Professional Documents
Culture Documents
CK 28
CK 28
EDISI 02 2020
KET.
DAFTAR UPAH PEKERJA
HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 105,000 115,000 16,429 16,429
2 Mandor Hr 130,000 145,000 20,714 20,714
3 Tukang listrik Hr 135,000 145,000 20,714 20,714
4 Tukang kayu Hr 135,000 145,000 20,714 20,714
5 Kep. tk. kayu Hr 140,000 150,000 21,429 21,429
6 Tukang batu Hr 135,000 145,000 20,714 20,714
7 Kep. tk. batu Hr 140,000 150,000 21,429 21,429
8 Tukang besi Hr 125,000 135,000 19,286 19,286
9 Kep. tk. besi Hr 140,000 150,000 21,429 21,429
10 T u k a n g c a t Hr 135,000 145,000 20,714 20,714
11 K e p . t k . c a t Hr 140,000 150,000 21,429 21,429
12 T u k a n g p l i t u r Hr 135,000 145,000 20,714 20,714
13 T u k a n g j a l a n Hr 105,000 115,000 16,429 16,429
14 T u k a n g g a l i Hr 105,000 115,000 16,429 16,429
15 Tukang masak aspal Hr 105,000 115,000 16,429 16,429
16 T k . l e i d e n g Hr 135,000 145,000 20,714 20,714
17 M a s i n i s Hr 175,000 200,000 28,571 28,571
18 P e m b . M a s i n i s Hr 125,000 150,000 21,429 21,429
19 P e n j a g a a p i Hr 105,000 115,000 16,429 16,429
20 P e n j a g a m a l a m Hr 105,000 115,000 16,429 16,429
21 Sopir Hr 175,000 200,000 28,571 28,571
22 Pembantu Sopir Hr 125,000 150,000 21,429 21,429
92,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 230,000 250,000
Bulat Belah m3 280,000 320,000
Pecah 10/15 m3 290,000 340,000
Pecah 5/7 m3 290,000 350,000
Pecah 3/5 m3 320,000 360,000
2 KERIKIL Timbun m3 180,000 200,000
Sawur / Koral m3 190,000 200,000
Beton 0,5/1 m3 320,000 380,000
Beton 1/2 m3 330,000 390,000
Beton 2/3 m3 340,000 380,000
Biasa m3 240,000 260,000
Tras Giling m3 290,000 320,000
3 BATU BATA ex lokal bh 550 580
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 28,000 31,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 34,000 36,500 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 50,000 55,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 60,000 70,000 panjang 4 m
Pipa PVC DN 63 ( 2" ) btg 85,000 105,000 panjang 4 m
Pipa PVC DN 90 ( 3" ) btg 165,000 185,000 panjang 4 m
Pipa PVC DN 110 ( 4" ) btg 270,000 280,000 panjang 4 m
Pipa PVC DN 160 ( 6" ) btg 530,000 550,000 panjang 4 m
Pipa PVC DN 200 ( 8" ) btg 900,000 1,050,000 panjang 4 m
Pipa PVC DN 250 ( 10" ) btg - - panjang 4 m
Pipa PVC DN 315 ( 12" ) btg - - panjang 4 m
VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,800 6,500
30 X 60 lbr 13,200 14,500
60 X 120 lbr 42,000 46,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 60,000 68,000
3 HARD BOARD-uk: 4'X 8' lbr 51,000 55,000
GYPROC uk.120cmx240cmx9mm lbr 60,000 65,000
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 65,000 75,000
. 120 X 240 X 3 mm lbr 80,000 95,000
. 90 X 210 X 4 mm lbr 65,000 85,000
. 90 X 210 X 9 mm lbr 115,000 125,000
. 90 X 210 X 12 mm lbr 135,000 170,000
. 90 X 210 X 15 mm lbr 200,000 240,000
. 90 X 210 X 18 mm lbr 295,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 50,000 61,500
. 120 X 240 X 4 mm lbr 65,000 70,000
. 120 X 240 X 6 mm lbr 75,000 86,000
Multipleks
. 120 X 240 X 9 mm lbr 110,000 160,000
. 120 X 240 X 12 mm lbr 165,000 185,000
. 120 X 240 X 15 mm lbr 190,000 220,000
. 120 X 240 X 18 mm lbr 215,000 265,000
Formika ukuran pintu lbr 70,000 75,000
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 30,000 32,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 4,100 5,000
Batu Apung kg 75,000 80,000
Cat dasar kg 40,000 42,500
. Emco kg 65,000 71,000
. Yunior 66 (nippon paint) kg 68,000 71,000
- Koas bh 17,500 20,000
. Deculux kg 67,000 75,000
. Siralax ons 20,000 21,000
. Spiritus ltr 15,000 18,000
. Plitur jadi ltr 65,000 71,000
2 TEMBOK
Kalkarium kg 4,500 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 25,000 32,000
Cat Tembok kg 23,000 28,400
Sintex 5 kg 125,000 135,000
Danabride 5 kg 130,000 140,000
Catylac interior 5 kg 130,000 142,000
Mowilex 2,50 kg 285,000 350,000
3 BESI
Menie kg 25,000 36,000
Cat mengkilat kg 62,000 72,500
Cat kg 40,000 45,000
Thinner A ltr 16,000 20,000
Minyak cat ltr 20,000 22,000
Thinner Super ltr 17,500 35,000
Residu (teer/aspal) drum 60,000 67,500
Fibre glass (tanki air)
kapasitas 550 liter. bh 1,025,000 1,100,000
kapasitas 1100 liter. bh 1,625,000 1,700,000
Lem Aica Aibon kg 55,000 65,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 90,000 95,000
5 mm m2 100,000 105,000
2 ES KABUR 3 mm m2 110,000 115,000
5 mm m2 130,000 135,000
3 RAY BAND 3 mm m2 95,000 100,000
5 mm m2 105,000 110,000
1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 5,250 5,500
2 SKAKELAR
Out bauw . Seri bh 25,000 35,000
XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 350,000 375,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,100,000
Fuji 250 watt bh 1,450,000 1,650,000
Shimizu . 100 watt bh 470,000 550,000
. 90 watt bh 350,000 425,000
Dab . 125 watt bh 400,000 420,000
. 175 watt bh 425,000 475,000
X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 90,000 95,000
Merah/hitam m2 95,000 105,000
2 HOLLAND Abu-abu m2 90,000 95,000
Merah/hitam m2 95,000 105,000
3 UNIDECOR Abu-abu m2 90,000 95,000
Merah/hitam m2 95,000 105,000
4 UNI Abu-abu m2 90,000 95,000
Merah/hitam m2 95,000 105,000
5 TRIHEX Abu-abu m2 90,000 95,000
Merah/hitam m2 95,000 105,000
6 OLYMPIA HEXA Abu-abu m2 90,000 95,000
7 HEXAGONAL Abu-abu m2 95,000 105,000
Merah/hitam m2 90,000 95,000
8 CASTLE Abu-abu m2 95,000 105,000
9 TRAPEZ Abu-abu m2 90,000 95,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 90,000 95,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500 8,500
12 BATACO BH 4,100 5,500
13 KANSTEEN m' 27,000 32,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000 60,000
2 Sliding Pintu J4 bh 200,000 235,000
3 Naco per Daun bh 40,000 42,000
4 Rolling door Besi m2 325,000 335,000
Rolling door Almunium m2 275,000 290,000
5 Awning Almunium m2 225,000 250,000
6 Kusen Almunium 4" Putih m' 95,000 100,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,425,000 1,545,600
8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 950,000 1,100,000
9 KACA
Cermin tebal 5 mm m2 275,000 325,000
6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 910,360.00 1,016,262.50
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 999,383.00 1,113,403.50
PP
Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4
8 A.3.2.1.8 m3 980,397.00 1,094,164.50
PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 627,924.00 726,874.50
24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 92,763.00 103,350.50
25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 120,752.50 134,502.50
29 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 62,931.00 67,177.00
8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 13,563.00 14,906.38
7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,825,769.27 1,974,643.54
9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 357,280.00 399,987.50
6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 910,360.00 1,016,262.50
Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10
7 A.3.2.1.7 m3 999,383.00 1,113,403.50
PP
Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4
8 A.3.2.1.8 m3 980,397.00 1,094,164.50
PP
9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 627,924.00 726,874.50
24 A.4.1.1.28 Membuat Ring Balok Beton Bertulang (11 x 11) cm m' 92,763.00 103,350.50
25 A.4.1.1.29 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 120,752.50 134,502.50
22 A.4.1.2.22 Upah Pekerjaan Gruot pada Joint Beton Pra Cetak ttk 71,186.50 76,648.00
8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 13,563.00 14,906.38
7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,825,769.27 1,974,643.54
9 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 357,280.00 399,987.50
10 A.5.1.1.14 Pemasangan Floor Drain buah 56,760.00 66,412.50
C PERALATAN
D Jumlah A + B + C 177,150.00 198,925.00
E Overhead & Profit (contah 10%) 10% 17,715.00 19,892.50
F Harga Satuan Pekerjaan (D+E) 194,865.00 218,817.50
6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 910,360.00 1,016,262.50
A Tenaga 279,000.00 303,375.00
L.01 1.5 OH Pekerja 105,000.00 115,000.00 157,500.00 172,500.00
L.02 0.750 OH Tukang Batu 135,000.00 145,000.00 101,250.00 108,750.00
L.03 0.075 OH Kepala Tukang 140,000.00 150,000.00 10,500.00 11,250.00
L.04 0.075 OH Mandor 130,000.00 145,000.00 9,750.00 10,875.00
B Bahan 548,600.00 620,500.00
1.2 m3 Batu Belah 15/20 290,000.00 340,000.00 348,000.00 408,000.00
0.17 m3 Kapur Pasang (KP) 300,000.00 310,000.00 51,000.00 52,700.00
0.17 Kg Semen Merah (SM) 200,000.00 200,000.00 34,000.00 34,000.00
0.340 m3 Pasir Pasang 340,000.00 370,000.00 115,600.00 125,800.00
C PERALATAN
D Jumlah A + B + C 827,600.00 923,875.00
E Overhead & Profit (contoh 10%) 10% 82,760.00 92,387.50
F Harga Satuan Pekerjaan (D+E) 910,360.00 1,016,262.50
24 A.4.1.1.28 1 m' Membuat Ring Balok Beton Bertulang (11 x 11) cm 92,763.00 103,350.50
A Tenaga 28,810.00 31,405.00
L.01 0.180 OH Pekerja 105,000.00 115,000.00 18,900.00 20,700.00
L.02 0.020 OH Tukang batu 135,000.00 145,000.00 2,700.00 2,900.00
L.02 0.020 OH Tukang Kayu 135,000.00 145,000.00 2,700.00 2,900.00
L.02 0.020 OH Tukang Besi 125,000.00 135,000.00 2,500.00 2,700.00
L.03 0.006 OH Kepala Tukang 140,000.00 150,000.00 840.00 900.00
L.04 0.009 OH Mandor 130,000.00 145,000.00 1,170.00 1,305.00
B Bahan 55,520.00 62,550.00
0.002 m3 Kayu Klas III 3,290,000.00 3,300,000.00 6,580.00 6,600.00
0.01 Kg Paku Biasa 2" - 5" 15,000.00 18,000.00 150.00 180.00
3.0 Kg Besi Beton Polos 10,200.00 12,150.00 30,600.00 36,450.00
0.45 Kg Kawat Beton 19,000.00 20,000.00 8,550.00 9,000.00
4.0 Kg Portland Semen 1,150.00 1,200.00 4,600.00 4,800.00
0.006 m3 Pasir Beton 360,000.00 380,000.00 2,160.00 2,280.00
0.009 m3 Kerikil 320,000.00 360,000.00 2,880.00 3,240.00
C PERALATAN
D Jumlah A + B + C 84,330.00 93,955.00
E Overhead & Profit (contoh 10%) 10% 8,433.00 9,395.50
F Harga Satuan Pekerjaan (D+E) 92,763.00 103,350.50
25 A.4.1.1.29 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 120,752.50 134,502.50
A Tenaga 47,570.00 51,855.00
L.01 0.297 OH Pekerja 105,000.00 115,000.00 31,185.00 34,155.00
L.02 0.033 OH Tukang batu 135,000.00 145,000.00 4,455.00 4,785.00
L.02 0.033 OH Tukang Kayu 135,000.00 145,000.00 4,455.00 4,785.00
L.02 0.033 OH Tukang Besi 125,000.00 135,000.00 4,125.00 4,455.00
L.03 0.01 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 62,205.00 70,420.00
0.003 m3 Kayu Klas III 3,290,000.00 3,300,000.00 9,870.00 9,900.00
0.02 Kg Paku Biasa 2" - 5" 15,000.00 18,000.00 300.00 360.00
3.6 Kg Besi Beton Polos 10,200.00 12,150.00 36,720.00 43,740.00
0.05 Kg Kawat Beton 19,000.00 20,000.00 950.00 1,000.00
5.5 Kg Portland Semen 1,150.00 1,200.00 6,325.00 6,600.00
0.009 m3 Pasir Beton 360,000.00 380,000.00 3,240.00 3,420.00
0.015 m3 Kerikil 320,000.00 360,000.00 4,800.00 5,400.00
C PERALATAN
D Jumlah A + B + C 109,775.00 122,275.00
E Overhead & Profit (contoh 10%) 10% 10,977.50 12,227.50
F Harga Satuan Pekerjaan (D+E) 120,752.50 134,502.50
11 A.4.1.2.11 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 78,309.00 76,985.00
12 A.4.1.2.12 1 m3 Penuangan / Menebar Beton untuk Komponen Plat Pracetak 80,536.50 79,170.00
1 1.0000 13 1.114
2 1.0000 14 1.134
3 1.0000 15 1.155
4 1.0000 16 1.176
5 1.0000 17 1.197
6 1.0000 18 1.219
7 1.0000 19 1.241
8 1.0180 20 1.264
9 1.0370 21 1.287
10 1.0550 22 1.310
11 1.0750 23 1.334
12 1.0940 24 1.358
2 1.0000 14 1.080
3 1.0000 15 1.092
4 1.0000 16 1.104
5 1.0000 17 1.116
6 1.0000 18 1.129
7 1.0000 19 1.141
8 1.0110 20 1.154
9 1.0220 21 1.166
10 1.0340 22 1.179
11 1.0450 23 1.192
12 1.0570 24 1.206
1 1.0000 13 1.162
2 1.0000 14 1.191
3 1.0000 15 1.221
4 1.0000 16 1.252
5 1.0000 17 1.284
6 1.0000 18 1.318
7 1.0000 19 1.350
8 1.0250 20 1.384
9 1.0510 21 1.419
10 1.0780 22 1.455
11 1.1050 23 1.492
12 1.1330 24 1.530
22 A.4.1.2.22 1 ttk Upah Pekerjaan Gruot pada Joint Beton Pra Cetak 71,186.50 76,648.00
A Tenaga 64,715.00 69,680.00
L.02 0.367 OH Tukang Batu 135,000.000 145,000.000 49,545.000 53,215.000
L.03 0.074 OH Kepala Tukang 140,000.000 150,000.000 10,360.000 11,100.000
L.04 0.037 OH Mandor 130,000.000 145,000.000 4,810.000 5,365.000
B Bahan - -
C PERALATAN - -
D Jumlah A + B + C 64,715.00 69,680.00
E Overhead & Profit (contoh 10%) 10% 6,471.50 6,968.00
F Harga Satuan Pekerjaan (D+E) 71,186.50 76,648.00
C PERALATAN - -
D Jumlah A + B + C 57,200.00 61,985.00
E Overhead & Profit (contoh 10%) 10% 5,720.00 6,198.50
F Harga Satuan Pekerjaan (D+E) 62,920.00 68,183.50
16 A.4.4.1.16 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 3PP 436,352.40 472,044.10
A Tenaga 61,440.00 66,860.00
L.01 0.350 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.150 OH Tukang Batu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
17 A.4.4.1.17 1 m2 Pemasangan Dinding HB/CB 20, speci camp. 1SP : 4PP 445,142.50 481,952.90
A Tenaga 61,440.00 66,860.00
L.01 0.350 OH Pekerja 105,000.00 115,000.00 36,750.00 40,250.00
L.02 0.150 OH Tukang Batu 135,000.00 145,000.00 20,250.00 21,750.00
L.03 0.015 OH Kepala Tukang 140,000.00 150,000.00 2,100.00 2,250.00
L.04 0.018 OH Mandor 130,000.00 145,000.00 2,340.00 2,610.00
18 A.4.4.1.18 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 3PP 344,648.70 372,636.00
A Tenaga 53,560.00 58,320.00
L.01 0.320 OH Pekerja 105,000.00 115,000.00 33,600.00 36,800.00
L.02 0.120 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.016 OH Mandor 130,000.00 145,000.00 2,080.00 2,320.00
B Bahan 259,757.00 280,440.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
22.740 kg PC 1,150.00 1,200.00 26,151.00 27,288.00
0.550 m3 Pasir Pasang 340,000.00 370,000.00 187,000.00 203,500.00
0.280 kg Besi Angkur Ø 8 mm 10,200.00 12,150.00 2,856.00 3,402.00
C PERALATAN
D Jumlah A + B + C 313,317.00 338,760.00
E Overhead & Profit (contoh 10%) 10% 31,331.70 33,876.00
F Harga Satuan Pekerjaan (D+E) 344,648.70 372,636.00
19 A.4.4.1.19 1 m2 Pemasangan Dinding HB/CB 15, speci camp. 1SP : 4PP 350,873.60 379,667.20
A Tenaga 53,560.00 58,320.00
L.01 0.320 OH Pekerja 105,000.00 115,000.00 33,600.00 36,800.00
L.02 0.120 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.016 OH Mandor 130,000.00 145,000.00 2,080.00 2,320.00
B Bahan 265,416.00 286,832.00
12.500 buah Batako 3,500.00 3,700.00 43,750.00 46,250.00
18.200 kg PC 1,150.00 1,200.00 20,930.00 21,840.00
0.582 m3 Pasir Pasang 340,000.00 370,000.00 197,880.00 215,340.00
0.280 kg Besi Angkur Ø 8 mm 10,200.00 12,150.00 2,856.00 3,402.00
C PERALATAN
D Jumlah A + B + C 318,976.00 345,152.00
E Overhead & Profit (contoh 10%) 10% 31,897.60 34,515.20
F Harga Satuan Pekerjaan (D+E) 350,873.60 379,667.20
20 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 268,015.00 305,468.90
A Tenaga 48,350.00 52,675.00
L.01 0.300 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.100 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
21 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 273,158.05 311,237.30
A Tenaga 48,350.00 52,675.00
L.01 0.300 OH Pekerja 105,000.00 115,000.00 31,500.00 34,500.00
L.02 0.100 OH Tukang Batu 135,000.00 145,000.00 13,500.00 14,500.00
L.03 0.010 OH Kepala Tukang 140,000.00 150,000.00 1,400.00 1,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
C PERALATAN
D Jumlah A + B + C 318,211.40 341,170.05
E Overhead & Profit (contoh 10%) 10% 31,821.14 34,117.01
F Harga Satuan Pekerjaan (D+E) 350,032.54 375,287.06
C PERALATAN
D Jumlah A + B + C 317,578.40 338,726.55
E Overhead & Profit (contoh 10%) 10% 31,757.84 33,872.66
F Harga Satuan Pekerjaan (D+E) 349,336.24 372,599.21
22 A.4.4.2.22 1 m' Pemasangan Plesteran Traso 1Pc : 2Traso, lebar 10 mm 121,368.50 131,626.00
26 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 322,423.75 354,887.50
C PERALATAN
D Jumlah A + B + C 150,359.00 161,870.00
E Overhead & Profit (contoh 10%) 10% 15,035.90 16,187.00
F Harga Satuan Pekerjaan (D+E) 165,394.90 178,057.00
29 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 62,931.00 67,177.00
Tenaga 31,260.00 33,870.00
L.01 0.12 OH Pekerja 105,000.00 115,000.00 12,600.00 13,800.00
L.02 0.12 OH Tukang Batu 135,000.00 145,000.00 16,200.00 17,400.00
L.03 0.012 OH Kepala Tukang 140,000.00 150,000.00 1,680.00 1,800.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
Bahan 25,950.00 27,200.00
0.003 m3 Papan Kayu Klas II 8,400,000.00 8,800,000.00 25,200.00 26,400.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 57,210.00 61,070.00
E Overhead & Profit (contoh 10%) 10% 5,721.00 6,107.00
F Harga Satuan Pekerjaan (D+E) 62,931.00 67,177.00
C PERALATAN
D Jumlah A + B + C 73,040.00 80,285.00
E Overhead & Profit (contoh 10%) 10% 7,304.00 8,028.50
F Harga Satuan Pekerjaan (D+E) 80,344.00 88,313.50
C PERALATAN
D Jumlah A + B + C 63,405.00 69,225.00
E Overhead & Profit (contoh 10%) 10% 6,340.50 6,922.50
F Harga Satuan Pekerjaan (D+E) 69,745.50 76,147.50
8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 13,563.00 14,906.38
A Tenaga 11,280.00 12,370.00
L.01 0.1 OH Pekerja 105,000.00 115,000.00 10,500.00 11,500.00
L.04 0.006 OH Mandor 130,000.00 145,000.00 780.00 870.00
B Bahan 1,050.00 1,181.25
0.35 Ltr Residu atau Ter 3,000.00 3,375.00 1,050.00 1,181.25
C PERALATAN
D Jumlah A + B + C 12,330.00 13,551.25
E Overhead & Profit (contoh 10%) 10% 1,233.00 1,355.13
F Harga Satuan Pekerjaan (D+E) 13,563.00 14,906.38
C PERALATAN
D Jumlah A + B + C 85,225.00 95,662.50
E Overhead & Profit (contoh 10%) 10% 8,522.50 9,566.25
F Harga Satuan Pekerjaan (D+E) 93,747.50 105,228.75
7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,825,769.27 1,974,643.54
A Tenaga 1,080,900.00 1,174,350.00
L.01 6.00 OH Pekerja 105,000.00 115,000.00 630,000.00 690,000.00
L.02 3.00 OH Tukang Batu 135,000.00 145,000.00 405,000.00 435,000.00
L.03 0.30 OH Kepala Tukang 140,000.00 150,000.00 42,000.00 45,000.00
L.04 0.03 OH Mandor 130,000.00 145,000.00 3,900.00 4,350.00
B Bahan 578,890.24 620,780.49
150.0 bh Batu Bata 550.00 580.00 82,500.00 87,000.00
120 Kg Portland Semen 0.11 1,150.00 1,200.00 138,000.00 144,000.00
0.3 m3 Pasir Pasang 0.0121 340,000.00 370,000.00 102,000.00 111,000.00
360 buah Porselen 11 x 11 cm 82.6446 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 12,000.00 15,000.00 72,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,659,790.24 1,795,130.49
E Overhead & Profit (contoh 10%) 10% 165,979.02 179,513.05
F Harga Satuan Pekerjaan (D+E) 1,825,769.27 1,974,643.54
9 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 357,280.00 399,987.50
A Tenaga 49,800.00 53,625.00
L.01 0.030 OH Pekerja 105,000.00 115,000.00 3,150.00 3,450.00
L.02 0.300 OH Tukang Batu 135,000.00 145,000.00 40,500.00 43,500.00
L.03 0.030 OH Kepala Tukang 140,000.00 150,000.00 4,200.00 4,500.00
L.04 0.015 OH Mandor 130,000.00 145,000.00 1,950.00 2,175.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 324,800.00 363,625.00
E Overhead & Profit (contoh 10%) 10% 32,480.00 36,362.50
F Harga Satuan Pekerjaan (D+E) 357,280.00 399,987.50
C PERALATAN
D Jumlah A + B + C 51,600.00 60,375.00
E Overhead & Profit (contoh 10%) 10% 5,160.00 6,037.50
F Harga Satuan Pekerjaan (D+E) 56,760.00 66,412.50
28 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 86,251.00 94,204.00
cm
A Tenaga 14,880.00 16,180.00
L.01 0.080 OH Pekerja 105,000.00 115,000.00 8,400.00 9,200.00
L.02 0.040 OH Tukang Batu 135,000.00 145,000.00 5,400.00 5,800.00
L.03 0.004 OH Kepala Tukang 140,000.00 150,000.00 560.00 600.00
L.04 0.004 OH Mandor 130,000.00 145,000.00 520.00 580.00
B Bahan 63,530.00 69,460.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,150.00 1,200.00 40,250.00 42,000.00
0.014 m3 Pasir Pasang 340,000.00 370,000.00 4,760.00 5,180.00
0.014 m3 Pasir Urug 180,000.00 220,000.00 2,520.00 3,080.00
- -
C PERALATAN
D Jumlah A + B + C 374,800.00 392,280.00
E Overhead & Profit (contoh 10%) 10% 37,480.00 39,228.00
F Harga Satuan Pekerjaan (D+E) 412,280.00 431,508.00
Overhead & Profit (contoh 10%)
2 A.8.4.6.2 1 buah Pemasangan MCB 505,340.00 536,448.00
A Tenaga 229,700.00 243,840.00
L.01 100 % Pekerja 229,700.00 243,840.00 229,700.00 243,840.00
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
D Jumlah A + B + C 78,865.00 87,045.00
E Overhead & Profit (contoh 10%) 10% 7,886.50 8,704.50
F Harga Satuan Pekerjaan (D+E) 86,751.50 95,749.50
34 A.8.4.1.34 1 m' Pemasangan Pipa GIP Ø 100 mm 102,703.33 116,380.00
A Tenaga 74,200.00 80,800.00
L.01 0.400 OH Pekerja 105,000.00 115,000.00 42,000.00 46,000.00
L.02 0.200 OH Tukang Pipa 135,000.00 145,000.00 27,000.00 29,000.00
L.04 0.040 OH Mandor 130,000.00 145,000.00 5,200.00 5,800.00
C PERALATAN
hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 - -
C PERALATAN
D Jumlah A + B + C 105,630.00 120,525.00
E Overhead & Profit (contoh 10%) 10% 10,563.00 12,052.50
F Harga Satuan Pekerjaan (D+E) 116,193.00 132,577.50
C PERALATAN
D Jumlah A + B + C 122,248.33 138,936.67
E Overhead & Profit (contoh 10%) 10% 12,224.83 13,893.67
F Harga Satuan Pekerjaan (D+E) 134,473.17 152,830.33
C PERALATAN
D Jumlah A + B + C 185,210.00 209,183.33
E Overhead & Profit (contoh 10%) 10% 18,521.00 20,918.33
F Harga Satuan Pekerjaan (D+E) 203,731.00 230,101.67
C PERALATAN
D Jumlah A + B + C 221,120.00 250,118.33
E Overhead & Profit (contoh 10%) 10% 22,112.00 25,011.83
F Harga Satuan Pekerjaan (D+E) 243,232.00 275,130.17
C PERALATAN
D Jumlah A + B + C 247,735.00 275,211.67
E Overhead & Profit (contoh 10%) 10% 24,773.50 27,521.17
F Harga Satuan Pekerjaan (D+E) 272,508.50 302,732.83
C PERALATAN
D Jumlah A + B + C 318,133.33 341,461.67
E Overhead & Profit (contoh 10%) 10% 31,813.33 34,146.17
F Harga Satuan Pekerjaan (D+E) 349,946.67 375,607.83
C PERALATAN
D Jumlah A + B + C 360,875.00 393,190.00
E Overhead & Profit (contoh 10%) 10% 36,087.50 39,319.00
F Harga Satuan Pekerjaan (D+E) 396,962.50 432,509.00
C PERALATAN
D Jumlah A + B + C 412,580.00 446,825.00
E Overhead & Profit (contoh 10%) 10% 41,258.00 44,682.50
F Harga Satuan Pekerjaan (D+E) 453,838.00 491,507.50
43 A.8.4.1.43 1 m' Pemasangan Pipa GIP Ø 600 mm 446,891.50 481,987.00
A Tenaga 246,265.00 268,170.00
L.01 1.327 OH Pekerja 105,000.00 115,000.00 139,335.00 152,605.00
L.02 0.664 OH Tukang Pipa 135,000.00 145,000.00 89,640.00 96,280.00
L.04 0.133 OH Mandor 130,000.00 145,000.00 17,290.00 19,285.00
C PERALATAN
D Jumlah A + B + C 406,265.00 438,170.00
E Overhead & Profit (contoh 10%) 10% 40,626.50 43,817.00
F Harga Satuan Pekerjaan (D+E) 446,891.50 481,987.00
C PERALATAN
D Jumlah A + B + C 631,630.00 680,025.00
E Overhead & Profit (contoh 10%) 10% 63,163.00 68,002.50
F Harga Satuan Pekerjaan (D+E) 694,793.00 748,027.50
C PERALATAN
D Jumlah A + B + C 716,595.00 779,875.00
E Overhead & Profit (contoh 10%) 10% 71,659.50 77,987.50
F Harga Satuan Pekerjaan (D+E) 788,254.50 857,862.50
B Bahan - -
- m' Pipa PVC Ø 63 mm 6,250.00 7,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 90 mm 7,500.00 8,750.00 - -
B Bahan - -
- m' Pipa PVC Ø 200 mm 15,000.00 26,250.00 - -
B Bahan - -
- m' Pipa PVC Ø 250 mm 20,000.00 46,250.00 - -
B Bahan - -
- m' Pipa PVC Ø 300 mm 45,000.00 70,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 400 mm 87,500.00 137,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 450 mm 225,000.00 262,500.00 - -
B Bahan - -
- m' Pipa PVC Ø 500 mm 280,000.00 285,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 600 mm 325,000.00 345,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 800 mm 425,000.00 450,000.00 - -
C PERALATAN 4,000.00 4,800.00
0.160 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 4,000.00 4,800.00
D Jumlah A + B + C 206,090.00 224,865.00
E Overhead & Profit (contoh 10%) 10% 20,609.00 22,486.50
F Harga Satuan Pekerjaan (D+E) 226,699.00 247,351.50
13 A.8.4.2.13 1 bh Pemotongan Pipa PVC Ø 900 mm 237,501.00 259,138.00
A Tenaga 211,710.00 230,540.00
L.01 1.141 OH Pekerja 105,000.00 115,000.00 119,805.00 131,215.00
L.02 0.571 OH Tukang Pipa 135,000.00 145,000.00 77,085.00 82,795.00
L.04 0.114 OH Mandor 130,000.00 145,000.00 14,820.00 16,530.00
B Bahan - -
- m' Pipa PVC Ø 900 mm 625,000.00 650,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.000 mm 730,000.00 750,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.100 mm 800,000.00 850,000.00 - -
B Bahan - -
- m' Pipa PVC Ø 1.200 mm 280,000.00 285,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 63 mm 15,000.00 17,500.00 - -
C PERALATAN - -
B Bahan - -
- m' Pipa GIP Ø 100 mm 19,166.67 25,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 125 mm 22,500.00 30,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 150 mm 28,333.33 36,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 24,355.00 26,520.00
E Overhead & Profit (contoh 10%) 10% 2,435.50 2,652.00
F Harga Satuan Pekerjaan (D+E) 26,790.50 29,172.00
37 A.8.4.2.37 1 bh Pemotongan Pipa GIP Ø 200 mm 69,377.00 75,548.00
A Tenaga 63,070.00 68,680.00
L.01 0.340 OH Pekerja 105,000.00 115,000.00 35,700.00 39,100.00
L.02 0.170 OH Tukang Pipa 135,000.00 145,000.00 22,950.00 24,650.00
L.04 0.034 OH Mandor 130,000.00 145,000.00 4,420.00 4,930.00
B Bahan - -
- m' Pipa GIP Ø 200 mm 37,500.00 48,333.33 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 250 mm 45,000.00 58,333.33 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 300 mm 70,000.00 81,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 400 mm 93,333.33 96,666.67 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 450 mm 110,000.00 120,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 500 mm 140,000.00 150,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 600 mm 160,000.00 170,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 800 mm 200,000.00 210,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 290,650.00 316,505.00
E Overhead & Profit (contoh 10%) 10% 29,065.00 31,650.50
F Harga Satuan Pekerjaan (D+E) 319,715.00 348,155.50
45 A.8.4.2.45 1 bh Pemotongan Pipa GIP Ø 900 mm 361,168.50 393,294.00
A Tenaga 328,335.00 357,540.00
L.01 1.770 OH Pekerja 105,000.00 115,000.00 185,850.00 203,550.00
L.02 0.885 OH Tukang Pipa 135,000.00 145,000.00 119,475.00 128,325.00
L.04 0.177 OH Mandor 130,000.00 145,000.00 23,010.00 25,665.00
B Bahan - -
- m' Pipa GIP Ø 900 mm 230,000.00 250,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.000 mm 260,000.00 270,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.100 mm 280,000.00 290,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
B Bahan - -
- m' Pipa GIP Ø 1.200 mm 310,000.00 320,000.00 - -
C PERALATAN
hari Peralatan Potong Pipa T1/manual (gergaji) 10,000.00 12,000.00 - -
D Jumlah A + B + C 441,835.00 481,135.00
E Overhead & Profit (contoh 10%) 10% 44,183.50 48,113.50
F Harga Satuan Pekerjaan (D+E) 486,018.50 529,248.50
49 A.8.4.2.49 1 bh Pemotongan Pipa DCI Ø 100 mm 11,313.50 12,370.60
A Tenaga 10,255.00 11,210.00
L.01 0.071 OH Pekerja 105,000.00 115,000.00 7,455.00 8,165.00
L.02 0.014 OH Tukang Pipa 135,000.00 145,000.00 1,890.00 2,030.00
L.04 0.007 OH Mandor 130,000.00 145,000.00 910.00 1,015.00
B Bahan - -
- m' Pipa DCI Ø 100 mm 25,000.00 30,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 125 mm 40,000.00 45,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 150 mm 60,000.00 70,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 200 mm 80,000.00 90,000.00 - -
B Bahan - -
- m' Pipa DCI Ø 250 mm 100,000.00 110,000.00 - -
B Bahan - -
m' Pipa DCI Ø 300 mm 120,000.00 130,000.00 - -
B Bahan - -
m' Pipa Baja Ø 63 mm 12,000.00 13,000.00 - -
B Bahan - -
m' Pipa Baja Ø 100 mm 12,500.00 15,000.00 - -
B Bahan - -
m' Pipa Baja Ø 125 mm 15,000.00 17,000.00 - -
B Bahan - -
m' Pipa Baja Ø 150 mm 20,000.00 25,000.00 - -
B Bahan - -
m' Pipa Baja Ø 200 mm 30,000.00 35,000.00 - -
B Bahan - -
m' Pipa Baja Ø 250 mm 50,000.00 60,000.00 - -
B Bahan - -
m' Pipa Baja Ø 300 mm 70,000.00 75,000.00 - -
B Bahan - -
m' Pipa Baja Ø 400 mm 85,000.00 90,000.00 - -
B Bahan - -
m' Pipa Baja Ø 450 mm 100,000.00 110,000.00 - -
B Bahan - -
m' Pipa Baja Ø 500 mm 125,000.00 150,000.00 - -
B Bahan - -
m' Pipa Baja Ø 600 mm 180,000.00 200,000.00 - -
B Bahan - -
m' Pipa Baja Ø 800 mm 250,000.00 275,000.00 - -
B Bahan - -
m' Pipa Baja Ø 900 mm 300,000.00 320,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.000 mm 350,000.00 375,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.100 mm 400,000.00 425,000.00 - -
B Bahan - -
m' Pipa Baja Ø 1.200 mm 450,000.00 475,000.00 - -
1 A.8.4.4.1 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 525,849.50 602,470.00
80 mm
A Tenaga 271,995.00 296,190.00
L.01 1.466 OH Pekerja 105,000.00 115,000.00 153,930.00 168,590.00
L.02 0.733 OH Tukang Pipa 135,000.00 145,000.00 98,955.00 106,285.00
L.04 0.147 OH Mandor 130,000.00 145,000.00 19,110.00 21,315.00
2 A.8.4.4.2 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 560,961.50 694,883.20
100 mm
A Tenaga 256,005.00 332,550.00
L.01 1.646 OH Pekerja 75,000.00 115,000.00 123,450.00 189,290.00
L.02 0.823 OH Tukang Pipa 135,000.00 145,000.00 111,105.00 119,335.00
L.04 0.165 OH Mandor 130,000.00 145,000.00 21,450.00 23,925.00
3 A.8.4.4.3 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 802,686.50 972,666.20
150 mm
A Tenaga 325,980.00 423,450.00
L.01 2.096 OH Pekerja 75,000.00 115,000.00 157,200.00 241,040.00
L.02 1.048 OH Tukang Pipa 135,000.00 145,000.00 141,480.00 151,960.00
L.04 0.210 OH Mandor 130,000.00 145,000.00 27,300.00 30,450.00
B Bahan 150,000.00 160,000.00
1 bh Pipa Ø 150 mm 150,000.00 160,000.00 150,000.00 160,000.00
C PERALATAN 253,735.00 300,792.00
0.76 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 19,000.00 22,800.00
0.369 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 55,350.00 62,730.00
1.353 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 169,125.00 202,950.00
1.026 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 10,260.00 12,312.00
D Jumlah A + B + C 729,715.00 884,242.00
E Overhead & Profit (contoh 10%) 10% 72,971.50 88,424.20
F Harga Satuan Pekerjaan (D+E) 802,686.50 972,666.20
4 A.8.4.4.4 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,011,411.50 1,228,449.20
200 mm
A Tenaga 395,955.00 514,350.00
L.01 2.546 OH Pekerja 75,000.00 115,000.00 190,950.00 292,790.00
L.02 1.273 OH Tukang Pipa 135,000.00 145,000.00 171,855.00 184,585.00
L.04 0.255 OH Mandor 130,000.00 145,000.00 33,150.00 36,975.00
B Bahan 200,000.00 220,000.00
1 bh Pipa Ø 200 mm 200,000.00 220,000.00 200,000.00 220,000.00
C PERALATAN 323,510.00 382,422.00
0.87 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 21,750.00 26,100.00
0.579 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 86,850.00 98,430.00
1.628 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 203,500.00 244,200.00
1.141 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 11,410.00 13,692.00
D Jumlah A + B + C 919,465.00 1,116,772.00
E Overhead & Profit (contoh 10%) 10% 91,946.50 111,677.20
F Harga Satuan Pekerjaan (D+E) 1,011,411.50 1,228,449.20
5 A.8.4.4.5 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,192,636.50 1,440,232.20
250 mm
A Tenaga 465,930.00 605,250.00
L.01 2.996 OH Pekerja 75,000.00 115,000.00 224,700.00 344,540.00
L.02 1.498 OH Tukang Pipa 135,000.00 145,000.00 202,230.00 217,210.00
L.04 0.300 OH Mandor 130,000.00 145,000.00 39,000.00 43,500.00
B Bahan 225,000.00 240,000.00
1 bh Pipa Ø 250 mm 225,000.00 240,000.00 225,000.00 240,000.00
C PERALATAN 393,285.00 464,052.00
0.980 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 24,500.00 29,400.00
0.789 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 118,350.00 134,130.00
1.903 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 237,875.00 285,450.00
1.256 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 12,560.00 15,072.00
D Jumlah A + B + C 1,084,215.00 1,309,302.00
E Overhead & Profit (contoh 10%) 10% 108,421.50 130,930.20
F Harga Satuan Pekerjaan (D+E) 1,192,636.50 1,440,232.20
6 A.8.4.4.6 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,362,861.50 1,641,015.20
300 mm
A Tenaga 535,905.00 696,150.00
L.01 3.446 OH Pekerja 75,000.00 115,000.00 258,450.00 396,290.00
L.02 1.723 OH Tukang Pipa 135,000.00 145,000.00 232,605.00 249,835.00
L.04 0.345 OH Mandor 130,000.00 145,000.00 44,850.00 50,025.00
B Bahan 240,000.00 250,000.00
1 bh Pipa Ø 250 mm 240,000.00 250,000.00 240,000.00 250,000.00
C PERALATAN 463,060.00 545,682.00
1.090 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 27,250.00 32,700.00
0.999 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 149,850.00 169,830.00
2.178 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 272,250.00 326,700.00
1.371 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 13,710.00 16,452.00
D Jumlah A + B + C 1,238,965.00 1,491,832.00
E Overhead & Profit (contoh 10%) 10% 123,896.50 149,183.20
F Harga Satuan Pekerjaan (D+E) 1,362,861.50 1,641,015.20
7 A.8.4.4.7 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,703,311.50 2,053,581.20
400 mm
A Tenaga 675,855.00 877,950.00
L.01 4.346 OH Pekerja 75,000.00 115,000.00 325,950.00 499,790.00
L.02 2.173 OH Tukang Pipa 135,000.00 145,000.00 293,355.00 315,085.00
L.04 0.435 OH Mandor 130,000.00 145,000.00 56,550.00 63,075.00
B Bahan 270,000.00 280,000.00
1 bh Pipa Ø 400 mm 270,000.00 280,000.00 270,000.00 280,000.00
C PERALATAN 602,610.00 708,942.00
1.310 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 32,750.00 39,300.00
1.419 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 212,850.00 241,230.00
2.728 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 341,000.00 409,200.00
1.601 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 16,010.00 19,212.00
D Jumlah A + B + C 1,548,465.00 1,866,892.00
E Overhead & Profit (contoh 10%) 10% 154,846.50 186,689.20
F Harga Satuan Pekerjaan (D+E) 1,703,311.50 2,053,581.20
8 A.8.4.4.8 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 1,879,036.50 2,265,364.20
450 mm
A Tenaga 745,830.00 968,850.00
L.01 4.796 OH Pekerja 75,000.00 115,000.00 359,700.00 551,540.00
L.02 2.398 OH Tukang Pipa 135,000.00 145,000.00 323,730.00 347,710.00
L.04 0.480 OH Mandor 130,000.00 145,000.00 62,400.00 69,600.00
9 A.8.4.4.9 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,065,761.50 2,488,147.20
500 mm
A Tenaga 815,805.00 1,059,750.00
L.01 5.246 OH Pekerja 75,000.00 115,000.00 393,450.00 603,290.00
L.02 2.623 OH Tukang Pipa 135,000.00 145,000.00 354,105.00 380,335.00
L.04 0.525 OH Mandor 130,000.00 145,000.00 68,250.00 76,125.00
10 A.8.4.4.10 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,406,211.50 2,900,713.20
600 mm
A Tenaga 955,755.00 1,241,550.00
L.01 6.146 OH Pekerja 75,000.00 115,000.00 460,950.00 706,790.00
L.02 3.073 OH Tukang Pipa 135,000.00 145,000.00 414,855.00 445,585.00
L.04 0.615 OH Mandor 130,000.00 145,000.00 79,950.00 89,175.00
B Bahan 350,000.00 360,000.00
1 bh Pipa Ø 600 mm 350,000.00 360,000.00 350,000.00 360,000.00
C PERALATAN 881,710.00 1,035,462.00
1.750 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 43,750.00 52,500.00
2.259 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 338,850.00 384,030.00
3.828 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 478,500.00 574,200.00
2.061 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 20,610.00 24,732.00
D Jumlah A + B + C 2,187,465.00 2,637,012.00
E Overhead & Profit (contoh 10%) 10% 218,746.50 263,701.20
F Harga Satuan Pekerjaan (D+E) 2,406,211.50 2,900,713.20
11 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 2,779,661.50 3,346,279.20
700 mm
A Tenaga 1,095,705.00 1,423,350.00
L.01 7.046 OH Pekerja 75,000.00 115,000.00 528,450.00 810,290.00
L.02 3.523 OH Tukang Pipa 135,000.00 145,000.00 475,605.00 510,835.00
L.04 0.705 OH Mandor 130,000.00 145,000.00 91,650.00 102,225.00
B Bahan 410,000.00 420,000.00
1 bh Pipa Ø 700 mm 410,000.00 420,000.00 410,000.00 420,000.00
C PERALATAN 1,021,260.00 1,198,722.00
1.970 hari Peralatan potong pipa T2/mekanik/cilinder saw 25,000.00 30,000.00 49,250.00 59,100.00
2.679 hari Sewa Genset 1500 Watt 150,000.00 170,000.00 401,850.00 455,430.00
4.378 hari Sewa Pompa Submersible 3 m³ / h 125,000.00 150,000.00 547,250.00 656,700.00
2.291 hari Sewa Tripod / Teckel & Handle Crane 2 Ton 10,000.00 12,000.00 22,910.00 27,492.00
12 A.8.4.4.11 1 bh
Penyambungan Pipa Baru ke Pipa yang ada Ø 3,109,111.50 3,758,845.20
800 mm
A Tenaga 1,235,655.00 1,605,150.00
L.01 7.946 OH Pekerja 75,000.00 115,000.00 595,950.00 913,790.00
L.02 3.973 OH Tukang Pipa 135,000.00 145,000.00 536,355.00 576,085.00
L.04 0.795 OH Mandor 130,000.00 145,000.00 103,350.00 115,275.00