Professional Documents
Culture Documents
33
July
2011
A Joint Publication of The Japan Iron and Steel Federation and Japanese Society of Steel Construction
Special Feature
Corrosion Protection for
Steel Pipe Piles and
Sheet Piles
http://www.jisf.or.jp/en/index.html
Steel Sheet and Pipe Piles
for Port Steel Structures
— Corrosion Protection Technology: Today and Tomorrow —
By D
r. Hidenori Hamada (Kyushu University), Dr. Toru Yamaji (Port and Airport Research Institute), and
Dr. Yoshikazu Akira (Port and Airport Research Institute)
The history of corrosion-protection technol- were imported to restore damage caused by ports. The Yamashita pier at the Port of Yo-
ogies in Japan extends more than 50 years. the Great Kanto Earthquake. The first steel kohama and the Maya pier at the Port of
As a result, these technologies have devel- sheet pile-type mooring quay was construct- Kobe are typical structures.
oped to the remarkable level where protec- ed in 1926 at the Port of Osaka. Very recently, jacket-type steel structures
tion against the corrosion of port and harbor Entering the Showa era (1926~1989), are increasingly being adopted for port and
steel structures is nearly complete. Also, the imports of steel sheet piles increased, initial- harbor facilities. The Ooi container berth
conditions affecting the application of cor- ly totaling 25,000~35,000 tons annually. and the new D-Runway at Tokyo Interna-
rosion protection technologies will differ Then in 1929, trial manufacture of steel tional Airport are typical structures.
from country to country, so the methods sheet piles started at the government-run
used will differ accordingly. However, the Yawata Steel Works, and full production ●F eatures of Port and Harbor Steel
diversity of experience acquired in this field started in 1930. In 1931 at the Port of Mi- Structures
in Japan will also be of use in other coun- yako, the domestically-produced steel sheet Currently, nearly a half of the mooring
tries. This article discusses corrosion-pro- piles were first applied to port steel struc- quays in Japan are constructed using steel
tection technologies applied to port and har- ture. Also, steel sheet pile mooring quays products. This is a feature in Japanese ports.
bor steel structures in Japan. We believe that were constructed in the early Showa era in A couple of major reasons for the greater use
this article will contribute to the develop- Osaka, Nagoya, Fushiki, Hakodate, and Ru- of steel products in Japan are the develop-
ment of appropriate corrosion-protection moi. In the post-war period, steel pipe piles ment of the Japanese steel industry as a core
technologies for steel structures in the were extensively used for port and harbor element in the country’s rapid economic
world. facilities. The application of piles in pier growth in the 1960s. Because Japan’s rapid
foundation structures was expanded follow- economic development beginning in the
Port and Harbor Steel Structures in ing the construction of Shiogama Port in 1960s demanded that port and harbor facili-
Japan 1954. The first cell-type mooring quay using ties be quickly improved, the possibility of
● History flat steel sheet piles was constructed at the rapid construction was an additional reason
The oldest steel harbor structure built in Ja- Port of Shiogama (1954~1959), followed by for the enthusiastic adoption of steel struc-
pan is a pier constructed using steel screw the Ports of Tobata, Nagoya, Naoetsu, Ao- tures. The total extent of mooring quays em-
piles in the Port of Kobe in 1876, followed mori, and Yokohama. ploying steel structures has reached 490 km.
successively by the Ports of Yokohama, Na- Entering the 1960s, steel pile piers were At the Port of Tokyo, the ratio of steel struc-
goya, Osaka, and Tsuruga. In the last part of developed and were increasingly used to tures to total port and harbor facilities (in-
the Taisho era (1912~1926), steel sheet piles build large-capacity mooring quays in many cluding breakwaters) has rapidly grown. Of
● Atmospheric zone
In most cases, the corrosion rate (corrosion
loss) for such structures is mostly around 0.1
mm/year.
● Splash zone
In the splash zone, the structure is constant-
ly subjected to seawater splashing, and
therefore a large amount of seawater and ox-
the total extension of more than 200 km of —P ier-type Mooring Quays ygen can be supplied to steel surface. Ac-
port and harbor facilities, steel facilities Pier-type mooring quays are constructed by cordingly, the splash zone is the most corro-
have surpassed 150 km. placing the upper structure on column mem- sive environment. In general, corrosion rate
bers (Fig. 2). The pier-type quay consists of in this zone reaches the level of 0.3 mm/
● Typical Port and Harbor Steel a pier located at the front of the quay and an year. According to surveys in the Okinawa
Structures earth-retaining structure to the rear, with area, there are examples of corrosion rate
— Steel Sheet Pile-type Quays steel products widely used for the front pier. reaching 0.5~0.6 mm/year due to the effect
Steel sheet pile-type mooring quays are con- Reinforced concrete or precast concrete of high temperature and high humidity.
structed by driving steel sheet piles into the beams and floor slabs are installed on the
ground to form an earth-retaining wall upper structure. Among port and harbor fa- ● Tidal zone
(Fig. 1). The most common steel sheet pile- cilities, the RC (reinforced concrete) upper The tidal zone is where structures undergo
type mooring quay is formed using tie rods structure is the site where structural deterio- periodic immersion in seawater and expo-
to connect the steel sheet pile wall to a strut ration due to salt damage most frequently sure to the atmosphere due to tidal action. In
structure (steel pipe, steel sheet pile, shape, occurs. this zone, corrosion rate in the vicinity of the
etc.) installed behind the wall. Depending mean seawater level (M.S.L.) is small, how-
on the scale of the load to be supported, two Features of Corrosion in Marine ever, corrosion rate in the vicinity just be-
kinds of piles are used for the pile wall— Environments neath the M.L.W.L. is extremely large. The
commonly adopted U-type steel sheet piles The environments where port and harbor reason for this is the formation of a macro-
and steel pipe piles having connection joints. steel structures are applied are roughly clas- cell with the cathode area around the M.S.L.
In cases when a small load is applied, as in sified into five zones, namely, atmospheric (high dissolved oxygen concentration), and
ports with shallow water depth, a self-sup- zone, splash zone, tidal zone, submerged the anode area, the vicinity just beneath the
porting wall structure is adopted without the zone, and mud zone. In cases where long M.L.W.L. (low dissolved oxygen concen-
use of a strut structure and tie rods. Even steel products such as steel sheet pile and tration). There are cases, depending on the
when using steel sheet piles or steel pipe steel pipe pile extend through multiple envi- circumstances, when corrosion rate in the
piles, the front surface of the pile wall is sub- ronments (tidal zone, submerged zone, and vicinity just beneath the M.L.W.L. exceeds
jected to harsh corrosive marine environ- mud zone), macro-cell corrosion attribut- that in the splash zone. This phenomenon is
ments. able to differences in these application envi- called “concentrated corrosion.” The con-
Concerns about Concentrated sion-protection technologies for such tion technologies for port/harbor steel
Corrosion structures had not yet been established, in structures in Japan can be organized as
Because port/harbor steel structures are ex- contrast to the current rapid progress of shown in Fig. 11). From the latter part of the
posed to severely corrosive environments, these technologies. Accordingly, among 1950s through the 1960s when a number of
the inappropriate application of corrosion the structures constructed then, there were port/harbor structures were constructed,
protection and maintenance is likely to some that suffered severe deterioration due cathodic protection relying on impressed
cause fatal structural deterioration, such as to concentrated corrosion. current system was applied to submerged
a significant reduction of loading capacity. Photo 1 shows an example of concen- structures, and design methods employing
During the period of high economic growth trated corrosion occurring in a steel prod- corrosion allowance were applied to struc-
in Japan from the latter part of the 1950s uct installed underwater. Photo 2 shows an tures installed above the tidal zone.
through the 1960s, numerous port/harbor example of pitting corrosion in the corro- In those days, because the importance of
facilities were constructed, as were many sion-protection coating applied to the maintenance was not yet recognized to the
other steel structures. At that time, corro- splash zone of a steel product. Under the extent that it is today, there were many cas-
conditions at work in these examples, if es of steel structures experiencing fatal de-
sufficient maintenance control is not ap- terioration due to concentrated corrosion
plied in time, deterioration will develop and pitting corrosion, as described above.
further, inevitably leading to fatal structur- A typical example of such fatal deteriora-
al damage. tion occurred in 1981 when concentrated
The development of corrosion-protec- corrosion caused the buckling of steel pipe
and reinforcement
±0.00
(rigidity)
−2.00
117.9 kN∙m
Design cross-section capacity
of steel product
158.0 kN∙m
Fig. 3 Conceptual Drawing of Repair and Reinforcement Employing Reinforced steel structures is standard practice, and,
Concrete further, the implementation of appropriate
(Existing) upper concrete maintenance for such structures is manda-
tory.
Nevertheless, a number of steel struc-
tures designed using corrosion allowance
criteria are in use, and further the corrosion
Underwater stud welding of steel products still occurs due to insuffi-
cient maintenance practices previously ap-
plied. Accordingly, steel structures still ex-
ist that are likely to suffer serious
deterioration. To this end, it is now neces-
Corrosion, hole
Vertical reinforcing bar sary to repair and reinforce these structures
capitalizing on the Corrosion-protection
Lateral reinforcing bar
ing and Repair Manual.
ver
for co
late This article introduces the latest tech-
el p
Ste nologies for repairing and reinforcing the
Underwater stud welding steel structures in which corrosion has al-
ready developed.
Underwater concrete
Fixing range
Design member
Calculation of member force (consideration
force working as the Design cross-section capacity
Fixing range
or steel plate)
Design cross-section
capacity of existing
steel product
79.0 kN∙m
● Execution Outline
In executing the method, the marine organ-
isms and loose rust that adhere to the target
Where structure are removed using scraping bars,
Sd : Design member force air chippers etc, and, in addition, surface
Rd : Design capacity of cross-section preparation is conducted on the stud bolt
γi : Coefficient of structure (in the joining section until the surface is suitable
case of adopting reinforced for welding (Photo 3).
concrete) Because the underwater studs are im-
portant members for integrating the pipe or
Specifically, reinforced concrete is firm- sheet pile with the reinforced concrete, an Photo 3 Marking of stud welding position and
ly affixed using underwater studs to the underwater stud welding method that al- surface preparation
sound section of the steel pipe pile or sheet lows secure weld-joining underwater is ad-
pile, the target member for repair and rein- opted (Photo 4). To ensure quality control
forcement, in order to integrate both the over the underwater stud welding, the
concrete and the pile so that the reinforced method is adopted that confirms the weld
concrete, the repair and reinforcement quality using the waveform of the current
member, can securely maintain the section- flowing during welding.
al strength. Then, reinforcing bars are installed on
Fig. 3 shows a conceptual drawing of the pile as necessary. And, when installing
the repair and reinforcement method using reinforcing bars on sheet piles, a frequently
reinforced concrete. The underwater studs used method is to employ bars that were
are weld-joined to both sides of the target- preassembled on land.
ed repair and reinforcement member, to As regards the concrete, commonly ap- Photo 4 Underwater stud welding
which the underwater reinforced concrete plied underwater concrete is adopted, but
having the reinforcing bar arrangement to in cases requiring that due attention be paid crete form removal. As seen in the photo,
satisfy the equation (1) is affixed. to the effect on water quality in the sur- the integration work can be carried out
The conceptual cross-section capacity rounding sea area, antiwashout underwater without damaging the configuration of the
recovered by use of this method is shown concrete with high separation resistance is pipe pile or sheet pile, and, accordingly,
by the dotted line in Fig. 4. commonly adopted. when conducting subsequent maintenance,
Photo 5 shows the condition after con- visual inspection can be done in the same
Japan.
Design and project execution control PH PH
Asphalt pavement t=75mm
4500
2500
Co., Ltd. and Nippon Engineering Consul- 2% 2700 2%
3000
cluding construction of the main bridge, is
being undertaken by a joint venture be- 3280 4x3330=13320 4x3330=13320 3280
tween IHI Corporation and Sumitomo Mit- 33200
sui Construction Co., Ltd. and is financed
as a yen-based STEP (Special Term for Fig. 2 General Drawing of P12 Main Tower
Economic Partnership) loan, a special Jap- 8000 3000
anese government ODA loan. Construction
work started in October 2009.
3000
5000
7200
● Bridge Outline
109310
―Project owner:
Ministry of Transport of Vietnam, 8000
Project Management Unit 85
3200
5000
28810
25910
φ1200
φ1200
3500
37500
48878
Slabs:
28000
109.31m
111.56m
110.81m
110.81m
109.31m
Fig. 4 Perspective of Nhat Tan Bridge upon Completion (Computer Graphics) main girder webs. The main girders and
cross beams form a composite girder struc-
ture to which precast slabs are connected
using dowels. Fairings are installed on the
outer edges of the slabs to improve wind
stability.
The cables employing parallel wire
strands are arranged in a fan-shaped form,
and the girders are suspended in a double-
plane format from the main towers.
● Main Towers
The reinforced-concrete main towers adopt
an A-shaped structure to secure rigidity
perpendicular to the bridge axis. Below the
crossbeams that support the superstructure,
the support columns of each tower draw
steadily inward as they descend, thereby
(Courtesy: Sumitomo Mitsui Construction Co., Ltd.) narrowing the space between the columns
in order to decrease the plane shape of the
vicinity of the bridge construction site it is ―Cables: foundation.
separated into two channels that sandwich Parallel strands using 7 mm-diameter Because axial tension force works on
a sandbar. According to the historical re- galvanized steel wire (tensile strength: the crossbeams, a prestressed concrete
cord, the riverbed is known to change over 1,770 MPa) structure was adopted. Anchor boxes em-
time with regard to the location of the river ―Steel pipe sheet piles: SKY400, SKY490 ploying steel plates are embedded near the
channels and the sandbar. Because of this, ―Design standard strength of concrete: top of the tower, and the cables are an-
future movement of the river channels and 40 MPa (main tower, slab); 30 MPa chored to the bearing brackets within the
sandbar were taken into consideration in (end piers, cast-in-place piles); 25 boxes.
selecting a six-span continuous cable- MPa (top slab of steel pipe sheet pile
stayed bridge plan having spans of equal foundations) ● Steel Pipe Sheet Pile Well Foun-
length (Figs. 3, 4). ―Reinforcing bars: SD390 dations
―PC strands: SWPR7BL With the aim of improving upon the con-
● Applied Standards struction quality of cast-in-place piles that
The bridge design conforms to the Specifi- ● Road Composition have occasionally offered application con-
cation for Bridge Design 22TCN-272-05 of The road is composed from its center: two cerns in Vietnam, steel pipe sheet pile well
Vietnam, which is based on the AASHTO- automobile lanes (3.75 m wide), a bus lane foundations were adopted for the first time
LRFD of the U.S. Further, such items as (3.75 m wide), a dual-use motorcycle-bicy- in Vietnam. Because this type of founda-
steel pipe sheet pile well foundations and cle lane (3.3 m wide), and a walkway (0.75 tion was developed in Japan, two Japanese
base-isolated bearings, which are not de- m) along the outer edge. specifications were adopted for design and
scribed in the Specification, followed spec- construction―Specifications for Highway
ifications in the design standards of Japan. ● Superstructure Bridges IV (2002) and Design and Con-
The superstructure is a continuous struc- struction Manual for Steel Pipe Sheet Pile
● Major Structural Materials ture spanning 1,500 m in total length. The Foundations (1997).
The major structural materials are as fol- main structure consists of two main I-gird- The scouring depth accounted for in the
lows: ers located along each edge of the roadway design was estimated to be, at maximum,
―Steel products: to which cross beams to support the slabs 15 m from the riverbed. The driving meth-
SS400, SM400, SM490, SM490Y, are arranged at 4-m intervals. The cables od for pile installation was adopted with
SM520, SM570 are anchored to the outside surface of the the aim of securing bearing capacity. The
H.W.L. +13.670
Water level at the time of construction +9.500
M.W.L. +4.400
13500
-34.500
48743
16891
Progress in Construction
At the end of May 2011, construction of the
main tower foundations was underway at
P13~P15; and driving of the steel pipe
sheet piles was completed and underwater
excavation, installation of the lower slabs
and upper slabs, etc. were underway at P12
and P16. (Photos 1, 2). Photo 2 On-land construction at sandbar
● Execution Yard and Machinery in the river, underwater construction is be- tions and to drive and close steel pipe sheet
The sandbar in the Red River where P14 is ing conducted using a crane ship, material piles with a maximum length of 50 m, it is
being constructed is utilized as a structural transport and other barges (Photo 3). important to execute precise vertical driv-
material yard, reinforcing bar fabrication ing of the piles. At the construction site, the
yard and emergency evacuation base. At ● Driving of Steel Pipe Piles pipe piles were driven using hydraulic vi-
P12, P13 and P15, which are located with- In order to construct large-scale founda- bratory hammers in combination with the
● Underwater Excavation
The method adopted to conduct underwa-
ter excavation inside the steel pipe sheet
Photo 4 Water jetting nozzle pile well was using pumps to discharge
both water and riverbed sand (Photos 6, 7).
● Subsequent Processes
After excavation, underwater placement of
the bottom concrete slabs, stud welding, re-
inforcing bar arrangement and concrete
placement of the top slabs will be under-
taken; following this, the main towers will
be constructed. These subsequent process-
es will be introduced at the next opportu-
nity. (Refer to Photo 8)
Project Outline outlined and its construction method is dis- Foundation Structures
At the Port of Tokyo, construction project cussed. The substructure of the Tokyo Gate Bridge
has begun on an 8-km section of the Tokyo Two features should be cited regarding (total length: 2.9 km) is composed of two
Port Coastal Highway to enhance the the construction of the Tokyo Gate Bridge. abutments and 21 piers (Fig. 1), of which 9
smooth distribution of international cargo One is that the bridge spans the No. 3 fair- piers are located in the offshore section (ex-
between the Port of Tokyo and its coastal way of the Port of Tokyo (crossing width: tension: about 1.6 km) of the substructure.
cities. Constituting a segment of this section about 310 m; below-girder clearance: A.P. Of the offshore piers, the main piers (MP2,
of the highway, the Tokyo Gate Bridge is a 54.6 m), and the other is that the construc- 3) are of the RC wall type (Photo 1) and the
large-scale structure composed of a main tion work had to adapt to impediments side-span piers (MP1, 4) are of the RC hol-
bridge (continuous 3-span truss-box com- posed by the restricted area surrounding To- low type.
posite bridge) that spans the No. 3 fairway kyo International Airport (A.P. +98.1 m). In As shown in Fig. 2, a layer of soft allu-
of the Port of Tokyo and two offshore-on- order to satisfy these restrictions at both the vial clay (AC2 layer, N value ≈ 0) is thickly
shore approach bridges (continuous multi- design stage and the construction stage and deposited over the foundation ground in the
span steel slab box girder bridges) at both to construct both a safer and higher-quality vicinity of the steel pipe well foundation.
sides of the main bridge. The bridge has a bridge through the pursuit of structural and Further, the layers that serve as the bearing
total length of 2.9 km and is scheduled to be economical rationality, it was necessary to strata of the piers are located at great depth:
completed in fiscal 2011. adopt the latest in bridge technology: steel the gravel layer (Dg1 layer) for the
Because the construction area of the To- slabs utilizing large-size ribs, truss welds at- CP9~MP2 piers is located at A.P.–75 m or
kyo Gate Bridge is located at a layer of al- tained by eliminating the use of splice plates, deeper, and the sand layer (Ds2 layer) for the
luvial clay (N value ≈ 0) that is 30 m or more BHS (bridge high-performance steel) prod- MP3~WP6 piers at A.P.–50 m or deeper.
thick, the foundation of the bridge rests on ucts, large-size base-isolated shoes etc. The gravel layer at A.P.–75.5 m mostly
bearing strata of sand and gravel located at Design of the steel pipe well foundation serves as the bearing stratum of the
the deepest section of the No. 7 stratum. And was made in accordance with the Specifica- CP9~MP2 piers, and the sand layer in the
since the foundation lies at least 65 m below tions for Highway Bridges (Japan Road As- vicinity of A.P.–54.5 m~ –50.5 m, shallower
the sea mud line, it is built as a great-depth sociation) and the Design and Construction than the above, serves as the bearing stratum
type structure. Because the foundation is re- of Steel Pipe Piles (Japanese Association for of the PM3~WP6 piers.
quired to possess a seismic deformation ca- Steel Pipe Piles). These two specifications Photo 2 shows the driving of the pipe
pacity suitable for expected seismic motion state that the required performances of the piles. Each pile is first driven into the bear-
between 534.7 Gal and – 434.2 Gal and be- foundation is constantly satisfied with re- ing stratum using a vibratory hammer and
cause economical structural sections must gard to bearing force and overturning and then a hydraulic hammer. The hammers
be built, it was decided that a large-scale that, in level 1 seismic motion, the structural used are IHC-S280 and IHC-S200. The
steel pipe sheet pile well foundation (pipe materials remain within the allowable stress planned embedding length to the bearing
pile diameter: 1,500 mm; checkered steel and the horizontal displacement is within 50 stratum is 3.0D~3.2D. The outer diameter of
plates + high-strength mortar-filled inter- mm, and that, in level 2 seismic motion, the the steel pipe piles used is 1,500 mm, and
locking joints) is adopted. material remains within the yielding value the wall thickness of the pile tip is 17 mm.
In this article, the large-scale steel pipe and the yielding area of the foundation Photo 3 shows the construction of the steel
sheet pile well foundation that was adopted ground is within 40%. pipe sheet pile well foundation.
for construction of the Tokyo Gate Bridge is
No. 3 fairway
Photo 1 Construction of MP2 Photo 2 Driving of steel pipe piles Photo 3 Construction of steel pipe sheet pile
well foundation
Fig. 2 Foundation Structure and Soil Property Loading Tests for Verti- ● Pile tip resistance by means of wave
30.5 cal Bearing Capacity matching analysis from the dynamic test
In applying steel pipe sheet ● Skin friction resistance from the static
piles (diameter: 1,500 mm) loading test
in the construction of the To- ● Set-up ratio (ratio of pile-tip static resis-
kyo Gate Bridge, on-site tance during installation to tip resistance
28.0
+2.1 loading tests were carried out after ground recovery) of tip resistance
N value in 2003 prior to the start of from the dynamic and static loading tests
10.0 10.0
–8.0
m
the construction work. The ● Relation between the skin friction resis-
10 20 30 40 50
3.0 aim of the tests was to clarify tance and the N value from the rapid load-
9.0 the bearing mechanism of ing test
large-diameter steel pipe (Refer to Tables 1 and 2, Fig. 3)
5.0
8.0 sheet piles that previously In relation to the design of the steel pipe
had incurred problems in pile well foundation, the embedding length
70.5
8.0
similar work implemented in of the steel pipe piles into the foundation
4.0
2.0
Tokyo Bay, and to modify layer and the enclosure ratio of the pile tip
Sand
3.0
3.0
conventional design and are prescribed. Further, the ground reaction
compaction 2.5 construction management of coefficient, vertical-direction ground reac-
pile 3.0
4.0 the foundation. tion and other factors described in the Spec-
4.0
Three kinds of loading ifications for Highway Bridges are con-
2.0 tests were carried out: dy- firmed. Photo 4 shows the static loading test.
6.0
namic loading tests (DLT), Utilizing four pipe piles as the reaction pile,
–78.5 static loading tests (SLT) test pipe piles were pressed into the bearing
6.0
(horizontal and vertical) and stratum to a depth three times the pile diam-
Unit: m rapid loading tests (STN), eter by means of a multi-cycle system em-
which led to the following re- ploying hydraulic jacks. The hydraulic jack
sults: capacity was 48,000 kN for pile ④, and
Table 1 Test Piles and Kinds of Loading Tests Table 2 Kinds and Objectives of Loading Tests
Test pile Pile diameter Pile tip depth • Static (vertical) loading test
Test kind
No. D (mm) A.P. (m) Kinds of • Static (horizontal) loading test
① φ1500 −86.0 DLT loading tests • Dynamic loading test
• Rapid loading test
② φ1500 −78.5 DLT
• Pile diameter
③ φ1200 −72.6 DLT, STN, CPT Test parameters • Embedding length to bearing stratum
④ φ1500 −73.5 DLT, SLT, HLT, CPT • Soil property of bearing stratum (sand or gravel)
⑤ φ1500 −86.0 DLT, SLT, CPT • Embedding length
• Tip bearing capacity
⑥ φ1500 −86.0 DLT
Examination of •• Skin friction resistance
⑦ φ1500 −86.0 DLT design values Ground reaction coefficient (vertical and horizontal
directions)
⑧ φ1800 −89.0 DLT • Coefficient in bearing capacity calculation equation
⑨ φ 800 −42.0 — • Enclosure ratio and correction coefficient of safety factor
Fig. 4 Results of Static Loading Tests tween the respec- Fig. 3 Relation between Bearing Stra-
tive measured sec- tum Thickness and N-value at
Load-residual displacement Test Position
curve tions can be
Load-elastic return curve 0 10 20 30 40 50
converted as fric- −40
Existing
position
tion resistance. The Existing result
result
Test position
Test
skin friction resis-
24000 80
tance is somewhat
12000 40 low in the upper
clay layer, but be-
12 9 6 3 800 160 240 3200 comes larger in the
Hour
60
Load Po (kN)
lower layer. Fig. 6
shows the relation −50
120 between the pile tip
bearing capacity
Displacement (mm)
180
and the total load
240 displacement,
which were ob-
tained by separat-
Time-displacement curve Load-displacement curve
ing from the total
−60
force. It can be
seen from the figure that the skin friction re- Ds2
load was 2,000 kN. The strains were mea- using the reaction thus generated by lifting
sured at 13 sections of the pile, and the axial with a loading time of about 0.1 second.
Tip of test pile ⑤
force distribution and the skin friction resis- This test offers advantages such as shorter Ds3
tance were calculated from the measure- test times and the elimination of reaction
ment results. Fig. 5 shows the distribution of piles. Photo 5 shows the loading device. The
the axial force of the pile. The axial force axial force and acceleration distribution are −90
was calculated from strain meters set in the calculated using a load cell, strain meter and
pipe pile. The difference in axial force be- accelerometer installed on the pile. Fig. 8
Pile
with the measurement results. Further, the 165.2 mm, and mortar with a compression
input wave (hammer load) and the reflection strength of about 20 MPa is used to fill the
wave (ground resistance) can be calculated interlocked pipe joints. In the current Tokyo
from the axial force and acceleration. These Gate Bridge project, it was necessary to in-
value forms are shown in Fig. 10. crease the rigidity of the joints so that the
Fig. 11 shows the axial force and skin horizontal displacement of the steel pipe
friction resistance of the piles as obtained sheet pile well foundation could remain
from wave-form matching analysis. While within its allowable value during earth-
the design of the steel pipe sheet pile well quakes.
foundation was basically implemented ac- In order to increase the rigidity of the
cording to the method described in the Spec- steel pipe sheet piles, high-strength mortar
ifications for Highway Bridges, various val- was used to fill the joint openings (Fig. 12)
ues applied in the design were modified to increase the adhesion between the mortar
based on the loading test results. Modifica- and the pipe joints. In the current project, the
tion was made mainly of the following: strength of the fill mortar was increased to
● The driving depth of pipe piles with an more than double (40 MPa) the convention-
outer diameter of 1,500 mm (D) was set at al level, and, further, checkered steel plate
Photo 5 Loading device 3D. The apparent enclosure ratio was 53% was used as the material of the pipe joints to
increase the adhesion. As a
Fig. 8 Matching Condition for Wave Form Fig. 9 Calculation Model for Tip Bearing Ca- result, it was confirmed that
40000 pacity and Skin Friction Resistance sufficiently large shear resis-
Static resistant component of ground:
35000
Spring + Slider
tance could be obtained by
30000
ULP 32.161kN
Pile
(spring coefficient, maximum resistant the use of these two ap-
Skin friction resistance
component)
Dynamic resistant component of ground:
proaches.
25000
Dashpot As the results of the mod-
Force (kN)
Depth (AP m)
Depth (AP m)
-5 −40 −40
−10
−50 −50
−15
−20 −60 −60
0 20 40 60 80
Time (ms)
−70 −70
Tip AP-72.6 Tip AP-72.6
−80 −80
Table 3 Fixing of Skin Friction Resistance
Fixing by Specifications Fixing by loading −90 0 5000 10000 15000 20000 25000 30000
−90 0 100 200 300 400
for Highway Bridges test result
(kN/m2) (kN/m2) Axial force (kN) Skin friction resistance (kN/m2)
Sandy soil 2N (≤100) 2N (≤100)
Clay soil 10N (≤150) 10N (≤150) Fig. 13 R
elation between Load and Displace-
ment
Gravel layer 2N (≤100) 3N (≤150)
2500
HPJ-1
1000 HPJ-2
HPJ-3
HPJ-4
500 HPJ-5
1000mm HPJ-6
HPJ-7
HPJ-8
0
0 5 10 15 20
Relative displacement (mm)
shear resistance described in the common After acquiring knowledge Table 4 Comparison of Designs of Steel Pipe
design specifications for steel pipe joint ma- of the bearing mechanism at the Sheet Pile Well Foundation
terial (Manual for Design and Construction construction site from the load- No. of pile
Planar configuration (MP2, MP3)
of Steel Pipe Sheet Pile Foundations, Japan ing tests conducted on large-di- Pile length
Road Association). ameter steel pipe sheet piles, Initial
design
15730.2
The configuration of the steel pipe sheet various design factors were re- 136
pile well foundation designed in the initial considered. Based on these, a
31460.4
stage was greatly reduced through the ap- more compact foundation con-
15730.2
propriate use of the loading test results and figuration was successfully
a reexamination of the ground coefficients, achieved by the combined use 84.5 m
which allowed for economical construction of large-diameter steel pipe 12234.6 15730.2 12234.6
the Tokyo Gate Bridge was constructed on also determined by the effec- 81.5 m
soft ground, and, further, large sectional tive use of the loading test re- 12235 12235 12235
36704
force and deformation capability during sults. As a result of these con-
earthquakes were required in its construc- siderations, the structural
tion. Thus in the design stage, the founda- dimensions of the steel pipe sheet pile foun- tion cost and improvements in structural
tion structure necessarily became quite large dation were reduced, thereby simultaneous- quality.
in terms of structural configuration. ly producing greater reductions in construc-