Professional Documents
Culture Documents
Project report Submitted to college of Management and Economics Studies for the partial
fulfillment of the degree of
Submitted by
Bisweswar Biswal
R250213012
New Delhi
Master plan of Dholera Airport
Certificate of Originality
This is to certify that the project report entitled “Development of Greenfield International
in partial fulfillment of the requirement for the award of the degree of MBA (Aviation) is an
original work carried out by Mr. Bisweswar Biswal, under the guidance of Mr. Sapan Thakur.
The matter embodied in this project is a genuine work done to the best of my knowledge and
belief and has not been submitted before, neither to this University nor to any other University
Dated:
Signature:
Bisweswar Biswal
Certificate
This is to certify that the project titled “Development of Greenfield International Airport at
Dholera” is an academic work done by “Bisweswar Biswal” submitted in the partial fulfillment
of the requirement for the award of the Degree of MBA (Aviation) from University of
Petroleum and Energy Studies, Dehradun. It has been completed under the guidance of
Mr. Manish Yadav (Faculty Guide) and Mr. Sapan Thakur (Corporate Mentor). We are
thankful to “India Aviation Consulting & Support” for having allowed our student to undergo
project work training. The authenticity of the project work will be examined by the viva
examiner which includes data verification, checking duplicity of information etc. and it may be
Acknowledgement
On the very outset of this report, I would like to extend my sincere & heartfelt obligation towards
all the personages who have helped me in this endeavor. Without their active guidance, help,
cooperation & encouragement, I would not have made headway in the project.
I am ineffably indebted to Mr. Kishu Teckchandani (CEO), Mr. Roshan Lal (Vice President)
Mr. Sapan Thakur (Manager Airport Planning) for conscientious guidance and
encouragement to accomplish this assignment.
I am extremely thankful and pay my gratitude to my faculty Prof Manish Yadav for his
valuable guidance and support on completion of this project.
I extend my gratitude to University of Petroleum and Energy Studies for giving me this
opportunity.
I also acknowledge with a deep sense of reverence, my gratitude towards my parents and
member of my family, who has always supported me morally as well as economically.
At last but not least gratitude goes to all of my friends who directly or indirectly helped me to
complete this project report.
Any omission in this brief acknowledgement does not mean lack of gratitude.
Bisweswar Biswal
Preface
MBA courses is designed in such a way that only theoretical knowledge is not sufficient, so it is
very essential to have real corporate experience and practical knowledge to successfully
complete the course. The summer project is designed to provide participation of MBA program
as on the job experience. This has given a chance to try and apply the academic knowledge and
gain insight into corporate culture. This helps in developing decision-making abilities and
emphasizes on active participation by the student.
Summer internships offer the important opportunity to work closely with professionals, and to
develop knowledge, competencies, and experience related directly to career goals. The Project
consists of our findings after data analysis & then conclusions were drawn and finally
recommendations were put forward.
Bisweswar Biswal
Executive Summary
After studying numerous theoretical concepts during 1st year of MBA program in Aviation,
University of Petroleum and Energy Studies, Dehradun understanding the practical implications
was the next step in the learning process. The MBA internship has given an opportunity to work
with the consulting company that is India Aviation Consulting & Support LLP located at East of
Kailash, New Delhi. Which is mainly a consulting agency and deals with master planning of
airports. In due course of completing internship project and compiling this report it was very
clear about the parameters considered for planning a Greenfield airport and the step by step
process used in master planning an airport.
Government of India has planned for establishing Dedicated Freight Corridor (DFC) between
Delhi and Mumbai. This includes two Investment Regions and four Industrial Areas. Out of the
six locations, state has identified Ahmedabad-Dholera belt as the location for Special Investment
Region (SIR). In order to meet the traffic and cargo movement, the Govt. has planned for the
International Airport at Dholera.
This report consist of seven chapters, in first section it covers about the need of the airport. In
next phase the parameters which are consider for planning of an airport. Proper utilization of the
land available and the designing of the runway, terminal building according to IMG norms and
other facilities at airport.
The entire project report was on analytical research which includes theoretical research and the
secondary data available with the company.
After the entire study the conclusion come out to be is the proper utilization of the land available
for the construction of airport. The entire design depends on the position of the runway, its
direction and the length of the runway. After runway, all other design are commenced according
to runway position.
The recommendation that comes out of this report is the single runway master plan with all other
design as same.
1. Introduction
1.1 Master planning
1.1.1 An Airport Master Plan is a study used to determine the long-term development strategies
for an airport. Because air conveyance is a vital community industry, it is important that the
requirements for new or enhanced airports be projected. It is also essential to replacement
adequate resources to encounter identified needs. Airport master planning is a critical device in
determining needs and programming progress of individual airports.
1.1.2 The Airport Master Plan process provides opportunities for political entities and the public
to contribute in the development of aviation plans. It provides an agenda for individual airport
development programs reliable with short, intermediate, and long-range airport system
requirements and regulates future financial requirements.
1.1.3 An Airport Master Plan focus on the expansion needs for a 20-year time period.
Modernizes is always required for any industry to be in the development stage. The Airport
Master Plan is a public's idea of the long-term development of airport. It realistically displays the
concept and reports the data and reason upon which the plan is based. The plans are prepared to
provision the modernization of existing airports and the creation of new ones.
1.1.4 The master planning process considers the needs and demands of airport occupants, users,
and the common public. The guiding opinion of the airport master planning process is the
development of a safe and effective airport. It must also be responsive to area-wide inclusive
transportation planning.
Airfield Plan
1.2.2 "The Development Plan, taking into account the DMIC objectives and goals, should focus
towards generating and permitting environment to protect native industries, improve venture
climate, improve quality of life, advancement human skills, create world class infrastructure and
attract global investment".
1.2.3 Project goals are to dual the employment potential, triple industrial output and multiply
exports from the region in next five years. (GIDB, n.d.)
2. Literature Review
2.1 Government of India has planned for establishing Dedicated Freight Corridor (DFC) between
Delhi and Mumbai. About 38 % of the DFC is passing through Gujarat and a corridor of 150 km
on both sides of the DFC is to be developed as Delhi Mumbai Industrial Corridor (DMIC). This
includes two Investment Regions and four Industrial Areas. As envisaged by Government of
India, these nodes are to be developed as global hubs of manufacturing and commercial
activities. Out of the six locations, state has identified Ahmedabad-Dholera belt as the location
for Special Investment Region (SIR). Dholera SIR is proposed to be developed in a usable area
of 360 KM and would be located at a distance approximately 100 KM from Ahmedabad and
DFC is passing through this area. State has worked out the strategy of development of SIR with
formation of company, legal frame work etc.
2.2 The existing airport of Ahmedabad has emerged as one with highest annual growth in traffic
and will get saturated much before the year 2020. The expansion of Ahmedabad airport is
difficult due to various reasons. Under the circumstances, a new international airport is required
to cater the future traffic.
2.3 While assessing the potential and requirements of the Dholera SIR, Government envisaged a
tremendous need for a Greenfield International Airport in its vicinity. The level of economic
activities in the SIR backed by enormous domestic and foreign investment shall need a world
class modern International Airport in this region. Therefore state has included the development
of an International Airport in the list of “Early Bird Projects” in consultation with Department of
Industrial Promotion and Policy.
2.4 The state Government identified the location for the proposed Airport and has earmarked the
land. A parcel of Government land admeasuring approximately 1700 hectors has been reserved
in the triangle of village Pachham-Valinda-Pipli of Taluka Dhandhuka district Ahmedabad in the
name of Gujarat Industrial Corridor Company Ltd (GICC), which would work as a project
development agency for DMIC. The site is about 80 KM from Ahmedabad and around 20 KM
from Dholera SIR. In addition to the SIR and Ahmedabad city, this location is also ideally placed
vis-à-vis the cities like Nadiyad, Bhavnagar, Vadodara and Rajkot.
2.5 GIDB has initiated the process for obtaining approvals from Government of India according
to procedure laid down in latest Greenfield Airport Policy.
2.6 The project involves all activities related to project development i.e. air side and city side
infrastructure development. This includes land acquisitions, land development, passenger &
cargo terminal, ATC, airfield lighting, fire station, electric substation, cargo facility, water
treatment plant, car parking , hangers, cargo and passenger apron, taxiway, runway,
administrative block ,isolation bay ,GSE storage and A.C plant, access internal roads, hotels and
commercial development, night parking, basic repair and maintenance etc.
2.7 The project can be developed through Public Private Partnership through the Develop,
Finance, Operate and Transfer principle. Government can enter into concession agreement with
an SPV formed to develop the project. The private sector player forming the SPV can be selected
through a transparent bidding process. Government can provide support in terms of land
acquisition and environment clearance and ensure adequate land availability. Their revenue
stream would be generated through aeronautical and non-aeronautical facility usage charges.
3. Research Methodology
3.1.1 Quantitative Research- Quantitative research generates numerical data or information that
can be converted into numbers. Only measurable data are being gathered and analyzed in this
type of research.
3.1.2 Qualitative Research- Qualitative Research on the other hand generates non-numerical
data. It focuses on gathering of mainly verbal data rather than measurements.
3.2.1 Secondary Data: - Secondary data means data that are already available i.e.: they refer to
the data which have already been collected and analyzed by someone else. Usually published
data are available in: Various publications of the central, state/local governments or foreign
governments, technical and trade journals etc. The secondary data involved in this project has
been gathered from the medical journals, literatures and internet. Mainly Secondary method is
used to complete this work.
4. Traffic Forecast
4.1.2 Also airports at Bhavnagar, Rajkot and Vadodara have inadequate capacities and expansion
of terminals at these airports are not possible due to non-availability of space. These airports are
going to be saturated around 2020-25.
4.1.3 In case of Mumbai International Airport, with the new development of the terminal and the
proposal of new airport at Navi Mumbai there is more expectation on Dholera airport.
4.1.4 To understand the dynamics of growth at Dholera with the perspective of generation of air-
traffic due to establishment of the proposed industrial node at Dholera and the Govt. of Gujarat
having already set in motion the proposed for Dholera SIR, the growth in passenger traffic at this
proposed new airport at Dholera is likely to see a gradual growth in passenger and freight traffic
with the industries coming in both by Indians and International investors and people coming to
live at Dholera.
4.1.5 To assess the traffic potential for new Greenfield airport at Dholera in 3 phases of 10 years
each on long term basis a study has been conducted on some of the potentially comparable
airports with cities and population. The study compares the total air traffic v/s city population
and the share between international and domestic traffic.
Passenger – 2011-2012
Sr. City Population Total Air Domestic/
No. Census Traffic Traffic/ International
2011 Population
Domestic International
4.1.6 As it can be seen the study reveals that there is wide variation in percentage of annual air
traffic v/s population and this depends predominantly on the nature of importance of the location.
4.1.7 Considering the study we can conclude that Dholera population by year 2047-48 is
expected to be 20 lakhs. Dholera is being developed as a node on the Delhi Mumbai Industrial
Corridor and is therefore, likely to have a population of well qualified personal and their families
with visits to and from foreign buyers as well as family leisure travel. Therefore it is presume
that the air traffic to population ratio of 2:1 against the best of 1.3:1 for Delhi & Coimbatore.
4.1.8 Therefore it has been undertaken that the master plan for Dholera airport by computing a
linear growth % over a period of 30 years increasing the initial traffic of 4.38 lakhs in the year
2018-19 to 40 lakhs in the year 2047-48. (India Aviation Consulting and Support LLP, 2014)
4.2.2 The annual compounded growth for international Cargo has been taken as 8% while that
for the domestic cargo has been taken as 6% keeping in view that the international cargo will
dominate over domestic cargo with the type of industry being setup in the DSIR. With the
industry getting setup the cargo will grow gradually and in the initial years the growth is likely to
be lower than that at Ahmedabad because Ahmedabad airport had been an existence in over 40
years and industry has grown around Ahmedabad over these long years. On the same
contradictory the initial growth percentage at Dholera cannot be high. We have presumed the
growth percentage as below: (India Aviation Consulting and Support LLP, 2014)
4.3.2 The rest of the domestic operations have been presumed to be by narrow body single aisle
aircraft like B-737 NG, A320, A319, A318 as well as A321. On an average 70 % seat occupancy
has been assumed on domestic aircraft operations.
4.3.3 Keeping in view all type of aircraft, average seat occupancy of 125 seats per domestic
flights has been assumed for calculating the aircraft movement based on the domestic traffic.
4.3.4 Taking international operations the 1st phase of 10 years takes into account narrow body
single aisle aircraft with very limited operation of wide body aircraft up to CAT 4E due to
limited length of the runway of 2910 meters.
4.3.5 The average seat occupancy for narrow body aircraft on international sectors has been
taken as 150 passenger and for wide body aircraft expected to operate one flight per day from the
11th year of operations onwards with average seat occupancy of 250 passengers per wide body
aircraft.
4.3.6 With the commissioning of the second runway of 4000 meters length with cat F type
aircraft operations become possible both for passengers and freight operations.
4.3.7 Freight of all narrow body passenger aircraft are assumed to be carrying up to 1 MT of
belly cargo while the wide body aircraft carry 3.5 MT of belly cargo.
4.3.8 Narrow body aircraft for domestic sector including B-737 (all series)/ Q-400/ ATR-72 and
all other category with carrying capacity (average- 125 seats) and International sector-150 seats
(narrow body) and 250 seats (wide body) with overall passenger capacity of 75% has been
considered while computing forecast of aircraft movements. (India Aviation Consulting and
Support LLP, 2014)
5.1.2 The land use plan provides for ultimate design for category F type of aircraft in phase II
and all provisions for separation distance between runways, taxiways, taxi lanes, Apron are for
ultimate design but it will be carried on phase wise with type of aircraft used for operations. The
provisions of norms as per report submitted by the IMG have been taken into consideration for
calculation of area of the terminal building keeping in view the IMG norms for peak hour,
average day calculation as well as multiplying constants based on the range of passenger traffic.
The calculation have been presented for 2 level terminal designs. (GIDB, n.d.)
5.2.2 As per the design there will be two parallel runways (2910 M and 4000 M long) with
independent operations. There will be six taxi tracks with parallel taxi tracks and taxiways for
push back and two taxiways linking the runways. The distance between the two parallel runways
is proposed to be 1150 meters. The enclosed area between the two runways will be utilized for
terminal building, cargo terminal building, car park, ATC, fire station, provision for emergency
and medical facilities, provision for commercial utilization like establishment of flight catering
units, possible hotels/ convention halls, police station, BCAS offices, ATC office complex, met
office, car and bus parking areas for travelers.
6. Master Plan
6.1 Master Planning
6.1.1 The proposed development plans primarily according to standards and recommended
practices set out by the international Civil Aviation Organization (ICAO) & Director General of
Civil Aviation (DGCA), India for the safe, regular and orderly operations of air traffic/ aircraft
operations besides meeting the aspirations of the all stake holders. The area computations for the
airport, the recommendations of the IMG norms are considered.
6.1.2 For the cost estimation of the project help of financial experts are carried out for project
viability studies, the pavements has been designed to project the estimated pavement costs. The
estimated cost of terminals, all ancillary buildings, airfield lighting requirements,
communication, Nav aids and surveillance equipment and the cost of operations of the airport
have been computed for the viability study.
6.2.2 As the city is developing from scratch it is proposed that the airport provides for operation
of B737/ A320 operations initially. The airport ultimately provides for two parallel runways. The
Northern runway is only with 2910 meters length for wide body aircraft with load penalty. The
runway and taxiway will be provide with Cat E type of aircraft. While in the phase II the
Southern runway with 4000 meters length will be developed with Cat F aircraft operation
facilities.
Code Aero plane reference Code Wing Span Outer Main Gear
No. Field Length Letter Wheel Span
(1) (2) (3) (4) (5)
1 Less than 800 meters A Up to but not including Up to but not including
15 meters 4.5 meters
2 800 meters up to but not B 15 meters up to but not 4.5 meters up to but not
Including 1200 meters including 24 meters including 9 meters
3 1200 meters up to but not C 24 meters up to but not 6 meters up to but not
Including 1800 meters including 36 meters including 9 meters
4 1800 meters and above D 36 meters up to but not 9 meters up to but not
including 52 meters including 14 meters
6.6.2 The second runway of length 4000 meters with Cat F type of aircraft operation facilities
will be constructed in phase II.
6.6.3 With of Runway: The width of the runway is proposed as 45 meters for first runway to
meet airport category 4E and 60 meters to meet Cat 4F in phase II if needed.
6.9 Taxiways
6.9.1 In phase I the runway will have a parallel taxi with full length of 2910 meters and two rapid
exit taxiway connecting parallel taxi track to the runway. The pushback taxi lane will be
provided to the first runway to meet the operation needs.
6.9.2 The parallel taxi track for second runway will be provided in phase I depending upon the
need. A provision for Cat F push back taxi lane has been provided for future construction as per
the need and requirement.
6.12 Hangers
6.12.1 Provision has been made to provide hangers for MRO and hangers for airlines. The
hangers can also be used for maintenance and repair of aircraft. An apron space is also proposed
in front of hangers and it will be connected to runway by link taxiway.
6.14.4 Precision Approach Path Indicator (PAPI) on both ends of the each runway
Since the airport is planned for all weather operations, it is proposed to provide standard runway
lighting system with double circuit.
Both the runway will be having simple approach lighting system up to 420 meter for runway 06
and the precision approach category I lighting system up to 920 meter at runway 24.
As per the specifications given by DGCA CAR taxiway edge lights will be provided.
6.16.2 The IMG norms adopted for design of passenger terminals stipulate the following with
regard to area per peak hour passenger as well as peak hour and average day PH/PD/AD norm.
Table No-6-03- Multiplying factors for PD/AD and PH/AD ratios (as per IMG) (AAI)
International Domestic
Sr. No Traffic
Peak Day/ Peak Hour/ Peak Day/ Peak Hour/
Average Day Average Day Average Day Average Day
2028- 3.4 5.43 8.83 0.45 0.35 932 1487 419 520 23023
2029
2038- 5.28 13.45 18.73 0.35 0.25 1447 3685 506 921 34979
2039
6.16.3 The peak hour passenger in phase I is 419 for international and 520 for domestic while in
phase II 506 for international and 921 for domestic.
6.16.4 The building design is a two level passenger terminal building with departures on the
upper floor and arrival on the ground floor.
6.16.5 Provision has also been made for future development of the terminal building at south of
the airport approach road and the area for Cat F apron and push back taxi lane is also provided.
6.17.2 Area for perishable cargo terminal of size 30 X 40 M has been provided for both
International and Domestic cargo.
6.17.3 The cargo terminal building will be a single level building for both the phases.
6.17.4 The cargo terminal design is based on peak day cargo data provides for dwell time of
International cargo of 3 days and dwell time for domestic cargo of 1.5 days. The design also
provides 50 % area for unclaimed or unclear cargo for international and 25 % area for domestic
unclaimed or unclear cargo.
6.17.5 The norms for designing the cargo terminal taken are 10 Sqm of space for handling 1 ton
of cargo both for international and domestic cargo operations.
6.18.2 City Side: Area of 50 m X 90 m for a building for airline city side offices has been
provided.
6.19 Airport Fire Station, Fire Control Tower and Static tanks
6.19.1 The location of airport fire station is almost midway along the length of the Northern as
well as the proposed southern runway in phase II. The location is 440 meter perpendicular to the
northern runway with a clear dedicated road network to both the runways in order to carry out
the fire fighting operations smoothly.
6.19.2 Static water tank of 1.5 lakhs liter capacity is provided at the fire station with dedicated
road to the fire station. Similar capacity static water tanks are also provided one near the cargo
terminal and other near the oil fuel depot within the airport operational area to cover both ends of
the runway in case of the emergency.
6.22 Roads
6.22.1 The airport approach road will be provided as per the plan and this will be connected to
Ahmedabad – Bhavnagar highway. A 25 meter wide approach road is provided which will split
in two levels for departures on first floor and arrivals on the ground floor.
6.23.2 BCAS block: 50 m X 90 m this is located adjoining the admin block of the airport
operator/ Airport authority for easy interaction and to save time and energy for interaction for the
officer of two organization.
6.23.3 Flight Catering: 3 X 100 X 100 M. 3 sites for flight catering units are marked on the road
to the cargo terminal for direct access from city side. The entry in to the operational area can be
either from the main airport entry point near the terminal or can be from near the cargo terminal.
6.23.4 Isolation Bay: 100 m X 100 m isolation bay is proposed in one of the extension of the
airport. The site is about 400 meter from the nearest edge of the runway with all other three sides
being in the coastal zone with no construction and habitation. (DGCA) (India Aviation
Consulting and Support LLP, 2014)
7.2 Considering the type of soil on which the airport has been proposed special attention must be
taken care of due to soft silt clay and corrosive nature of the soil. Some important construction
technique must be consider particularly for this site like pile foundation and vibrio stone
columns. These technique will definitely increase the cost of construction and extra budget must
be consider for it.
8. Salient Recommendations
8.1 One of the major nodes of the DMICDC is located in Gujarat and the Govt. of Gujarat has
approved establishment of a Greenfield International Airport at Dholera to meet the needs of the
air travel of special investment region. Dholera location is surrounded by five airports but in the
long run Dholera Airport will be a major airport as the Ahmedabad airport will reach saturation
by 2025. All other airport will also be saturated by 2030. The Dholera Airport will then become
an alternate airport for Ahmedabad airport.
8.2 Once Dholera International Airport is commissioned and starts international flights then the
entire international and bit of domestic air traffic of the southern and western Gujarat will be
diverted to Dholera as Dholera will likely to have better air connectivity then other airports.
8.3 Runways
8.3.1 In the long run the airport is schedule to have two parallel runways with the distance of
1150 meters between the runways. Both the runways are proposed to be provided with ground
lighting systems consisting of runway edge lights, taxiway lights, approach lighting systems,
PAPI, apron lighting systems as per standard practices. Initially airport with the runway length of
2910 meters, 45 meters width and 7.5 meter shoulder on either sides is expected to manage the
operations by narrow body aircraft with wide body aircraft with load penalties. The runway
orientation 06/24 will be equipped with ILS with cat 1 precision approach lighting on one side
and simple approach lighting systems on other side.
8.4 Taxiways
8.4.1 Taxiways developed as per requirement during phase development will meet Cat E
operation requirements with first runway 06L/24R.
8.5 ATC
8.5.1 The ATC control tower will be with a height of 45 meters and the adjoining control tower
block will be on a plot of measuring 80 X 120 meters.
8.6.1 The main fire station 100 X 30 meters is proposed to be located between two proposed
runways so that minimum time is required to reach any location at the airport.
8.7 Hangers
8.7.1 Hangers considering the expected passenger air traffic as well as freight traffic the airport
is expected to house many aircraft. As such a number of hangers are provided for the airlines as
well as for possible futures MROs located at Dholera.
8.8.1 The aircraft fueling/ refueling is proposed by underground hydrant systems for the main
apron area but for remote parking bays bowser systems of fuel supply can also be adopted.
8.9.1 An integrated passenger terminal of both international and domestic passengers has been
designed for phase I and Phase II developments. The terminal designs are 2 level passenger
terminal departures on the 1st floor and arrivals on the ground floor.
8.10.1 Initially majority of the cargo will be carried out be belly cargo carried by scheduled
passenger flights and rarely freighter aircraft. The cargo tonnage is expected to be small. The
cargo terminal for phase I and Phase II will be adjoining to the passenger terminal. (India
Aviation Consulting and Support LLP, 2014)
9. Conclusions
9.1 On the whole, this internship was a useful experience. Gaining of new knowledge, skills and
meeting with new people. Certainly have achieved several of learning goals, however for some
the conditions did not permit. Got an insight into professional practice.
9.2 Coming to this internship project that was assigned was very important and useful for
acquiring knowledge about the airports. The parameters that are used for the Master Planning of
an airport was very important to know, which was possible with this Project that is
“Development of Greenfield International airport at Dholera”. The important point which is
consider in master plan of an airport is proper utilization of the land available for the
development of the airport. The second most important point is the location of the runway,
according to its location all other parameters are planned and designed as per the requirement.
9.3 After studying the report of Dholera Airport it can be recommended that instead of two
runway projection the airport can be planned according to one runway and all other facilities will
be same as per two runway master plan. One important point to be consider about the runway, its
location. The purpose for one runway on southern side as the first runway with ultimate design
capability of catering to type F aircrafts operations. More investment is required for the southern
runway as it is located along the costal side and soil condition is not up to mark for runway
condition.
9.4 By the internship it was also good to find out the internal strengths and weaknesses. This
helped to define what skills and knowledge to be improved in the coming time. It would be better
that the knowledge level of the language is sufficient to contribute fully to projects. This
internship has created a confidence to move ahead in the career. It would also be better to present
and express more confidently.
9.5 At last this internship has given new insights and motivation to pursue a career in master
planning of airports.
Bibliography
REFERENCES
1. DGCA CAR Section 4.(2006), Aero Standards & ATS Series
2. DCGA. (2006). Civil Aviation Requirements.
3. DGCA. (2004). DCGA CAR
4. DGCA Dimensions & Slopes of OLS. (2006). Title 4.1 & 4.2.
5. DCGA Section-4 Aero Standards. (2006). Aero Standards & ATS
6. IATA. (1995). Airport Development reference manual. Montreal:
International air transport association, c1995-
7. ICAO Aerodromes Vol1. (2006). Aerodromes Standards.
8. ICAO Design Manual
9. ICAO. (1987). Airport master planning. Montreal: International Civil
Aviation Organization.
10. ICAO Annexes 14( July 2004)
11. ICAO dimensions & slopes of OLS
12. http://www.indiaaviationconsulting.com/investment.html,
13. S.O 84E of Ministry of civil aviation on control of construction and
removal.
14. (2006). Aerodrome design and operations. New Delhi: govt. of India.
15. http://www.dholerasir.co/
16. http://dholerasir.webs.com/
17. http://www.dholerainfrastructure.com/project-vision.htm