Professional Documents
Culture Documents
BUS 7305
Law of Contract
Law of Contract
To be continued from previous lecture…
b) For part-performance of contract:
if one of the parties has performed the contract partly but
not completely and then the other party has shown
willingness to accept the part performed, in that case, the
strict rule will, usually not apply and can claim money for
that part performance of a contract.
To be continued…
The level of part-performance may be-
Substantial performance:
Limitation of frustration:
Notwithstanding the fact, however, there are the
limitations of frustrations in the following cases:
* Frustration took place where external
circumstances have caused the performance to
be radically different from that agreed.
Case: Davis Contractors Ltd vs Fareham Urban
District Council (1956) A.C. 696.
To be continued…
Fact: P contractors agreed to build 78 houses for D
for 92,425 pounds within the eight months.
Due to a shortage of skilled labor and building
materials, the work took 22 months and cost
111,076.
P claimed that the contract was frustrated by the
long delay and claimed the additional costs on a
quantum meruit basis.
HL Held: the contract was not frustrated because the
cause of the delay was not unforeseeable.