 187.25 - - - 0 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2202 Grid 11 & 12 / G-N ( B3 ) 0 14.00 42 - - - - -
2203 Main Bars 6 2 7 14 15.83 0 - - - - -
2204 Extra Bars On Edge 6 2 3 6 6.08 304 114 - - - -
2205 Extra Bars On Centers 6 2 21 42 0 - - - 624.375 -
2206 Extra Bars On Centers 6 0 3 0 128.190 1794.66 - - - 128.25 -
2207 Stirrups 3 5" & 8" 2 244 488 6.125 36.75 - - - - -
2208 Y-AXIS 0 14.00 588 - - - - -
2209 Grid A / 2 - 4, 8-10, 11-12 ( B2 ) 0 15.00 0 - - - 210.375 -
2210 Main Bars 6 3 6 18 6.08 2967.04 1112.64 - - 42.75 -
2211 Extra Bars On Edge 6 3 4 12 0 - - - - -
2212 Stirrups 3 5" & 8" 3 40 120 0 - - - - -
2213 Grid A / 5 - 7 ( B2 ) 0 23.125 416.25 - - - 1732.5 -
2214 Main Bars 6 1 6 6 7.125 85.5 - - - - -
2215 Extra Bars On Edge 6 1 4 4 6.08 729.6 273.6 - - 256.5 -
2216 Stirrups 3 5" & 8" 1 41 41 0 - - - 504 -
2217 Grid B & C / 2 - 7 ( B4 ) 0 23.375 140.25 - - - - 74.76
2218 Main Bars 6 2 10 20 7.125 28.5 - - - - -
2219 Main Bars 4 2 2 4 6.08 249.28 93.48 - - - -
2220 Extra Bars On Edge 6 2 12 24 0 - - - 1725 -
2221 Extra Bars On Centers 6 2 6 12 57.750 1155 - - - - -
2222 Spacer Bars 8 2 14 28 56.250 225 - 150.075 - 256.5 -
2223 Stirrups 3 4" & 6" 2 132 264 7.125 171 - - - 504 -
2224 Grid B & C / 8 - 12 ( B4 ) 0 28.00 336 - - - - 64.08
2225 Main Bars 6 2 10 20 1.00 28 - - - - -
2226 Main Bars 4 2 2 4 6.08 1605.12 601.92 - - - -
2227 Extra Bars On Edge 6 2 12 24 0 - - - 228.75 -
2228 Extra Bars On Centers 6 2 6 12 57.500 1150 - - - - -
2229 Spacer Bars 8 2 12 24 56.000 224 - 149.408 - 123.75 -
2230 Stirrups 3 4" & 6" 1 132 132 7.125 171 - - - - -
2231 Grid D / 1 - 2 ( B4 ) 0 28.00 336 - - - - -
2232 Main Bars 6 1 10 10 1.00 24 - - - 2062.5 -
2233 Main Bars 4 1 2 2 6.08 802.56 300.96 - - - -
2234 Extra Bars On Edge 6 1 6 6 0 - - - 128.25 -
2235 Stirrups 3 4" 1 34 34 15.250 152.5 - - - 144 -
2236 Grid E / 1 - 12 ( B4 ) 0 13.750 27.5 - 18.3425 - 756 -
2237 Main Bars 6 1 10 10 13.750 82.5 - - - - 117.48
2238 Main Bars 4 1 2 2 6.08 206.72 77.52 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2239 Extra Bars On Edge 6 1 12 12 0 - - - - -
2240 Extra Bars On Centers 6 1 6 6 137.500 1375 - - - 2403.75 -
2241 Extra Bars On Centers 6 1 18 18 134.500 269 - 179.423 - - -
2242 Spacer Bars 8 1 44 44 7.125 85.5 - - - 128.25 -
2243 Stirrups 3 4" & 6" 1 325 325 16.00 96 - - - 1440 -
2244 Grid G & I / 1 - 8 ( B4 ) 0 28.00 504 - - - - 138.84
2245 Main Bars 6 2 10 20 1.00 44 - - - - -
2246 Main Bars 4 2 2 4 6.08 1976 741 - - - -
2247 Extra Bars On Edge 6 2 6 12 0 - - - 1016.25 -
2248 Extra Bars On Centers 6 2 30 60 80.125 1602.5 - - - - -
2249 Spacer Bars 8 2 26 52 78.875 315.5 - 210.4385 - 168 -
2250 Stirrups 3 4" & 6" 2 193 386 7.125 85.5 - - - - 53.4
2251 Grid G & I / 8 - 11 ( B4C ) 0 16.00 960 - - - - -
2252 Main Bars 6 2 10 20 1.00 52 - - - - -
2253 Main Bars 4 2 2 4 6.08 2346.88 880.08 - - 675 -
2254 Extra Bars On Centers 6 2 2 4 0 - - - - -
2255 Spacer Bars 8 2 10 20 33.875 677.5 - - - 128.25 -
2256 Stirrups 3 4" & 6" 2 81 162 33.875 135.5 - 90.3785 - 0 -
2257 Grid G & I / 11 - 12 ( B4 ) 0 28.00 112 - - - - 37.38
2258 Main Bars 6 2 10 20 1.00 20 - - - - -
2259 Main Bars 4 2 2 4 6.08 984.96 369.36 - - - -
2260 Extra Bars On Edge 6 2 6 12 0 - - - 1156.875 -
2261 Extra Bars On Centers 6 0 6 0 22.500 450 - - - - -
2262 Spacer Bars 8 2 7 14 21.750 87 - 58.029 - 128.25 -
2263 Stirrups 3 2 51 102 7.125 85.5 - - - 576 -
2264 Grid H / 1' - 8 ( B4 ) 0 16.00 0 - - - - 53.4
2265 Main Bars 6 1 10 10 1.00 14 - - - - -
2266 Main Bars 4 1 2 2 6.08 620.16 232.56 - - - -
2267 Extra Bars On Edge 6 2 6 12 0 - - - 346.875 -
2268 Extra Bars On Centers 6 4 6 24 77.125 771.25 - - - - -
2269 Spacer Bars 8 1 20 20 75.125 150.25 - 100.21675 - 128.25 -
2270 Stirrups 3 4" & 6" 1 186 186 7.125 85.5 - - - - -
2271 Grid H / 11 - 12 ( B4 ) 0 16.00 384 - - - - -
2272 Main Bars 6 1 10 10 1.00 20 - - - 10312.5 -
2273 Main Bars 4 1 2 2 6.08 1130.88 424.08 - - - -
2274 Extra Bars On Edge 6 2 6 12 0 - - - 641.25 -
2275 Stirrups 3 1 51 51 23.125 231.25 - - - 4320 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2276 Grid J,K,L,M & N / 1 - 12 ( B4 ) 0 21.625 43.25 - 28.84775 - - 707.55
2277 Main Bars 6 5 10 50 7.125 85.5 - - - - -
2278 Main Bars 4 5 2 10 6.08 310.08 116.28 - - - -
2279 Extra Bars On Edge 6 5 12 60 0 - - - - -
2280 Extra Bars On Centers 6 5 36 180 137.500 6875 - - - 687.75 -
2281 Spacer Bars 8 5 53 265 134.500 1345 - 897.115 - 51.75 -
2282 Stirrups 3 4" & 6" 5 319 1595 7.125 427.5 - - - 173.25 -
2283 Right Side porch 0 16.00 2880 - - - - -
2284 Grid 11 & 12 / N - P ( B3 ) 0 1.00 265 - - - - -
2285 Main Bars 6 2 7 14 6.08 9697.6 3636.6 - - 208.125 -
2286 Extra Bars On Edge 6 2 3 6 0 - - - 40.5 -
2287 Extra Bars On Centers 6 2 3 6 0 - - - - -
2288 Stirrups 3 5" & 8" 2 58 116 32.750 458.5 - - - - -
2289 Grid P / 11 - 12 ( B2 ) 0 5.750 34.5 - - - - -
2290 Main Bars 6 1 6 6 19.250 115.5 - - - 546.1875 -
2291 Extra Bars On Edge 6 1 4 4 6.08 705.28 264.48 - - - -
2292 Stirrups 3 5" & 8" 1 37 37 0 - - - - -
2293 Concelled Beams 0 23.125 138.75 - - - - -
2294 Grid F / 2 - 12 0 6.750 27 - - - 60.1875 -
2295 Main Bars 6 1 3 3 6.08 224.96 84.36 - - - -
2296 Main Bars 4 1 2 2 0 - - - - -
2297 Stirrups 3 9" 1 155 155 0 - - - - -
2298 Grid F / 1 - 2 (Depressed) 0 121.375 364.125 - - - 98.4375 -
2299 Main Bars 6 1 3 3 118.875 237.75 - 158.57925 - - -
2300 Main Bars 4 1 2 2 3.160 489.8 183.675 - - - -
2301 Stirrups 3 9" 1 16 16 0 - - - - -
2302 Grid E' / 2 - 4 (Depressed) 0 13.375 40.125 - - - 115.3125 -
2303 Main Bars 6 1 3 3 13.375 26.75 - 17.84225 - - -
2304 Main Bars 4 1 2 2 4.000 64 24 - - - -
2305 Stirrups 3 9" 1 27 27 0 - - - - -
2306 Grid 3 / E - G (Depressed) 0 21.875 65.625 - - - 98.4375 -
2307 Main Bars 6 1 3 3 21.875 43.75 - 29.18125 - - -
2308 Main Bars 4 1 2 2 4.000 108 40.5 - - - -
2309 Stirrups 3 9" 1 32 32 0 - - - - -
2310 Grid E' / 5 - 7 (Depressed) 0 25.625 76.875 - - - 115.3125 -
2311 Main Bars 6 1 3 3 25.625 51.25 - 34.18375 - - -
2312 Main Bars 4 1 2 2 4.000 128 48 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2313 Stirrups 3 9" 1 27 27 0 - - - - -
2314 Grid 6 / E - G (Depressed) 0 21.875 65.625 - - - 164.0625 -
2315 Main Bars 6 1 3 3 21.875 43.75 - 29.18125 - - -
2316 Main Bars 4 1 2 2 4.000 108 40.5 - - - -
2317 Stirrups 3 9" 1 32 32 0 - - - 192.1875 -
2318 Grid E' / 8 - 10 (Depressed) 0 25.625 76.875 - - - - -
2319 Main Bars 6 1 5 5 25.625 51.25 - 34.18375 - - -
2320 Stirrups 3 9" 1 27 27 4.000 128 48 - - 164.0625 -
2321 Grid 9 / E - G (Depressed) 0 0 - - - - -
2322 Main Bars 6 1 5 5 21.875 109.375 - - - - -
2323 Stirrups 3 9" 1 32 32 4.000 108 40.5 - - 192.1875 -
2324 Grid E' / 11 - 12 (Depressed) 0 0 - - - - -
2325 Main Bars 6 1 5 5 25.625 128.125 - - - - -
2326 Stirrups 3 9" 1 27 27 4.000 128 48 - - 98.235 -
2327 Grid 11' / E - G (Depressed) 0 0 - - - - -
2328 Main Bars 6 1 5 5 21.875 109.375 - - - - -
2329 Stirrups 3 9" 1 32 32 4.000 108 40.5 - - - -
2330 Grid 2 / J - K (Depressed) 0 0 - - - 234.18 -
2331 Main Bars 6 1 3 3 25.625 128.125 - - - - -
2332 Main Bars 4 1 2 2 4.000 128 48 - - - -
2333 Stirrups 3 9" 1 25 25 0 - - - - -
2334 Grid 7' / K - N 0 21.830 65.49 - - - 99.5625 -
2335 Main Bars 6 1 3 3 21.830 43.66 - 29.12122 - - -
2336 Main Bars 4 1 2 2 4.000 100 37.5 - - - -
2337 Stirrups 3 9" 1 66 66 0 - - - - -
2338 Grid J' / 4 - 6 0 52.040 156.12 - - - 99.5625 -
2339 Main Bars 6 1 3 3 52.040 104.08 - 69.42136 - - -
2340 Main Bars 4 1 2 2 3.160 208.56 78.21 - - - -
2341 Stirrups 3 9" 1 27 27 0 - - - - -
2342 Grid K' / 4 - 6 0 22.125 66.375 - - - 300.9375 -
2343 Main Bars 6 1 3 3 22.125 44.25 - 29.51475 - - -
2344 Main Bars 4 1 2 2 3.160 85.32 31.995 - - - -
2345 Stirrups 3 9" 1 27 27 0 - - - - -
2346 Grid M' / 7 - 12 0 22.125 66.375 - - - - -
2347 Main Bars 6 1 3 3 22.125 44.25 - 29.51475 - - -
2348 Main Bars 4 1 2 2 3.160 85.32 31.995 - - - -
2349 Stirrups 3 9" 1 82 82 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2350 Ground Floor Slab 2nd Portion 0 66.875 200.625 - - - - -
2351 S1 0 66.875 133.75 - 89.21125 - - -
2352 Grid D-E / 1-2 0 3.160 259.12 97.17 - - - -
2353 Main Bars 4 8" C/C 1 18 18 0 - - - - -
2354 Dist Bars 4 8" C/C 1 10 10 0 - - - - -
2355 S1 0 0 - - - - -
2356 Grid E-G / 1-2 0 8.29 149.22 - 99.52974 - - -
2357 Main Bars 4 8" C/C 1 37 37 13.54 135.4 - 90.3118 - - -
2358 Dist Bars 4 8" C/C 1 18 18 0 - - - - -
2359 S4 0 0 - - - - -
2360 Grid A-B / 2-4 0 13.54 500.98 - 334.15366 - - -
2361 Main Bars 4 8" C/C 1 30 30 26 468 - 312.156 - - -
2362 Dist Bars 4 10" C/C 1 12 12 0 - - - - -
2363 S1 0 0 - - - - -
2364 Grid B-C / 2-4 0 11.92 357.6 - 238.5192 - - -
2365 Main Bars 4 8" C/C 1 30 30 21.71 260.52 - 173.76684 - - -
2366 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
2367 S2 0 0 - - - - -
2368 Grid C-E / 2-4 0 20.5 615 - 410.205 - - -
2369 Main Bars 4 7" C/C 1 44 44 21.71 607.88 - 405.45596 - - -
2370 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
2371 S1 0 0 - - - - -
2372 Grid E-G / 2-4 0 21.71 955.24 - 637.14508 - - -
2373 Main Bars 4 8" C/C 1 37 37 27.5 825 - 550.275 - - -
2374 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
2375 S1 0 0 - - - - -
2376 Grid G-H / 2-4 0 21.71 803.27 - 535.78109 - - -
2377 Main Bars 4 8" C/C 1 30 30 25.83 774.9 - 516.8583 - - -
2378 Dist Bars 4 8" C/C 1 29 29 0 - - - - -
2379 S1 0 0 - - - - -
2380 Grid H-I / 2-4 0 20.9 627 - 418.209 - - -
2381 Main Bars 4 8" C/C 1 30 30 21.71 629.59 - 419.93653 - - -
2382 Dist Bars 4 8" C/C 1 29 29 0 - - - - -
2383 S4 0 0 - - - - -
2384 Grid B-C / 4-5 0 20.92 627.6 - 418.6092 - - -
2385 Main Bars 4 8" C/C 1 29 29 21.71 629.59 - 419.93653 - - -
2386 Dist Bars 4 10" C/C 1 13 13 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2387 S2 0 0 - - - - -
2388 Grid C-E / 4-5 0 12.5 362.5 - 241.7875 - - -
2389 Main Bars 4 7" C/C 1 44 44 20.875 271.375 - 181.007125 - - -
2390 Dist Bars 4 8" C/C 1 16 16 0 - - - - -
2391 S4 0 0 - - - - -
2392 Grid E-G / 4-5 0 12.5 550 - 366.85 - - -
2393 Main Bars 4 8" C/C 1 37 37 27.5 440 - 293.48 - - -
2394 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2395 S4 0 0 - - - - -
2396 Grid G-H / 4-5 0 12.5 462.5 - 308.4875 - - -
2397 Main Bars 4 8" C/C 1 29 29 26 338 - 225.446 - - -
2398 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2399 S4 0 0 - - - - -
2400 Grid H-I / 4-5 0 12.5 362.5 - 241.7875 - - -
2401 Main Bars 4 8" C/C 1 29 29 20.89 271.57 - 181.13719 - - -
2402 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2403 S4 0 0 - - - - -
2404 Grid A-B / 5-7 0 12.5 362.5 - 241.7875 - - -
2405 Main Bars 4 8" C/C 1 31 31 20.92 271.96 - 181.39732 - - -
2406 Dist Bars 4 10" C/C 1 12 12 0 - - - - -
2407 S1 0 0 - - - - -
2408 Grid B-C / 5-7 0 11.92 369.52 - 246.46984 - - -
2409 Main Bars 4 8" C/C 1 31 31 22 264 - 176.088 - - -
2410 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
2411 S2 0 0 - - - - -
2412 Grid C-E / 5-7 0 20.5 635.5 - 423.8785 - - -
2413 Main Bars 4 7" C/C 1 44 44 22.125 619.5 - 413.2065 - - -
2414 Dist Bars 4 8" C/C 1 31 31 0 - - - - -
2415 S1 0 0 - - - - -
2416 Grid E-G / 5-7 0 22.125 973.5 - 649.3245 - - -
2417 Main Bars 4 8" C/C 1 37 37 27.5 852.5 - 568.6175 - - -
2418 Dist Bars 4 8" C/C 1 31 31 0 - - - - -
2419 S1 0 0 - - - - -
2420 Grid G-G' / 5-7 0 22.125 818.625 - 546.022875 - - -
2421 Main Bars 4 8" C/C 1 13 13 26 806 - 537.602 - - -
2422 Main Bars 4 8" C/C 2 10 20 0 - - - - -
2423 Dist Bars 4 8" C/C 1 10 10 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2424 S4 0 7.375 95.875 - 63.948625 - - -
2425 Grid E-G / 7-8 0 10 200 - 133.4 - - -
2426 Main Bars 4 8" C/C 1 37 37 22.125 221.25 - 147.57375 - - -
2427 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
2428 S4 0 0 - - - - -
2429 Grid G-H / 7-8 0 11.125 411.625 - 274.553875 - - -
2430 Main Bars 4 8" C/C 1 29 29 26.375 290.125 - 193.513375 - - -
2431 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
2432 S4 0 0 - - - - -
2433 Grid H-I / 7-8 0 11.125 322.625 - 215.190875 - - -
2434 Main Bars 4 8" C/C 1 29 29 20.9 229.9 - 153.3433 - - -
2435 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
2436 S4 0 0 - - - - -
2437 Grid A-B / 8-10,11-12 0 11.875 344.375 - 229.698125 - - -
2438 Main Bars 4 8" C/C 2 30 60 20.92 230.12 - 153.49004 - - -
2439 Dist Bars 4 10" C/C 2 12 24 0 - - - - -
2440 S1 0 0 - - - - -
2441 Grid B-C / 8-10,11-12 0 11.92 715.2 - 477.0384 - - -
2442 Main Bars 4 8" C/C 2 30 60 21.875 525 - 350.175 - - -
2443 Dist Bars 4 8" C/C 2 29 58 0 - - - - -
2444 S2 0 0 - - - - -
2445 Grid C-E /8-10,11-12 0 20.5 1230 - 820.41 - - -
2446 Main Bars 4 7" C/C 1 44 44 21.875 1268.75 - 846.25625 - - -
2447 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
2448 S1 0 0 - - - - -
2449 Grid E-G' / 8-10 0 21.875 962.5 - 641.9875 - - -
2450 Main Bars 4 8" C/C 1 37 37 27.5 825 - 550.275 - - -
2451 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
2452 For 4.375' projection Dist Bars 4 6" C/C 1 11 11 0 - - - - -
2453 S3 0 21.875 809.375 - 539.853125 - - -
2454 Grid B-G / 10-11 0 30.75 922.5 - 615.3075 - - -
2455 Main Bars 4 8" C/C 1 118 118 33.125 364.375 - 243.038125 - - -
2456 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2457 S1 0 0 - - - - -
2458 Grid E-G / 11-12 0 12.5 1475 - 983.825 - - -
2459 Main Bars 4 8" C/C 1 37 37 78.25 1017.25 - 678.50575 - - -
2460 Dist Bars 4 8" C/C 1 30 30 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2461 S1 0 0 - - - - -
2462 Grid G-H / 11-12 0 21.875 809.375 - 539.853125 - - -
2463 Main Bars 4 8" C/C 1 30 30 26 780 - 520.26 - - -
2464 Dist Bars 4 8" C/C 1 29 29 0 - - - - -
2465 S1 0 0 - - - - -
2466 Grid H-I / 11-12 0 20.91 627.3 - 418.4091 - - -
2467 Main Bars 4 8" C/C 1 30 30 21.875 634.375 - 423.128125 - - -
2468 Dist Bars 4 8" C/C 1 29 29 0 - - - - -
2469 S3 0 0 - - - - -
2470 Main Bars ( I - J ) / 1 - 8 4 8" C/C 1 114 114 20.91 627.3 - 418.4091 - - -
2471 Main Bars ( I - J ) / 8 - 11 4 8" C/C 1 46 46 21.875 634.375 - 423.128125 - - -
2472 Main Bars ( I - J ) / 11 - 12 4 8" C/C 1 30 30 0 - - - - -
2473 Dist Bars ( I - J ) / 1 - 9 4 10" C/C 1 13 13 12.5 1425 - 950.475 - - -
2474 Dist Bars ( I - J ) / 9 - 11 4 10" C/C 1 18 18 16.875 776.25 - 517.75875 - - -
2475 Dist Bars ( I - J ) / 8 - 11 4 6" C/C 1 13 13 12.5 375 - 250.125 - - -
2476 S1 0 92 1196 - 797.732 - - -
2477 Grid J-K / 1 - 3 0 32.375 582.75 - 388.69425 - - -
2478 Main Bars 4 8" C/C 1 34 34 21.875 284.375 - 189.678125 - - -
2479 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
2480 S1 0 0 - - - - -
2481 Grid K-L / 1 - 3 0 20.21 687.14 - 458.32238 - - -
2482 Main Bars 4 8" C/C 1 34 34 24.25 679 - 452.893 - - -
2483 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
2484 S1 0 0 - - - - -
2485 Grid L-M / 1 - 3 0 19.83 674.22 - 449.70474 - - -
2486 Main Bars 4 8" C/C 1 34 34 24.25 654.75 - 436.71825 - - -
2487 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
2488 S1 0 0 - - - - -
2489 Grid M-N / 1 - 3 0 15.79 536.86 - 358.08562 - - -
2490 Main Bars 4 8" C/C 1 34 34 24.25 509.25 - 339.66975 - - -
2491 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
2492 S4 0 0 - - - - -
2493 Grid J-K / 3 - 4 0 16.17 549.78 - 366.70326 - - -
2494 Main Bars 4 8" C/C 1 27 27 24.25 533.5 - 355.8445 - - -
2495 Dist Bars 4 10" C/C 1 10 10 0 - - - - -
2496 S4 0 0 - - - - -
2497 Grid K-L / 3 - 4 0 10.125 273.375 - 182.341125 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2498 Main Bars 4 8" C/C 1 28 28 20.21 202.1 - 134.8007 - - -
2499 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
2500 S4 0 0 - - - - -
2501 Grid L-M / 3 - 4 0 10.125 283.5 - 189.0945 - - -
2502 Main Bars 4 8" C/C 1 21 21 19.83 218.13 - 145.49271 - - -
2503 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
2504 S4 0 0 - - - - -
2505 Grid M-N / 3 - 4 0 10.125 212.625 - 141.820875 - - -
2506 Main Bars 4 8" C/C 1 22 22 15.79 173.69 - 115.85123 - - -
2507 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
2508 S1 0 0 - - - - -
2509 Grid J-K / 4 - 6 0 10.125 222.75 - 148.57425 - - -
2510 Main Bars 4 8" C/C 1 30 30 16.17 177.87 - 118.63929 - - -
2511 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
2512 S1 0 0 - - - - -
2513 Grid K-L / 4 - 6 0 20.21 606.3 - 404.4021 - - -
2514 Main Bars 4 8" C/C 1 30 30 21.75 609 - 406.203 - - -
2515 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
2516 S1 0 0 - - - - -
2517 Grid L-M / 4 - 6 0 19.83 594.9 - 396.7983 - - -
2518 Main Bars 4 8" C/C 1 30 30 21.75 587.25 - 391.69575 - - -
2519 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
2520 S1 0 0 - - - - -
2521 Grid M-N / 4 - 6 0 15.79 473.7 - 315.9579 - - -
2522 Main Bars 4 8" C/C 1 30 30 21.75 456.75 - 304.65225 - - -
2523 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
2524 S4 0 0 - - - - -
2525 Grid J-K / 6 - 7 0 16.17 485.1 - 323.5617 - - -
2526 Main Bars 4 8" C/C 1 28 28 21.75 478.5 - 319.1595 - - -
2527 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2528 S4 0 0 - - - - -
2529 Grid K-L / 6 - 7 0 12.5 350 - 233.45 - - -
2530 Main Bars 4 8" C/C 1 27 27 20.58 267.54 - 178.44918 - - -
2531 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2532 S4 0 0 - - - - -
2533 Grid L-M / 6 - 7 0 12.5 337.5 - 225.1125 - - -
2534 Main Bars 4 8" C/C 1 21 21 19.83 257.79 - 171.94593 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2535 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2536 S4 0 0 - - - - -
2537 Grid M-N / 6 - 7 0 12.5 262.5 - 175.0875 - - -
2538 Main Bars 4 8" C/C 1 22 22 15.79 205.27 - 136.91509 - - -
2539 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2540 S1 0 0 - - - - -
2541 Grid J-K / 7 - 9 0 12.5 275 - 183.425 - - -
2542 Main Bars 4 8" C/C 1 33 33 16.17 210.21 - 140.21007 - - -
2543 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
2544 S1 0 0 - - - - -
2545 Grid K-L / 7 - 9 0 20.58 679.14 - 452.98638 - - -
2546 Main Bars 4 8" C/C 1 33 33 23.375 654.5 - 436.5515 - - -
2547 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
2548 S1 0 0 - - - - -
2549 Grid L-M / 7 - 9 0 19.83 654.39 - 436.47813 - - -
2550 Main Bars 4 8" C/C 1 33 33 23.375 631.125 - 420.960375 - - -
2551 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
2552 S1 0 0 - - - - -
2553 Grid M-N / 7 - 9 0 15.79 521.07 - 347.55369 - - -
2554 Main Bars 4 8" C/C 1 33 33 23.375 490.875 - 327.413625 - - -
2555 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
2556 S1 0 0 - - - - -
2557 Grid J-K / 9 - 11 0 16.17 533.61 - 355.91787 - - -
2558 Main Bars 4 8" C/C 1 31 31 23.375 514.25 - 343.00475 - - -
2559 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
2560 S1 0 0 - - - - -
2561 Grid K-L / 9 - 11 0 20.58 637.98 - 425.53266 - - -
2562 Main Bars 4 8" C/C 1 31 31 22 616 - 410.872 - - -
2563 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
2564 S1 0 0 - - - - -
2565 Grid L-M / 9 - 11 0 19.83 614.73 - 410.02491 - - -
2566 Main Bars 4 8" C/C 1 31 31 22 594 - 396.198 - - -
2567 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
2568 S1 0 0 - - - - -
2569 Grid M-N / 9 - 11 0 15.79 489.49 - 326.48983 - - -
2570 Main Bars 4 8" C/C 1 31 31 22 462 - 308.154 - - -
2571 Dist Bars 4 8" C/C 1 22 22 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2572 S3 0 0 - - - - -
2573 Grid I-J / 11 - 12 0 16.32 505.92 - 337.44864 - - -
2574 Main Bars 4 8" C/C 1 30 30 22 484 - 322.828 - - -
2575 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
2576 S1 0 0 - - - - -
2577 Grid J-K / 11 - 12 0 12.5 375 - 250.125 - - -
2578 Main Bars 4 8" C/C 1 5 5 21.875 284.375 - 189.678125 - - -
2579 Main Bars 4 8" C/C 1 16 16 0 - - - - -
2580 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
2581 S1 0 20.58 102.9 - 68.6343 - - -
2582 Grid K-L / 11 - 12 0 8.75 140 - 93.38 - - -
2583 Main Bars 4 8" C/C 1 30 30 4.5 99 - 66.033 - - -
2584 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
2585 S1 0 0 - - - - -
2586 Grid L-M / 11 - 12 0 19.83 594.9 - 396.7983 - - -
2587 Main Bars 4 8" C/C 1 30 30 21.875 590.625 - 393.946875 - - -
2588 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
2589 S1 0 0 - - - - -
2590 Grid M-N / 11 - 12 0 15.79 473.7 - 315.9579 - - -
2591 Main Bars 4 8" C/C 1 30 30 21.875 459.375 - 306.403125 - - -
2592 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
2593 S2 0 0 - - - - -
2594 Grid N-P / 11 - 12 0 16.17 485.1 - 323.5617 - - -
2595 Main Bars 4 6" C/C 1 62 62 21.875 481.25 - 320.99375 - - -
2596 Dist Bars 4 7" C/C 1 34 34 0 - - - - -
2597 Extra Bars 0 0 - - - - -
2598 X-AXIS 0 21.875 1356.25 - 904.61875 - - -
2599 Grid 1 / D - G 4 7" C/C 1 53 53 33 1122 - 748.374 - - -
2600 Grid 1 / D - G Temp 3 12" C/C 1 3 3 0 - - - - -
2601 Grid 1 / D - G Temp 3 12" C/C 1 3 3 0 - - - - -
2602 Grid 2 & 4 / A -B 4 7" C/C 2 17 34 3.73 197.69 - 131.85923 - - -
2603 Grid 2 & 4 / A -B Temp 3 12" C/C 2 5 10 4.74 14.22 5.3325 - - - -
2604 Grid 2 / B -D 4 7" & 6" 1 70 70 9.83 29.49 11.05875 - - - -
2605 Grid 2 / B -D Temp 3 12" C/C 1 5 5 5.375 182.75 - 121.89425 - - -
2606 Grid 2 / B -D Temp 3 12" C/C 1 5 5 6.43 64.3 24.1125 - - - -
2607 Grid 2 / D -G 4 7" C/C 1 52 52 5.375 376.25 - 250.95875 - - -
2608 Grid 2 / E -G Temp 3 12" C/C 1 12 12 5 8 3 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2609 Grid 2 / G -I 4 7" C/C 1 66 66 5 10.33 3.87375 - - - -
2610 Grid 2 / G -I Temp 3 12" C/C 1 10 10 11.29 587.08 - 391.58236 - - -
2611 Grid 4 / B -I 4 7" & 6" 1 188 188 9.83 117.96 44.235 - - - -
2612 Grid 4 / B -C Temp 3 12" C/C 1 12 12 5.375 354.75 - 236.61825 - - -
2613 Grid 4 / C -E 3 12" C/C 1 12 12 8.14 81.4 30.525 - - - -
2614 Grid 4 / E -G 3 12" C/C 1 12 12 11.04 2075.52 - 1384.37184 - - -
2615 Grid 4 / G -H 3 12" C/C 1 12 12 8 96 36 - - - -
2616 Grid4 / H -I Temp 3 12" C/C 1 12 12 10.33 123.96 46.485 - - - -
2617 Grid 5 & 7 / A -B 4 7" C/C 2 16 32 9.83 117.96 44.235 - - - -
2618 Grid 5 & 7 / A -B Temp 3 12" C/C 2 5 10 8.14 97.68 36.63 - - - -
2619 Grid 5 / B -G 4 7" & 6" 1 126 126 8.14 97.68 36.63 - - - -
2620 Grid 5 / B -C TeMP 3 12" C/C 1 12 12 5.375 172 - 114.724 - - -
2621 Grid 5 / C -E Temp 3 12" C/C 1 12 12 6.43 64.3 24.1125 - - - -
2622 Grid 5 / E -G Temp 3 12" C/C 1 12 12 11.125 1401.75 - 934.96725 - - -
2623 Grid 5 - 7 / G-G' & - H' I 4 7" C/C 2 10 20 10.4 124.8 46.8 - - - -
2624 Grid 5 , 7 / G' - H' 4 7" C/C 2 23 46 10.33 123.96 46.485 - - - -
2625 Grid 5 , 7 / G - I Temp 3 12" C/C 2 6 12 9.83 117.96 44.235 - - - -
2626 Grid 7 / B -E 4 7" & 6" 1 83 83 26.71 534.2 - 356.3114 - - -
2627 Grid 7 / B -C Temp 3 12" C/C 1 6 6 4.58 210.68 - 140.52356 - - -
2628 Grid 7 / C -E Temp 3 12" C/C 1 6 6 8.23 98.76 37.035 - - - -
2629 Grid 7 / E -G 4 7" C/C 1 42 42 5.43 450.69 - 300.61023 - - -
2630 Grid 7 / E -G Temp 3 12" C/C 1 12 12 8 48 18 - - - -
2631 Grid 8,10,11 & 12 / A -B 4 7" C/C 4 17 68 10.33 61.98 23.2425 - - - -
2632 Grid 8,10,11 & 12 / A -B Temp 3 12" C/C 4 6 24 10.67 448.14 - 298.90938 - - -
2633 Grid 8 & 12 / B -E 4 7" & 6" 1 83 83 9.83 117.96 44.235 - - - -
2634 Grid 8 & 12 / B -C Temp 3 12" C/C 1 6 6 5.375 365.5 - 243.7885 - - -
2635 Grid 8 & 12 / C -E Temp 3 12" C/C 1 6 6 6.43 154.32 57.87 - - - -
2636 Grid 8 / E -G 4 7" C/C 1 41 41 5.375 446.125 - 297.565375 - - -
2637 Grid 8 / E -G Temp 3 12" C/C 1 11 11 8 48 18 - - - -
2638 Grid 8 / G -I 4 7" C/C 1 64 64 10.33 61.98 23.2425 - - - -
2639 Grid 8 / G - I Temp 3 12" C/C 1 3 3 10.42 427.22 - 284.95574 - - -
2640 Grid 10 & 11 / B -G 4 7" & 6" 2 123 246 9.75 107.25 40.21875 - - - -
2641 Grid 10 & 11 / B -C Temp 3 12" C/C 2 12 24 3.23 206.72 - 137.88224 - - -
2642 Grid 10 & 11 / C -E Temp 3 12" C/C 2 12 24 8.23 24.69 9.25875 - - - -
2643 Grid 10 & 11 / E -G Temp 3 12" C/C 2 12 24 10.875 2675.25 - 1784.39175 - - -
2644 Grid 12 / E - G 4 7" C/C 1 41 41 10.25 246 92.25 - - - -
2645 Grid 12 / E - G Temp 3 12" C/C 1 6 6 10.25 246 92.25 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2646 Grid 11 & 12 / G - I 4 7" C/C 2 64 128 9.75 234 87.75 - - - -
2647 Grid 11 & 12 / G - I Temp 3 12" C/C 2 12 24 5.125 210.125 - 140.153375 - - -
2648 Grid 1 / I - N 4 7" C/C 1 124 124 9.75 58.5 21.9375 - - - -
2649 Grid 1 / I - J 3 12" C/C 1 7 7 5.125 656 - 437.552 - - -
2650 Grid 1 / J - K 3 12" C/C 1 7 7 8.06 193.44 72.54 - - - -
2651 Grid 1 / K - L 3 12" C/C 1 7 7 5.78 716.72 - 478.05224 - - -
2652 Grid 1 / L - M 3 12" C/C 1 7 7 5.33 37.31 13.99125 - - - -
2653 Grid 1 / M - N 3 12" C/C 1 7 7 7.9 55.3 20.7375 - - - -
2654 Grid 3 / J - N 4 7" C/C 1 109 109 7.69 53.83 20.18625 - - - -
2655 Grid 3 / J - K Temp 3 12" C/C 1 12 12 6.35 44.45 16.66875 - - - -
2656 Grid 3 / K - L Temp 3 12" C/C 1 12 12 8.21 57.47 21.55125 - - - -
2657 Grid 3 / L - M Temp 3 12" C/C 1 12 12 11.08 1207.72 - 805.54924 - - -
2658 Grid 3 / M - N Temp 3 12" C/C 1 12 12 7.9 94.8 35.55 - - - -
2659 Grid 4 / J - N 4 7" C/C 1 109 109 7.69 92.28 34.605 - - - -
2660 Grid 4 / J - K 3 12" C/C 1 11 11 6.35 76.2 28.575 - - - -
2661 Grid 4 / K - L 3 12" C/C 1 11 11 8.21 98.52 36.945 - - - -
2662 Grid 4 / L - M 3 12" C/C 1 11 11 10.25 1117.25 - 745.20575 - - -
2663 Grid 4 / M - N 3 12" C/C 1 11 11 7.9 86.9 32.5875 - - - -
2664 Grid 6 / J - N 4 7" C/C 1 109 109 7.69 84.59 31.72125 - - - -
2665 Grid 6 / J - K 3 12" C/C 1 11 11 6.35 69.85 26.19375 - - - -
2666 Grid 6 / K - L 3 12" C/C 1 11 11 8.21 90.31 33.86625 - - - -
2667 Grid 6 / L - M 3 12" C/C 1 11 11 10.875 1185.375 - 790.645125 - - -
2668 Grid 6 / M - N 3 12" C/C 1 11 11 7.9 86.9 32.5875 - - - -
2669 Grid 7 / I - J 4 7" C/C 1 19 19 7.69 84.59 31.72125 - - - -
2670 Grid 7 / I - J 3 12" C/C 1 30 30 6.35 69.85 26.19375 - - - -
2671 Grid 7 / J - N 4 7" C/C 1 112 112 8.21 90.31 33.86625 - - - -
2672 Grid 7 / J - K 3 12" C/C 1 12 12 29.12 553.28 - 369.03776 - - -
2673 Grid 7 / K - L 3 12" C/C 1 12 12 6.78 203.4 76.275 - - - -
2674 Grid 7 / L - M 3 12" C/C 1 12 12 11.42 1279.04 - 853.11968 - - -
2675 Grid 7 / M - N 3 12" C/C 1 12 12 7.9 94.8 35.55 - - - -
2676 Grid 9 / I - J 4 7" C/C 1 19 19 7.69 92.28 34.605 - - - -
2677 Grid 9 / I - J 3 12" C/C 1 15 15 6.35 76.2 28.575 - - - -
2678 Grid 9 / J - N 4 7" C/C 1 109 109 8.21 98.52 36.945 - - - -
2679 Grid 9 / J - K 3 12" C/C 1 15 15 14.42 273.98 - 182.74466 - - -
2680 Grid 9 / K - L 3 12" C/C 1 15 15 6.78 101.7 38.1375 - - - -
2681 Grid 9 / L - M 3 12" C/C 1 15 15 14.42 1571.78 - 1048.37726 - - -
2682 Grid 9 / M - N 3 12" C/C 1 15 15 7.9 118.5 44.4375 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2683 Grid 11 / I - J & K - N 4 7" C/C 1 97 97 7.69 115.35 43.25625 - - - -
2684 Grid 11 / I - J 3 12" C/C 1 15 15 6.35 95.25 35.71875 - - - -
2685 Grid 11 / K - L 3 12" C/C 1 15 15 8.21 123.15 46.18125 - - - -
2686 Grid 11 / L - M 3 12" C/C 1 15 15 13.875 1345.875 - 897.698625 - - -
2687 Grid 11 / M - N 3 12" C/C 1 15 15 6.78 101.7 38.1375 - - - -
2688 Grid 11 / J - K 4 7" C/C 1 32 32 7.69 115.35 43.25625 - - - -
2689 Grid 11 / J - K 3 12" C/C 1 6 6 6.35 95.25 35.71875 - - - -
2690 Grid 12 / I - N 4 7" C/C 1 128 128 8.21 123.15 46.18125 - - - -
2691 Grid 12 / I - J 3 12" C/C 1 6 6 5.05 161.6 - 107.7872 - - -
2692 Grid 12 / J - K 3 12" C/C 1 6 6 7.9 47.4 17.775 - - - -
2693 Grid 12 / K - L 3 12" C/C 1 6 6 5.03 643.84 - 429.44128 - - -
2694 Grid 12 / L - M 3 12" C/C 1 6 6 6.78 40.68 15.255 - - - -
2695 Grid 12 / M - N 3 12" C/C 1 6 6 7.9 47.4 17.775 - - - -
2696 Grid 11 & 12 / N - P 4 6" C/C 2 57 114 7.69 46.14 17.3025 - - - -
2697 Grid 11 & 12 / N - P 3 12" C/C 1 6 6 6.35 38.1 14.2875 - - - -
2698 Y-AXIS 0 8.21 49.26 18.4725 - - - -
2699 Grid D / 1 - 2 4 7" C/C 1 20 20 5.04 574.56 - 383.23152 - - -
2700 Grid D / 1 - 2 3 12" C/C 1 3 3 15.07 90.42 33.9075 - - - -
2701 Grid E / 1 - 2 4 7" C/C 1 20 20 0 - - - - -
2702 Grid E / 1 - 2 3 12" C/C 1 12 12 2.6 52 - 34.684 - - -
2703 Grid G / 1 - 2 4 7" C/C 1 17 17 7.08 21.24 7.965 - - - -
2704 Grid G / 1 - 2 3 12" C/C 1 15 15 10.83 216.6 - 144.4722 - - -
2705 Grid I / 1 - 2 4 7" C/C 1 17 17 7.08 84.96 31.86 - - - -
2706 Grid I / 1 - 2 3 12" C/C 1 12 12 15.06 256.02 - 170.76534 - - -
2707 Grid A / 2 -4, 8-10, 11-12 4 7" C/C 3 34 102 7.08 106.2 39.825 - - - -
2708 Grid A / 2 - 4, 8-10, 11-12 3 12" C/C 3 3 9 10.72 182.24 - 121.55408 - - -
2709 Grid A / 5 -7 4 7" C/C 1 35 35 7.08 84.96 31.86 - - - -
2710 Grid A / 5 -7 3 12" C/C 1 3 3 3.33 339.66 - 226.55322 - - -
2711 Grid B / 2 -4, 5-7,8-10 & 11-12 4 7" C/C 4 34 136 13.33 119.97 44.98875 - - - -
2712 Grid B / 2 -4, 5-7,8-10 & 11-12 3 12" C/C 4 11 44 3.33 116.55 - 77.73885 - - -
2713 Grid B / 4 -5, 10-11 4 7" C/C 2 18 36 13.78 41.34 15.5025 - - - -
2714 Grid B / 4 -5, 10-11 3 12" C/C 2 6 12 10.21 1388.56 - 926.16952 - - -
2715 Grid C / 2 -7 4 7" C/C 1 86 86 10.81 475.64 178.365 - - - -
2716 Grid C / 2 - 4 3 12" C/C 1 16 16 5.05 181.8 - 121.2606 - - -
2717 Grid C / 4 - 5 3 12" C/C 1 16 16 5.33 63.96 23.985 - - - -
2718 Grid C / 5 - 7 3 12" C/C 1 16 16 15.42 1326.12 - 884.52204 - - -
2719 Grid C / 8 -12 4 7" C/C 1 86 86 10.81 172.96 64.86 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2720 Grid C / 8 - 10 ,11-12 3 12" C/C 1 16 16 5.05 80.8 30.3 - - - -
2721 Grid C / 10 - 11 3 12" C/C 1 16 16 10.93 174.88 65.58 - - - -
2722 Grid E / 2 -7 4 7" C/C 1 86 86 15.42 1326.12 - 884.52204 - - -
2723 Grid E / 2 - 4, 5-7 3 12" C/C 2 18 36 10.81 172.96 64.86 - - - -
2724 Grid E / 4 - 5 3 12" C/C 1 18 18 5.05 80.8 30.3 - - - -
2725 Grid E / 7 -8 4 7" C/C 1 16 16 17.25 1483.5 - 989.4945 - - -
2726 Grid E / 7 - 8 3 12" C/C 1 6 6 10.81 389.16 145.935 - - - -
2727 Grid E / 8 -12 4 7" C/C 1 86 86 5.05 90.9 34.0875 - - - -
2728 Grid E / 8 - 10, 11-12 3 12" C/C 2 18 36 6.15 98.4 - 65.6328 - - -
2729 Grid E / 10 - 11 3 12" C/C 1 18 18 4.875 29.25 10.96875 - - - -
2730 Grid G / 2 -5 4 7" C/C 1 51 51 17.25 1483.5 - 989.4945 - - -
2731 Grid G / 2 - 4 3 12" C/C 1 16 16 10.81 389.16 145.935 - - - -
2732 Grid G / 4 - 5 3 12" C/C 1 16 16 5.05 90.9 34.0875 - - 1243.875 -
2733 Grid G / 5 -7 4 7" C/C 1 34 34 15.06 768.06 - 512.29602 - - -
2734 Grid G / 5 - 7 3 12" C/C 1 8 8 10.69 171.04 64.14 - - - -
2735 Grid G / 7 -8 4 7" C/C 1 16 16 4.67 74.72 28.02 - - - -
2736 Grid G / 7 - 8 3 12" C/C 1 16 16 14.25 484.5 - 323.1615 - - -
2737 Grid G / 8 -11 6 6" C/C 1 62 62 8.375 67 25.125 - - - -
2738 Grid G / 8 - 11 3 12" C/C 1 14 14 15.06 240.96 - 160.72032 - - -
2739 Grid G / 11 -12 4 7" C/C 1 34 34 6.03 96.48 36.18 - - - -
2740 Grid G / 11 - 12 3 12" C/C 1 16 16 13.375 829.25 - - - - -
2741 Grid H / 2 -5 4 7" C/C 1 51 51 32.375 453.25 169.96875 - - - -
2742 Grid H / 2 - 4 3 12" C/C 1 14 14 15.06 512.04 - 341.53068 - - -
2743 Grid H / 4 - 5 3 12" C/C 1 14 14 13.33 213.28 79.98 - - - -
2744 Grid H / 7 -8 4 7" C/C 1 16 16 13.36 681.36 - 454.46712 - - -
2745 Grid H / 7 - 8 3 12" C/C 1 14 14 10.69 149.66 56.1225 - - - -
2746 Grid H / 11 -12 4 7" C/C 1 34 34 6.67 93.38 35.0175 - 584.02016 - -
2747 Grid H / 11 - 12 3 12" C/C 1 16 16 13.36 213.76 - 142.57792 - - -
2748 Grid I / 1 - 8 4 7" C/C 1 128 128 7.18 100.52 37.695 - - - -
2749 Grid I / 2 - 4 3 12" C/C 1 7 7 15.06 512.04 - 341.53068 - - -
2750 Grid I / 4 - 5, 7-8 3 12" C/C 2 7 14 13.33 213.28 79.98 - - - -
2751 Grid I / 8 - 11 5 6" C/C 1 62 62 10.72 1372.16 - 915.23072 - - -
2752 Grid I / 8 - 11 4 6" C/C 1 10 10 10.69 74.83 28.06125 - - - -
2753 Grid I / 9 - 11 3 12" C/C 1 6 6 5.33 74.62 27.9825 - - - -
2754 Grid I / 11 - 12 4 7" C/C 1 34 34 9.04 560.48 - - - - -
2755 Grid I / 11 - 12 3 12" C/C 1 12 12 32.375 323.75 - 215.94125 - - -
2756 Grid J / 1 - 11 4 7" C/C 1 182 182 8.33 49.98 18.7425 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2757 Grid J / 1 - 3 3 12" C/C 1 12 12 10.69 363.46 - 242.42782 - - -
2758 Grid J / 3 - 4 3 12" C/C 1 12 12 13.33 159.96 59.985 - - - -
2759 Grid J / 4 - 6 3 12" C/C 1 12 12 10.56 1921.92 - 1281.92064 - - -
2760 Grid J / 6 - 7 3 12" C/C 1 12 12 18.375 220.5 82.6875 - - - -
2761 Grid J / 7 - 9 3 12" C/C 1 12 12 4.71 56.52 21.195 - - - -
2762 Grid J / 9 - 11 3 12" C/C 1 12 12 8.29 99.48 37.305 - - - -
2763 Grid J / 11 - 12 4 7" C/C 1 34 34 5.33 63.96 23.985 - - - -
2764 Grid J / 11 - 12 3 12" C/C 1 4 4 8.83 105.96 39.735 - - - -
2765 Grid K / 1 - 11 4 7" C/C 1 175 175 8.33 99.96 37.485 - - - -
2766 Grid K / 1 - 3 3 12" C/C 1 13 13 3.33 113.22 - 75.51774 - - -
2767 Grid K /3 - 4 3 12" C/C 1 13 13 10.81 43.24 16.215 - - - -
2768 Grid K /4 - 6 3 12" C/C 1 13 13 12.84 2247 - 1498.749 - - -
2769 Grid K /6 - 7 3 12" C/C 1 13 13 18.375 238.875 89.578125 - - - -
2770 Grid K /7 - 9 3 12" C/C 1 13 13 4.71 61.23 22.96125 - - - -
2771 Grid K /9 - 11 3 12" C/C 1 13 13 8.29 107.77 40.41375 - - - -
2772 Grid K / 11 - 12 4 7" C/C 1 34 34 5.33 69.29 25.98375 - - - -
2773 Grid K / 11 - 12 3 12" C/C 1 6 6 8.83 114.79 43.04625 - - - -
2774 Grid L / 1 - 12 4 7" C/C 1 209 209 10.87 141.31 52.99125 - - - -
2775 Grid L / 1 - 3 3 12" C/C 1 12 12 4.67 158.78 - 105.90626 - - -
2776 Grid L / 3 - 4 3 12" C/C 1 12 12 10.81 64.86 24.3225 - - - -
2777 Grid L / 4 - 6 3 12" C/C 1 12 12 11.29 2359.61 - 1573.85987 - - -
2778 Grid L / 6 - 7 3 12" C/C 1 12 12 18.375 220.5 82.6875 - - - -
2779 Grid L / 7 - 9 3 12" C/C 1 12 12 4.71 56.52 21.195 - - - -
2780 Grid L / 9 - 11 3 12" C/C 1 12 12 8.29 99.48 37.305 - - - -
2781 Grid L / 11 - 12 3 12" C/C 1 12 12 5.33 63.96 23.985 - - - -
2782 Grid M / 1 - 12 4 7" C/C 1 209 209 8.83 105.96 39.735 - - - -
2783 Grid M / 1 - 3 3 12" C/C 1 11 11 10.87 130.44 48.915 - - - -
2784 Grid M /3 - 4 3 12" C/C 1 11 11 10.81 129.72 48.645 - - - -
2785 Grid M /4 - 6 3 12" C/C 1 11 11 10.03 2096.27 - 1398.21209 - - -
2786 Grid M /6 - 7 3 12" C/C 1 11 11 18.375 202.125 75.796875 - - - -
2787 Grid M /7 - 9 3 12" C/C 1 11 11 4.71 51.81 19.42875 - - - -
2788 Grid M /9 - 11 3 12" C/C 1 11 11 8.29 91.19 34.19625 - - - -
2789 Grid M /11 - 12 3 12" C/C 1 11 11 5.33 58.63 21.98625 - - - -
2790 Grid N / 1 - 11 4 7" C/C 1 175 175 8.83 97.13 36.42375 - - - -
2791 Grid N / 1 - 3 3 12" C/C 1 4 4 10.87 119.57 44.83875 - - - -
2792 Grid N / 3 - 4 3 12" C/C 1 4 4 10.81 118.91 44.59125 - - - -
2793 Grid N / 4 - 6 3 12" C/C 1 4 4 4.16 728 - 485.576 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2794 Grid N / 6 - 7 3 12" C/C 1 4 4 18.375 73.5 27.5625 - - - -
2795 Grid N / 7 - 9 3 12" C/C 1 4 4 4.71 18.84 7.065 - - - -
2796 Grid N / 9 - 11 3 12" C/C 1 4 4 8.29 33.16 12.435 - - - -
2797 Grid N / 11 - 12 4 7" C/C 1 34 34 5.33 21.32 7.995 - - - -
2798 Grid N / 11 - 12 3 12" C/C 1 16 16 8.83 35.32 13.245 - - - -
2799 Grid P / 11 - 12 4 6" C/C 1 39 39 10.87 43.48 16.305 - - - -
2800 Grid P / 11 - 12 3 12" C/C 1 9 9 15.01 510.34 - 340.39678 - - -
2801 For 3" Projection 0 13.375 214 80.25 - - - -
2802 Distribution outer 0 8.85 345.15 - 230.21505 - - -
2803 Grid A 1-2, 8-10 & (11-12), 3 3 1 3 13.625 122.625 45.984375 - - - -
2804 Grid 4,5, 10 & 11 / A - B 3 4 1 4 0 - - - - -
2805 Grid 7 & 8 ( A - E) 3 2 1 2 0 - - - - -
2806 Grid A / 5 - 7 3 1 1 1 22.25 66.75 25.03125 - - - -
2807 Grid A - D1 / 2 3 1 1 1 10.75 43 16.125 - - - -
2808 Grid D1 / 1 - 2 3 1 1 1 58.25 116.5 43.6875 - - - -
2809 Grid D1 - G / 1 3 1 1 1 22.5 22.5 8.4375 - - - -
2810 Grid G & I / 1 - 1' 3 2 1 2 51.25 51.25 19.21875 - - - -
2811 Grid G - I / 1' 3 1 1 1 12.5 12.5 4.6875 - - - -
2812 Grid 1 / I - N 3 1 1 1 33.75 33.75 12.65625 - - - -
2813 Grid N / 1 - 11 3 1 1 1 3.75 7.5 2.8125 - - - -
2814 Grid N' / 12 - 16 3 1 1 1 37.25 37.25 13.96875 - - - -
2815 Grid 16 / N - N' 3 1 1 1 70.75 70.75 26.53125 - - - -
2816 Front curve 3 1 1 1 111 111 41.625 - - - -
2817 Grid J / 16 - 17 3 1 1 1 40 40 15 - - - -
2818 Grid 16 / E - J 3 1 1 1 8.75 8.75 3.28125 - - - -
2819 Grid 15 - 16 / D 3 1 1 1 133.5 133.5 50.0625 - - 390 -
2820 Grid 14a / A - D 3 1 1 1 21.25 21.25 7.96875 - - - -
2821 Curve 3 1 1 1 88.5 88.5 33.1875 -
2822 Dist Bars 3 1 1 1 22 22 8.25 - - - -
2823 For Windows 2' Projection 0 34.25 34.25 12.84375 - - - -
2824 Main Bars 6 20 4 80 31.25 31.25 11.71875 - - - 1589.8248
2825 Dist Bars 3 6" C/C 20 5 100 10.5 10.5 3.9375 - - - -
2826 0 - - - - -
First Floor Column's ( 1st portion Grid 13-19/
2827 A-N ) Up to S.F Center 0 3.25 260 - - - - -
2828 C-1 0 2.17 217 81.375 - - - -
2829 Main Bars 8 3 12 36 - - 5299.416
2830 Stirrups 3 4"&6" C/C 3 25 75 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2831 Stirrups 3 4"&6" C/C 3 25 75 0 - - - - -
2832 Stirrups 3 4"&6" C/C 3 25 75 16.54 595.44 - - - - -
2833 C-2 0 7.5 562.5 210.9375 - - - -
2834 Main Bars 8 10 12 120 5.5 412.5 154.6875 - - - 8479.0656
2835 Stirrups 3 6" C/C 10 25 250 5.5 412.5 154.6875 - - - -
2836 Stirrups 3 6" C/C 10 25 250 0 - - - - -
2837 Stirrups 3 6" C/C 10 25 250 16.54 1984.8 - - - - -
2838 C-3 0 5.5 1375 515.625 - - - -
2839 Main Bars 8 16 12 192 4 1000 375 - - - 883.236
2840 Stirrups 3 6" C/C 16 25 400 4 1000 375 - - - 112.941
2841 Stirrups 3 6" C/C 16 25 400 0 - - - - -
2842 Stirrups 3 6" C/C 16 25 400 16.54 3175.68 - - - - -
2843 C-5 0 5.5 2200 825 - - - 8832.36
2844 Main Bars 8 1 20 20 4 1600 600 - - - -
2845 Main Bars 8 1 5 5 4 1600 600 - - - -
2846 Stirrups 3 6" C/C 1 28 28 0 - - - 1958.04 -
2847 C-6 0 16.54 330.8 - - - - -
2848 Main Bars 8 10 20 200 8.46 42.3 - - - - -
2849 Stirrups 3 6" C/C 10 28 280 9.14 255.92 95.97 - 1554.49728 - -
2850 C-7 0 0 - - - - -
2851 Main Bars 6 7 12 84 16.54 3308 - - - - -
2852 Stirrups 3 4" C/C 7 37 259 7.56 2116.8 793.8 - - - -
2853 C-9 0 0 - - - 1492.995 -
2854 Main Bars 5 12 8 96 15.54 1305.36 - - - 55.125 -
2855 Stirrups 3 6" C/C 12 22 264 4.42 1144.78 429.2925 - - 315 -
2856 B3 0 0 - - - 130.5 -
2857 Grid 13 / F-N 0 15.54 1491.84 - - - - -
2858 Main Bars 6 1 7 7 5.5 1452 544.5 - - - -
2859 Extra Bars On Edge 6 2 3 6 0 - - - - -
2860 Extra Bars On Centers 6 5 3 15 0 - - - 3500.49 -
2861 Extra Bars On Centers 6 2 3 6 142.19 995.33 - - - 55.125 -
2862 Stirrups 3 5" & 8 " 1 244 244 6.13 36.75 - - - 72 -
2863 B3 0 14.00 210 - - - 567 -
2864 Grid 15 & 16 / D-N 0 14.50 87 - - - 456.75 -
2865 Main Bars 6 2 7 14 6.08 1483.52 556.32 - - - -
2866 Extra Bars On Edge 6 2 3 6 0 - - - - -
2867 Extra Bars On Edge 6 2 3 6 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2868 Extra Bars On Centers 6 9 3 27 166.69 2333.66 - - - 769.125 -
2869 Extra Bars On Centers 6 7 3 21 6.13 36.75 - - - 55.125 -
2870 Stirrups 3 5" & 8 " 2 295 590 8.00 48 - - - 63 -
2871 B3 0 14.00 378 - - - 67.5 -
2872 Grid 17 / J-N 0 14.50 304.5 - - - 65.25 -
2873 Main Bars 6 1 7 7 6.08 3587.2 1345.2 - - - -
2874 Extra Bars On Edge 6 2 3 6 0 - - - - -
2875 Extra Bars On Centers 6 1 3 3 0 - - - - -
2876 Extra Bars On Centers 6 1 3 3 73.25 512.75 - - - 204.75 -
2877 Extra Bars On Centers 6 1 3 3 6.13 36.75 - - - 42.75 -
2878 Stirrups 3 5" & 8 " 1 125 125 14.00 42 - - - 54 -
2879 B2 0 15.00 45 - - - - -
2880 Grid 15 & 16 /N - N' 0 14.50 43.5 - - - - -
2881 Main Bars 6 2 6 12 6.08 760 285 - - - -
2882 Extra Bars On Edge 6 2 2 4 0 - - - - -
2883 Extra Bars On Edge 6 2 2 4 0 - - - 420.75 -
2884 Stirrups 3 5" & 8 " 1 17 17 11.375 136.5 - - - 85.5 -
2885 Y-AXIS 0 7.125 28.5 - - - - -
2886 B2 0 9.0 36 - - - - -
2887 Grid D & N' / 15-16 0 6.08 103.36 38.76 - - - -
2888 Main Bars 6 2 6 12 0 - - - 2607 -
2889 Extra Bars On Edge 6 4 2 8 0 - - - - -
2890 Stirrups 3 5" & 8 " 2 41 82 0 - - - 513 -
2891 B4 0 23.375 280.5 - - - 594 -
2892 Grid F,G,H & I / 13-16 0 7.125 57 - - - 108 -
2893 Main Bars 6 4 10 40 6.08 498.56 186.96 - - - -
2894 Main Bars 4 4 2 8 0 - - - - -
2895 Extra Bars On Edge 6 8 6 48 0 - - - - -
2896 Extra Bars On Centers 6 4 6 24 43.45 1738 - - - 3024 -
2897 Spacer Bars 6 4 18 72 40.45 323.6 - 215.8412 - - -
2898 Stirrups 3 4"&6" C/C 4 97 388 7.13 342 - - - 192.375 -
2899 B4 0 16.50 396 - - - 137.25 -
2900 Grid J,K,L,M & N / 13-16 0 1.00 72 - - - 1008 -
2901 Main Bars 6 5 10 50 6.08 2359.04 884.64 - - 445.5 -
2902 Main Bars 4 5 2 10 0 - - - 180 -
2903 Extra Bars On Edge 6 3 6 18 0 - - - - -
2904 Extra Bars On Edge 6 2 6 12 40.32 2016 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2905 Extra Bars On Centers 6 7 6 42 40.07 400.7 - 267.2669 - - -
2906 Extra Bars On Centers 6 3 6 18 7.13 128.25 - - - 1040.625 -
2907 Spacer Bars 6 4 30 120 7.63 91.5 - - - - -
2908 Stirrups 3 4"&6" C/C 4 97 388 16.00 672 - - - 58.5 -
2909 B4 0 16.50 297 - - - 288 -
2910 Grid J,M & N / 16-17 0 1.00 120 - - - 54 -
2911 Main Bars 6 3 10 30 6.08 2359.04 884.64 - - - -
2912 Main Bars 4 3 2 6 0 - - - - -
2913 Extra Bars On Edge 6 1 6 6 0 - - - - -
2914 Extra Bars On Centers 6 2 6 12 23.13 693.75 - - - 354.375 -
2915 Spacer Bars 6 3 12 36 23.13 138.75 - 92.54625 - - -
2916 Stirrups 3 4"&6" C/C 3 53 159 6.50 39 - - - 63 -
2917 B4 0 16.00 192 - - - 18 -
2918 Grid K / 16-17 0 1.00 36 - - - - -
2919 Main Bars 6 1 10 10 6.08 966.72 362.52 - - - -
2920 Main Bars 4 1 2 2 0 - - - - -
2921 Extra Bars On Edge 6 1 6 6 0 - - - 361.875 -
2922 Spacer Bars 6 1 12 12 23.63 236.25 - - - - -
2923 Stirrups 3 4"&6" C/C 1 52 52 23.63 47.25 - 31.51575 - 67.5 -
2924 B4 0 7.00 42 - - - 18 -
2925 Grid L / 16-17 0 1.00 12 - - - - -
2926 Main Bars 6 1 10 10 6.08 316.16 118.56 - - - -
2927 Main Bars 4 1 2 2 0 - - - - -
2928 Extra Bars On Edge 6 1 6 6 0 - - - 1730.85 -
2929 Spacer Bars 6 1 12 12 24.13 241.25 - - - - -
2930 Stirrups 3 4"&6" C/C 1 51 51 24.13 48.25 - 32.18275 - 1008 -
2931 B4 0 7.50 45 - - - 445.5 -
2932 OPD CURVE 0 1.00 12 - - - 45 -
2933 Main Bars 6 1 10 10 6.08 310.08 116.28 - - - -
2934 Main Bars 4 1 2 2 0 - - - - -
2935 Extra Bars On Centers 6 7 6 42 0 - - - - -
2936 Extra Bars On Centers 6 3 6 18 115.39 1153.9 - - - - 722.769
2937 Spacer Bars 6 1 30 30 112.89 225.78 - 150.59526 - - -
2938 Stirrups 3 4"&6" C/C 1 265 265 16.00 672 - - - - 142.1775
2939 B5 0 16.50 297 - - - - 272.34
2940 Grid J1-K / 17-18 0 1.00 30 - - - - 18.69
2941 Main Bars 8 1 10 10 6.08 1611.2 604.2 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2942 Main Bars 4 1 2 2 0 - - - - -
2943 Extra Bars 8 1 6 6 0 - - - - -
2944 Extra Bars 8 2 6 12 27.07 270.7 - - - - -
2945 Spacer Bars 8 1 7 7 26.57 53.14 - 35.44438 - - 1005.522
2946 Stirrups 3 4" C/C 1 65 65 8.875 53.25 - - - - -
2947 Stirrups 3 4" C/C 1 38 38 8.50 102 - - - - 142.1775
2948 B5 0 1.00 7 - - - - 144.18
2949 Grid K-L / 17-18 0 7.08 460.2 172.575 - - - 21.36
2950 Main Bars 8 1 10 10 6.00 228 85.5 - - - -
2951 Main Bars 4 1 2 2 0 - - - - -
2952 Extra Bars 8 1 6 6 0 - - - - -
2953 Extra Bars 8 1 6 6 37.66 376.6 - - - - -
2954 Spacer Bars 8 1 8 8 37.16 74.32 - 49.57144 - - 947.85
2955 Stirrups 3 4" C/C 1 104 104 8.875 53.25 - - - - -
2956 Stirrups 3 4" C/C 1 38 38 9.00 54 - - - - 142.1775
2957 B5 0 1.00 8 - - - - 128.16
2958 Grid L-M / 17-18 0 7.08 736.32 276.12 - - - 18.69
2959 Main Bars 8 1 10 10 6.00 228 85.5 - - - -
2960 Main Bars 4 1 2 2 0 - - - - -
2961 Extra Bars 8 1 6 6 0 - - - - -
2962 Extra Bars 8 1 6 6 35.50 355 - - - 312.75 -
2963 Spacer Bars 8 1 7 7 35.00 70 - 46.69 - - -
2964 Stirrups 3 4" C/C 1 97 97 8.875 53.25 - - - - -
2965 Stirrups 3 4" C/C 1 38 38 8.00 48 - - - - -
2966 CB1 ( Curve ) 0 1.00 7 - - - 148.5 -
2967 Main Bars 6 1 3 3 7.08 686.76 257.535 - - - -
2968 Main Bars 4 1 2 2 6.00 228 85.5 - - - -
2969 Stirrups 3 9" C/C 1 72 72 0 - - - - -
2970 CB2 ( Paramedics Lounge ) 0 69.50 208.5 - - - 155.25 -
2971 Main Bars 6 1 3 3 68.25 136.5 - 91.0455 - - -
2972 Main Bars 4 1 2 2 3.16 227.52 85.32 - - - -
2973 Stirrups 3 9" C/C 1 32 32 0 - - - - -
2974 CB3 ( Wash & CH: ) 0 33.00 99 - - - 112.5 -
2975 Main Bars 6 1 3 3 33.00 66 - 44.022 - - -
2976 Main Bars 4 1 2 2 3.16 101.12 37.92 - - - -
2977 Stirrups 3 9" C/C 1 42 42 0 - - - - -
2978 CB4 ( Wash & CH: ) 0 34.50 103.5 - - - 131.625 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
2979 Main Bars 6 1 3 3 34.50 69 - 46.023 - - -
2980 Main Bars 4 1 2 2 3.16 132.72 49.77 - - - -
2981 Stirrups 3 9" C/C 1 26 26 0 - - - - -
2982 CB5 ( Nurses Lounge ) 0 25.00 75 - - - 74.25 -
2983 Main Bars 6 1 3 3 25.00 50 - 33.35 - - -
2984 Main Bars 4 1 2 2 3.16 82.16 30.81 - - - -
2985 Stirrups 3 9" C/C 1 32 32 0 - - - - -
2986 CB6 ( Junior Doctor Lounge ) 0 29.25 87.75 - - - 90 -
2987 Main Bars 6 1 3 3 29.25 58.5 - 39.0195 - - -
2988 Main Bars 4 1 2 2 3.16 101.12 37.92 - - - -
2989 Stirrups 3 9" C/C 1 18 18 0 - - - - -
2990 CB7 ( O.T Nurse ) 0 16.50 49.5 - - - - -
2991 Main Bars 6 1 3 3 16.50 33 - 22.011 - - -
2992 Main Bars 4 1 2 2 3.16 56.88 21.33 - - - -
2993 Stirrups 3 9" C/C 1 23 23 0 - - - - -
2994 Slab Steel 0 20.00 60 - - - - -
2995 Grid F-I / 13-16 0 20.00 40 - 26.68 - - -
2996 Main Bars 4 8" C/C 1 55 55 3.16 72.68 27.255 - - - -
2997 Dist Bars 4 8" C/C 1 76 76 0 - - - - -
2998 Grid I-J / 13-16 0 0 - - - - -
2999 Main Bars 4 8" C/C 1 55 55 54.31 2987.05 - 1992.36235 - - -
3000 Dist Bars 4 10" C/C 1 14 14 39.46 2998.96 - 2000.30632 - - -
3001 Grid J-N / 13-16 0 0 - - - - -
3002 Main Bars 4 8" C/C 1 55 55 13.50 742.5 - 495.2475 - - -
3003 Dist Bars 4 8" C/C 1 96 96 39.46 552.44 - 368.47748 - - -
3004 Grid N-N1 / 15'-16 0 0 - - - - -
3005 Main Bars 4 7" C/C 1 14 14 69.88 3843.125 - 2563.364375 - - -
3006 Dist Bars 4 8" C/C 1 6 6 39.46 3788.16 - 2526.70272 - - -
3007 Grid J-N / 16-17 0 0 - - - - -
3008 Main Bars 4 8" C/C 1 31 31 8.00 112 - 74.704 - - -
3009 Dist Bars 4 8" C/C 1 98 98 10.13 60.75 - 40.52025 - - -
3010 Curve 0 0 - - - - -
3011 Grid J-K / 17-18 0 70.25 2177.75 - 1452.55925 - - -
3012 Main Bars 4 7" C/C 1 23 23 22.16 2171.68 - 1448.51056 - - -
3013 Dist Bars 4 8" C/C 1 26 26 0 - - - - -
3014 Grid K-L / 17-19 0 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3015 Main Bars 4 7" C/C 1 57 57 12.94 297.62 - 198.51254 - - -
3016 Dist Bars 4 8" C/C 1 29 29 15.77 410.02 - 273.48334 - - -
3017 Grid L-M / 17-19 0 0 - - - - -
3018 Main Bars 4 7" C/C 1 59 59 17.00 969 - 646.323 - - -
3019 Dist Bars 4 8" C/C 1 24 24 32.00 928 - 618.976 - - -
3020 Grid M-N / 17-19 0 0 - - - - -
3021 Main Bars 4 7" C/C 1 53 53 18.58 1096.22 - 731.17874 - - -
3022 Dist Bars 4 8" C/C 1 21 21 35.63 855 - 570.285 - - -
3023 Extra Bars 0 0 - - - - -
3024 X-AXIS 0 18.54 982.62 - 655.40754 - - -
3025 Grid 13 / F-N 4 7" C/C 1 209 209 29.47 618.87 - 412.78629 - - -
3026 Grid 13 / F-G 3 12" C/C 1 4 4 0 - - - - -
3027 Grid 13 / G-H 3 12" C/C 1 4 4 0 - - - - -
3028 Grid 13 / H-I 3 12" C/C 1 4 4 4.75 992.75 - 662.16425 - - -
3029 Grid 13 / I-J 3 12" C/C 1 4 4 6.33 25.336 9.501 - - - -
3030 Grid 13 / J-K 3 12" C/C 1 4 4 9.50 38 14.25 - - - -
3031 Grid 13 / K-L 3 12" C/C 1 4 4 9.58 38.32 14.37 - - - -
3032 Grid 13 / L-M 3 12" C/C 1 4 4 6.00 24 9 - - - -
3033 Grid 13 / M-N 3 12" C/C 1 4 4 8.66 34.64 12.99 - - - -
3034 Grid 15 / F-N 4 7" C/C 1 209 209 8.50 34 12.75 - - - -
3035 Grid 15 / F-G 3 12" C/C 1 13 13 7.58 30.32 11.37 - - - -
3036 Grid 15 / G-H 3 12" C/C 1 13 13 8.25 33 12.375 - - - -
3037 Grid 15 / H-I 3 12" C/C 1 13 13 13.25 2769.25 - 1847.08975 - - -
3038 Grid 15 / I-J 3 12" C/C 1 13 13 6.33 82.342 30.87825 - - - -
3039 Grid 15 / J-K 3 12" C/C 1 13 13 9.50 123.5 46.3125 - - - -
3040 Grid 15 / K-L 3 12" C/C 1 13 13 9.58 124.54 46.7025 - - - -
3041 Grid 15 / L-M 3 12" C/C 1 13 13 6.00 78 29.25 - - - -
3042 Grid 15 / M-N 3 12" C/C 1 13 13 8.66 112.58 42.2175 - - - -
3043 Grid 16 / F-J 4 7" C/C 1 103 103 8.50 110.5 41.4375 - - - -
3044 Grid 16 / F-G 3 12" C/C 1 5 5 7.58 98.54 36.9525 - - - -
3045 Grid 16 / G-H 3 12" C/C 1 5 5 8.25 107.25 40.21875 - - - -
3046 Grid 16 / H-I 3 12" C/C 1 5 5 5.42 558.26 - 372.35942 - - -
3047 Grid 16 / I-J 3 12" C/C 1 5 5 6.33 31.67 11.87625 - - - -
3048 Grid 16 / J-N 4 7" C/C 1 109 109 9.50 47.5 17.8125 - - - -
3049 Grid 16 / J-K 3 12" C/C 1 14 14 9.58 47.9 17.9625 - - - -
3050 Grid 16 / K-L 3 12" C/C 1 14 14 6.00 30 11.25 - - - -
3051 Grid 16 / L-M 3 12" C/C 1 14 14 14.16 1543.44 - 1029.47448 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3052 Grid 16 / M-N 3 12" C/C 1 14 14 8.66 121.24 45.465 - - - -
3053 Grid 17 / J-K 4 6" C/C 1 38 38 8.50 119 44.625 - - - -
3054 Grid 17 / J-K 3 12" C/C 1 13 13 7.58 106.12 39.795 - - - -
3055 Grid 17 / K-L 4 6" C/C 1 36 36 8.25 115.5 43.3125 - - - -
3056 Grid 17 / K-L 3 12" C/C 1 18 18 13.88 527.44 - 351.80248 - - -
3057 Grid 17 / L-M 4 6" C/C 1 28 28 8.66 112.58 42.2175 - - - -
3058 Grid 17 / L-M 3 12" C/C 1 18 18 19.00 684 - 456.228 - - -
3059 Grid 17 / M-N 4 6" C/C 1 28 28 8.50 153 57.375 - - - -
3060 Grid 17 / M-N 3 12" C/C 1 17 17 19.00 532 - 354.844 - - -
3061 Y-AXIS 0 7.58 136.44 51.165 - - - -
3062 Grid F / 13-16 4 7" C/C 1 63 63 18.00 504 - 336.168 - - -
3063 Grid F / 13-15 3 12" C/C 1 4 4 8.25 140.25 52.59375 - - - -
3064 Grid F / 15-16 3 12" C/C 1 4 4 0 - - - - -
3065 Grid G / 13-16 4 7" C/C 1 63 63 6.25 393.75 - 262.63125 - - -
3066 Grid G / 13-15 3 12" C/C 1 11 11 10.25 41 15.375 - - - -
3067 Grid G / 15-16 3 12" C/C 1 11 11 11.00 44 16.5 - - - -
3068 Grid H / 13-16 4 7" C/C 1 63 63 10.96 690.48 - 460.55016 - - -
3069 Grid H / 13-15 3 12" C/C 1 14 14 10.25 112.75 42.28125 - - - -
3070 Grid H / 15-16 3 12" C/C 1 14 14 11.00 121 45.375 - - - -
3071 Grid I / 13-16 4 7" C/C 1 63 63 13.54 853.02 - 568.96434 - - -
3072 Grid I / 13-15 3 12" C/C 1 11 11 10.25 143.5 53.8125 - - - -
3073 Grid I / 15-16 3 12" C/C 1 11 11 11.00 154 57.75 - - - -
3074 Grid J / 13-16 4 7" C/C 1 63 63 10.96 690.48 - 460.55016 - - -
3075 Grid J / 13-15 3 12" C/C 1 10 10 10.25 112.75 42.28125 - - - -
3076 Grid J / 15-16 3 12" C/C 1 10 10 11.00 121 45.375 - - - -
3077 Grid K / 13-16 4 7" C/C 1 63 63 10.75 677.25 - 451.72575 - - -
3078 Grid K / 13-15 3 12" C/C 1 12 12 10.25 102.5 38.4375 - - - -
3079 Grid K / 15-16 3 12" C/C 1 12 12 9.00 90 33.75 - - - -
3080 Grid L / 13-16 4 7" C/C 1 63 63 12.93 814.59 - 543.33153 - - -
3081 Grid L / 13-15 3 12" C/C 1 11 11 10.25 123 46.125 - - - -
3082 Grid L / 15-16 3 12" C/C 1 11 11 9.00 108 40.5 - - - -
3083 Grid M / 13-16 4 7" C/C 1 63 63 11.46 721.98 - 481.56066 - - -
3084 Grid M / 13-15 3 12" C/C 1 10 10 10.25 112.75 42.28125 - - - -
3085 Grid M / 15-16 3 12" C/C 1 10 10 9.00 99 37.125 - - - -
3086 Grid N / 13-15' 4 7" C/C 1 56 56 10.12 637.56 - 425.25252 - - -
3087 Grid N / 13-15 3 12" C/C 1 4 4 10.25 102.5 38.4375 - - - -
3088 Grid N / 15'-16 4 7" C/C 1 7 7 9.00 90 33.75 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3089 Grid N / 15-16 3 12" C/C 1 4 4 8.19 458.64 - 305.91288 - - -
3090 Grid J / 16-17 4 7" C/C 1 35 35 10.25 41 15.375 - - - -
3091 Grid J / 16-17 3 12" C/C 1 4 4 12.85 89.95 - 59.99665 - - -
3092 Grid K / 16-17 4 7" C/C 1 35 35 9.00 36 13.5 - - - -
3093 Grid K /16-17 3 12" C/C 1 12 12 5.04 176.4 - 117.6588 - - -
3094 Grid L / 16-17 4 7" C/C 1 35 35 9.00 36 13.5 - - - -
3095 Grid L /16-17 3 12" C/C 1 11 11 12.93 452.55 - 301.85085 - - -
3096 Grid M / 16-17 4 7" C/C 1 35 35 9.00 108 40.5 - - - -
3097 Grid M / 16-17 3 12" C/C 1 10 10 11.46 401.1 - 267.5337 - - -
3098 Grid N / 16-17 4 7" C/C 1 35 35 9.00 99 37.125 - - - -
3099 Grid N / 16-17 3 12" C/C 1 4 4 10.12 354.2 - 236.2514 - - -
3100 Grid J-K / 17-19 4 6" C/C 1 39 39 9.00 90 33.75 - - - -
3101 Grid J / 17-18 3 12" C/C 1 5 5 3.91 136.85 - 91.27895 - - -
3102 Grid K-L / 17-19 4 6" C/C 1 37 37 9.00 36 13.5 - - - -
3103 Grid K /17-18 3 12" C/C 1 4 4 5.66 220.74 - 147.23358 - - -
3104 Grid L-M / 17-19 4 6" C/C 1 40 40 9.00 45 16.875 - - - -
3105 Grid L /17-18 3 12" C/C 1 8 8 8.00 296 - 197.432 - - -
3106 Grid N-M / 17-19 4 6" C/C 1 79 79 13.00 52 19.5 - - - -
3107 Grid M-N / 17-18 3 12" C/C 1 8 8 8.25 330 - 220.11 - - -
3108 Grid k / 17-18 4 6" C/C 1 62 62 12.00 96 36 - - - -
3109 B5 - Grid K - 17-18 3 12" C/C 1 11 11 4.25 335.75 - 223.94525 - - -
3110 Grid L / 17-19 4 6" C/C 1 62 62 16.00 128 48 - - - -
3111 B5 - Grid L - 17-19 3 12" C/C 1 11 11 12.93 801.66 - 534.70722 - - -
3112 Grid M / 17-19 4 6" C/C 1 66 66 10.00 110 41.25 - - - -
3113 B5 - Grid M - 17-19 3 12" C/C 1 10 10 11.46 710.52 - 473.91684 - - -
3114 Steel For projection 0 15.00 165 61.875 - - - -
3115 Main Bars 4 8" C/C 1 28 28 12.08 797.28 - 531.78576 - - -
3116 Dist Bars 3 1 1 1 14.50 145 54.375 - - - -
3117 Main Bars 4 8" C/C 1 34 34 0 - - - - -
3118 Dist Bars 3 1 1 1 1.25 35 - 23.345 - - -
3119 Main Bars 4 8" C/C 2 14 28 17.58 17.58 6.5925 - - - -
3120 Dist Bars 3 2 1 2 1.25 42.5 - 28.3475 - - -
3121 Main Bars 4 8" C/C 2 33 66 22.38 22.375 8.390625 - - - -
3122 Dist Bars 3 2 1 2 1.25 35 - 23.345 - - -
3123 Curve Main Bars 4 8" C/C 1 164 164 9.00 18 6.75 - - - -
3124 Dist Bars 3 1 1 1 1.25 82.5 - 55.0275 - - -
3125 Main Bars 4 8" C/C 1 130 130 22.50 45 16.875 - - 156 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3126 Dist Bars 3 1 1 1 1.25 205 - 136.735 - - -
3127 Main Bars 4 8" C/C 1 34 34 111.55 111.55 41.83125 - - - -
3128 Dist Bars 3 1 1 1 1.25 162.5 - 108.3875 - - -
3129 For Windows 2' Projection 0 84.44 84.44 31.665 - - - -
3130 Main Bars 6 8 4 32 1.25 42.5 - 28.3475 - 915.9 -
3131 Stirrups 3 6" C/C 8 5 40 22.125 22.125 8.296875 - - 13.875 -
3132 Ramp Beams 0 0 - - - 142.5 -
3133 B1 0 3.25 104 - - - - -
3134 Grid 13 & 15 / B 1 - E1 0 2.170 86.8 32.55 - - - -
3135 Main Bars 6 2 5 10 0 - - - 262.5 -
3136 Extra Bars On Edge 6 2 1 2 0 - - - 42.75 -
3137 Extra Bars On Centers 6 10 1 10 0 - - - - -
3138 Stirrups 3 7" C/C 2 83 166 61.06 610.6 - - - - -
3139 B1 on curve 0 4.63 9.25 - - - 111.5625 -
3140 Main Bars 6 1 5 5 9.50 95 - - - 13.875 -
3141 Extra Bars On Centers 6 3 1 3 5.50 913 342.375 - - - -
3142 Stirrups 3 7" C/C 1 53 53 0 - - - - -
3143 Grid 14 / A1 - B1 0 35.00 175 - - - 333 -
3144 Main Bars 6 1 5 5 9.50 28.5 - - - 27.75 -
3145 Extra Bars On Edge 6 2 1 2 5.50 291.5 109.3125 - - 28.5 -
3146 Stirrups 3 7" C/C 1 19 19 0 - - - - -
3147 Grid B1 & E1 / 13 - 14 a 0 14.88 74.375 - - - - -
3148 Main Bars 6 2 6 12 4.63 9.25 - - - 915.9 -
3149 Extra Bars On Edge 6 4 1 4 5.50 104.5 39.1875 - - - -
3150 Extra Bars On Centers 6 2 1 2 0 - - - - -
3151 Stirrups 3 7" C/C 2 25 50 18.50 222 - - - 580.2 -
3152 ( CB ) on Grid 14 / B1 - E1 0 4.63 18.5 - - - - -
3153 Main Bars 6 2 5 10 9.50 19 - - - - -
3154 Stirrups 3 7" C/C 2 83 166 5.50 275 103.125 - - - -
3155 ( CB ) Grid B2,C1,C2 & D2 / 13 - 14 & 14 - 15 0 0 - - - - -
3156 Main Bars 6 8 5 40 61.06 610.6 - - - - -
3157 Stirrups 3 7" C/C 8 13 104 3.16 524.56 196.71 - - - -
3158 Ramp Slab Steel 0 0 - - - - -
3159 Grid 14 - 14a / B1 - E1 0 9.67 386.8 - - - - -
3160 Main Bars 4 10" C/C 2 61 122 3.16 328.64 123.24 - - - -
3161 Dist Bars 4 10" C/C 2 9 18 0 - - - - -
3162 Curve 0 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3163 Main Bars 4 10" C/C 2 13 26 8.75 1067.5 - 712.0225 - - -
3164 Dist Bars 4 10" C/C 2 18 36 59.00 1062 - 708.354 - - -
3165 Extra Bars 0 0 - - - - -
3166 On Grid 14a 4 10" C/C 2 61 122 14.125 367.25 - 244.95575 - - -
3167 On Grid B2 , C1 , C2 , E1 4 10" C/C 8 9 72 10.71 385.56 - 257.16852 - - -
3168 On Grid B1 4 10" C/C 4 9 36 0 - - - - -
3169 Extra Bars 0 2.50 305 - 203.435 - - -
3170 On Edges 4 10" C/C 2 29 58 7.50 540 - 360.18 - - -
3171 On Grid 14 4 10" C/C 1 12 12 7.50 270 - 180.09 - - -
3172 Temperatures Bars 0 0 - - - - -
3173 On Grid E1 3 12" C/C 2 3 6 3.33 193.14 - 128.82438 - - -
3174 On Grid E , C2 , C1 , B2 / 14 - 14a 3 12" C/C 8 6 48 5.88 70.5 - 47.0235 - - -
3175 On Grid B1 3 12" C/C 4 3 12 0 - - - - -
3176 on curve external 3 12" C/C 2 2 4 5.00 30 11.25 - - - -
3177 Grid 15 - 16 / E1 - F 0 5.00 240 90 - - - -
3178 Main Bars 4 8" C/C 1 28 28 5.00 60 22.5 - - - -
3179 Dist Bars 4 8" C/C 1 14 14 10.17 40.68 15.255 - - - -
3180 Extra Bars 0 0 - - - 36 -
3181 On Grid E1 4 7" C/C 1 32 32 12.00 336 - 224.112 - - -
3182 On Grid 15 & 16 4 7" C/C 1 15 15 21.29 298.06 - 198.80602 - - -
3183 Stairs in F.F to S.F Grid N - N1 0 0 - - - - -
3184 Beam 0 12.00 384 - 256.128 - - -
3185 Main Bars 6 1 6 6 21.29 319.35 - 213.00645 - - -
3186 Stirrups 3 6" C/C 1 9 9 0 - - - - -
3187 ( Stairs up to landing ) Main Bars 4 7" C/C 1 8 8 0 - - - - -
3188 Dist Bars 3 9" C/C 1 20 20 4.00 24 - - - - -
3189 Extra Bars 4 7" C/C 1 8 8 3.00 27 10.125 - - - -
3190 Dist Bars 3 9" C/C 1 5 5 17.625 141 - 94.047 - - -
3191 Landing 0 4.00 80 30 - - - -
3192 Main Bars T & B 4 7" C/C 2 15 30 4.000 32 - 21.344 - - -
3193 Dist Bars 4 7" C/C 2 8 16 4.000 20 7.5 - - - -
3194 Dist Bars 3 9" C/C 2 5 10 0 - - - - -
3195 ( Stairs up to F.F Slab ) Main Bars 4 7" C/C 1 8 8 7.00 210 - 140.07 - - -
3196 Dist Bars 3 9" C/C 1 20 20 9.33 149.28 - 99.56976 - - -
3197 Steel For Lifts F.Floor 0 4.50 45 16.875 - - - -
3198 Lifts 6' x 9' 0 14.375 115 - 76.705 - - -
3199 Long Walls 0 4.50 90 33.75 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3200 Main Bars 4 9" C/C 8 15 120 0 - - - - -
3201 Dist Bars 3 9" C/C 8 10 80 0 - - - - -
3202 Short Walls 0 0 - - - - -
3203 Main Bars 4 9" C/C 8 10 80 15.790 1894.8 - 1263.8316 - - -
3204 Dist Bars 3 9" C/C 8 10 80 11.25 900 337.5 - - - -
3205 Lifts 7'-3" x 6'-7.5" 0 0 - - - - -
3206 Long Walls 0 15.790 1263.2 - 842.5544 - - -
3207 Main Bars 4 9" C/C 8 13 104 8.25 660 247.5 - - - -
3208 Dist Bars 3 9" C/C 8 10 80 0 - - - - -
3209 Short Walls 0 0 - - - - 21197.664
3210 Main Bars 4 9" C/C 8 11 88 15.790 1642.16 - 1095.32072 - - -
3211 Dist Bars 3 9" C/C 8 10 80 9.00 720 270 - - - -
First Floor Column ( 2nd portion Grid 1-12/ A-
3212 P ) Up to S.F Center 0 0 - - - - -
3213 C2 0 15.790 1389.52 - 926.80984 - - -
3214 Main Bars 8 40 12 480 8.375 670 251.25 - - - 30736.6128
3215 Stirrups upto beam bottom 3 4"&6" C/C 40 27 1080 0 - - - - -
3216 Stirrups 3 4"&6" C/C 40 27 1080 0 - - - - -
3217 Stirrups 3 4"&6" C/C 40 27 1080 16.54 7939.2 - - - - -
3218 C3 0 5.5 5940 2227.5 - - - -
3219 Main Bars 8 58 12 696 4.25 4590 1721.25 - - - 529.9416
3220 Stirrups 3 4"&6" C/C 58 27 1566 4.25 4590 1721.25 - - - -
3221 Stirrups 3 4"&6" C/C 58 27 1566 0 - - - - -
3222 Stirrups 3 4"&6" C/C 58 27 1566 16.54 11511.84 - - - - -
3223 C4 0 5.5 8613 3229.875 - - - 1766.472
3224 Main Bars 8 1 12 12 4.25 6655.5 2495.8125 - - - -
3225 Stirrups 3 6" C/C 1 22 22 4.25 6655.5 2495.8125 - - - -
3226 Stirrups 3 6" C/C 1 22 22 0 - - - - -
3227 C6 0 16.54 198.48 - - - 521.25 -
3228 Main Bars 8 2 20 40 6.5 143 53.625 - - - -
3229 Stirrups 3 4" C/C 2 33 66 4.67 102.74 38.5275 - - 128.25 -
3230 First Floor Beams 2nd Portion 0 0 - - - 144 -
3231 Grid 1 / D-G ( B4 ) 0 16.54 661.6 - - - - 21.36
3232 Main Bars 6 1 10 10 7.56 498.96 187.11 - - - -
3233 Main Bars 4 1 2 2 0 - - - - -
3234 Extra Bars On Edge 6 2 6 12 0 - - - 457.38 -
3235 Extra Bars On Centers 6 1 6 6 34.75 347.5 - - - 55.125 -
3236 Spacer Bars 8 1 8 8 33.25 66.5 - 44.3555 - 65.25 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3237 Stirrups 3 4" & 6" 1 75 75 7.125 85.5 - - - - -
3238 Grid 1' / G-I ( B3 ) 0 16.00 96 - - - - -
3239 Main Bars 6 1 7 7 1.00 8 - - - 912.1875 -
3240 Extra Bars On Edge 6 2 3 6 6.08 456 171 - - 55.125 -
3241 Extra Bars On Centers 6 1 3 3 0 - - - 252 -
3242 Stirrups 3 5" & 8" 1 72 72 43.56 304.92 - - - - -
3243 Grid 1 / I-N ( B3 ) 0 6.125 36.75 - - - - -
3244 Main Bars 6 1 7 7 14.50 43.5 - - - 2709 -
3245 Extra Bars On Edge 6 2 3 6 6.08 437.76 164.16 - - 220.5 -
3246 Extra Bars On Centers 6 4 3 12 0 - - - 504 -
3247 Stirrups 3 5" & 8" 1 155 155 86.875 608.125 - - - 540 -
3248 Grid 2,4,5,7,8,10,11&12 / A-C ( B3 ) 0 6.125 36.75 - - - - -
3249 Main Bars 6 8 7 56 14.00 168 - - - - -
3250 Extra Bars On Edge 6 8 3 24 6.08 942.4 353.4 - - 5827.5 -
3251 Extra Bars On Centers 6 8 3 24 0 - - - - -
3252 Extra Bars On Centers 6 8 3 24 32.25 1806 - - - 283.5 -
3253 Stirrups 3 5" & 8" 8 57 456 6.125 147 - - - 504 -
3254 Grid 2,4,5,7,8,10&11 / C-G ( B4 ) 0 14.00 336 - - - - 242.97
3255 Main Bars 6 7 10 70 15.00 360 - - - - -
3256 Main Bars 4 7 2 14 6.08 2772.48 1039.68 - - - -
3257 Extra Bars On Edge 6 7 3 21 0 - - - 2339.4 -
3258 Extra Bars On Centers 6 7 3 21 55.50 3885 - - - 137.8125 -
3259 Spacer Bars 8 7 13 91 55.00 770 - 513.59 - 337.5 -
3260 Stirrups 3 4" & 6" 7 129 903 9.000 189 - - - 315 -
3261 Grid 2,4,5,7 & 8 / G-I ( B3 ) 0 16.00 336 - - - - -
3262 Main Bars 6 5 7 35 1.00 91 - - - - -
3263 Extra Bars On Edge 6 5 3 15 6.08 5490.24 2058.84 - - 3039.75 -
3264 Extra Bars On Centers 6 5 3 15 0 - - - 220.5 -
3265 Extra Bars On Centers 6 5 3 15 44.56 1559.6 - - - 756 -
3266 Stirrups 3 5" & 8" 5 75 375 6.125 91.875 - - - - -
3267 Grid 3,4,6 & 7 / J-N ( B3 ) 0 15.00 225 - - - - -
3268 Main Bars 6 4 7 28 14.00 210 - - - 912.1875 -
3269 Extra Bars On Edge 6 8 3 24 6.08 2280 855 - - 55.125 -
3270 Extra Bars On Centers 6 12 3 36 0 - - - 252 -
3271 Stirrups 3 5" & 8" 4 131 524 72.38 2026.5 - - - - -
3272 Grid 9 / I-N ( B3 ) 0 6.13 147 - - - - -
3273 Main Bars 6 1 7 7 14.00 504 - - - 280.875 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3274 Extra Bars On Edge 6 2 3 6 6.08 3185.92 1194.72 - - 63 -
3275 Extra Bars On Centers 6 4 3 12 0 - - - 0 -
3276 Stirrups 3 5" & 8" 1 155 155 86.88 608.125 - - - - -
3277 Grid 12 / E-G ( B3 ) 0 6.13 36.75 - - - - -
3278 Main Bars 6 1 7 7 14.00 168 - - - 2691.99 -
3279 Extra Bars On Edge 6 1 3 3 6.08 942.4 353.4 - - 55.125 -
3280 Extra Bars On Edge 6 0 3 0 0 - - - 882 -
3281 Stirrups 3 5" 1 50 50 26.750 187.25 - - - 0 -
3282 Grid 11 & 12 / G-N ( B3 ) 0 14.00 42 - - - - -
3283 Main Bars 6 2 7 14 15.83 0 - - - - -
3284 Extra Bars On Edge 6 2 3 6 6.08 304 114 - - - -
3285 Extra Bars On Centers 6 2 21 42 0 - - - 624.375 -
3286 Extra Bars On Centers 6 0 3 0 128.190 1794.66 - - - 128.25 -
3287 Stirrups 3 5" & 8" 2 244 488 6.125 36.75 - - - - -
3288 Y-AXIS 0 14.00 588 - - - - -
3289 Grid A / 2 - 4, 8-10, 11-12 ( B2 ) 0 15.00 0 - - - 210.375 -
3290 Main Bars 6 3 6 18 6.08 2967.04 1112.64 - - 42.75 -
3291 Extra Bars On Edge 6 3 4 12 0 - - - - -
3292 Stirrups 3 5" & 8" 3 40 120 0 - - - - -
3293 Grid A / 5 - 7 ( B2 ) 0 23.125 416.25 - - - 1732.5 -
3294 Main Bars 6 1 6 6 7.125 85.5 - - - - -
3295 Extra Bars On Edge 6 1 4 4 6.08 729.6 273.6 - - 256.5 -
3296 Stirrups 3 5" & 8" 1 41 41 0 - - - 504 -
3297 Grid B & C / 2 - 7 ( B4 ) 0 23.375 140.25 - - - - 74.76
3298 Main Bars 6 2 10 20 7.125 28.5 - - - - -
3299 Main Bars 4 2 2 4 6.08 249.28 93.48 - - - -
3300 Extra Bars On Edge 6 2 12 24 0 - - - 1725 -
3301 Extra Bars On Centers 6 2 6 12 57.750 1155 - - - - -
3302 Spacer Bars 8 2 14 28 56.250 225 - 150.075 - 256.5 -
3303 Stirrups 3 4" & 6" 2 132 264 7.125 171 - - - 504 -
3304 Grid B & C / 8 - 12 ( B4 ) 0 28.00 336 - - - - 64.08
3305 Main Bars 6 2 10 20 1.00 28 - - - - -
3306 Main Bars 4 2 2 4 6.08 1605.12 601.92 - - - -
3307 Extra Bars On Edge 6 2 12 24 0 - - - 228.75 -
3308 Extra Bars On Centers 6 2 6 12 57.500 1150 - - - - -
3309 Spacer Bars 8 2 12 24 56.000 224 - 149.408 - 123.75 -
3310 Stirrups 3 4" & 6" 1 132 132 7.125 171 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3311 Grid D / 1 - 2 ( B4 ) 0 28.00 336 - - - - -
3312 Main Bars 6 1 10 10 1.00 24 - - - 2062.5 -
3313 Main Bars 4 1 2 2 6.08 802.56 300.96 - - - -
3314 Extra Bars On Edge 6 1 6 6 0 - - - 128.25 -
3315 Stirrups 3 4" 1 34 34 15.250 152.5 - - - 144 -
3316 Grid E / 1 - 12 ( B4 ) 0 13.750 27.5 - 18.3425 - 756 -
3317 Main Bars 6 1 10 10 13.750 82.5 - - - - 117.48
3318 Main Bars 4 1 2 2 6.08 206.72 77.52 - - - -
3319 Extra Bars On Edge 6 1 12 12 0 - - - - -
3320 Extra Bars On Centers 6 1 6 6 137.500 1375 - - - 2403.75 -
3321 Extra Bars On Centers 6 1 18 18 134.500 269 - 179.423 - - -
3322 Spacer Bars 8 1 44 44 7.125 85.5 - - - 128.25 -
3323 Stirrups 3 4" & 6" 1 325 325 16.00 96 - - - 1440 -
3324 Grid G & I / 1 - 8 ( B4 ) 0 28.00 504 - - - - 138.84
3325 Main Bars 6 2 10 20 1.00 44 - - - - -
3326 Main Bars 4 2 2 4 6.08 1976 741 - - - -
3327 Extra Bars On Edge 6 2 6 12 0 - - - 1016.25 -
3328 Extra Bars On Centers 6 2 30 60 80.125 1602.5 - - - - -
3329 Spacer Bars 8 2 26 52 78.875 315.5 - 210.4385 - 168 -
3330 Stirrups 3 4" & 6" 2 193 386 7.125 85.5 - - - - 53.4
3331 Grid G & I / 8 - 11 ( B4C ) 0 16.00 960 - - - - -
3332 Main Bars 6 2 10 20 1.00 52 - - - - -
3333 Main Bars 4 2 2 4 6.08 2346.88 880.08 - - 675 -
3334 Extra Bars On Centers 6 2 2 4 0 - - - - -
3335 Spacer Bars 8 2 10 20 33.875 677.5 - - - 128.25 -
3336 Stirrups 3 4" & 6" 2 81 162 33.875 135.5 - 90.3785 - 0 -
3337 Grid G & I / 11 - 12 ( B4 ) 0 28.00 112 - - - - 37.38
3338 Main Bars 6 2 10 20 1.00 20 - - - - -
3339 Main Bars 4 2 2 4 6.08 984.96 369.36 - - - -
3340 Extra Bars On Edge 6 2 6 12 0 - - - 1156.875 -
3341 Extra Bars On Centers 6 0 6 0 22.500 450 - - - - -
3342 Spacer Bars 8 2 7 14 21.750 87 - 58.029 - 128.25 -
3343 Stirrups 3 2 51 102 7.125 85.5 - - - 576 -
3344 Grid H / 1' - 8 ( B4 ) 0 16.00 0 - - - - 53.4
3345 Main Bars 6 1 10 10 1.00 14 - - - - -
3346 Main Bars 4 1 2 2 6.08 620.16 232.56 - - - -
3347 Extra Bars On Edge 6 2 6 12 0 - - - 346.875 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3348 Extra Bars On Centers 6 4 6 24 77.125 771.25 - - - - -
3349 Spacer Bars 8 1 20 20 75.125 150.25 - 100.21675 - 128.25 -
3350 Stirrups 3 4" & 6" 1 186 186 7.125 85.5 - - - - -
3351 Grid H / 11 - 12 ( B4 ) 0 16.00 384 - - - - -
3352 Main Bars 6 1 10 10 1.00 20 - - - 10312.5 -
3353 Main Bars 4 1 2 2 6.08 1130.88 424.08 - - - -
3354 Extra Bars On Edge 6 2 6 12 0 - - - 641.25 -
3355 Stirrups 3 1 51 51 23.125 231.25 - - - 4320 -
3356 Grid J,K,L,M & N / 1 - 12 ( B4 ) 0 21.625 43.25 - 28.84775 - - 707.55
3357 Main Bars 6 5 10 50 7.125 85.5 - - - - -
3358 Main Bars 4 5 2 10 6.08 310.08 116.28 - - - -
3359 Extra Bars On Edge 6 5 12 60 0 - - - - -
3360 Extra Bars On Centers 6 5 36 180 137.500 6875 - - - 687.75 -
3361 Spacer Bars 8 5 53 265 134.500 1345 - 897.115 - 51.75 -
3362 Stirrups 3 4" & 6" 5 319 1595 7.125 427.5 - - - 173.25 -
3363 Right Side porch 0 16.00 2880 - - - - -
3364 Grid 11 & 12 / N - P ( B3 ) 0 1.00 265 - - - - -
3365 Main Bars 6 2 7 14 6.08 9697.6 3636.6 - - 208.125 -
3366 Extra Bars On Edge 6 2 3 6 0 - - - 40.5 -
3367 Extra Bars On Centers 6 2 3 6 0 - - - - -
3368 Stirrups 3 5" & 8" 2 58 116 32.750 458.5 - - - - -
3369 Grid P / 11 - 12 ( B2 ) 0 5.750 34.5 - - - - -
3370 Main Bars 6 1 6 6 19.250 115.5 - - - 546.1875 -
3371 Extra Bars On Edge 6 1 4 4 6.08 705.28 264.48 - - - -
3372 Stirrups 3 5" & 8" 1 37 37 0 - - - - -
3373 Concelled Beams 0 23.125 138.75 - - - - -
3374 Grid F / 2 - 12 0 6.750 27 - - - 60.1875 -
3375 Main Bars 6 1 3 3 6.08 224.96 84.36 - - - -
3376 Main Bars 4 1 2 2 0 - - - - -
3377 Stirrups 3 9" 1 155 155 0 - - - - -
3378 Grid F / 1 - 2 (Depressed) 0 121.375 364.125 - - - 98.4375 -
3379 Main Bars 6 1 3 3 118.875 237.75 - 158.57925 - - -
3380 Main Bars 4 1 2 2 3.160 489.8 183.675 - - - -
3381 Stirrups 3 9" 1 16 16 0 - - - - -
3382 Grid E' / 2 - 4 (Depressed) 0 13.375 40.125 - - - 115.3125 -
3383 Main Bars 6 1 3 3 13.375 26.75 - 17.84225 - - -
3384 Main Bars 4 1 2 2 4.000 64 24 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3385 Stirrups 3 9" 1 27 27 0 - - - - -
3386 Grid 3 / E - G (Depressed) 0 21.875 65.625 - - - 98.4375 -
3387 Main Bars 6 1 3 3 21.875 43.75 - 29.18125 - - -
3388 Main Bars 4 1 2 2 4.000 108 40.5 - - - -
3389 Stirrups 3 9" 1 32 32 0 - - - - -
3390 Grid E' / 5 - 7 (Depressed) 0 25.625 76.875 - - - 115.3125 -
3391 Main Bars 6 1 3 3 25.625 51.25 - 34.18375 - - -
3392 Main Bars 4 1 2 2 4.000 128 48 - - - -
3393 Stirrups 3 9" 1 27 27 0 - - - - -
3394 Grid 6 / E - G (Depressed) 0 21.875 65.625 - - - 164.0625 -
3395 Main Bars 6 1 3 3 21.875 43.75 - 29.18125 - - -
3396 Main Bars 4 1 2 2 4.000 108 40.5 - - - -
3397 Stirrups 3 9" 1 32 32 0 - - - 192.1875 -
3398 Grid E' / 8 - 10 (Depressed) 0 25.625 76.875 - - - - -
3399 Main Bars 6 1 5 5 25.625 51.25 - 34.18375 - - -
3400 Stirrups 3 9" 1 27 27 4.000 128 48 - - 164.0625 -
3401 Grid 9 / E - G (Depressed) 0 0 - - - - -
3402 Main Bars 6 1 5 5 21.875 109.375 - - - - -
3403 Stirrups 3 9" 1 32 32 4.000 108 40.5 - - 192.1875 -
3404 Grid E' / 11 - 12 (Depressed) 0 0 - - - - -
3405 Main Bars 6 1 5 5 25.625 128.125 - - - - -
3406 Stirrups 3 9" 1 27 27 4.000 128 48 - - 98.235 -
3407 Grid 11' / E - G (Depressed) 0 0 - - - - -
3408 Main Bars 6 1 5 5 21.875 109.375 - - - - -
3409 Stirrups 3 9" 1 32 32 4.000 108 40.5 - - - -
3410 Grid 2 / J - K (Depressed) 0 0 - - - 234.18 -
3411 Main Bars 6 1 3 3 25.625 128.125 - - - - -
3412 Main Bars 4 1 2 2 4.000 128 48 - - - -
3413 Stirrups 3 9" 1 25 25 0 - - - - -
3414 Grid 7' / K - N 0 21.830 65.49 - - - 99.5625 -
3415 Main Bars 6 1 3 3 21.830 43.66 - 29.12122 - - -
3416 Main Bars 4 1 2 2 4.000 100 37.5 - - - -
3417 Stirrups 3 9" 1 66 66 0 - - - - -
3418 Grid J' / 4 - 6 0 52.040 156.12 - - - 99.5625 -
3419 Main Bars 6 1 3 3 52.040 104.08 - 69.42136 - - -
3420 Main Bars 4 1 2 2 3.160 208.56 78.21 - - - -
3421 Stirrups 3 9" 1 27 27 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3422 Grid K' / 4 - 6 0 22.125 66.375 - - - 300.9375 -
3423 Main Bars 6 1 3 3 22.125 44.25 - 29.51475 - - -
3424 Main Bars 4 1 2 2 3.160 85.32 31.995 - - - -
3425 Stirrups 3 9" 1 27 27 0 - - - - -
3426 Grid M' / 7 - 12 0 22.125 66.375 - - - - -
3427 Main Bars 6 1 3 3 22.125 44.25 - 29.51475 - - -
3428 Main Bars 4 1 2 2 3.160 85.32 31.995 - - - -
3429 Stirrups 3 9" 1 82 82 0 - - - - -
3430 First Floor Slab 2nd Portion 0 66.875 200.625 - - - - -
3431 S1 0 66.875 133.75 - 89.21125 - - -
3432 Grid D-E / 1-2 0 3.160 259.12 97.17 - - - -
3433 Main Bars 4 8" C/C 1 18 18 0 - - - - -
3434 Dist Bars 4 8" C/C 1 10 10 0 - - - - -
3435 S1 0 0 - - - - -
3436 Grid E-G / 1-2 0 8.29 149.22 - 99.52974 - - -
3437 Main Bars 4 8" C/C 1 37 37 13.54 135.4 - 90.3118 - - -
3438 Dist Bars 4 8" C/C 1 18 18 0 - - - - -
3439 S4 0 0 - - - - -
3440 Grid A-B / 2-4 0 13.54 500.98 - 334.15366 - - -
3441 Main Bars 4 8" C/C 1 30 30 26 468 - 312.156 - - -
3442 Dist Bars 4 10" C/C 1 12 12 0 - - - - -
3443 S1 0 0 - - - - -
3444 Grid B-C / 2-4 0 11.92 357.6 - 238.5192 - - -
3445 Main Bars 4 8" C/C 1 30 30 21.71 260.52 - 173.76684 - - -
3446 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
3447 S2 0 0 - - - - -
3448 Grid C-E / 2-4 0 20.5 615 - 410.205 - - -
3449 Main Bars 4 7" C/C 1 44 44 21.71 607.88 - 405.45596 - - -
3450 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
3451 S1 0 0 - - - - -
3452 Grid E-G / 2-4 0 21.71 955.24 - 637.14508 - - -
3453 Main Bars 4 8" C/C 1 37 37 27.5 825 - 550.275 - - -
3454 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
3455 S1 0 0 - - - - -
3456 Grid G-H / 2-4 0 21.71 803.27 - 535.78109 - - -
3457 Main Bars 4 8" C/C 1 30 30 25.83 774.9 - 516.8583 - - -
3458 Dist Bars 4 8" C/C 1 29 29 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3459 S1 0 0 - - - - -
3460 Grid H-I / 2-4 0 20.9 627 - 418.209 - - -
3461 Main Bars 4 8" C/C 1 30 30 21.71 629.59 - 419.93653 - - -
3462 Dist Bars 4 8" C/C 1 29 29 0 - - - - -
3463 S4 0 0 - - - - -
3464 Grid B-C / 4-5 0 20.92 627.6 - 418.6092 - - -
3465 Main Bars 4 8" C/C 1 29 29 21.71 629.59 - 419.93653 - - -
3466 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3467 S2 0 0 - - - - -
3468 Grid C-E / 4-5 0 12.5 362.5 - 241.7875 - - -
3469 Main Bars 4 7" C/C 1 44 44 20.875 271.375 - 181.007125 - - -
3470 Dist Bars 4 8" C/C 1 16 16 0 - - - - -
3471 S4 0 0 - - - - -
3472 Grid E-G / 4-5 0 12.5 550 - 366.85 - - -
3473 Main Bars 4 8" C/C 1 37 37 27.5 440 - 293.48 - - -
3474 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3475 S4 0 0 - - - - -
3476 Grid G-H / 4-5 0 12.5 462.5 - 308.4875 - - -
3477 Main Bars 4 8" C/C 1 29 29 26 338 - 225.446 - - -
3478 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3479 S4 0 0 - - - - -
3480 Grid H-I / 4-5 0 12.5 362.5 - 241.7875 - - -
3481 Main Bars 4 8" C/C 1 29 29 20.89 271.57 - 181.13719 - - -
3482 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3483 S4 0 0 - - - - -
3484 Grid A-B / 5-7 0 12.5 362.5 - 241.7875 - - -
3485 Main Bars 4 8" C/C 1 31 31 20.92 271.96 - 181.39732 - - -
3486 Dist Bars 4 10" C/C 1 12 12 0 - - - - -
3487 S1 0 0 - - - - -
3488 Grid B-C / 5-7 0 11.92 369.52 - 246.46984 - - -
3489 Main Bars 4 8" C/C 1 31 31 22 264 - 176.088 - - -
3490 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
3491 S2 0 0 - - - - -
3492 Grid C-E / 5-7 0 20.5 635.5 - 423.8785 - - -
3493 Main Bars 4 7" C/C 1 44 44 22.125 619.5 - 413.2065 - - -
3494 Dist Bars 4 8" C/C 1 31 31 0 - - - - -
3495 S1 0 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3496 Grid E-G / 5-7 0 22.125 973.5 - 649.3245 - - -
3497 Main Bars 4 8" C/C 1 37 37 27.5 852.5 - 568.6175 - - -
3498 Dist Bars 4 8" C/C 1 31 31 0 - - - - -
3499 S1 0 0 - - - - -
3500 Grid G-G' / 5-7 0 22.125 818.625 - 546.022875 - - -
3501 Main Bars 4 8" C/C 1 13 13 26 806 - 537.602 - - -
3502 Main Bars 4 8" C/C 2 10 20 0 - - - - -
3503 Dist Bars 4 8" C/C 1 10 10 0 - - - - -
3504 S4 0 7.375 95.875 - 63.948625 - - -
3505 Grid E-G / 7-8 0 10 200 - 133.4 - - -
3506 Main Bars 4 8" C/C 1 37 37 22.125 221.25 - 147.57375 - - -
3507 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
3508 S4 0 0 - - - - -
3509 Grid G-H / 7-8 0 11.125 411.625 - 274.553875 - - -
3510 Main Bars 4 8" C/C 1 29 29 26.375 290.125 - 193.513375 - - -
3511 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
3512 S4 0 0 - - - - -
3513 Grid H-I / 7-8 0 11.125 322.625 - 215.190875 - - -
3514 Main Bars 4 8" C/C 1 29 29 20.9 229.9 - 153.3433 - - -
3515 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
3516 S4 0 0 - - - - -
3517 Grid A-B / 8-10,11-12 0 11.875 344.375 - 229.698125 - - -
3518 Main Bars 4 8" C/C 2 30 60 20.92 230.12 - 153.49004 - - -
3519 Dist Bars 4 10" C/C 2 12 24 0 - - - - -
3520 S1 0 0 - - - - -
3521 Grid B-C / 8-10,11-12 0 11.92 715.2 - 477.0384 - - -
3522 Main Bars 4 8" C/C 2 30 60 21.875 525 - 350.175 - - -
3523 Dist Bars 4 8" C/C 2 29 58 0 - - - - -
3524 S2 0 0 - - - - -
3525 Grid C-E /8-10,11-12 0 20.5 1230 - 820.41 - - -
3526 Main Bars 4 7" C/C 1 44 44 21.875 1268.75 - 846.25625 - - -
3527 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
3528 S1 0 0 - - - - -
3529 Grid E-G' / 8-10 0 21.875 962.5 - 641.9875 - - -
3530 Main Bars 4 8" C/C 1 37 37 27.5 825 - 550.275 - - -
3531 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
3532 For 4.375' projection Dist Bars 4 6" C/C 1 11 11 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3533 S3 0 21.875 809.375 - 539.853125 - - -
3534 Grid B-G / 10-11 0 30.75 922.5 - 615.3075 - - -
3535 Main Bars 4 8" C/C 1 118 118 33.125 364.375 - 243.038125 - - -
3536 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3537 S1 0 0 - - - - -
3538 Grid E-G / 11-12 0 12.5 1475 - 983.825 - - -
3539 Main Bars 4 8" C/C 1 37 37 78.25 1017.25 - 678.50575 - - -
3540 Dist Bars 4 8" C/C 1 30 30 0 - - - - -
3541 S1 0 0 - - - - -
3542 Grid G-H / 11-12 0 21.875 809.375 - 539.853125 - - -
3543 Main Bars 4 8" C/C 1 30 30 26 780 - 520.26 - - -
3544 Dist Bars 4 8" C/C 1 29 29 0 - - - - -
3545 S1 0 0 - - - - -
3546 Grid H-I / 11-12 0 20.91 627.3 - 418.4091 - - -
3547 Main Bars 4 8" C/C 1 30 30 21.875 634.375 - 423.128125 - - -
3548 Dist Bars 4 8" C/C 1 29 29 0 - - - - -
3549 S3 0 0 - - - - -
3550 Main Bars ( I - J ) / 1 - 8 4 8" C/C 1 114 114 20.91 627.3 - 418.4091 - - -
3551 Main Bars ( I - J ) / 8 - 11 4 8" C/C 1 46 46 21.875 634.375 - 423.128125 - - -
3552 Main Bars ( I - J ) / 11 - 12 4 8" C/C 1 30 30 0 - - - - -
3553 Dist Bars ( I - J ) / 1 - 9 4 10" C/C 1 13 13 12.5 1425 - 950.475 - - -
3554 Dist Bars ( I - J ) / 9 - 11 4 10" C/C 1 18 18 16.875 776.25 - 517.75875 - - -
3555 Dist Bars ( I - J ) / 8 - 11 4 6" C/C 1 13 13 12.5 375 - 250.125 - - -
3556 S1 0 92 1196 - 797.732 - - -
3557 Grid J-K / 1 - 3 0 32.375 582.75 - 388.69425 - - -
3558 Main Bars 4 8" C/C 1 34 34 21.875 284.375 - 189.678125 - - -
3559 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
3560 S1 0 0 - - - - -
3561 Grid K-L / 1 - 3 0 20.21 687.14 - 458.32238 - - -
3562 Main Bars 4 8" C/C 1 34 34 24.25 679 - 452.893 - - -
3563 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
3564 S1 0 0 - - - - -
3565 Grid L-M / 1 - 3 0 19.83 674.22 - 449.70474 - - -
3566 Main Bars 4 8" C/C 1 34 34 24.25 654.75 - 436.71825 - - -
3567 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
3568 S1 0 0 - - - - -
3569 Grid M-N / 1 - 3 0 15.79 536.86 - 358.08562 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3570 Main Bars 4 8" C/C 1 34 34 24.25 509.25 - 339.66975 - - -
3571 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
3572 S4 0 0 - - - - -
3573 Grid J-K / 3 - 4 0 16.17 549.78 - 366.70326 - - -
3574 Main Bars 4 8" C/C 1 27 27 24.25 533.5 - 355.8445 - - -
3575 Dist Bars 4 10" C/C 1 10 10 0 - - - - -
3576 S4 0 0 - - - - -
3577 Grid K-L / 3 - 4 0 10.125 273.375 - 182.341125 - - -
3578 Main Bars 4 8" C/C 1 28 28 20.21 202.1 - 134.8007 - - -
3579 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
3580 S4 0 0 - - - - -
3581 Grid L-M / 3 - 4 0 10.125 283.5 - 189.0945 - - -
3582 Main Bars 4 8" C/C 1 21 21 19.83 218.13 - 145.49271 - - -
3583 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
3584 S4 0 0 - - - - -
3585 Grid M-N / 3 - 4 0 10.125 212.625 - 141.820875 - - -
3586 Main Bars 4 8" C/C 1 22 22 15.79 173.69 - 115.85123 - - -
3587 Dist Bars 4 10" C/C 1 11 11 0 - - - - -
3588 S1 0 0 - - - - -
3589 Grid J-K / 4 - 6 0 10.125 222.75 - 148.57425 - - -
3590 Main Bars 4 8" C/C 1 30 30 16.17 177.87 - 118.63929 - - -
3591 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
3592 S1 0 0 - - - - -
3593 Grid K-L / 4 - 6 0 20.21 606.3 - 404.4021 - - -
3594 Main Bars 4 8" C/C 1 30 30 21.75 609 - 406.203 - - -
3595 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
3596 S1 0 0 - - - - -
3597 Grid L-M / 4 - 6 0 19.83 594.9 - 396.7983 - - -
3598 Main Bars 4 8" C/C 1 30 30 21.75 587.25 - 391.69575 - - -
3599 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
3600 S1 0 0 - - - - -
3601 Grid M-N / 4 - 6 0 15.79 473.7 - 315.9579 - - -
3602 Main Bars 4 8" C/C 1 30 30 21.75 456.75 - 304.65225 - - -
3603 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
3604 S4 0 0 - - - - -
3605 Grid J-K / 6 - 7 0 16.17 485.1 - 323.5617 - - -
3606 Main Bars 4 8" C/C 1 28 28 21.75 478.5 - 319.1595 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3607 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3608 S4 0 0 - - - - -
3609 Grid K-L / 6 - 7 0 12.5 350 - 233.45 - - -
3610 Main Bars 4 8" C/C 1 27 27 20.58 267.54 - 178.44918 - - -
3611 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3612 S4 0 0 - - - - -
3613 Grid L-M / 6 - 7 0 12.5 337.5 - 225.1125 - - -
3614 Main Bars 4 8" C/C 1 21 21 19.83 257.79 - 171.94593 - - -
3615 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3616 S4 0 0 - - - - -
3617 Grid M-N / 6 - 7 0 12.5 262.5 - 175.0875 - - -
3618 Main Bars 4 8" C/C 1 22 22 15.79 205.27 - 136.91509 - - -
3619 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3620 S1 0 0 - - - - -
3621 Grid J-K / 7 - 9 0 12.5 275 - 183.425 - - -
3622 Main Bars 4 8" C/C 1 33 33 16.17 210.21 - 140.21007 - - -
3623 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
3624 S1 0 0 - - - - -
3625 Grid K-L / 7 - 9 0 20.58 679.14 - 452.98638 - - -
3626 Main Bars 4 8" C/C 1 33 33 23.375 654.5 - 436.5515 - - -
3627 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
3628 S1 0 0 - - - - -
3629 Grid L-M / 7 - 9 0 19.83 654.39 - 436.47813 - - -
3630 Main Bars 4 8" C/C 1 33 33 23.375 631.125 - 420.960375 - - -
3631 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
3632 S1 0 0 - - - - -
3633 Grid M-N / 7 - 9 0 15.79 521.07 - 347.55369 - - -
3634 Main Bars 4 8" C/C 1 33 33 23.375 490.875 - 327.413625 - - -
3635 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
3636 S1 0 0 - - - - -
3637 Grid J-K / 9 - 11 0 16.17 533.61 - 355.91787 - - -
3638 Main Bars 4 8" C/C 1 31 31 23.375 514.25 - 343.00475 - - -
3639 Dist Bars 4 8" C/C 1 28 28 0 - - - - -
3640 S1 0 0 - - - - -
3641 Grid K-L / 9 - 11 0 20.58 637.98 - 425.53266 - - -
3642 Main Bars 4 8" C/C 1 31 31 22 616 - 410.872 - - -
3643 Dist Bars 4 8" C/C 1 27 27 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3644 S1 0 0 - - - - -
3645 Grid L-M / 9 - 11 0 19.83 614.73 - 410.02491 - - -
3646 Main Bars 4 8" C/C 1 31 31 22 594 - 396.198 - - -
3647 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
3648 S1 0 0 - - - - -
3649 Grid M-N / 9 - 11 0 15.79 489.49 - 326.48983 - - -
3650 Main Bars 4 8" C/C 1 31 31 22 462 - 308.154 - - -
3651 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
3652 S3 0 0 - - - - -
3653 Grid I-J / 11 - 12 0 16.32 505.92 - 337.44864 - - -
3654 Main Bars 4 8" C/C 1 30 30 22 484 - 322.828 - - -
3655 Dist Bars 4 10" C/C 1 13 13 0 - - - - -
3656 S1 0 0 - - - - -
3657 Grid J-K / 11 - 12 0 12.5 375 - 250.125 - - -
3658 Main Bars 4 8" C/C 1 5 5 21.875 284.375 - 189.678125 - - -
3659 Main Bars 4 8" C/C 1 16 16 0 - - - - -
3660 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
3661 S1 0 20.58 102.9 - 68.6343 - - -
3662 Grid K-L / 11 - 12 0 8.75 140 - 93.38 - - -
3663 Main Bars 4 8" C/C 1 30 30 4.5 99 - 66.033 - - -
3664 Dist Bars 4 8" C/C 1 27 27 0 - - - - -
3665 S1 0 0 - - - - -
3666 Grid L-M / 11 - 12 0 19.83 594.9 - 396.7983 - - -
3667 Main Bars 4 8" C/C 1 30 30 21.875 590.625 - 393.946875 - - -
3668 Dist Bars 4 8" C/C 1 21 21 0 - - - - -
3669 S1 0 0 - - - - -
3670 Grid M-N / 11 - 12 0 15.79 473.7 - 315.9579 - - -
3671 Main Bars 4 8" C/C 1 30 30 21.875 459.375 - 306.403125 - - -
3672 Dist Bars 4 8" C/C 1 22 22 0 - - - - -
3673 S2 0 0 - - - - -
3674 Grid N-P / 11 - 12 0 16.17 485.1 - 323.5617 - - -
3675 Main Bars 4 6" C/C 1 62 62 21.875 481.25 - 320.99375 - - -
3676 Dist Bars 4 7" C/C 1 34 34 0 - - - - -
3677 Extra Bars 0 0 - - - - -
3678 X-AXIS 0 21.875 1356.25 - 904.61875 - - -
3679 Grid 1 / D - G 4 7" C/C 1 53 53 33 1122 - 748.374 - - -
3680 Grid 1 / D - G Temp 3 12" C/C 1 3 3 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3681 Grid 1 / D - G Temp 3 12" C/C 1 3 3 0 - - - - -
3682 Grid 2 & 4 / A -B 4 7" C/C 2 17 34 3.73 197.69 - 131.85923 - - -
3683 Grid 2 & 4 / A -B Temp 3 12" C/C 2 5 10 4.74 14.22 5.3325 - - - -
3684 Grid 2 / B -D 4 7" & 6" 1 70 70 9.83 29.49 11.05875 - - - -
3685 Grid 2 / B -D Temp 3 12" C/C 1 5 5 5.375 182.75 - 121.89425 - - -
3686 Grid 2 / B -D Temp 3 12" C/C 1 5 5 6.43 64.3 24.1125 - - - -
3687 Grid 2 / D -G 4 7" C/C 1 52 52 5.375 376.25 - 250.95875 - - -
3688 Grid 2 / E -G Temp 3 12" C/C 1 12 12 5 8 3 - - - -
3689 Grid 2 / G -I 4 7" C/C 1 66 66 5 10.33 3.87375 - - - -
3690 Grid 2 / G -I Temp 3 12" C/C 1 10 10 11.29 587.08 - 391.58236 - - -
3691 Grid 4 / B -I 4 7" & 6" 1 188 188 9.83 117.96 44.235 - - - -
3692 Grid 4 / B -C Temp 3 12" C/C 1 12 12 5.375 354.75 - 236.61825 - - -
3693 Grid 4 / C -E 3 12" C/C 1 12 12 8.14 81.4 30.525 - - - -
3694 Grid 4 / E -G 3 12" C/C 1 12 12 11.04 2075.52 - 1384.37184 - - -
3695 Grid 4 / G -H 3 12" C/C 1 12 12 8 96 36 - - - -
3696 Grid4 / H -I Temp 3 12" C/C 1 12 12 10.33 123.96 46.485 - - - -
3697 Grid 5 & 7 / A -B 4 7" C/C 2 16 32 9.83 117.96 44.235 - - - -
3698 Grid 5 & 7 / A -B Temp 3 12" C/C 2 5 10 8.14 97.68 36.63 - - - -
3699 Grid 5 / B -G 4 7" & 6" 1 126 126 8.14 97.68 36.63 - - - -
3700 Grid 5 / B -C TeMP 3 12" C/C 1 12 12 5.375 172 - 114.724 - - -
3701 Grid 5 / C -E Temp 3 12" C/C 1 12 12 6.43 64.3 24.1125 - - - -
3702 Grid 5 / E -G Temp 3 12" C/C 1 12 12 11.125 1401.75 - 934.96725 - - -
3703 Grid 5 - 7 / G-G' & - H' I 4 7" C/C 2 10 20 10.4 124.8 46.8 - - - -
3704 Grid 5 , 7 / G' - H' 4 7" C/C 2 23 46 10.33 123.96 46.485 - - - -
3705 Grid 5 , 7 / G - I Temp 3 12" C/C 2 6 12 9.83 117.96 44.235 - - - -
3706 Grid 7 / B -E 4 7" & 6" 1 83 83 26.71 534.2 - 356.3114 - - -
3707 Grid 7 / B -C Temp 3 12" C/C 1 6 6 4.58 210.68 - 140.52356 - - -
3708 Grid 7 / C -E Temp 3 12" C/C 1 6 6 8.23 98.76 37.035 - - - -
3709 Grid 7 / E -G 4 7" C/C 1 42 42 5.43 450.69 - 300.61023 - - -
3710 Grid 7 / E -G Temp 3 12" C/C 1 12 12 8 48 18 - - - -
3711 Grid 8,10,11 & 12 / A -B 4 7" C/C 4 17 68 10.33 61.98 23.2425 - - - -
3712 Grid 8,10,11 & 12 / A -B Temp 3 12" C/C 4 6 24 10.67 448.14 - 298.90938 - - -
3713 Grid 8 & 12 / B -E 4 7" & 6" 1 83 83 9.83 117.96 44.235 - - - -
3714 Grid 8 & 12 / B -C Temp 3 12" C/C 1 6 6 5.375 365.5 - 243.7885 - - -
3715 Grid 8 & 12 / C -E Temp 3 12" C/C 1 6 6 6.43 154.32 57.87 - - - -
3716 Grid 8 / E -G 4 7" C/C 1 41 41 5.375 446.125 - 297.565375 - - -
3717 Grid 8 / E -G Temp 3 12" C/C 1 11 11 8 48 18 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3718 Grid 8 / G -I 4 7" C/C 1 64 64 10.33 61.98 23.2425 - - - -
3719 Grid 8 / G - I Temp 3 12" C/C 1 3 3 10.42 427.22 - 284.95574 - - -
3720 Grid 10 & 11 / B -G 4 7" & 6" 2 123 246 9.75 107.25 40.21875 - - - -
3721 Grid 10 & 11 / B -C Temp 3 12" C/C 2 12 24 3.23 206.72 - 137.88224 - - -
3722 Grid 10 & 11 / C -E Temp 3 12" C/C 2 12 24 8.23 24.69 9.25875 - - - -
3723 Grid 10 & 11 / E -G Temp 3 12" C/C 2 12 24 10.875 2675.25 - 1784.39175 - - -
3724 Grid 12 / E - G 4 7" C/C 1 41 41 10.25 246 92.25 - - - -
3725 Grid 12 / E - G Temp 3 12" C/C 1 6 6 10.25 246 92.25 - - - -
3726 Grid 11 & 12 / G - I 4 7" C/C 2 64 128 9.75 234 87.75 - - - -
3727 Grid 11 & 12 / G - I Temp 3 12" C/C 2 12 24 5.125 210.125 - 140.153375 - - -
3728 Grid 1 / I - N 4 7" C/C 1 124 124 9.75 58.5 21.9375 - - - -
3729 Grid 1 / I - J 3 12" C/C 1 7 7 5.125 656 - 437.552 - - -
3730 Grid 1 / J - K 3 12" C/C 1 7 7 8.06 193.44 72.54 - - - -
3731 Grid 1 / K - L 3 12" C/C 1 7 7 5.78 716.72 - 478.05224 - - -
3732 Grid 1 / L - M 3 12" C/C 1 7 7 5.33 37.31 13.99125 - - - -
3733 Grid 1 / M - N 3 12" C/C 1 7 7 7.9 55.3 20.7375 - - - -
3734 Grid 3 / J - N 4 7" C/C 1 109 109 7.69 53.83 20.18625 - - - -
3735 Grid 3 / J - K Temp 3 12" C/C 1 12 12 6.35 44.45 16.66875 - - - -
3736 Grid 3 / K - L Temp 3 12" C/C 1 12 12 8.21 57.47 21.55125 - - - -
3737 Grid 3 / L - M Temp 3 12" C/C 1 12 12 11.08 1207.72 - 805.54924 - - -
3738 Grid 3 / M - N Temp 3 12" C/C 1 12 12 7.9 94.8 35.55 - - - -
3739 Grid 4 / J - N 4 7" C/C 1 109 109 7.69 92.28 34.605 - - - -
3740 Grid 4 / J - K 3 12" C/C 1 11 11 6.35 76.2 28.575 - - - -
3741 Grid 4 / K - L 3 12" C/C 1 11 11 8.21 98.52 36.945 - - - -
3742 Grid 4 / L - M 3 12" C/C 1 11 11 10.25 1117.25 - 745.20575 - - -
3743 Grid 4 / M - N 3 12" C/C 1 11 11 7.9 86.9 32.5875 - - - -
3744 Grid 6 / J - N 4 7" C/C 1 109 109 7.69 84.59 31.72125 - - - -
3745 Grid 6 / J - K 3 12" C/C 1 11 11 6.35 69.85 26.19375 - - - -
3746 Grid 6 / K - L 3 12" C/C 1 11 11 8.21 90.31 33.86625 - - - -
3747 Grid 6 / L - M 3 12" C/C 1 11 11 10.875 1185.375 - 790.645125 - - -
3748 Grid 6 / M - N 3 12" C/C 1 11 11 7.9 86.9 32.5875 - - - -
3749 Grid 7 / I - J 4 7" C/C 1 19 19 7.69 84.59 31.72125 - - - -
3750 Grid 7 / I - J 3 12" C/C 1 30 30 6.35 69.85 26.19375 - - - -
3751 Grid 7 / J - N 4 7" C/C 1 112 112 8.21 90.31 33.86625 - - - -
3752 Grid 7 / J - K 3 12" C/C 1 12 12 29.12 553.28 - 369.03776 - - -
3753 Grid 7 / K - L 3 12" C/C 1 12 12 6.78 203.4 76.275 - - - -
3754 Grid 7 / L - M 3 12" C/C 1 12 12 11.42 1279.04 - 853.11968 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3755 Grid 7 / M - N 3 12" C/C 1 12 12 7.9 94.8 35.55 - - - -
3756 Grid 9 / I - J 4 7" C/C 1 19 19 7.69 92.28 34.605 - - - -
3757 Grid 9 / I - J 3 12" C/C 1 15 15 6.35 76.2 28.575 - - - -
3758 Grid 9 / J - N 4 7" C/C 1 109 109 8.21 98.52 36.945 - - - -
3759 Grid 9 / J - K 3 12" C/C 1 15 15 14.42 273.98 - 182.74466 - - -
3760 Grid 9 / K - L 3 12" C/C 1 15 15 6.78 101.7 38.1375 - - - -
3761 Grid 9 / L - M 3 12" C/C 1 15 15 14.42 1571.78 - 1048.37726 - - -
3762 Grid 9 / M - N 3 12" C/C 1 15 15 7.9 118.5 44.4375 - - - -
3763 Grid 11 / I - J & K - N 4 7" C/C 1 97 97 7.69 115.35 43.25625 - - - -
3764 Grid 11 / I - J 3 12" C/C 1 15 15 6.35 95.25 35.71875 - - - -
3765 Grid 11 / K - L 3 12" C/C 1 15 15 8.21 123.15 46.18125 - - - -
3766 Grid 11 / L - M 3 12" C/C 1 15 15 13.875 1345.875 - 897.698625 - - -
3767 Grid 11 / M - N 3 12" C/C 1 15 15 6.78 101.7 38.1375 - - - -
3768 Grid 11 / J - K 4 7" C/C 1 32 32 7.69 115.35 43.25625 - - - -
3769 Grid 11 / J - K 3 12" C/C 1 6 6 6.35 95.25 35.71875 - - - -
3770 Grid 12 / I - N 4 7" C/C 1 128 128 8.21 123.15 46.18125 - - - -
3771 Grid 12 / I - J 3 12" C/C 1 6 6 5.05 161.6 - 107.7872 - - -
3772 Grid 12 / J - K 3 12" C/C 1 6 6 7.9 47.4 17.775 - - - -
3773 Grid 12 / K - L 3 12" C/C 1 6 6 5.03 643.84 - 429.44128 - - -
3774 Grid 12 / L - M 3 12" C/C 1 6 6 6.78 40.68 15.255 - - - -
3775 Grid 12 / M - N 3 12" C/C 1 6 6 7.9 47.4 17.775 - - - -
3776 Grid 11 & 12 / N - P 4 6" C/C 2 57 114 7.69 46.14 17.3025 - - - -
3777 Grid 11 & 12 / N - P 3 12" C/C 1 6 6 6.35 38.1 14.2875 - - - -
3778 Y-AXIS 0 8.21 49.26 18.4725 - - - -
3779 Grid D / 1 - 2 4 7" C/C 1 20 20 5.04 574.56 - 383.23152 - - -
3780 Grid D / 1 - 2 3 12" C/C 1 3 3 15.07 90.42 33.9075 - - - -
3781 Grid E / 1 - 2 4 7" C/C 1 20 20 0 - - - - -
3782 Grid E / 1 - 2 3 12" C/C 1 12 12 2.6 52 - 34.684 - - -
3783 Grid G / 1 - 2 4 7" C/C 1 17 17 7.08 21.24 7.965 - - - -
3784 Grid G / 1 - 2 3 12" C/C 1 15 15 10.83 216.6 - 144.4722 - - -
3785 Grid I / 1 - 2 4 7" C/C 1 17 17 7.08 84.96 31.86 - - - -
3786 Grid I / 1 - 2 3 12" C/C 1 12 12 15.06 256.02 - 170.76534 - - -
3787 Grid A / 2 -4, 8-10, 11-12 4 7" C/C 3 34 102 7.08 106.2 39.825 - - - -
3788 Grid A / 2 - 4, 8-10, 11-12 3 12" C/C 3 3 9 10.72 182.24 - 121.55408 - - -
3789 Grid A / 5 -7 4 7" C/C 1 35 35 7.08 84.96 31.86 - - - -
3790 Grid A / 5 -7 3 12" C/C 1 3 3 3.33 339.66 - 226.55322 - - -
3791 Grid B / 2 -4, 5-7,8-10 & 11-12 4 7" C/C 4 34 136 13.33 119.97 44.98875 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3792 Grid B / 2 -4, 5-7,8-10 & 11-12 3 12" C/C 4 11 44 3.33 116.55 - 77.73885 - - -
3793 Grid B / 4 -5, 10-11 4 7" C/C 2 18 36 13.78 41.34 15.5025 - - - -
3794 Grid B / 4 -5, 10-11 3 12" C/C 2 6 12 10.21 1388.56 - 926.16952 - - -
3795 Grid C / 2 -7 4 7" C/C 1 86 86 10.81 475.64 178.365 - - - -
3796 Grid C / 2 - 4 3 12" C/C 1 16 16 5.05 181.8 - 121.2606 - - -
3797 Grid C / 4 - 5 3 12" C/C 1 16 16 5.33 63.96 23.985 - - - -
3798 Grid C / 5 - 7 3 12" C/C 1 16 16 15.42 1326.12 - 884.52204 - - -
3799 Grid C / 8 -12 4 7" C/C 1 86 86 10.81 172.96 64.86 - - - -
3800 Grid C / 8 - 10 ,11-12 3 12" C/C 1 16 16 5.05 80.8 30.3 - - - -
3801 Grid C / 10 - 11 3 12" C/C 1 16 16 10.93 174.88 65.58 - - - -
3802 Grid E / 2 -7 4 7" C/C 1 86 86 15.42 1326.12 - 884.52204 - - -
3803 Grid E / 2 - 4, 5-7 3 12" C/C 2 18 36 10.81 172.96 64.86 - - - -
3804 Grid E / 4 - 5 3 12" C/C 1 18 18 5.05 80.8 30.3 - - - -
3805 Grid E / 7 -8 4 7" C/C 1 16 16 17.25 1483.5 - 989.4945 - - -
3806 Grid E / 7 - 8 3 12" C/C 1 6 6 10.81 389.16 145.935 - - - -
3807 Grid E / 8 -12 4 7" C/C 1 86 86 5.05 90.9 34.0875 - - - -
3808 Grid E / 8 - 10, 11-12 3 12" C/C 2 18 36 6.15 98.4 - 65.6328 - - -
3809 Grid E / 10 - 11 3 12" C/C 1 18 18 4.875 29.25 10.96875 - - - -
3810 Grid G / 2 -5 4 7" C/C 1 51 51 17.25 1483.5 - 989.4945 - - -
3811 Grid G / 2 - 4 3 12" C/C 1 16 16 10.81 389.16 145.935 - - - -
3812 Grid G / 4 - 5 3 12" C/C 1 16 16 5.05 90.9 34.0875 - - 1243.875 -
3813 Grid G / 5 -7 4 7" C/C 1 34 34 15.06 768.06 - 512.29602 - - -
3814 Grid G / 5 - 7 3 12" C/C 1 8 8 10.69 171.04 64.14 - - - -
3815 Grid G / 7 -8 4 7" C/C 1 16 16 4.67 74.72 28.02 - - - -
3816 Grid G / 7 - 8 3 12" C/C 1 16 16 14.25 484.5 - 323.1615 - - -
3817 Grid G / 8 -11 6 6" C/C 1 62 62 8.375 67 25.125 - - - -
3818 Grid G / 8 - 11 3 12" C/C 1 14 14 15.06 240.96 - 160.72032 - - -
3819 Grid G / 11 -12 4 7" C/C 1 34 34 6.03 96.48 36.18 - - - -
3820 Grid G / 11 - 12 3 12" C/C 1 16 16 13.375 829.25 - - - - -
3821 Grid H / 2 -5 4 7" C/C 1 51 51 32.375 453.25 169.96875 - - - -
3822 Grid H / 2 - 4 3 12" C/C 1 14 14 15.06 512.04 - 341.53068 - - -
3823 Grid H / 4 - 5 3 12" C/C 1 14 14 13.33 213.28 79.98 - - - -
3824 Grid H / 7 -8 4 7" C/C 1 16 16 13.36 681.36 - 454.46712 - - -
3825 Grid H / 7 - 8 3 12" C/C 1 14 14 10.69 149.66 56.1225 - - - -
3826 Grid H / 11 -12 4 7" C/C 1 34 34 6.67 93.38 35.0175 - 584.02016 - -
3827 Grid H / 11 - 12 3 12" C/C 1 16 16 13.36 213.76 - 142.57792 - - -
3828 Grid I / 1 - 8 4 7" C/C 1 128 128 7.18 100.52 37.695 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3829 Grid I / 2 - 4 3 12" C/C 1 7 7 15.06 512.04 - 341.53068 - - -
3830 Grid I / 4 - 5, 7-8 3 12" C/C 2 7 14 13.33 213.28 79.98 - - - -
3831 Grid I / 8 - 11 5 6" C/C 1 62 62 10.72 1372.16 - 915.23072 - - -
3832 Grid I / 8 - 11 4 6" C/C 1 10 10 10.69 74.83 28.06125 - - - -
3833 Grid I / 9 - 11 3 12" C/C 1 6 6 5.33 74.62 27.9825 - - - -
3834 Grid I / 11 - 12 4 7" C/C 1 34 34 9.04 560.48 - - - - -
3835 Grid I / 11 - 12 3 12" C/C 1 12 12 32.375 323.75 - 215.94125 - - -
3836 Grid J / 1 - 11 4 7" C/C 1 182 182 8.33 49.98 18.7425 - - - -
3837 Grid J / 1 - 3 3 12" C/C 1 12 12 10.69 363.46 - 242.42782 - - -
3838 Grid J / 3 - 4 3 12" C/C 1 12 12 13.33 159.96 59.985 - - - -
3839 Grid J / 4 - 6 3 12" C/C 1 12 12 10.56 1921.92 - 1281.92064 - - -
3840 Grid J / 6 - 7 3 12" C/C 1 12 12 18.375 220.5 82.6875 - - - -
3841 Grid J / 7 - 9 3 12" C/C 1 12 12 4.71 56.52 21.195 - - - -
3842 Grid J / 9 - 11 3 12" C/C 1 12 12 8.29 99.48 37.305 - - - -
3843 Grid J / 11 - 12 4 7" C/C 1 34 34 5.33 63.96 23.985 - - - -
3844 Grid J / 11 - 12 3 12" C/C 1 4 4 8.83 105.96 39.735 - - - -
3845 Grid K / 1 - 11 4 7" C/C 1 175 175 8.33 99.96 37.485 - - - -
3846 Grid K / 1 - 3 3 12" C/C 1 13 13 3.33 113.22 - 75.51774 - - -
3847 Grid K /3 - 4 3 12" C/C 1 13 13 10.81 43.24 16.215 - - - -
3848 Grid K /4 - 6 3 12" C/C 1 13 13 12.84 2247 - 1498.749 - - -
3849 Grid K /6 - 7 3 12" C/C 1 13 13 18.375 238.875 89.578125 - - - -
3850 Grid K /7 - 9 3 12" C/C 1 13 13 4.71 61.23 22.96125 - - - -
3851 Grid K /9 - 11 3 12" C/C 1 13 13 8.29 107.77 40.41375 - - - -
3852 Grid K / 11 - 12 4 7" C/C 1 34 34 5.33 69.29 25.98375 - - - -
3853 Grid K / 11 - 12 3 12" C/C 1 6 6 8.83 114.79 43.04625 - - - -
3854 Grid L / 1 - 12 4 7" C/C 1 209 209 10.87 141.31 52.99125 - - - -
3855 Grid L / 1 - 3 3 12" C/C 1 12 12 4.67 158.78 - 105.90626 - - -
3856 Grid L / 3 - 4 3 12" C/C 1 12 12 10.81 64.86 24.3225 - - - -
3857 Grid L / 4 - 6 3 12" C/C 1 12 12 11.29 2359.61 - 1573.85987 - - -
3858 Grid L / 6 - 7 3 12" C/C 1 12 12 18.375 220.5 82.6875 - - - -
3859 Grid L / 7 - 9 3 12" C/C 1 12 12 4.71 56.52 21.195 - - - -
3860 Grid L / 9 - 11 3 12" C/C 1 12 12 8.29 99.48 37.305 - - - -
3861 Grid L / 11 - 12 3 12" C/C 1 12 12 5.33 63.96 23.985 - - - -
3862 Grid M / 1 - 12 4 7" C/C 1 209 209 8.83 105.96 39.735 - - - -
3863 Grid M / 1 - 3 3 12" C/C 1 11 11 10.87 130.44 48.915 - - - -
3864 Grid M /3 - 4 3 12" C/C 1 11 11 10.81 129.72 48.645 - - - -
3865 Grid M /4 - 6 3 12" C/C 1 11 11 10.03 2096.27 - 1398.21209 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3866 Grid M /6 - 7 3 12" C/C 1 11 11 18.375 202.125 75.796875 - - - -
3867 Grid M /7 - 9 3 12" C/C 1 11 11 4.71 51.81 19.42875 - - - -
3868 Grid M /9 - 11 3 12" C/C 1 11 11 8.29 91.19 34.19625 - - - -
3869 Grid M /11 - 12 3 12" C/C 1 11 11 5.33 58.63 21.98625 - - - -
3870 Grid N / 1 - 11 4 7" C/C 1 175 175 8.83 97.13 36.42375 - - - -
3871 Grid N / 1 - 3 3 12" C/C 1 4 4 10.87 119.57 44.83875 - - - -
3872 Grid N / 3 - 4 3 12" C/C 1 4 4 10.81 118.91 44.59125 - - - -
3873 Grid N / 4 - 6 3 12" C/C 1 4 4 4.16 728 - 485.576 - - -
3874 Grid N / 6 - 7 3 12" C/C 1 4 4 18.375 73.5 27.5625 - - - -
3875 Grid N / 7 - 9 3 12" C/C 1 4 4 4.71 18.84 7.065 - - - -
3876 Grid N / 9 - 11 3 12" C/C 1 4 4 8.29 33.16 12.435 - - - -
3877 Grid N / 11 - 12 4 7" C/C 1 34 34 5.33 21.32 7.995 - - - -
3878 Grid N / 11 - 12 3 12" C/C 1 16 16 8.83 35.32 13.245 - - - -
3879 Grid P / 11 - 12 4 6" C/C 1 39 39 10.87 43.48 16.305 - - - -
3880 Grid P / 11 - 12 3 12" C/C 1 9 9 15.01 510.34 - 340.39678 - - -
3881 For 3" Projection 0 13.375 214 80.25 - - - -
3882 Distribution outer 0 8.85 345.15 - 230.21505 - - -
3883 Grid A 1-2, 8-10 & (11-12), 3 3 1 3 13.625 122.625 45.984375 - - - -
3884 Grid 4,5, 10 & 11 / A - B 3 4 1 4 0 - - - - -
3885 Grid 7 & 8 ( A - E) 3 2 1 2 0 - - - - -
3886 Grid A / 5 - 7 3 1 1 1 22.25 66.75 25.03125 - - - -
3887 Grid A - D1 / 2 3 1 1 1 10.75 43 16.125 - - - -
3888 Grid D1 / 1 - 2 3 1 1 1 58.25 116.5 43.6875 - - - -
3889 Grid D1 - G / 1 3 1 1 1 22.5 22.5 8.4375 - - - -
3890 Grid G & I / 1 - 1' 3 2 1 2 51.25 51.25 19.21875 - - - -
3891 Grid G - I / 1' 3 1 1 1 12.5 12.5 4.6875 - - - -
3892 Grid 1 / I - N 3 1 1 1 33.75 33.75 12.65625 - - - -
3893 Grid N / 1 - 11 3 1 1 1 3.75 7.5 2.8125 - - - -
3894 Grid N' / 12 - 16 3 1 1 1 37.25 37.25 13.96875 - - - -
3895 Grid 16 / N - N' 3 1 1 1 70.75 70.75 26.53125 - - - -
3896 Front curve 3 1 1 1 111 111 41.625 - - - -
3897 Grid J / 16 - 17 3 1 1 1 40 40 15 - - - -
3898 Grid 16 / E - J 3 1 1 1 8.75 8.75 3.28125 - - - -
3899 Grid 15 - 16 / D 3 1 1 1 133.5 133.5 50.0625 - - 390 -
3900 Grid 14a / A - D 3 1 1 1 21.25 21.25 7.96875 - - - -
3901 Curve 3 1 1 1 88.5 88.5 33.1875 - - - -
3902 Dist Bars 3 1 1 1 22 22 8.25 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3903 For Windows 2' Projection 0 34.25 34.25 12.84375 - - - 1589.8248
3904 Main Bars 6 20 4 80 31.25 31.25 11.71875 - - - -
3905 Dist Bars 3 6" C/C 20 5 100 10.5 10.5 3.9375 - - - -
Second Floor Column's ( 1st portion Grid 13-
3906 19/ A-N ) Up to T.F Center 0 0 - - - - -
3907 C-1 0 3.25 260 - - - - -
3908 Main Bars 8 3 12 36 2.17 217 81.375 - - - 5299.416
3909 Stirrups 3 4"&6" C/C 3 25 75 0 - - - - -
3910 Stirrups 3 4"&6" C/C 3 25 75 0 - - - - -
3911 Stirrups 3 4"&6" C/C 3 25 75 16.54 595.44 - - - - -
3912 C-2 0 7.5 562.5 210.9375 - - - -
3913 Main Bars 8 10 12 120 5.5 412.5 154.6875 - - - 8479.0656
3914 Stirrups 3 6" C/C 10 25 250 5.5 412.5 154.6875 - - - -
3915 Stirrups 3 6" C/C 10 25 250 0 - - - - -
3916 Stirrups 3 6" C/C 10 25 250 16.54 1984.8 - - - - -
3917 C-3 0 5.5 1375 515.625 - - - -
3918 Main Bars 8 16 12 192 4 1000 375 - - - 883.236
3919 Stirrups 3 6" C/C 16 25 400 4 1000 375 - - - 112.941
3920 Stirrups 3 6" C/C 16 25 400 0 - - - - -
3921 Stirrups 3 6" C/C 16 25 400 16.54 3175.68 - - - - -
3922 C-5 0 5.5 2200 825 - - - 8832.36
3923 Main Bars 8 1 20 20 4 1600 600 - - - -
3924 Main Bars 8 1 5 5 4 1600 600 - - - -
3925 Stirrups 3 6" C/C 1 28 28 0 - - - 1958.04 -
3926 C-6 0 16.54 330.8 - - - - -
3927 Main Bars 8 10 20 200 8.46 42.3 - - - - -
3928 Stirrups 3 6" C/C 10 28 280 9.14 255.92 95.97 - 1554.49728 - -
3929 C-7 0 0 - - - - -
3930 Main Bars 6 7 12 84 16.54 3308 - - - - -
3931 Stirrups 3 4" C/C 7 37 259 7.56 2116.8 793.8 - - - -
3932 C-9 0 0 - - - 1492.995 -
3933 Main Bars 5 12 8 96 15.54 1305.36 - - - 55.125 -
3934 Stirrups 3 6" C/C 12 22 264 4.42 1144.78 429.2925 - - 315 -
3935 B3 0 0 - - - 130.5 -
3936 Grid 13 / F-N 0 15.54 1491.84 - - - - -
3937 Main Bars 6 1 7 7 5.5 1452 544.5 - - - -
3938 Extra Bars On Edge 6 2 3 6 0 - - - - -
3939 Extra Bars On Centers 6 5 3 15 0 - - - 3500.49 -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3940 Extra Bars On Centers 6 2 3 6 142.19 995.33 - - - 55.125 -
3941 Stirrups 3 5" & 8 " 1 244 244 6.13 36.75 - - - 72 -
3942 B3 0 14.00 210 - - - 567 -
3943 Grid 15 & 16 / D-N 0 14.50 87 - - - 456.75 -
3944 Main Bars 6 2 7 14 6.08 1483.52 556.32 - - - -
3945 Extra Bars On Edge 6 2 3 6 0 - - - - -
3946 Extra Bars On Edge 6 2 3 6 0 - - - - -
3947 Extra Bars On Centers 6 9 3 27 166.69 2333.66 - - - 769.125 -
3948 Extra Bars On Centers 6 7 3 21 6.13 36.75 - - - 55.125 -
3949 Stirrups 3 5" & 8 " 2 295 590 8.00 48 - - - 63 -
3950 B3 0 14.00 378 - - - 67.5 -
3951 Grid 17 / J-N 0 14.50 304.5 - - - 65.25 -
3952 Main Bars 6 1 7 7 6.08 3587.2 1345.2 - - - -
3953 Extra Bars On Edge 6 2 3 6 0 - - - - -
3954 Extra Bars On Centers 6 1 3 3 0 - - - - -
3955 Extra Bars On Centers 6 1 3 3 73.25 512.75 - - - 204.75 -
3956 Extra Bars On Centers 6 1 3 3 6.13 36.75 - - - 42.75 -
3957 Stirrups 3 5" & 8 " 1 125 125 14.00 42 - - - 54 -
3958 B2 0 15.00 45 - - - - -
3959 Grid 15 & 16 /N - N' 0 14.50 43.5 - - - - -
3960 Main Bars 6 2 6 12 6.08 760 285 - - - -
3961 Extra Bars On Edge 6 2 2 4 0 - - - - -
3962 Extra Bars On Edge 6 2 2 4 0 - - - 420.75 -
3963 Stirrups 3 5" & 8 " 1 17 17 11.375 136.5 - - - 85.5 -
3964 Y-AXIS 0 7.125 28.5 - - - - -
3965 B2 0 9.0 36 - - - - -
3966 Grid D & N' / 15-16 0 6.08 103.36 38.76 - - - -
3967 Main Bars 6 2 6 12 0 - - - 2607 -
3968 Extra Bars On Edge 6 4 2 8 0 - - - - -
3969 Stirrups 3 5" & 8 " 2 41 82 0 - - - 513 -
3970 B4 0 23.375 280.5 - - - 594 -
3971 Grid F,G,H & I / 13-16 0 7.125 57 - - - 108 -
3972 Main Bars 6 4 10 40 6.08 498.56 186.96 - - - -
3973 Main Bars 4 4 2 8 0 - - - - -
3974 Extra Bars On Edge 6 8 6 48 0 - - - - -
3975 Extra Bars On Centers 6 4 6 24 43.45 1738 - - - 3024 -
3976 Spacer Bars 6 4 18 72 40.45 323.6 - 215.8412 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
3977 Stirrups 3 4"&6" C/C 4 97 388 7.13 342 - - - 192.375 -
3978 B4 0 16.50 396 - - - 137.25 -
3979 Grid J,K,L,M & N / 13-16 0 1.00 72 - - - 1008 -
3980 Main Bars 6 5 10 50 6.08 2359.04 884.64 - - 445.5 -
3981 Main Bars 4 5 2 10 0 - - - 180 -
3982 Extra Bars On Edge 6 3 6 18 0 - - - - -
3983 Extra Bars On Edge 6 2 6 12 40.32 2016 - - - - -
3984 Extra Bars On Centers 6 7 6 42 40.07 400.7 - 267.2669 - - -
3985 Extra Bars On Centers 6 3 6 18 7.13 128.25 - - - 1040.625 -
3986 Spacer Bars 6 4 30 120 7.63 91.5 - - - - -
3987 Stirrups 3 4"&6" C/C 4 97 388 16.00 672 - - - 58.5 -
3988 B4 0 16.50 297 - - - 288 -
3989 Grid J,M & N / 16-17 0 1.00 120 - - - 54 -
3990 Main Bars 6 3 10 30 6.08 2359.04 884.64 - - - -
3991 Main Bars 4 3 2 6 0 - - - - -
3992 Extra Bars On Edge 6 1 6 6 0 - - - - -
3993 Extra Bars On Centers 6 2 6 12 23.13 693.75 - - - 354.375 -
3994 Spacer Bars 6 3 12 36 23.13 138.75 - 92.54625 - - -
3995 Stirrups 3 4"&6" C/C 3 53 159 6.50 39 - - - 63 -
3996 B4 0 16.00 192 - - - 18 -
3997 Grid K / 16-17 0 1.00 36 - - - - -
3998 Main Bars 6 1 10 10 6.08 966.72 362.52 - - - -
3999 Main Bars 4 1 2 2 0 - - - - -
4000 Extra Bars On Edge 6 1 6 6 0 - - - 361.875 -
4001 Spacer Bars 6 1 12 12 23.63 236.25 - - - - -
4002 Stirrups 3 4"&6" C/C 1 52 52 23.63 47.25 - 31.51575 - 67.5 -
4003 B4 0 7.00 42 - - - 18 -
4004 Grid L / 16-17 0 1.00 12 - - - - -
4005 Main Bars 6 1 10 10 6.08 316.16 118.56 - - - -
4006 Main Bars 4 1 2 2 0 - - - - -
4007 Extra Bars On Edge 6 1 6 6 0 - - - 1730.85 -
4008 Spacer Bars 6 1 12 12 24.13 241.25 - - - - -
4009 Stirrups 3 4"&6" C/C 1 51 51 24.13 48.25 - 32.18275 - 1008 -
4010 B4 0 7.50 45 - - - 445.5 -
4011 OPD CURVE 0 1.00 12 - - - 45 -
4012 Main Bars 6 1 10 10 6.08 310.08 116.28 - - - -
4013 Main Bars 4 1 2 2 0 - - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
4014 Extra Bars On Centers 6 7 6 42 0 - - - - -
4015 Extra Bars On Centers 6 3 6 18 115.39 1153.9 - - - - 722.769
4016 Spacer Bars 6 1 30 30 112.89 225.78 - 150.59526 - - -
4017 Stirrups 3 4"&6" C/C 1 265 265 16.00 672 - - - - 142.1775
4018 B5 0 16.50 297 - - - - 272.34
4019 Grid J1-K / 17-18 0 1.00 30 - - - - 18.69
4020 Main Bars 8 1 10 10 6.08 1611.2 604.2 - - - -
4021 Main Bars 4 1 2 2 0 - - - - -
4022 Extra Bars 8 1 6 6 0 - - - - -
4023 Extra Bars 8 2 6 12 27.07 270.7 - - - - -
4024 Spacer Bars 8 1 7 7 26.57 53.14 - 35.44438 - - 1005.522
4025 Stirrups 3 4" C/C 1 65 65 8.875 53.25 - - - - -
4026 Stirrups 3 4" C/C 1 38 38 8.50 102 - - - - 142.1775
4027 B5 0 1.00 7 - - - - 144.18
4028 Grid K-L / 17-18 0 7.08 460.2 172.575 - - - 21.36
4029 Main Bars 8 1 10 10 6.00 228 85.5 - - - -
4030 Main Bars 4 1 2 2 0 - - - - -
4031 Extra Bars 8 1 6 6 0 - - - - -
4032 Extra Bars 8 1 6 6 37.66 376.6 - - - - -
4033 Spacer Bars 8 1 8 8 37.16 74.32 - 49.57144 - - 947.85
4034 Stirrups 3 4" C/C 1 104 104 8.875 53.25 - - - - -
4035 Stirrups 3 4" C/C 1 38 38 9.00 54 - - - - 142.1775
4036 B5 0 1.00 8 - - - - 128.16
4037 Grid L-M / 17-18 0 7.08 736.32 276.12 - - - 18.69
4038 Main Bars 8 1 10 10 6.00 228 85.5 - - - -
4039 Main Bars 4 1 2 2 0 - - - - -
4040 Extra Bars 8 1 6 6 0 - - - - -
4041 Extra Bars 8 1 6 6 35.50 355 - - - 312.75 -
4042 Spacer Bars 8 1 7 7 35.00 70 - 46.69 - - -
4043 Stirrups 3 4" C/C 1 97 97 8.875 53.25 - - - - -
4044 Stirrups 3 4" C/C 1 38 38 8.00 48 - - - - -
4045 CB1 ( Curve ) 0 1.00 7 - - - 148.5 -
4046 Main Bars 6 1 3 3 7.08 686.76 257.535 - - - -
4047 Main Bars 4 1 2 2 6.00 228 85.5 - - - -
4048 Stirrups 3 9" C/C 1 72 72 0 - - - - -
4049 CB2 ( Paramedics Lounge ) 0 69.50 208.5 - - - 155.25 -
4050 Main Bars 6 1 3 3 68.25 136.5 - 91.0455 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
4051 Main Bars 4 1 2 2 3.16 227.52 85.32 - - - -
4052 Stirrups 3 9" C/C 1 32 32 0 - - - - -
4053 CB3 ( Wash & CH: ) 0 33.00 99 - - - 112.5 -
4054 Main Bars 6 1 3 3 33.00 66 - 44.022 - - -
4055 Main Bars 4 1 2 2 3.16 101.12 37.92 - - - -
4056 Stirrups 3 9" C/C 1 42 42 0 - - - - -
4057 CB4 ( Wash & CH: ) 0 34.50 103.5 - - - 131.625 -
4058 Main Bars 6 1 3 3 34.50 69 - 46.023 - - -
4059 Main Bars 4 1 2 2 3.16 132.72 49.77 - - - -
4060 Stirrups 3 9" C/C 1 26 26 0 - - - - -
4061 CB5 ( Nurses Lounge ) 0 25.00 75 - - - 74.25 -
4062 Main Bars 6 1 3 3 25.00 50 - 33.35 - - -
4063 Main Bars 4 1 2 2 3.16 82.16 30.81 - - - -
4064 Stirrups 3 9" C/C 1 32 32 0 - - - - -
4065 CB6 ( Junior Doctor Lounge ) 0 29.25 87.75 - - - 90 -
4066 Main Bars 6 1 3 3 29.25 58.5 - 39.0195 - - -
4067 Main Bars 4 1 2 2 3.16 101.12 37.92 - - - -
4068 Stirrups 3 9" C/C 1 18 18 0 - - - - -
4069 CB7 ( O.T Nurse ) 0 16.50 49.5 - - - - -
4070 Main Bars 6 1 3 3 16.50 33 - 22.011 - - -
4071 Main Bars 4 1 2 2 3.16 56.88 21.33 - - - -
4072 Stirrups 3 9" C/C 1 23 23 0 - - - - -
4073 Slab Steel 0 20.00 60 - - - - -
4074 Grid F-I / 13-16 0 20.00 40 - 26.68 - - -
4075 Main Bars 4 8" C/C 1 55 55 3.16 72.68 27.255 - - - -
4076 Dist Bars 4 8" C/C 1 76 76 0 - - - - -
4077 Grid I-J / 13-16 0 0 - - - - -
4078 Main Bars 4 8" C/C 1 55 55 54.31 2987.05 - 1992.36235 - - -
4079 Dist Bars 4 10" C/C 1 14 14 39.46 2998.96 - 2000.30632 - - -
4080 Grid J-N / 13-16 0 0 - - - - -
4081 Main Bars 4 8" C/C 1 55 55 13.50 742.5 - 495.2475 - - -
4082 Dist Bars 4 8" C/C 1 96 96 39.46 552.44 - 368.47748 - - -
4083 Grid N-N1 / 15'-16 0 0 - - - - -
4084 Main Bars 4 7" C/C 1 14 14 69.88 3843.125 - 2563.364375 - - -
4085 Dist Bars 4 8" C/C 1 6 6 39.46 3788.16 - 2526.70272 - - -
4086 Grid J-N / 16-17 0 0 - - - - -
4087 Main Bars 4 8" C/C 1 31 31 8.00 112 - 74.704 - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
4088 Dist Bars 4 8" C/C 1 98 98 10.13 60.75 - 40.52025 - - -
4089 Curve 0 0 - - - - -
4090 Grid J-K / 17-18 0 70.25 2177.75 - 1452.55925 - - -
4091 Main Bars 4 7" C/C 1 23 23 22.16 2171.68 - 1448.51056 - - -
4092 Dist Bars 4 8" C/C 1 26 26 0 - - - - -
4093 Grid K-L / 17-19 0 0 - - - - -
4094 Main Bars 4 7" C/C 1 57 57 12.94 297.62 - 198.51254 - - -
4095 Dist Bars 4 8" C/C 1 29 29 15.77 410.02 - 273.48334 - - -
4096 Grid L-M / 17-19 0 0 - - - - -
4097 Main Bars 4 7" C/C 1 59 59 17.00 969 - 646.323 - - -
4098 Dist Bars 4 8" C/C 1 24 24 32.00 928 - 618.976 - - -
4099 Grid M-N / 17-19 0 0 - - - - -
4100 Main Bars 4 7" C/C 1 53 53 18.58 1096.22 - 731.17874 - - -
4101 Dist Bars 4 8" C/C 1 21 21 35.63 855 - 570.285 - - -
4102 Extra Bars 0 0 - - - - -
4103 X-AXIS 0 18.54 982.62 - 655.40754 - - -
4104 Grid 13 / F-N 4 7" C/C 1 209 209 29.47 618.87 - 412.78629 - - -
4105 Grid 13 / F-G 3 12" C/C 1 4 4 0 - - - - -
4106 Grid 13 / G-H 3 12" C/C 1 4 4 0 - - - - -
4107 Grid 13 / H-I 3 12" C/C 1 4 4 4.75 992.75 - 662.16425 - - -
4108 Grid 13 / I-J 3 12" C/C 1 4 4 6.33 25.336 9.501 - - - -
4109 Grid 13 / J-K 3 12" C/C 1 4 4 9.50 38 14.25 - - - -
4110 Grid 13 / K-L 3 12" C/C 1 4 4 9.58 38.32 14.37 - - - -
4111 Grid 13 / L-M 3 12" C/C 1 4 4 6.00 24 9 - - - -
4112 Grid 13 / M-N 3 12" C/C 1 4 4 8.66 34.64 12.99 - - - -
4113 Grid 15 / F-N 4 7" C/C 1 209 209 8.50 34 12.75 - - - -
4114 Grid 15 / F-G 3 12" C/C 1 13 13 7.58 30.32 11.37 - - - -
4115 Grid 15 / G-H 3 12" C/C 1 13 13 8.25 33 12.375 - - - -
4116 Grid 15 / H-I 3 12" C/C 1 13 13 13.25 2769.25 - 1847.08975 - - -
4117 Grid 15 / I-J 3 12" C/C 1 13 13 6.33 82.342 30.87825 - - - -
4118 Grid 15 / J-K 3 12" C/C 1 13 13 9.50 123.5 46.3125 - - - -
4119 Grid 15 / K-L 3 12" C/C 1 13 13 9.58 124.54 46.7025 - - - -
4120 Grid 15 / L-M 3 12" C/C 1 13 13 6.00 78 29.25 - - - -
4121 Grid 15 / M-N 3 12" C/C 1 13 13 8.66 112.58 42.2175 - - - -
4122 Grid 16 / F-J 4 7" C/C 1 103 103 8.50 110.5 41.4375 - - - -
4123 Grid 16 / F-G 3 12" C/C 1 5 5 7.58 98.54 36.9525 - - - -
4124 Grid 16 / G-H 3 12" C/C 1 5 5 8.25 107.25 40.21875 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF OLYMPI PLAZA AT QAYUM STADIUM PESHAWAR
BAR BENDING SCHEDULE OF IPC # 13
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
4125 Grid 16 / H-I 3 12" C/C 1 5 5 5.42 558.26 - 372.35942 - - -
4126 Grid 16 / I-J 3 12" C/C 1 5 5 6.33 31.67 11.87625 - - - -
4127 Grid 16 / J-N 4 7" C/C 1 109 109 9.50 47.5 17.8125 - - - -
4128 Grid 16 / J-K 3 12" C/C 1 14 14 9.58 47.9 17.9625 - - - -
4129 Grid 16 / K-L 3 12" C/C 1 14 14 6.00 30 11.25 - - - -
4130 Grid 16 / L-M 3 12" C/C 1 14 14 14.16 1543.44 - 1029.47448 - - -
4131 Grid 16 / M-N 3 12" C/C 1 14 14 8.66 121.24 45.465 - - - -
4132 Grid 17 / J-K 4 6" C/C 1 38 38 8.50 119 44.625 - - - -
4133 Grid 17 / J-K 3 12" C/C 1 13 13 7.58 106.12 39.795 - - - -
4134 Grid 17 / K-L 4 6" C/C 1 36 36 8.25 115.5 43.3125 - - - -
4135 Grid 17 / K-L 3 12" C/C 1 18 18 13.88 527.44 - 351.80248 - - -
4136 Grid 17 / L-M 4 6" C/C 1 28 28 8.66 112.58 42.2175 - - - -
4137 Grid 17 / L-M 3 12" C/C 1 18 18 19.00 684 - 456.228 - - -
4138 Grid 17 / M-N 4 6" C/C 1 28 28 8.50 153 57.375 - - - -
4139 Grid 17 / M-N 3 12" C/C 1 17 17 19.00 532 - 354.844 - - -
4140 Y-AXIS 0 7.58 136.44 51.165 - - - -
4141 Grid F / 13-16 4 7" C/C 1 63 63 18.00 504 - 336.168 - - -
4142 Grid F / 13-15 3 12" C/C 1 4 4 8.25 140.25 52.59375 - - - -
4143 Grid F / 15-16 3 12" C/C 1 4 4 0 - - - - -
4144 Grid G / 13-16 4 7" C/C 1 63 63 6.25 393.75 - 262.63125 - - -
4145 Grid G / 13-15 3 12" C/C 1 11 11 10.25 41 15.375 - - - -
4146 Grid G / 15-16 3 12" C/C 1 11 11 11.00 44 16.5 - - - -
4147 Grid H / 13-16 4 7" C/C 1 63 63 10.96 690.48 - 460.55016 - - -
4148 Grid H / 13-15 3 12" C/C 1 14 14 10.25 112.75 42.28125 - - - -
4149 Grid H / 15-16 3 12" C/C 1 14 14 11.00 121 45.375 - - - -

Contractor Q.S VERIFIED BY STE INSPECTOR


M / S NATIONAL RCC WORKS (Pvt) Ltd.

CONSTRUCTION OF OLYMPIC PLAZA

ABSTRACT OF COST ( IPC # 12 ) INTERNAL ELECTRIFICATION (CSR 2009)

Sub Head : Internal Electrification QAYUM STADIUM PESHAWER ……../…….. 2015

S.# CSR Ref # Description Unit Unit. Rate QUANTITY Amount

Wiring form Switch Board to first light, Fan point


3 / .029" single core, PVC Insulated 250/440 voltage
grade copper conductor cables in 3/4" or 1" PVC
1 15 - 50 Each 867.02 294 254903.88
conduit concealed or run on surface of walls, column's
complete in all respect and as required by the Engineer
Incharge.

Same as above item No E-1 but wiring form First light


2 15 - 50 / 2 Each 502.54 0 0.00
point to other lighy point.

Supply and Erection PVC pipes for wiring purpose


3
complete Recessed in walls including chase etc.

4 15.02.b.02 PVC conduit 20 mm ( 3/4 " ) dia Mtr 116.13 826.22 95948.87

5 15.02.b.03 PVC conduit 25 mm ( 1 " ) dia Mtr 130.72 1422.56 185957.17

6 15.02.b.06 PVC conduit 25 mm ( 2 " ) dia Mtr 178.74 472.56 84465.55

Providing and Laying of single core PVCinsulated core


7 15-05-c Mtr 42.47 167.68 7121.49
cable :7"/0.029"

Providing and Laying of single core PVCinsulated core


8 15-06-d Mtr 102.6 765.24 78514.02
cable :7"/0.036"

Contractor Q.S Consultant R.E


Providing and Laying of single core PVCinsulated core
9 15-05-e Mtr 96.5 455.79 43983.99
cable :7"/0.044"

Providing and Fixing of PVC heavy gauge Fan hook box


10 15-68-C suitable for RCC roof with MS bar 5/8" dia & Completed in Each 63.13 70 4419.10
all respect as approved by Engineer Incharge.

Supply & errection of best quality ceiling fan with GI road


11 Each 2191.13 70 153379.10
56" sweep

Total 908693.18

12 NSI ADD 38.15 PREMIUM 346666.45

13 NSI Distribution Board Each 4660 30 139800.00

supply & installation of 2 Pair cable


14 NSI Mtr 250 539.94 134984.76
approved make

supply & installation of 1 Pair cable


15 NSI Mtr 200 320.12 64024.39
approved make

NET AMOUNT 1594168.78

Contractor Q.S Consultant R.E


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……./…... 2015
S-No Description Quantity Unit
Wiring form Switch Board to first light, Fan point 2x 3 / .029"
single core, PVC Insulated 250/440 voltage grade copper
1 conductor cables in 3/4" or 1" PVC conduit concealed or run
on surface of walls, column's complete in all respect and as
required by the Engineer Incharge.
Per shop 6
Ground Floor shop 20
Stair 2
Total Quantity A 122
Per Flat 17
First Floor flat 10
Stair 2
Total Quantity B 172 Each
Total Quantity A + B 294 Each

Supply & Errection,PVC pipe for wiring purpose recessed in


2 RCC. 3/4" i/d (G-floor)
(G-floor)
form DB to AC (24 x 20) 480 Rft
form DB TO PP (24 x 20 ) 480 Rft
form DB TO ON OFF BOARD 200
(F-floor)
for AC & PP 1200
form DB TO ON OFF BOARD 350
Total Quantity 2710 Rft
OR 826.22 Mtr
Supply & Errection,PVC pipe for wiring purpose recessed in
3 RCC. 1" i/d
(G-floor)
form MDB 1050 Rft
form meter to DB (7.5 x 20) 150 Rft
For telephone 1050 Rft
(F-floor)
form MDB (29.5 x 10) 295 Rft
form DB 350 Rft
For telephone 1771 Rft
Total Quantity 4666 Rft
OR 1422.56 Mtr

Supply & Errection,PVC pipe for wiring purpose recessed in


4 RCC. 2" i/d
for main supply (G-floor) 1050 Rft
for main supply (F-floor) 500 Rft
Total Quantity 1550 Rft
OR 472.56 Mtr

5 Providing & Laying of single core cable 7"/0.029"


for on off board 550.00 Rft
OR 167.68 Mtr

6 Providing & Laying of single core cable 7"/0.036"


for DB & AC 2510.00 Rft

Contractor Q.S Verified by site Inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……./…... 2015
S-No Description Quantity Unit
OR 765.24 Mtr

7 Providing & Laying of single core cable 7"/0.044"


for MDB & METER 1495.00 Rft
OR 455.79 Mtr

8 1 PAIR TELEPHONE CABLE


G-FLOOR 1050.00 Rft
OR 320.12 Mtr

2 PAIR TELEPHONE CABLE


G-FLOOR 1771.00 Rft
OR 539.94 Mtr
9 Fan hook
Ground floor 40 Each
First floor 30 Each
Total Quantity 70 Each
10 Ceiling fan
Ground floor 40 Each
First floor 30 Each
Total Quantity 70 Each
11 Distribution Board
Ground floor 20 Each
First floor 10 Each
Total Quantity 30 Each

Contractor Q.S Verified by site Inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……./…... 2015
S-No Description Quantity Unit

B3 to G.F - DB 05 60 Rft
B Y3 to G.F - DB 05 56 Rft
R3 to G.F - DB 05 50.75 Rft
i R5 to G.F - DB 05 28 Rft
Ground Floor 2nd Portion Rft
R4 to G.F DB 01 85 Rft
ii B2 to G.F DB 01 93 Rft
B1 to G.F DB 01 53 Rft
R2 to G.F DB 01 60 Rft
Y3 to G.F DB 01 26 Rft
R1 to G.F DB 01 22 Rft
iii Y1 to G.F DB 01 28 Rft
R3 to G.F DB 01 34 Rft
B3 to G.F DB 01 34 Rft
Y2 to G.F DB 01 37 Rft
Y4 to G.F DB 01 22 Rft
iv Y2 to G.F DB 02 70 Rft
Y1 to G.F DB 02 45 Rft
R3 to G.F DB 02 48 Rft
Y3 to G.F DB 02 30 Rft
R1 to G.F DB 02 37 Rft
B1 to G.F DB 02 58 Rft
B2 to G.F DB 02 80 Rft
R2 to G.F DB 02 45 Rft
B3 to G.F DB 02 15 Rft
R4 to G.F DB 02 10 Rft
Y1 to G.F DB 03 58 Rft
v B1 to G.F DB 03 75 Rft
Y4 to G.F DB 03 85 Rft
R2 to G.F DB 03 48 Rft
B2 to G.F DB 03 34 Rft
Y2 to G.F DB 03 50 Rft
R4 to G.F DB 03 15 Rft
Y3 to G.F DB 03 55 Rft
R3 to G.F DB 03 52 Rft
R1 to G.F DB 03 78 Rft
R2 to G.F DB 04 85 Rft
R4 to G.F DB 04 80 Rft
Y2 to G.F DB 04 60 Rft
B2 to G.F DB 04 50 Rft
B3 to G.F DB 04 28 Rft
Y3 to G.F DB 04 18 Rft
R3 to G.F DB 04 18 Rft
B1 to G.F DB 04 31 Rft
Y1 to G.F DB 04 26 Rft
R1 to G.F DB 04 38 Rft
Y4 to G.F DB 04 14 Rft
PVC Conduit For Camera
Basement

Contractor Q.S Verified by site Inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……./…... 2015
S-No Description Quantity Unit
Basement 1st Portion
4 Camera 1 to Multiplexer 02 87 Rft
Camera 1 to B-DB 52 Rft
Basement 2nd Portion
Camera 2 to Multiplexer 02 31.5 Rft
Camera 2 to B-DB 43 Rft
Camera 3 to Multiplexer 01 50 Rft
Camera 3 to B-DB 103 Rft
Ground Floor porch
Camera 1 to Multiplexer 01 65 Rft
Camera 1 to DB 05 86 Rft
Camera 2 to Multiplexer 02 65 Rft
Camera 2 to DB 05 10 Rft
Ground Floor 1st Portion
Camera 1 to Multiplexer 01 54 Rft
Camera 1 to DB 05 82 Rft
Camera 2 to Multiplexer 01 30 Rft
Camera 2 to DB 05 92 Rft
Camera 3 to Multiplexer 02 38 Rft
Camera 3 to DB 05 40 Rft
Camera 4 to Multiplexer 02 65 Rft
Camera 4 to DB 05 49 Rft
Camera 5 to Multiplexer 02 124.5 Rft
Camera 5 to DB 05 45 Rft
Ground Floor 2nd Portion
Camera 1 to Multiplexer 01 48 Rft
Camera 1 to DB 04 52 Rft
Camera 2 to Multiplexer 01 24 Rft
Camera 2 to DB 04 23 Rft
Camera 3 to Multiplexer 01 66 Rft
Camera 3 to DB 01 20 Rft
Camera 4 to Multiplexer 01 106 Rft
Camera 4 to DB 01 45 Rft
Camera 5 to Multiplexer 01 110 Rft
Camera 5 to DB 01 40 Rft
Camera 1 to Multiplexer 02 25 Rft
Camera 1 to DB 02 10 Rft
Camera 2 to Multiplexer 02 60 Rft
Camera 2 to DB 02 30 Rft
Camera 3 to Multiplexer 02 110 Rft
Camera 3 to DB 02 40 Rft
Camera 4 to Multiplexer 02 120 Rft
Camera 4 to DB 02 50 Rft
Camera 5 to Multiplexer 02 185 Rft
Camera 5 to DB 02 110 Rft
Total Quantity in Rft 4610.75 Rft
Total Quantity in Mtr 428.508 Mtr
PVC conduit 25 mm ( 1 " ) dia
PVC Conduit For Fire Alarm
Basement 1st Portion
5 1st P Box to 2nd P Box. 55 Rft
A 3rd P Box to 4th P Box. 62 Rft

Contractor Q.S Verified by site Inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……./…... 2015
S-No Description Quantity Unit
B Basement 2nd Portion
C MCP 1 - MCP -2 35 Rft
MCP 2 - MCP -3 148 Rft
MCP 3 - MCP -4 79 Rft
MCP 4 - P Box. 25 Rft
3rd P Box MCP - 5 16 Rft
MCP - 5 2nd P Box 27 Rft
Ground Floor 1st Portion
1st P Box to MCP 1 414 Rft
MCP 1 - Incoming from Basement floor joint box. 70 Rft
MCP 2 - out going 1st floor joint box. 36 Rft
MCP 2 - P Box 40 Rft
Ground Floor 2nd Portion
1st P Box to MCP 1 63 Rft
MCP 1 - MCP -2 79 Rft
MCP 2 - MCP -3 200 Rft
MCP 3 - MCP -4 66 Rft
MCP 4 - MCP -5 413 Rft
MCP 5 - MCP -6 26 Rft
MCP 6 - MCP -7 247 Rft
MCP 7 - MCP -8 92 Rft
MCP 8 - 2nd P Box. 51 Rft
PVC Conduit For A.C
Ground Floor 2nd Portion
R3 to G.F A.C DB 02 85 Rft
Y3 to G.F A.C DB 02 100 Rft
B2 to G.F A.C DB 02 85 Rft
Y2 to G.F A.C DB 02 65 Rft
R2 to G.F A.C DB 02 65 Rft
B1 to G.F A.C DB 02 48 Rft
Y1 to G.F A.C DB 02 100 Rft
R1 to G.F A.C DB 02 75 Rft
R4 to G.F A.C DB 02 66 Rft
B3 to G.F A.C DB 02 92 Rft
Y3 to G.F A.C DB 03 70 Rft
R3 to G.F A.C DB 03 60 Rft
Y2 to G.F A.C DB 03 90 Rft
R2 to G.F A.C DB 03 95 Rft
B2 to G.F A.C DB 03 73 Rft
B1 to G.F A.C DB 03 38 Rft
Y1 to G.F A.C DB 03 60 Rft
R1 to G.F A.C DB 03 96 Rft
Total Quantity in Rft 3607 Rft
Total Quantity in Mtr 335.223 Mtr
Providing and Fixing of PVC heavy gauge Fan hook box suitable
for RCC roof with MS bar 5/8" dia & Completed in all respect as
approved by Engineer Incharge.
Basement 27 Each
Ground Floor 1st Portion 21 Each
Ground Floor 2nd Portion 68 Each
Total Quantity ( A + B + C ) 116 Each

Contractor Q.S Verified by site Inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……/…... 2015
S-No Description Quantity Unit
Wiring form Switch Board to first light, Fan point 2x 3 / .029"
single core, PVC Insulated 250/440 voltage grade copper
1 conductor cables in 3/4" or 1" PVC conduit concealed or run
on surface of walls, column's complete in all respect and as
required by the Engineer Incharge.
Per Flat 17
2nd Floor flat 10
Stair 2
Total Quantity 172 Each

Supply & Errection,PVC pipe for wiring purpose recessed in


2
RCC. 3/4" i/d (G-floor)
form DB to AC 480 Rft
form DB TO PP 480 Rft
Total Quantity 960 Rft
OR 292.68 Mtr
Supply & Errection,PVC pipe for wiring purpose recessed in
3
RCC. 1" i/d (G-floor)
form MDB 1050 Rft
form meter to DB 150 Rft
For telephone 1050 Rft
Total Quantity 2250 Rft
OR 685.98 Mtr

Supply & Errection,PVC pipe for wiring purpose recessed in


4 RCC. 2" i/d (G-floor)
for main supply 1050 Rft
Total Quantity 1050 Rft
OR 320.12 Mtr

Fan hook
2nd floor 40 Each
Total Quantity 40 Each
Ceiling fan
2nd floor 40 Each
Total Quantity 40 Each
Distribution Board
2nd floor 10 Each
Total Quantity 10 Each

Contractor Q.S Verified by site inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……/…... 2015
S-No Description Quantity Unit

R5 to B-DB 40 Rft
Y2 to B-DB 38 Rft
iv R3 to B-DB 25 Rft
B1 to B-DB 18 Rft
R2 to B-DB 12 Rft
Y1 to B-DB 10 Rft
R1 to B-DB 54 Rft
Ground Floor porch
B5 to G.F - DB 05 15 Rft
Ground Floor 1st Portion
Y6 to G.F - DB 05 81.5 Rft
R6 to G.F - DB 05 60 Rft
Y5 to G.F - DB 05 22 Rft
Y2 to G.F - DB 05 38 Rft
B6 to G.F - DB 05 35 Rft
R2 to G.F - DB 05 40 Rft
B2 to G.F - DB 05 55 Rft
R1 to G.F - DB 05 60 Rft
Y1 to G.F - DB 05 68.5 Rft
B1 to G.F - DB 05 71 Rft
B4 to G.F - DB 05 15 Rft
Y4 to G.F - DB 05 29 Rft
R4 to G.F - DB 05 55.25 Rft
B3 to G.F - DB 05 60 Rft
Y3 to G.F - DB 05 56 Rft
R3 to G.F - DB 05 50.75 Rft
R5 to G.F - DB 05 28 Rft
Ground Floor 2nd Portion Rft
R4 to G.F DB 01 85 Rft
B2 to G.F DB 01 93 Rft
B1 to G.F DB 01 53 Rft
R2 to G.F DB 01 60 Rft
Y3 to G.F DB 01 26 Rft
R1 to G.F DB 01 22 Rft
Y1 to G.F DB 01 28 Rft
R3 to G.F DB 01 34 Rft
B3 to G.F DB 01 34 Rft
Y2 to G.F DB 01 37 Rft
Y4 to G.F DB 01 22 Rft
Y2 to G.F DB 02 70 Rft
Y1 to G.F DB 02 45 Rft
R3 to G.F DB 02 48 Rft
Y3 to G.F DB 02 30 Rft

Contractor Q.S Verified by site inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……/…... 2015
S-No Description Quantity Unit
R1 to G.F DB 02 37 Rft
B1 to G.F DB 02 58 Rft
B B2 to G.F DB 02 80 Rft
R2 to G.F DB 02 45 Rft
i B3 to G.F DB 02 15 Rft
R4 to G.F DB 02 10 Rft
Y1 to G.F DB 03 58 Rft
ii B1 to G.F DB 03 75 Rft
Y4 to G.F DB 03 85 Rft
R2 to G.F DB 03 48 Rft
B2 to G.F DB 03 34 Rft
Y2 to G.F DB 03 50 Rft
iii R4 to G.F DB 03 15 Rft
Y3 to G.F DB 03 55 Rft
R3 to G.F DB 03 52 Rft
R1 to G.F DB 03 78 Rft
R2 to G.F DB 04 85 Rft
iv R4 to G.F DB 04 80 Rft
Y2 to G.F DB 04 60 Rft
B2 to G.F DB 04 50 Rft
B3 to G.F DB 04 28 Rft
Y3 to G.F DB 04 18 Rft
R3 to G.F DB 04 18 Rft
B1 to G.F DB 04 31 Rft
Y1 to G.F DB 04 26 Rft
R1 to G.F DB 04 38 Rft
Y4 to G.F DB 04 14 Rft
PVC Conduit For Camera
v Basement
Basement 1st Portion
Camera 1 to Multiplexer 02 87 Rft
Camera 1 to B-DB 52 Rft
Basement 2nd Portion
Camera 2 to Multiplexer 02 31.5 Rft
Camera 2 to B-DB 43 Rft
Camera 3 to Multiplexer 01 50 Rft
Camera 3 to B-DB 103 Rft
Ground Floor porch
Camera 1 to Multiplexer 01 65 Rft
Camera 1 to DB 05 86 Rft
Camera 2 to Multiplexer 02 65 Rft
Camera 2 to DB 05 10 Rft
Ground Floor 1st Portion
Camera 1 to Multiplexer 01 54 Rft
Camera 1 to DB 05 82 Rft

Contractor Q.S Verified by site inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……/…... 2015
S-No Description Quantity Unit
Camera 2 to Multiplexer 01 30 Rft
Camera 2 to DB 05 92 Rft
Camera 3 to Multiplexer 02 38 Rft
Camera 3 to DB 05 40 Rft
Camera 4 to Multiplexer 02 65 Rft
Camera 4 to DB 05 49 Rft
4 Camera 5 to Multiplexer 02 124.5 Rft
Camera 5 to DB 05 45 Rft
Ground Floor 2nd Portion
Camera 1 to Multiplexer 01 48 Rft
Camera 1 to DB 04 52 Rft
Camera 2 to Multiplexer 01 24 Rft
Camera 2 to DB 04 23 Rft
Camera 3 to Multiplexer 01 66 Rft
Camera 3 to DB 01 20 Rft
Camera 4 to Multiplexer 01 106 Rft
Camera 4 to DB 01 45 Rft
Camera 5 to Multiplexer 01 110 Rft
Camera 5 to DB 01 40 Rft
Camera 1 to Multiplexer 02 25 Rft
Camera 1 to DB 02 10 Rft
Camera 2 to Multiplexer 02 60 Rft
Camera 2 to DB 02 30 Rft
Camera 3 to Multiplexer 02 110 Rft
Camera 3 to DB 02 40 Rft
Camera 4 to Multiplexer 02 120 Rft
Camera 4 to DB 02 50 Rft
Camera 5 to Multiplexer 02 185 Rft
Camera 5 to DB 02 110 Rft
Total Quantity in Rft 5453 Rft
Total Quantity in Mtr 506.784 Mtr
PVC conduit 25 mm ( 1 " ) dia
PVC Conduit For Fire Alarm
Basement 1st Portion
1st P Box to 2nd P Box. 55 Rft
3rd P Box to 4th P Box. 62 Rft
Basement 2nd Portion
MCP 1 - MCP -2 35 Rft
MCP 2 - MCP -3 148 Rft
MCP 3 - MCP -4 79 Rft
MCP 4 - P Box. 25 Rft
3rd P Box MCP - 5 16 Rft
MCP - 5 2nd P Box 27 Rft
Ground Floor 1st Portion
1st P Box to MCP 1 414 Rft

Contractor Q.S Verified by site inspector


M / S NATIONAL RCC WORKS (Pvt) Ltd.
CONSTRUCTION OF OLYMIC PLAZA
……/…... 2015
S-No Description Quantity Unit
MCP 1 - Incoming from Basement floor joint box. 70 Rft
MCP 2 - out going 1st floor joint box. 36 Rft
MCP 2 - P Box 40 Rft
Ground Floor 2nd Portion
1st P Box to MCP 1 63 Rft
MCP 1 - MCP -2 79 Rft
MCP 2 - MCP -3 200 Rft
MCP 3 - MCP -4 66 Rft
MCP 4 - MCP -5 413 Rft
MCP 5 - MCP -6 26 Rft
5 MCP 6 - MCP -7 247 Rft
A MCP 7 - MCP -8 92 Rft
B MCP 8 - 2nd P Box. 51 Rft
C PVC Conduit For A.C
Ground Floor 2nd Portion
R3 to G.F A.C DB 02 85 Rft
Y3 to G.F A.C DB 02 100 Rft
B2 to G.F A.C DB 02 85 Rft
Y2 to G.F A.C DB 02 65 Rft
R2 to G.F A.C DB 02 65 Rft
B1 to G.F A.C DB 02 48 Rft
Y1 to G.F A.C DB 02 100 Rft
R1 to G.F A.C DB 02 75 Rft
R4 to G.F A.C DB 02 66 Rft
B3 to G.F A.C DB 02 92 Rft
Y3 to G.F A.C DB 03 70 Rft
R3 to G.F A.C DB 03 60 Rft
Y2 to G.F A.C DB 03 90 Rft
R2 to G.F A.C DB 03 95 Rft
B2 to G.F A.C DB 03 73 Rft
B1 to G.F A.C DB 03 38 Rft
Y1 to G.F A.C DB 03 60 Rft
R1 to G.F A.C DB 03 96 Rft
Total Quantity in Rft 3607 Rft
Total Quantity in Mtr 335.223 Mtr
Providing and Fixing of PVC heavy gauge Fan hook box suitable
for RCC roof with MS bar 5/8" dia & Completed in all respect as
approved by Engineer Incharge.
Basement 27 Each
Ground Floor 1st Portion 21 Each
Ground Floor 2nd Portion 68 Each
Total Quantity ( A + B + C ) 116 Each

Contractor Q.S Verified by site inspector


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF GIRLS HOSTEL AT UNIVERSITY OF SWAT
BAR BENDING SCHEDULE
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
FOOTING

1 F1 (X-AXIS) 4 6" 4 21 84 10.75 903 - 602.301 - - -


2 F1 (Y-AXIS) 4 6" 4 21 84 10.75 903 - 602.301 - - -
3 F2 (X-AXIS) 4 6" 16 19 304 9.75 2964 - 1976.988 - - -
4 F2 (Y-AXIS) 4 6" 16 19 304 9.75 2964 - 1976.988 - - -
5 F3 (X-AXIS) 4 6" 10 17 170 8.75 1487.5 - 992.1625 - - -
6 F3 (Y-AXIS) 4 6" 10 17 170 8.75 1487.5 - 992.1625 - - -
7 F5 (X-AXIS) 4 6" 4 19 76 15.75 1197 - 798.399 - - -
8 F5 (Y-AXIS) 4 6" 4 31 124 9.75 1209 - 806.403 - - -
9 F9 (X-AXIS) 4 5" 2 27 54 11.75 634.5 - 423.2115 - - -
10 F9 (Y-AXIS) 4 6" 2 23 46 11.75 540.5 - 360.5135 - - -
11 F10 (X-AXIS) 4 6" 2 17 34 9.25 314.5 - 209.7715 - - -
12 F10 (Y-AXIS) 4 6" 2 17 34 9.25 314.5 - 209.7715 - - -
13 F12 (X-AXIS) 4 5" 4 33 132 22.75 3003 - 2003.001 - - -
14 F12 (Y-AXIS) 4 6" 4 45 180 14.25 2565 - 1710.855 - - -
15 F13 (X-AXIS) 4 8" 1 25 25 23.75 593.75 - 396.03125 - - -
16 F13 (Y-AXIS) 4 8" 1 35 35 16.75 586.25 - 391.02875 - - -
17 F14 (X-AXIS) (Bottom bar)Avg cutelngth 4 4" 1 17 17 20.75 352.75 - 235.28425 - - -
18 F14 (Y-AXIS) (Top bar) Avg cutelngth 4 4" 1 17 17 19.33 328.61 - 219.18287 - - -
19 Sec:1-1 (X-AXIS) (Bottom bar) Lap 4 5" 2 49 98 130.16 12755.68 - 8508.03856 - - -
20 Sec:1-1 (Y-AXIS) (Bottom bar) 4 4" 2 369 738 20.75 15313.5 - 10214.1045 - - -
21 Sec:1-1 (X-AXIS) (Top bar) 4 4" 2 39 78 130.16 10152.48 - 6771.70416 - - -
22 Sec:1-1 (Y-AXIS) (Top bar) 4 5" 2 295 590 12.50 7375 - 4919.125 - - -
23 Sec:2-2 (X-AXIS) 4 6" 2 75 150 9.25 1387.5 - 925.4625 - - -
24 Sec:2-2 (Y-AXIS) 4 5" 2 21 42 31.75 1333.5 - 889.4445 - - -
25 Sec:3-3 (X-AXIS) 4 6" 2 77 154 7.75 1193.5 - 796.0645 - - -
26 Sec:3-3 (Y-AXIS) 4 5" 2 18 36 39.00 1404 - 936.468 - - -
27 SHORT COLUMNS
28 C1 (Grid 1,2,3/D to K,5,6,7/L) 8 13 10 130 22.33 2902.9 - - - - 7750.743
29 Stirrups (Type 1) (up to Plinth) 3 6" 13 26 338 4.50 1521 570.375 - - - -
Stirrups (Type 2) 3 6" 13 26 338 3.00 1014 380.25 - - - -
C1 8 75 10 750 13.33 9997.5 - - - - 26693.325
Stirrups (Type 1) (up to Plinth) 3 6" 13 26 338 4.50 1521 570.375 - - - -
Stirrups (Type 2) 3 6" 13 26 338 3.00 1014 380.25 - - - -
30 C2 8 4 12 48 13.33 639.84 - - - - 1708.3728
31 Stirrups (Type 1) 3 6" 4 8 32 5.50 176 66 - - - -
32 Stirrups (Type 2) 3 6" 4 8 32 3.83 122.56 45.96 - - - -
Stirrups (Type 3) 3 6" 4 8 32 3.83 122.56 45.96 - - - -
33 C3 8 10 4 40 13.33 533.2 - - - - 1423.644
34 C3 6 10 8 80 13.33 1066.4 - - - 1599.6 -
35 Stirrups (Type 1) 3 6" 10 8 80 5.50 440 165 - - - -
36 Stirrups (Type 2) 3 6" 10 8 80 3.83 306.4 114.9 - - - -
Stirrups (Type 3) 3 6" 4 8 32 3.83 122.56 45.96 - - - -
37 C4 8 4 4 16 13.33 213.28 - - - - 569.4576
38 C4 6 4 8 32 13.33 426.56 - - - 639.84 -
39 Stirrups (Type 1) 3 6" 4 8 32 5.50 176 66 - - - -

Contractor Q.S VERIFIED BY Consultants RE


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF GIRLS HOSTEL AT UNIVERSITY OF SWAT
BAR BENDING SCHEDULE
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
40 Stirrups (Type 2) 3 6" 4 8 32 3.75 120 45 - - - -
41 C5 8 1 4 4 13.33 53.32 - - - - 142.3644
42 C5 6 1 10 10 13.33 133.3 - - - 199.95 -
43 Stirrups (Type 1) 3 6" 1 10 10 5.50 55 20.625 - - - -
44 Stirrups (Type 2) 3 6" 1 10 10 3.75 37.5 14.0625 - - - -
45 C6 6 4 10 40 13.33 533.2 - - - 799.8 -
46 Stirrups 3 6" 4 8 32 5.00 160 60 - - - -
47 C7 8 2 14 28 13.33 373.24 - - - - 996.5508
48 Stirrups (Type 1) 2^r (2 x 3.142 x .875 + .5) 3 6" 2 8 16 6.00 96 36 - - - -
49 FOOTING BEAM
51 Grid 2 & 40/E to K (FB-2)
52 Bottom Bar 6 2 6 12 29.75 357 - - - 535.5 -
53 Top Bar 6 2 4 8 29.75 238 - - - 357 -
54 Stirrups 3 5" 2 70 140 8.50 1190 446.25 - - - -
55 Grid 3 & 39/D to K (FB-2)
56 Bottom Bar 6 2 6 12 38.00 456 - - - 684 -
57 Top Bar 6 2 4 8 38.00 304 - - - 456 -
58 Stirrups 3 5" 2 91 182 8.50 1547 580.125 - - - -
59 Grid 18 & 24/B to C (FB-2)
60 Bottom Bar 6 2 6 12 21.75 261 - - - 391.5 -
61 Top Bar 6 2 4 8 21.75 174 - - - 261 -
62 Stirrups 3 5" 2 52 104 8.50 884 331.5 - - - -
63 Grid 21/D to G (FB-3)
64 Bottom Bar 8 1 7 7 22.75 159.25 - - - - 425.1975
65 Top Bar 8 1 7 7 22.75 159.25 - - - - 425.1975
66 Stirrups (Type 1) 3 5" 1 54 54 9.50 513 192.375 - - - -
67 Stirrups (Type 2) 3 5" 1 54 54 9.00 486 182.25 - - - -
68 Grid D/7 to 8 & 34 to 35 (FB-2)
69 Bottom Bar 6 2 6 12 14.75 177 - - - 265.5 -
70 Top Bar 6 2 4 8 14.75 118 - - - 177 -
71 Stirrups 3 5" 2 35 70 8.50 595 223.125 - - - -
72 Grid F & H/5 to 17 & 25 to 37 (FB-1)
73 Bottom Bar 8 2 6 12 122.50 1470 - - - - 3924.9
74 Top Bar 8 2 4 8 122.50 980 - - - - 2616.6
75 Stirrups (Type 1) 3 5" 2 294 588 9.50 5586 2094.75 - - - -
76 Stirrups (Type 2) 3 5" 2 294 588 6.70 3939.6 1477.35 - - - -
77 Grid L/11 to 12 & 30 to 31 (FB-2)
78 Bottom Bar 6 2 6 12 14.75 177 - - - 265.5 -
79 Top Bar 6 2 4 8 14.75 118 - - - 177 -
80 Stirrups 3 5" 2 35 70 8.50 595 223.125 - - - -

Contractor Q.S VERIFIED BY Consultants RE


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF GIRLS HOSTEL AT UNIVERSITY OF SWAT
BAR BENDING SCHEDULE
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
81 Grid M & N/18 & 23 (FB-2)
82 Bottom Bar 6 2 6 12 21.75 261 - - - 391.5 -
83 Top Bar 6 2 4 8 21.75 174 - - - 261 -
84 Stirrups 3 5" 2 52 104 8.50 884 331.5 - - - -
85 PLINTH BEAM
86 Grid C /18 to 24 (PB-1) X-XISIS
87 Bottom Bar 6 1 3 3 48.47 145.41 - - - 218.115 -
88 Top Bar 6 1 3 3 48.47 145.41 - - - 218.115 -
89 Stirrups 3 7" 1 81 81 3.00 243 91.125 - - - -
94 Grid D/3 to 7 & 35 to 39 (PB-2 )
95 Bottom Bar 6 2 3 6 44.540 267.24 - - - 400.86 -
96 Top Bar 6 2 3 6 44.540 267.24 - - - 400.86 -
97 Stirrups 3 8" 2 60 120 3.00 360 135 - - - -
98 Grid D/8 to 17 & 25 to 34 (PB-2 )
99 Bottom Bar 6 2 3 6 85.625 513.75 - - - 770.625 -
100 Top Bar 6 2 3 6 85.625 513.75 - - - 770.625 -
101 Stirrups 3 8" 2 116 232 3.00 696 261 - - - -
106 Grid E/2 to 3 & 39 to 40 (PB-1 )
107 Bottom Bar 6 2 3 6 11.50 69 - - - 103.5 -
108 Top Bar 6 2 3 6 11.50 69 - - - 103.5 -
109 Stirrups 3 7" 2 20 40 3.00 120 45 - - - -
110 Grid F/7 to 8 & 34 to 35 (PB-1 )
111 Bottom Bar 6 2 3 6 8.25 49.5 - - - 74.25 -
112 Top Bar 6 2 3 6 8.25 49.5 - - - 74.25 -
113 Stirrups 3 7" 2 13 26 3.00 78 29.25 - - - -
114 Grid F/1 to 2 & 40 to 41 (PB-1 )
115 Bottom Bar 6 2 3 6 16.125 96.75 - - - 145.125 -
116 Top Bar 6 2 3 6 16.125 96.75 - - - 145.125 -
117 Stirrups 3 7" 2 26 52 3.00 156 58.5 - - - -
122 Grid G/3 to 7 & 35 to 39 (PB-2 )
123 Bottom Bar 6 2 3 6 44.540 267.24 - - - 400.86 -
124 Top Bar 6 2 3 6 44.540 267.24 - - - 400.86 -
125 Stirrups 3 8" 2 60 120 3.00 360 135 - - - -
126 Grid G/8 to 17 & 25 to 34 (PB-2 )
127 Bottom Bar 6 2 3 6 85.625 513.75 - - - 770.625 -
128 Top Bar 6 2 3 6 85.625 513.75 - - - 770.625 -
129 Stirrups 3 8" 2 116 232 3.00 696 261 - - - -
130 Grid G/18 to 24 (PB-2 )
131 Bottom Bar 6 1 3 3 51.720 155.16 - - - 232.74 -
132 Top Bar 6 1 3 3 51.720 155.16 - - - 232.74 -
133 Stirrups 3 8" 1 71 71 3.00 213 79.875 - - - -
134 Grid H/3 to 17 & 25 to 39 (PB-1 & 2 )
135 Bottom Bar 6 2 3 6 136.39 818.34 - - - 1227.51 -

Contractor Q.S VERIFIED BY Consultants RE


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF GIRLS HOSTEL AT UNIVERSITY OF SWAT
BAR BENDING SCHEDULE
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
136 Top Bar 6 2 3 6 136.39 818.34 - - - 1227.51 -
137 Stirrups 3 7" & 8" 2 181 362 3.00 1086 407.25 - - - -
138 Grid B/W H & K/18 to 26 (PB-2 )
139 Bottom Bar 6 1 3 3 56.22 168.66 - - - 252.99 -
140 Top Bar 6 1 3 3 56.22 168.66 - - - 252.99 -
141 Stirrups 3 8" 1 78 78 3.00 234 87.75 - - - -
142 Grid J/1 to 2 & 40 to 41 (PB-1 )
143 Bottom Bar 6 2 3 6 14.875 89.25 - - - 133.875 -
144 Top Bar 6 2 3 6 14.875 89.25 - - - 133.875 -
145 Stirrups 3 7" 2 24 48 3.00 144 54 - - - -
146 Grid K/2 to 3 & 39 to 40 (PB-1 )
147 Bottom Bar 6 2 3 6 13.250 79.5 - - - 119.25 -
148 Top Bar 6 2 3 6 13.250 79.5 - - - 119.25 -
149 Stirrups 3 7" 2 22 44 3.00 132 49.5 - - - -
150 Grid L/5 to 11 & 31 to 37 (PB-1 & 2 )
151 Bottom Bar 6 2 3 6 66.620 399.72 - - - 599.58 -
152 Top Bar 6 2 3 6 66.620 399.72 - - - 599.58 -
153 Stirrups 3 7" & 8" 2 99 198 3.00 594 222.75 - - - -
154 Grid L/12 to 14 & 28 to 30 (PB-1 & 2 )
155 Bottom Bar 6 2 3 6 31.290 187.74 - - - 281.61 -
156 Top Bar 6 2 3 6 31.290 187.74 - - - 281.61 -
157 Stirrups 3 7" & 8" 2 51 102 3.00 306 114.75 - - - -
158 Grid M/14 to 16 & 26 to 28 (PB-1 )
159 Bottom Bar 6 2 3 6 14.750 88.5 - - - 132.75 -
160 Top Bar 6 2 3 6 14.750 88.5 - - - 132.75 -
161 Stirrups 3 7" 2 24 48 3.00 144 54 - - - -
162 Grid N/17 to 26 (PB-1 )
163 Bottom Bar 6 1 3 3 56.220 168.66 - - - 252.99 -
164 Top Bar 6 1 3 3 56.220 168.66 - - - 252.99 -
165 Stirrups 3 7" 1 89 89 3.00 267 100.125 - - - -
166 Y-XISIS
167 Grid 1 & 41/F to J (PB-1 )
168 Bottom Bar 6 2 3 6 18.750 112.5 - - - 168.75 -
169 Top Bar 6 2 3 6 18.750 112.5 - - - 168.75 -
170 Stirrups 3 7" 2 31 62 3.00 186 69.75 - - - -
171 Grid 2 & 40/E to K (PB-1 & 2)
172 Bottom Bar 6 2 3 6 28.750 172.5 - - - 258.75 -
173 Top Bar 6 2 3 6 28.750 172.5 - - - 258.75 -
174 Stirrups 3 7" & 8" 2 45 90 3.00 270 101.25 - - - -

175 Grid 3 & 39/D to H (PB-1 & 2)

176 Bottom Bar 6 2 3 6 24.500 147 - - - 220.5 -


177 Top Bar 6 2 3 6 24.500 147 - - - 220.5 -
178 Stirrups 3 7" & 8" 2 38 76 3.00 228 85.5 - - - -

Contractor Q.S VERIFIED BY Consultants RE


M / S NATIONAL RCC WORKS Pvt (Ltd)
CONSTRUCTION OF GIRLS HOSTEL AT UNIVERSITY OF SWAT
BAR BENDING SCHEDULE
1 2 3 4 5 6 7= 5x6 8 9= 7x8 10 11 12 13 14
Bar No of No of Bar in Total Weight (LBS)
S.No Name & Type of member Reference
Spacing C/C
member each Numbers
Cut Length Total Length
#3 #4 #5 #6 #8
179 Grid 4 & 38/H to K (PB-1 )

180 Bottom Bar 6 2 3 6 11.125 66.75 - - - 100.125 -


181 Top Bar 6 2 3 6 11.125 66.75 - - - 100.125 -
182 Stirrups 3 7" 2 18 36 3.00 108 40.5 - - - -
Grid
183 5,6,7,8,10,12,13,14,15,27,28,29,30,32,34,35,36 &
37/D to G (PB-1 & 2)
184 Bottom Bar 6 18 3 54 16.500 891 - - - 1336.5 -
185 Top Bar 6 18 3 54 16.500 891 - - - 1336.5 -
186 Stirrups 3 7" & 8" 18 27 486 3.00 1458 546.75 - - - -
Grid 5,6,7,9,11,12,13,29,30,31,33,35,36 & 37/H
187
to L (PB-1 & 2)
188 Bottom Bar 6 14 3 42 16.720 702.24 - - - 1053.36 -
189 Top Bar 6 14 3 42 16.720 702.24 - - - 1053.36 -
190 Stirrups 3 7" & 8" 14 27 378 3.00 1134 425.25 - - - -
191 Grid 14,15,16,26,27 & 28/H to M (PB-1 & 2 )
192 Bottom Bar 6 6 3 18 18.470 332.46 - - - 498.69 -
193 Top Bar 6 6 3 18 18.470 332.46 - - - 498.69 -
194 Stirrups 3 7" & 8" 6 28 168 3.00 504 189 - - - -
195 Grid 18 & 24/C to G (PB-1 )
Grid 18 & 24/C to G (PB-1 )
Bottom Bar 6 2 3 6 32.170 193.02 - - - 289.53 -
Top Bar 6 2 3 6 32.170 193.02 - - - 289.53 -
Stirrups 3 7" 2 54 108 3.00 324 121.5 - - - -
Grid 21/C to G (PB-2 )
295 Bottom Bar 6 1 3 3 32.170 96.51 - - - 144.765 -
296 Top Bar 6 1 3 3 32.170 96.51 - - - 144.765 -
297 Stirrups 3 8" 1 47 47 3.00 141 52.875 - - - -
298 12527.3175 48866.76784 27838.14 46676.3526
299 Total Weight in Ton/Dia 5.6839008621 22.171854737 12.630735027 21.178018421
300 Total Weight in Lbs 135908.58
301 Total Weight in Kg 61664.51
302 Total Weight in Ton 61.665