Professional Documents
Culture Documents
Sloof Dia. Besi Pajang Tulangan (M) Panjang Berat/m' Jlh.Tul. Total Berat
No Uraian
(m) (mm) Tulangan Kait Total (Kg/m') (Bh) (Kg)
Kolom Dia. Besi Pajang Tulangan (M) Panjang Berat/m' Jlh.Tul. Total Berat
No Uraian (m) (mm) Total
Tulangan Kait (Kg/m') (Bh) (Kg)
No Uraian Tiang Dia. Besi Pajang Tulanngan (M) Panjang Berat/m' Jlh.Tul. Total Berat
(mm) Tulangan Kait Total (Kg/m') (Bh) (Kg)
Sloof Dia. Besi Pajang Tulangan (M) Panjang Berat/m' Jlh.Tul. Total Berat
No Uraian
(m) (mm) Tulangan Kait Total (Kg/m') (Bh) (Kg)
Sloof Dia. Besi Pajang Tulangan (M) Panjang Berat/m' Jlh.Tul. Total Berat
No Uraian
(m) (mm) Tulangan Kait Total (Kg/m') (Bh) (Kg)
1 M3 PEMBESIAN dinding
Kolom Dia. Besi Pajang Tulangan (m) Panjang Berat/m' Jlh.Tul. Total Berat
No. Uraian Dia. (m) (mm) Total
Tulangan Kait (Kg/m') (Bh) (Kg)
Balok Dia. Besi Pajang Tulangan (m) Panjang Berat/m' Jlh.Tul. Total Berat
No Uraian
(m) (mm) Tulangan Kait Total (Kg/m') (Bh) (Kg)
1 Tulangan Utama 0.15 10 33.33 0.05 33.38 0.61 5 102.27
2 Sengkang/Beugel 0.20 6 0.70 0.03 0.73 0.22 167 26.84
JUMLAH TOTAL 129.11
Uraian Balok Dia. Besi Pajang Tulangan (m) Panjang Berat/m' Jlh.Tul. Total Berat
No
(m) (mm) Tulangan Kait Total (Kg/m') (Bh) (Kg)
Balok Dia. Besi Pajang Tulangan (m) Panjang Berat/m' Jlh.Tul. Total Berat
No Uraian
(m) (mm) Tulangan Kait Total (Kg/m') (Bh) (Kg)
AHSP PU A.4.1.1.5 1 m3 Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
Tenaga :
1.650 OH Pekerja @ Rp 95,000.00 Rp 156,750.00
0.275 OH Tukang @ Rp 125,000.00 Rp 34,375.00
0.028 OH Kepala Tukang @ Rp 250,000.00 Rp 7,000.00
0.083 OH Mandor @ Rp 120,000.00 Rp 9,960.00
Bahan :
326.000 Kg Semen Portland @ Rp 1,875.00 Rp 611,250.00
760.000 Kg Pasir Beton @ Rp 167.86 Rp 127,571.43
1,029.000 Kg Kerikil @ Rp 167.86 Rp 172,725.00
215.000 Liter Air @ Rp 80.00 Rp 17,200.00
Jumlah Rp 1,136,831.43
Jumlah Bahan -
C. PERALATAN
1 Water Pass Sewa-Hari 0.0040 - -
2 Theodolit Sewa-Hari 0.0040 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,140.00
E Overhead & Profit 15% X D 171.00
F Harga Satuan Pekerjaan ( D + E ) 1,311.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 74,250.00
E Overhead & Profit 15% X D 11,137.50
F Harga Satuan Pekerjaan ( D + E ) 85,387.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 90,900.00
E Overhead & Profit 15% X D 13,635.00
F Harga Satuan Pekerjaan ( D + E ) 104,535.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 107,790.00
E Overhead & Profit 15% X D
F Harga Satuan Pekerjaan ( D + E ) 107,790.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 98,840.00
E Overhead & Profit 15% X D 14,826.00
F Harga Satuan Pekerjaan ( D + E ) 113,666.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 149,700.00
E Overhead & Profit 15% X D 22,455.00
F Harga Satuan Pekerjaan ( D + E ) 172,155.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 119,400.00
E Overhead & Profit 15% X D 17,910.00
F Harga Satuan Pekerjaan ( D + E ) 137,310.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 32,550.00
E Overhead & Profit 15% X D 4,882.50
F Harga Satuan Pekerjaan ( D + E ) 37,432.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 33,750.00
E Overhead & Profit 15% X D
F Harga Satuan Pekerjaan ( D + E ) 33,750.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 53,500.00
E Overhead & Profit 15% X D 8,025.00
F Harga Satuan Pekerjaan ( D + E ) 61,525.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 29,700.00
E Overhead & Profit 15% X D 4,455.00
F Harga Satuan Pekerjaan ( D + E ) 34,155.00
Jenis Pekerjaan : Urugan Tanah Bekas Galian Termasuk Perataan dan Pemadatan (stamper)
Satuan / Unit : M3
Analisa : AHSP PU - T.14 b
Jumlah Bahan -
C. PERALATAN
1 Pemadat Timbunan (Stamper) Sewa-Hari 0.0500 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 53,500.00
E Overhead & Profit 15% X D 8,025.00
F Harga Satuan Pekerjaan ( D + E ) 61,525.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 29,700.00
E Overhead & Profit 15% X D 4,455.00
F Harga Satuan Pekerjaan ( D + E ) 34,155.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 569,625.00
E Overhead & Profit 15% X D 85,443.75
F Harga Satuan Pekerjaan ( D + E ) 655,068.75
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 137,280.00
E Overhead & Profit 15% X D 20,592.00
F Harga Satuan Pekerjaan ( D + E ) 157,872.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Dinding Bata Merah Tebal 1/2 Bata Campuran 1 : 2
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.7
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 80,831.25
E Overhead & Profit 15% X D 12,124.69
F Harga Satuan Pekerjaan ( D + E ) 92,955.94
Jenis Pekerjaan : Pasangan Dinding Bata Merah Tebal 1/2 Bata Campuran 1 : 4
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.9
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 66,862.50
E Overhead & Profit 15% X D 10,029.38
F Harga Satuan Pekerjaan ( D + E ) 76,891.88
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 65,925.00
E Overhead & Profit 15% X D 9,888.75
F Harga Satuan Pekerjaan ( D + E ) 75,813.75
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 71,970.00
E Overhead & Profit 15% X D 10,795.50
F Harga Satuan Pekerjaan ( D + E ) 82,765.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 64,500.00
E Overhead & Profit 15% X D 9,675.00
F Harga Satuan Pekerjaan ( D + E ) 74,175.00
Jenis Pekerjaan : Lantai Kerja Beton Mutu F'c = 7,4 Mpa (K 100), Slump (3-6) cm, W/c = 0,87
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.4
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 920,735.71
E Overhead & Profit 15% X D 138,110.36
F Harga Satuan Pekerjaan ( D + E ) 1,058,846.07
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,136,831.43
E Overhead & Profit 15% X D
F Harga Satuan Pekerjaan ( D + E ) 1,136,831.43
Jenis Pekerjaan : Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, W/c = 0,58
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.7
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,213,820.71
E Overhead & Profit 15% X D 182,073.11
F Harga Satuan Pekerjaan ( D + E ) 1,395,893.82
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,235,845.71
E Overhead & Profit 15% X D 185,376.86
F Harga Satuan Pekerjaan ( D + E ) 1,421,222.57
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 214,700.00
E Per Kg Pembesian = D / 10 21,470.00
F Overhead & Profit 15% X E
G Harga Satuan Pekerjaan ( E + F ) 21,470.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 25,730.00
E Overhead & Profit 15% X D 3,859.50
F Harga Satuan Pekerjaan ( D + E ) 29,589.50
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 382,910.00
E Bekisting Dipakai 2 x = D/2 191,455.00
F Overhead & Profit 15% X E 28,718.25
G Harga Satuan Pekerjaan ( E + F ) 220,173.25
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Sloof
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.21
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 420,805.00
E Bekisting Dipakai 2 x = D/2 210,402.50
F Overhead & Profit 15% X E 31,560.38
G Harga Satuan Pekerjaan ( E + F ) 241,962.88
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 747,650.00
E Bekisting Dipakai 2 x = D/2 373,825.00
F Overhead & Profit 15% X E 56,073.75
G Harga Satuan Pekerjaan ( E + F ) 429,898.75
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Balok
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.23
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 772,025.00
E Bekisting Dipakai 2 x = D/2 386,012.50
F Overhead & Profit 15% X E 57,901.88
G Harga Satuan Pekerjaan ( E + F ) 443,914.38
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Plat Lantai
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.24
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,067,650.00
E Bekisting Dipakai 2 x = D/2 533,825.00
F Overhead & Profit 15% X E 80,073.75
G Harga Satuan Pekerjaan ( E + F ) 613,898.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 805,025.00
E Bekisting Dipakai 2 x = D/2 402,512.50
F Overhead & Profit 15% X E
G Harga Satuan Pekerjaan ( E + F ) 402,512.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 13,780.00
E Overhead & Profit 15% X D 2,067.00
F Harga Satuan Pekerjaan ( D + E ) 15,847.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 15,885.00
E Overhead & Profit 15% X D 2,382.75
F Harga Satuan Pekerjaan ( D + E ) 18,267.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 17,920.00
E Overhead & Profit 15% X D 2,688.00
F Harga Satuan Pekerjaan ( D + E ) 20,608.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 20,025.00
E Overhead & Profit 15% X D 3,003.75
F Harga Satuan Pekerjaan ( D + E ) 23,028.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 32,110.00
E Overhead & Profit 15% X D 4,816.50
F Harga Satuan Pekerjaan ( D + E ) 36,926.50
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 43,440.00
E Overhead & Profit 15% X D 6,516.00
F Harga Satuan Pekerjaan ( D + E ) 49,956.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 49,785.00
E Overhead & Profit 15% X D 7,467.75
F Harga Satuan Pekerjaan ( D + E ) 57,252.75
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 70,972.50
E Overhead & Profit 15% X D 10,645.88
F Harga Satuan Pekerjaan ( D + E ) 81,618.38
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 92,160.00
E Overhead & Profit 15% X D 13,824.00
F Harga Satuan Pekerjaan ( D + E ) 105,984.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 65,905.00
E Overhead & Profit 15% X D 9,885.75
F Harga Satuan Pekerjaan ( D + E ) 75,790.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 71,185.00
E Overhead & Profit 15% X D 10,677.75
F Harga Satuan Pekerjaan ( D + E ) 81,862.75
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 76,465.00
E Overhead & Profit 15% X D 11,469.75
F Harga Satuan Pekerjaan ( D + E ) 87,934.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 93,530.00
E Overhead & Profit 15% X D 14,029.50
F Harga Satuan Pekerjaan ( D + E ) 107,559.50
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 146,930.00
E Overhead & Profit 15% X D 22,039.50
F Harga Satuan Pekerjaan ( D + E ) 168,969.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 174,960.00
E Overhead & Profit 15% X D 26,244.00
F Harga Satuan Pekerjaan ( D + E ) 201,204.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 186,720.00
E Overhead & Profit 15% X D 28,008.00
F Harga Satuan Pekerjaan ( D + E ) 214,728.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 249,527.50
E Overhead & Profit 15% X D 37,429.13
F Harga Satuan Pekerjaan ( D + E ) 286,956.63
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 312,335.00
E Overhead & Profit 15% X D 46,850.25
F Harga Satuan Pekerjaan ( D + E ) 359,185.25
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 5,810.00
E Overhead & Profit 15% X D 871.50
F Harga Satuan Pekerjaan ( D + E ) 6,681.50
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 6,295.00
E Overhead & Profit 15% X D 944.25
F Harga Satuan Pekerjaan ( D + E ) 7,239.25
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 6,780.00
E Overhead & Profit 15% X D 1,017.00
F Harga Satuan Pekerjaan ( D + E ) 7,797.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,485.00
E Overhead & Profit 15% X D 1,572.75
F Harga Satuan Pekerjaan ( D + E ) 12,057.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 17,265.00
E Overhead & Profit 15% X D 2,589.75
F Harga Satuan Pekerjaan ( D + E ) 19,854.75
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 22,570.00
E Overhead & Profit 15% X D 3,385.50
F Harga Satuan Pekerjaan ( D + E ) 25,955.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 28,815.00
E Overhead & Profit 15% X D 4,322.25
F Harga Satuan Pekerjaan ( D + E ) 33,137.25
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 38,985.00
E Overhead & Profit 15% X D 5,847.75
F Harga Satuan Pekerjaan ( D + E ) 44,832.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 49,155.00
E Overhead & Profit 15% X D 7,373.25
F Harga Satuan Pekerjaan ( D + E ) 56,528.25
Jenis Pekerjaan : Membuat dan Memasang Kusen pintu dan Kusen Jendela, Kayu Kelas I
Satuan / Unit : M3
Analisa : AHSP PU A.4.6.1.1
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 19,283,625.00
E Overhead & Profit 15% X D 2,892,543.75
F Harga Satuan Pekerjaan ( D + E ) 22,176,168.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,247,045.00
E Overhead & Profit 15% X D 187,056.75
F Harga Satuan Pekerjaan ( D + E ) 1,434,101.75
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 20,880,980.00
E Overhead & Profit 15% X D 3,132,147.00
F Harga Satuan Pekerjaan ( D + E ) 24,013,127.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,593,800.00
E Overhead & Profit 15% X D 1,589,070.00
F Harga Satuan Pekerjaan ( D + E ) 12,182,870.00
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 202,962.50
E Overhead & Profit 15% X D 30,444.38
F Harga Satuan Pekerjaan ( D + E ) 233,406.88
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 6 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.1.5
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 25,739.00
E Overhead & Profit 15% X D 3,860.85
F Harga Satuan Pekerjaan ( D + E ) 29,599.85
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 138,556.25
E Overhead & Profit 15% X D 20,783.44
F Harga Satuan Pekerjaan ( D + E ) 159,339.69
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 138,556.25
E Overhead & Profit 15% X D 20,783.44
F Harga Satuan Pekerjaan ( D + E ) 159,339.69
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 21,120.00
E Overhead & Profit 15% X D 3,168.00
F Harga Satuan Pekerjaan ( D + E ) 24,288.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 32,200.00
E Overhead & Profit 15% X D 4,830.00
F Harga Satuan Pekerjaan ( D + E ) 37,030.00
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 103,278.00
E Overhead & Profit 15% X D 15,491.70
F Harga Satuan Pekerjaan ( D + E ) 118,769.70
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,175.00
E Overhead & Profit 15% X D 1,526.25
F Harga Satuan Pekerjaan ( D + E ) 11,701.25
Jenis Pekerjaan : Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar,2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.4
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 9,635.00
E Overhead & Profit 15% X D 1,445.25
F Harga Satuan Pekerjaan ( D + E ) 11,080.25
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengecatan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 11,650.00
E Overhead & Profit 15% X D 1,747.50
F Harga Satuan Pekerjaan ( D + E ) 13,397.50
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 9,260.00
E Overhead & Profit 15% X D 1,389.00
F Harga Satuan Pekerjaan ( D + E ) 10,649.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 160,400.00
E Overhead & Profit 15% X D 24,060.00
F Harga Satuan Pekerjaan ( D + E ) 184,460.00
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 676,700.00
E Overhead & Profit 15% X D 101,505.00
F Harga Satuan Pekerjaan ( D + E ) 778,205.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 16,550.00
E Overhead & Profit 15% X D 2,482.50
F Harga Satuan Pekerjaan ( D + E ) 19,032.50
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 75,835.00
E Overhead & Profit 15% X D 11,375.25
F Harga Satuan Pekerjaan ( D + E ) 87,210.25
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 24,015.00
E Overhead & Profit 15% X D 3,602.25
F Harga Satuan Pekerjaan ( D + E ) 27,617.25
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,016.00
E Overhead & Profit 15% X D 152.40
F Harga Satuan Pekerjaan ( D + E ) 1,168.40
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,176.00
E Overhead & Profit 15% X D 176.40
F Harga Satuan Pekerjaan ( D + E ) 1,352.40
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,496.00
E Overhead & Profit 15% X D 224.40
F Harga Satuan Pekerjaan ( D + E ) 1,720.40
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 2,296.00
E Overhead & Profit 15% X D 344.40
F Harga Satuan Pekerjaan ( D + E ) 2,640.40
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 3,336.00
E Overhead & Profit 15% X D 500.40
F Harga Satuan Pekerjaan ( D + E ) 3,836.40
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 4,776.00
E Overhead & Profit 15% X D 716.40
F Harga Satuan Pekerjaan ( D + E ) 5,492.40
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 6,536.00
E Overhead & Profit 15% X D 980.40
F Harga Satuan Pekerjaan ( D + E ) 7,516.40
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,936.00
E Overhead & Profit 15% X D 1,640.40
F Harga Satuan Pekerjaan ( D + E ) 12,576.40
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0370 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 3,770.00
E Overhead & Profit 15% X D 565.50
F Harga Satuan Pekerjaan ( D + E ) 4,335.50
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0370 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 7,465.00
E Overhead & Profit 15% X D 1,119.75
F Harga Satuan Pekerjaan ( D + E ) 8,584.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0400 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 11,160.00
E Overhead & Profit 15% X D 1,674.00
F Harga Satuan Pekerjaan ( D + E ) 12,834.00
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0450 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 24,265.00
E Overhead & Profit 15% X D 3,639.75
F Harga Satuan Pekerjaan ( D + E ) 27,904.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0600 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 62,855.00
E Overhead & Profit 15% X D 9,428.25
F Harga Satuan Pekerjaan ( D + E ) 72,283.25
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0680 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 87,530.00
E Overhead & Profit 15% X D 13,129.50
F Harga Satuan Pekerjaan ( D + E ) 100,659.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0720 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 98,280.00
E Overhead & Profit 15% X D 14,742.00
F Harga Satuan Pekerjaan ( D + E ) 113,022.00
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0885 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 144,180.00
E Overhead & Profit 15% X D 21,627.00
F Harga Satuan Pekerjaan ( D + E ) 165,807.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.1050 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 190,080.00
E Overhead & Profit 15% X D 28,512.00
F Harga Satuan Pekerjaan ( D + E ) 218,592.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 15,060.00
E Overhead & Profit 15% X D 2,259.00
F Harga Satuan Pekerjaan ( D + E ) 17,319.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 64,200.00
E Overhead & Profit 15% X D 9,630.00
F Harga Satuan Pekerjaan ( D + E ) 73,830.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,700.00
E Overhead & Profit 15% X D 1,605.00
F Harga Satuan Pekerjaan ( D + E ) 12,305.00
ANALISA HARGA SATUAN PEKERJAAN
Rekapitulasi :
I PEKERJAAN PERSIAPAN 850,000.00
II PEKERJAAN TANAH 803,520.00
III PEKERJAAN STRUKTUR BETON BERTULANG 17,930,101.08
IV PEKERJAAN LANTAI 255,787.07
V PEKERJAAN LAIN-LAIN 2,400,000.00
Jumlah Total 22,239,408.15
Dibulatkan 22,239,000.00
Terbilang : ###
Galian Dan Urugan
Galian Tanah Panjang
Dia. Pipa Volume Galian
Penampang Ukuran Volume (M3) Pipa
Pipa
Dalam Luar Urugan
Tinggi Lebar Galian M' Galian
dia. 400 415 0.135 1.800 0.850 1.530 1.395 -
dia. 350 365 0.105 1.600 0.750 1.200 1.095 -
dia. 300 315 0.078 1.500 0.500 0.750 0.672 -
dia. 250 265 0.055 1.400 0.450 0.630 0.575 -
dia. 200 210 0.035 1.350 0.400 0.540 0.505 - -
dia. 150 160 0.020 1.100 0.350 0.385 0.365 - -
dia. 100 110 0.009 1.000 0.300 0.300 0.291 - -
dia. 75 90 0.006 0.875 0.250 0.219 0.212 - -
dia. 50 63 0.003 0.750 0.200 0.150 0.147 -
dia. 40 50 0.002 0.650 0.200 0.130 0.128 -
JUMLAH - -
Dia. Pipa
Tebal Pipa Keliling Pipa Umpak
Urugan Sisi
Urugan T P
Dipadatkan Miring
- - 2.30 2.30 6.51
- - 2.10 2.10 5.94
- - 2.00 2.00 5.66
- - 1.90 1.90 5.37
- - 1.85 1.85 5.23
- - 1.60 1.60 4.53
- - 1.50 1.50 4.24
- - 1.38 1.38 3.89
- - 1.25 1.25 3.54
- - 1.15 1.15 3.25
- -
Vol 2 Unit
0.214
0.199
0.184
0.151
0.138
0.110
0.098
0.069
0.064
0.062
Back Up Perlintasan Dia 50 mm
L 1
No Uraian Satuan
Jumlah Pembulatan
- - - - -
- - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
igunakan Tergantung
- - - - - - -
igunakan - - - - - -
- - - - - - -
- - - - - -
igunakan
- - - - - -
- - - - - - -
igunakan - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
- - - - - - -
- - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
igunakan Tergantung
- - - - - -
igunakan
- - - - - - -
L 1 ---5 M L 6 --- 12 M
Jumlah Pembulatan
- - - - -
- - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
igunakan Tergantung
- - - - - - -
igunakan - - - - - -
- - - - - - -
- - - - - -
igunakan
- - - - - -
- - - - - - -
igunakan - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
- - - - - - -
- - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
igunakan Tergantung
- - - - - -
igunakan
- - - - - - -
L 1 ---5 M L 6 --- 12 M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - 5.24 6.00 - - - -
- - - - 4.00 4.00 - - - -
- - - - 2.00 2.00 - - - -
- - - - 2.00 2.00 - - - -
- - - - - -
igunakan - - - -
- - - - 8.00 8.00 - - - -
igunakan - - - - - -
- - - - 0.09 0.09 - - - -
- - - - - -
igunakan
- - - - - -
- - - - 0.60 0.60 - - - -
igunakan - - - - - -
erlu Diisi 6.00 Gak Perlu Diisi
- - - - 3.00 3.00 - - - -
- - - - 6.00 6.00 - - - -
- - - - 2.00 2.00 - - - -
erlu Diisi 2.07 Gak Perlu Diisi
- - - - 6.00 6.00 - - - -
- - - -
igunakan
- - - -
- -
igunakan - - - -
- - - - 0.10 0.10 - - - -
L 1 ---5 M L 6 --- 12 M
Jumlah Pembulatan
- - - - -
- - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - -
igunakan - -
- - - - - - -
igunakan - - - - - -
- - - - - - -
- - - - - -
igunakan
- - - - - -
- - - - - - -
igunakan - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
- - - - - - -
- - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
- -
igunakan
igunakan
- -
- - - - - -
igunakan
- - - - - - -
L 1 ---5 M L 6 --- 12 M
Jumlah Pembulatan
- - - - -
- - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - -
igunakan Tergantung
- - - - - - -
igunakan - - - - - -
- - - - - - -
- - - - - -
igunakan
- - - - - -
- - - - - - -
igunakan - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
- - - - - - -
- - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
igunakan Tergantung
- - - - - -
igunakan
- - - - - - -
L 1 ---5 M L 6 --- 12 M
Jumlah Pembulatan
- - - - -
- - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- - - - - - -
- -
igunakan Tergantung
- - - - - - -
igunakan - - - - - -
- - - - - - -
- - - - - -
igunakan
- - - - - -
- - - - - - -
igunakan - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
- - - - - - -
- - - - - - -
erlu Diisi - Gak Perlu Diisi
- - - - - - -
igunakan Tergantung
- - - - - -
igunakan
- - - - - - -
L 6 --- 12 M L 13 --- 18 M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- -
- - - - - - -
ergantung
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - -
ergantung - - - - -
- - - - - - - - -
-
- - - - - - - - - -
L 6 --- 12 M L 13 --- 18 M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- -
- - - - -
ergantung - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - -
ergantung - - - - -
- - - - - - - - -
-
- - - - - - - - - -
L 6 --- 12 M L 13 --- 18 M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - -
- - - - -
- -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - -
- -
- - - - -
- -
- - - - -
- - - - -
- - - - - - - - - -
L 6 --- 12 M L 13 --- 18 M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - -
- - - - -
- -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - -
- -
- - - - -
- -
- - - - - - - - -
-
- - - - - - - - - -
L 6 --- 12 M L 13 --- 18 M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- -
- - - - -
ergantung - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - -
ergantung - - - - -
- - - - - - - - -
-
- - - - - - - - - -
L 6 --- 12 M L 13 --- 18 M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- -
- - - - -
ergantung - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- Gak Perlu Diisi
- - - - - - - - - -
- - - - -
ergantung - - - - -
- - - - - - - - -
-
- - - - - - - - - -
L 13 --- 18 M L 19 --- Lebih Besar M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - -
- - - - - - - - - -
- -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
L 13 --- 18 M L 19 --- Lebih Besar M
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - -
- - - - - - - - - -
- -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - -
- - - - - - - - - -
- - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - -
- - - - - - - - - -
- - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - -
- - - - - - - - - -
- - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Jumlah Pembulatan
- - - - - - - -
- - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - -
- - - - - - - - - -
- -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - -
- - - - - - - - - -
Diisi - Gak Perlu Diisi
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
- - - - - - - - - -
bih Besar M
LUBANG BAUT
Jumlah Pembulatan DN mm in L D D1
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
- - -
- -
- - -
-
- - -
- - -
- - -
- - -
- - -
bih Besar M
LUBANG BAUT
Jumlah Pembulatan DN mm in L D D1
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
- - -
- -
- - -
-
- - -
- - -
- - -
- - -
- - -
bih Besar M
LUBANG BAUT
Jumlah Pembulatan DN mm in L D D1
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
- - -
- -
- - -
-
- - -
- - -
- - -
- - -
- - -
bih Besar M
LUBANG BAUT
Jumlah Pembulatan DN mm in L D D1
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
- - -
- -
- - -
-
- - -
- - -
- - -
- - -
- - -
bih Besar M
LUBANG BAUT
Jumlah Pembulatan DN mm in L D D1
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
- - -
- -
- - -
-
- - -
- - -
- - -
- - -
- - -
bih Besar M
LUBANG BAUT
Jumlah Pembulatan DN mm in L D D1
- - -
- - -
- - -
- - -
- - -
- - -
- - -
-
- - -
- -
- - -
-
- - -
- - -
- - -
- - -
- - -
Asumsi 50
Luas Jumlah
D2 b H D0 W(kg) Diameter Dia
Paking Baut
100 16 409 200 24 0.1550 0.0240 4.00 400
120 18 535 250 31 0.1750 0.0306 4.00 350
130 18 570 250 40 0.1850 0.0342 4.00 300
155 18 590 250 55 0.2100 0.0441 4.00 250
215 22 630 300 90 0.2800 0.0784 8.00 200
265 22 960 350 145 0.3300 0.1089 10.00 150
325 24 1158 400 230 0.4000 0.1600 12.00 100
370 24 1378 450 330 0.4500 0.2025 16.00 75
415 26 1543 500 460 0.4900 0.2401 16.00 50
475 28 1738 600 600 0.5600 0.3136 16.00 40
530 30 1959 600 980 0.6200 0.3844 20.00
585 30 2214 680 960 0.6750 0.4556 20.00
Asumsi 50
Luas Jumlah
D2 b H D0 W(kg) Diameter Dia
Paking Baut
100 16 409 200 24 0.1550 0.0240 4.00 400
120 18 535 250 31 0.1750 0.0306 4.00 350
130 18 570 250 40 0.1850 0.0342 4.00 300
155 18 590 250 55 0.2100 0.0441 4.00 250
215 22 630 300 90 0.2800 0.0784 8.00 200
265 22 960 350 145 0.3300 0.1089 10.00 150
325 24 1158 400 230 0.4000 0.1600 12.00 100
370 24 1378 450 330 0.4500 0.2025 16.00 75
415 26 1543 500 460 0.4900 0.2401 16.00 50
475 28 1738 600 600 0.5600 0.3136 16.00 40
530 30 1959 600 980 0.6200 0.3844 20.00
585 30 2214 680 960 0.6750 0.4556 20.00
Asumsi 50
Luas Jumlah
D2 b H D0 W(kg) Diameter Dia
Paking Baut
100 16 409 200 24 0.1550 0.0240 4.00 400
120 18 535 250 31 0.1750 0.0306 4.00 350
130 18 570 250 40 0.1850 0.0342 4.00 300
155 18 590 250 55 0.2100 0.0441 4.00 250
215 22 630 300 90 0.2800 0.0784 8.00 200
265 22 960 350 145 0.3300 0.1089 10.00 150
325 24 1158 400 230 0.4000 0.1600 12.00 100
370 24 1378 450 330 0.4500 0.2025 16.00 75
415 26 1543 500 460 0.4900 0.2401 16.00 50
475 28 1738 600 600 0.5600 0.3136 16.00 40
530 30 1959 600 980 0.6200 0.3844 20.00
585 30 2214 680 960 0.6750 0.4556 20.00
Asumsi 50
Luas Jumlah
D2 b H D0 W(kg) Diameter Dia
Paking Baut
100 16 409 200 24 0.1550 0.0240 4.00 400
120 18 535 250 31 0.1750 0.0306 4.00 350
130 18 570 250 40 0.1850 0.0342 4.00 300
155 18 590 250 55 0.2100 0.0441 4.00 250
215 22 630 300 90 0.2800 0.0784 8.00 200
265 22 960 350 145 0.3300 0.1089 10.00 150
325 24 1158 400 230 0.4000 0.1600 12.00 100
370 24 1378 450 330 0.4500 0.2025 16.00 75
415 26 1543 500 460 0.4900 0.2401 16.00 50
475 28 1738 600 600 0.5600 0.3136 16.00 40
530 30 1959 600 980 0.6200 0.3844 20.00
585 30 2214 680 960 0.6750 0.4556 20.00
Asumsi 50
Luas Jumlah
D2 b H D0 W(kg) Diameter Paking Baut
Dia
0.50 0.50 0.70 0.70 0.80 0.25 0.49 0.296 0.592 0.810
0.45 0.45 0.60 0.60 0.80 0.20 0.36 0.225 0.450 0.640
0.40 0.40 0.50 0.50 0.80 0.16 0.25 0.164 0.328 0.490
0.35 0.35 0.50 0.50 0.80 0.12 0.25 0.149 0.298 0.490
0.30 0.30 0.50 0.50 0.80 0.09 0.25 0.136 0.272 0.490
0.25 0.25 0.50 0.50 0.80 0.06 0.25 0.125 0.250 0.490
0.20 0.20 0.50 0.50 0.80 0.04 0.25 0.116 0.232 0.490
0.18 0.18 0.50 0.50 0.80 0.03 0.25 0.112 0.225 0.490
0.15 0.15 0.50 0.50 0.80 0.02 0.25 0.109 0.218 0.490
Dalam Galian 0.500
Umpak
Galian
P Atas L Atas P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Umpak
0.50 0.50 0.70 0.70 0.80 0.25 0.49 0.296 0.592 0.810
0.45 0.45 0.60 0.60 0.80 0.20 0.36 0.225 0.450 0.640
0.40 0.40 0.50 0.50 0.80 0.16 0.25 0.164 0.328 0.490
0.35 0.35 0.50 0.50 0.80 0.12 0.25 0.149 0.298 0.490
0.30 0.30 0.50 0.50 0.80 0.09 0.25 0.136 0.272 0.490
0.25 0.25 0.50 0.50 0.80 0.06 0.25 0.125 0.250 0.490
0.20 0.20 0.50 0.50 0.80 0.04 0.25 0.116 0.232 0.490
0.18 0.18 0.50 0.50 0.80 0.03 0.25 0.112 0.225 0.490
0.15 0.15 0.50 0.50 0.80 0.02 0.25 0.109 0.218 0.490
Dalam Galian 0.500
Umpak
Galian
P Atas L Atas P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Umpak
0.50 0.50 0.70 0.70 0.80 0.25 0.49 0.296 0.592 0.810
0.45 0.45 0.60 0.60 0.80 0.20 0.36 0.225 0.450 0.640
0.40 0.40 0.50 0.50 0.80 0.16 0.25 0.164 0.328 0.490
0.35 0.35 0.50 0.50 0.80 0.12 0.25 0.149 0.298 0.490
0.30 0.30 0.50 0.50 0.80 0.09 0.25 0.136 0.272 0.490
0.25 0.25 0.50 0.50 0.80 0.06 0.25 0.125 0.250 0.490
0.20 0.20 0.50 0.50 0.80 0.04 0.25 0.116 0.232 0.490
0.18 0.18 0.50 0.50 0.80 0.03 0.25 0.112 0.225 0.490
0.15 0.15 0.50 0.50 0.80 0.02 0.25 0.109 0.218 0.490
Dalam Galian 0.500
Umpak
Galian
P Atas L Atas P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Umpak
0.50 0.50 0.70 0.70 0.80 0.25 0.49 0.296 0.592 0.810
0.45 0.45 0.60 0.60 0.80 0.20 0.36 0.225 0.450 0.640
0.40 0.40 0.50 0.50 0.80 0.16 0.25 0.164 0.328 0.490
0.35 0.35 0.50 0.50 0.80 0.12 0.25 0.149 0.298 0.490
0.30 0.30 0.50 0.50 0.80 0.09 0.25 0.136 0.272 0.490
0.25 0.25 0.50 0.50 0.80 0.06 0.25 0.125 0.250 0.490
0.20 0.20 0.50 0.50 0.80 0.04 0.25 0.116 0.232 0.490
0.18 0.18 0.50 0.50 0.80 0.03 0.25 0.112 0.225 0.490
0.15 0.15 0.50 0.50 0.80 0.02 0.25 0.109 0.218 0.490
Dalam Galian 0.500
Umpak
Galian
P Atas L Atas P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Umpak
0.50 0.50 0.70 0.70 0.80 0.25 0.49 0.296 0.592 0.810
0.45 0.45 0.60 0.60 0.80 0.20 0.36 0.225 0.450 0.640
0.40 0.40 0.50 0.50 0.80 0.16 0.25 0.164 0.328 0.490
0.35 0.35 0.50 0.50 0.80 0.12 0.25 0.149 0.298 0.490
0.30 0.30 0.50 0.50 0.80 0.09 0.25 0.136 0.272 0.490
0.25 0.25 0.50 0.50 0.80 0.06 0.25 0.125 0.250 0.490
0.20 0.20 0.50 0.50 0.80 0.04 0.25 0.116 0.232 0.490
0.18 0.18 0.50 0.50 0.80 0.03 0.25 0.112 0.225 0.490
0.15 0.15 0.50 0.50 0.80 0.02 0.25 0.109 0.218 0.490
Dalam Galian 0.500
Umpak
Galian
P Atas L Atas P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Umpak
0.50 0.50 0.70 0.70 0.80 0.25 0.49 0.296 0.592 0.810
0.45 0.45 0.60 0.60 0.80 0.20 0.36 0.225 0.450 0.640
0.40 0.40 0.50 0.50 0.80 0.16 0.25 0.164 0.328 0.490
0.35 0.35 0.50 0.50 0.80 0.12 0.25 0.149 0.298 0.490
0.30 0.30 0.50 0.50 0.80 0.09 0.25 0.136 0.272 0.490
0.25 0.25 0.50 0.50 0.80 0.06 0.25 0.125 0.250 0.490
0.20 0.20 0.50 0.50 0.80 0.04 0.25 0.116 0.232 0.490
0.18 0.18 0.50 0.50 0.80 0.03 0.25 0.112 0.225 0.490
0.15 0.15 0.50 0.50 0.80 0.02 0.25 0.109 0.218 0.490
Um
Beton Besi Strip
Bekisting Urugan Plesteran
Tertanam Umpak Dia P Atas L Atas
P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Bekisting
P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Bekisting
P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Bekisting
P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Bekisting
P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Bekisting
P Bawah L Bawah Tinggi Luas Atas Luas Bawah Volume Vol 2 Unit Bekisting
No Uraian Kegiatan Volume Satuan Analisa Harga Satuan (Rp) Jumlah Harga (Rp)
Jumlah 1,205,456.25
Lampiran - 6 : Pengadaan Sambungan Rumah dan Accessories Sambungan Rumah
Pekerjaaan : #REF!
Lokasi : #REF!
Tahun Anggaran : #REF!
Harga Satuan
No Uraian Kegiatan Volume Satuan Analisa (Rp) Jumlah Harga (Rp)
Pekerjaan Persiapan
1 Uitset Pengukuran Jarak M' AHSP PU - T.04 1,311.00
Pekerjaan Tanah
2 Galian Tanah Biasa Sedalam 1 Meter M3 AHSP PU A.2.3.1.1 85,387.50
3 Galian Tanah Biasa Sedalam 2 Meter M3 AHSP PU A.2.3.1.2 104,535.00
4 Galian Tanah Biasa Sedalam 3 Meter M3 AHSP PU A.2.3.1.3 123,958.50
5 Galian Tanah Keras Sedalam 1 Meter M3 AHSP PU A.2.3.1.4 113,666.00
6 Galian Tanah Cadas Sedalam 1 Meter M3 AHSP PU A.2.3.1.5 172,155.00
7 Galian Tanah Tanah Lumpur Sedalam 1 Meter M3 AHSP PU A.2.3.1.6 137,310.00
8 Pembuangan Tanah Sejauh 30 Meter M3 AHSP PU A.2.3.1.8 37,432.50
9 Mengurug Kembali Galian M3 AHSP PU A.2.3.1.9 38,812.50
10 Memadatkan tanah (per 20 cm) M3 AHSP PU A.2.3.1.10 61,525.00
11 Timbunan Tanah Didatangkan M3 AHSP PU A.2.3.1.11a 34,155.00
12 Urugan Tanah Bekas Galian Termasuk Perataan dan Pemadatan (stamper) M3 AHSP PU - T.14 b 61,525.00
13 Timbunan Tanah didatangkan Termasuk Perataan dan Pemadatan M3 AHSP PU - T.14 E 61,525.00
14 Urugan Pasir M3 AHSP PU A.2.3.1.11 34,155.00
Pekerjaan Pasangan
15 Pondasi Batu Belah / Kali Campuran 1 : 4 M3 AHSP PU A.3.2.1.2 655,068.75
16 Pasangan Batu Kosong ( Anstamping ) M3 AHSP PU A.3.2.1.9 157,872.00
17 Pasangan Dinding Bata Merah Tebal 1/2 Bata Campuran 1 : 2 M2 AHSP PU A.4.4.1.7 92,955.94
18 Pasangan Dinding Bata Merah Tebal 1/2 Bata Campuran 1 : 4 M2 AHSP PU A.4.4.1.9 76,891.88
19 Pasangan Dinding Terawang ( Roster ) Campuran 1 : 4 M2 AHSP PU A.4.4.1.23 75,813.75
20 Plesteran 1 : 2 Tebal 15 mm M2 AHSP PU A.4.4.2.2 82,765.50
21 Plesteran 1 : 4 Tebal 15 mm M2 AHSP PU A.4.4.2.4 74,175.00
Pekerjaan Beton
22 Lantai Kerja Beton Mutu F'c = 7,4 Mpa (K 100), Slump (3-6) cm, W/c = 0,87 M3 AHSP PU A.4.1.1.4 1,058,846.07
23 Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66 M3 AHSP PU A.4.1.1.5 1,307,356.14
24 Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, W/c = 0,58 M3 AHSP PU A.4.1.1.7 1,395,893.82
25 Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56 M3 AHSP PU A.4.1.1.8 1,421,222.57
26 Pembesian 1 Kg Dengan Besi Polos Atau Besi Ulir Kg AHSP PU A.4.1.1.17 24,690.50
27 Memasang 1 Kg Jaring Kawat Baja / Wire Mesh Kg AHSP PU A.4.1.1.19 29,589.50
28 Memasang Bekisting Untuk Pondasi M2 AHSP PU A.4.1.1.20 220,173.25
29 Memasang Bekisting Untuk Sloof M2 AHSP PU A.4.1.1.21 241,520.13
30 Memasang Bekisting Untuk Kolom M2 AHSP PU A.4.1.1.22 429,556.63
31 Memasang Bekisting Untuk Balok M2 AHSP PU A.4.1.1.23 443,572.25
32 Memasang Bekisting Untuk Plat Lantai M2 AHSP PU A.4.1.1.24 613,556.63
33 Memasang Bekisting Untuk Dinding M2 AHSP PU A.4.1.1.25 391,155.25
Pekerjaan Pengelasan
34 Pengelasan dengan Listrik M' AHSP PU A.4.2.1.5 80,960.00
35 1 M' Pengelasan Pipa HDPE M' Anl. HDPE. A 80,960.00
Pekerjaan Pemasangan Pipa PVC
36 Memasang 1 M' pipa PVC dia. 50 mm M' AHSP PU A.8.4.1.1 15,847.00
37 Memasang 1 M' pipa PVC dia. 75 mm M' AHSP PU A.8.4.1.2 18,267.75
38 Memasang 1 M' pipa PVC dia. 100 mm M' AHSP PU A.8.4.1.3 20,608.00
39 Memasang 1 M' pipa PVC dia. 150 mm M' AHSP PU A.8.4.1.4 23,028.75
40 Memasang 1 M' pipa PVC dia. 200 mm M' AHSP PU A.8.4.1.5 36,926.50
41 Memasang 1 M' pipa PVC dia. 250 mm M' AHSP PU A.8.4.1.6 49,956.00
42 Memasang 1 M' pipa PVC dia. 300 mm M' AHSP PU A.8.4.1.7 57,252.75
43 Memasang 1 M' pipa PVC dia. 350 mm M' AHSP PU A.8.4.1.7a 81,618.38
44 Memasang 1 M' pipa PVC dia. 400 mm M' AHSP PU A.8.4.1.8 105,984.00
Pekerjaan Pemasangan Pipa Steel
No Uraian Pekerjaan Satuan Analisa Harga Satuan
Jumlah Bahan -
C. PERALATAN
1 Water Pass Sewa-Hari 0.0040 - -
2 Theodolit Sewa-Hari 0.0040 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,140.00
E Overhead & Profit 15% X D 171.00
F Harga Satuan Pekerjaan ( D + E ) 1,311.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 74,250.00
E Overhead & Profit 15% X D 11,137.50
F Harga Satuan Pekerjaan ( D + E ) 85,387.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 90,900.00
E Overhead & Profit 15% X D 13,635.00
F Harga Satuan Pekerjaan ( D + E ) 104,535.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 107,790.00
E Overhead & Profit 15% X D 16,168.50
F Harga Satuan Pekerjaan ( D + E ) 123,958.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 98,840.00
E Overhead & Profit 15% X D 14,826.00
F Harga Satuan Pekerjaan ( D + E ) 113,666.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 149,700.00
E Overhead & Profit 15% X D 22,455.00
F Harga Satuan Pekerjaan ( D + E ) 172,155.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 119,400.00
E Overhead & Profit 15% X D 17,910.00
F Harga Satuan Pekerjaan ( D + E ) 137,310.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 32,550.00
E Overhead & Profit 15% X D 4,882.50
F Harga Satuan Pekerjaan ( D + E ) 37,432.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 33,750.00
E Overhead & Profit 15% X D 5,062.50
F Harga Satuan Pekerjaan ( D + E ) 38,812.50
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 53,500.00
E Overhead & Profit 15% X D 8,025.00
F Harga Satuan Pekerjaan ( D + E ) 61,525.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 29,700.00
E Overhead & Profit 15% X D 4,455.00
F Harga Satuan Pekerjaan ( D + E ) 34,155.00
Jenis Pekerjaan : Urugan Tanah Bekas Galian Termasuk Perataan dan Pemadatan (stamper)
Satuan / Unit : M3
Analisa : AHSP PU - T.14 b
Jumlah Bahan -
C. PERALATAN
1 Pemadat Timbunan (Stamper) Sewa-Hari 0.0500 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 53,500.00
E Overhead & Profit 15% X D 8,025.00
F Harga Satuan Pekerjaan ( D + E ) 61,525.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 29,700.00
E Overhead & Profit 15% X D 4,455.00
F Harga Satuan Pekerjaan ( D + E ) 34,155.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 569,625.00
E Overhead & Profit 15% X D 85,443.75
F Harga Satuan Pekerjaan ( D + E ) 655,068.75
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 137,280.00
E Overhead & Profit 15% X D 20,592.00
F Harga Satuan Pekerjaan ( D + E ) 157,872.00
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pasangan Dinding Bata Merah Tebal 1/2 Bata Campuran 1 : 2
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.7
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 80,831.25
E Overhead & Profit 15% X D 12,124.69
F Harga Satuan Pekerjaan ( D + E ) 92,955.94
Jenis Pekerjaan : Pasangan Dinding Bata Merah Tebal 1/2 Bata Campuran 1 : 4
Satuan / Unit : M2
Analisa : AHSP PU A.4.4.1.9
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 66,862.50
E Overhead & Profit 15% X D 10,029.38
F Harga Satuan Pekerjaan ( D + E ) 76,891.88
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 65,925.00
E Overhead & Profit 15% X D 9,888.75
F Harga Satuan Pekerjaan ( D + E ) 75,813.75
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 71,970.00
E Overhead & Profit 15% X D 10,795.50
F Harga Satuan Pekerjaan ( D + E ) 82,765.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 64,500.00
E Overhead & Profit 15% X D 9,675.00
F Harga Satuan Pekerjaan ( D + E ) 74,175.00
Jenis Pekerjaan : Lantai Kerja Beton Mutu F'c = 7,4 Mpa (K 100), Slump (3-6) cm, W/c = 0,87
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.4
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 920,735.71
E Overhead & Profit 15% X D 138,110.36
F Harga Satuan Pekerjaan ( D + E ) 1,058,846.07
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F'c = 14,5 Mpa (K 175), Slump (12 ± 2) cm, W/c = 0,66
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.5
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,136,831.43
E Overhead & Profit 15% X D 170,524.71
F Harga Satuan Pekerjaan ( D + E ) 1,307,356.14
Jenis Pekerjaan : Beton Mutu F'c = 19,3 Mpa (K 225), Slump (12 ± 2) cm, W/c = 0,58
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.7
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,213,820.71
E Overhead & Profit 15% X D 182,073.11
F Harga Satuan Pekerjaan ( D + E ) 1,395,893.82
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Beton Mutu F'c = 21,7 Mpa (K 250), Slump (12 ± 2) cm, W/c = 0,56
Satuan / Unit : M3
Analisa : AHSP PU A.4.1.1.8
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,235,845.71
E Overhead & Profit 15% X D 185,376.86
F Harga Satuan Pekerjaan ( D + E ) 1,421,222.57
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 214,700.00
E Per Kg Pembesian = D / 10 21,470.00
F Overhead & Profit 15% X E 3,220.50
G Harga Satuan Pekerjaan ( E + F ) 24,690.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 25,730.00
E Overhead & Profit 15% X D 3,859.50
F Harga Satuan Pekerjaan ( D + E ) 29,589.50
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 382,910.00
E Bekisting Dipakai 2 x = D/2 191,455.00
F Overhead & Profit 15% X E 28,718.25
G Harga Satuan Pekerjaan ( E + F ) 220,173.25
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Sloof
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.21
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 420,035.00
E Bekisting Dipakai 2 x = D/2 210,017.50
F Overhead & Profit 15% X E 31,502.63
G Harga Satuan Pekerjaan ( E + F ) 241,520.13
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 747,055.00
E Bekisting Dipakai 2 x = D/2 373,527.50
F Overhead & Profit 15% X E 56,029.13
G Harga Satuan Pekerjaan ( E + F ) 429,556.63
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Balok
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.23
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 771,430.00
E Bekisting Dipakai 2 x = D/2 385,715.00
F Overhead & Profit 15% X E 57,857.25
G Harga Satuan Pekerjaan ( E + F ) 443,572.25
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Bekisting Untuk Plat Lantai
Satuan / Unit : M2
Analisa : AHSP PU A.4.1.1.24
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,067,055.00
E Bekisting Dipakai 2 x = D/2 533,527.50
F Overhead & Profit 15% X E 80,029.13
G Harga Satuan Pekerjaan ( E + F ) 613,556.63
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 680,270.00
E Bekisting Dipakai 2 x = D/2 340,135.00
F Overhead & Profit 15% X E 51,020.25
G Harga Satuan Pekerjaan ( E + F ) 391,155.25
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 13,780.00
E Overhead & Profit 15% X D 2,067.00
F Harga Satuan Pekerjaan ( D + E ) 15,847.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 15,885.00
E Overhead & Profit 15% X D 2,382.75
F Harga Satuan Pekerjaan ( D + E ) 18,267.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 17,920.00
E Overhead & Profit 15% X D 2,688.00
F Harga Satuan Pekerjaan ( D + E ) 20,608.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 20,025.00
E Overhead & Profit 15% X D 3,003.75
F Harga Satuan Pekerjaan ( D + E ) 23,028.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 32,110.00
E Overhead & Profit 15% X D 4,816.50
F Harga Satuan Pekerjaan ( D + E ) 36,926.50
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 43,440.00
E Overhead & Profit 15% X D 6,516.00
F Harga Satuan Pekerjaan ( D + E ) 49,956.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 49,785.00
E Overhead & Profit 15% X D 7,467.75
F Harga Satuan Pekerjaan ( D + E ) 57,252.75
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 70,972.50
E Overhead & Profit 15% X D 10,645.88
F Harga Satuan Pekerjaan ( D + E ) 81,618.38
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 92,160.00
E Overhead & Profit 15% X D 13,824.00
F Harga Satuan Pekerjaan ( D + E ) 105,984.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 65,905.00
E Overhead & Profit 15% X D 9,885.75
F Harga Satuan Pekerjaan ( D + E ) 75,790.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 71,185.00
E Overhead & Profit 15% X D 10,677.75
F Harga Satuan Pekerjaan ( D + E ) 81,862.75
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 76,465.00
E Overhead & Profit 15% X D 11,469.75
F Harga Satuan Pekerjaan ( D + E ) 87,934.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 93,530.00
E Overhead & Profit 15% X D 14,029.50
F Harga Satuan Pekerjaan ( D + E ) 107,559.50
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 146,930.00
E Overhead & Profit 15% X D 22,039.50
F Harga Satuan Pekerjaan ( D + E ) 168,969.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 174,960.00
E Overhead & Profit 15% X D 26,244.00
F Harga Satuan Pekerjaan ( D + E ) 201,204.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 186,720.00
E Overhead & Profit 15% X D 28,008.00
F Harga Satuan Pekerjaan ( D + E ) 214,728.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 249,527.50
E Overhead & Profit 15% X D 37,429.13
F Harga Satuan Pekerjaan ( D + E ) 286,956.63
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 312,335.00
E Overhead & Profit 15% X D 46,850.25
F Harga Satuan Pekerjaan ( D + E ) 359,185.25
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 5,810.00
E Overhead & Profit 15% X D 871.50
F Harga Satuan Pekerjaan ( D + E ) 6,681.50
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 6,295.00
E Overhead & Profit 15% X D 944.25
F Harga Satuan Pekerjaan ( D + E ) 7,239.25
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 6,780.00
E Overhead & Profit 15% X D 1,017.00
F Harga Satuan Pekerjaan ( D + E ) 7,797.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,485.00
E Overhead & Profit 15% X D 1,572.75
F Harga Satuan Pekerjaan ( D + E ) 12,057.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 17,265.00
E Overhead & Profit 15% X D 2,589.75
F Harga Satuan Pekerjaan ( D + E ) 19,854.75
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 22,570.00
E Overhead & Profit 15% X D 3,385.50
F Harga Satuan Pekerjaan ( D + E ) 25,955.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 28,815.00
E Overhead & Profit 15% X D 4,322.25
F Harga Satuan Pekerjaan ( D + E ) 33,137.25
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 38,985.00
E Overhead & Profit 15% X D 5,847.75
F Harga Satuan Pekerjaan ( D + E ) 44,832.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 49,155.00
E Overhead & Profit 15% X D 7,373.25
F Harga Satuan Pekerjaan ( D + E ) 56,528.25
Jenis Pekerjaan : Membuat dan Memasang Kusen pintu dan Kusen Jendela, Kayu Kelas I
Satuan / Unit : M3
Analisa : AHSP PU A.4.6.1.1
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 19,283,625.00
E Overhead & Profit 15% X D 2,892,543.75
F Harga Satuan Pekerjaan ( D + E ) 22,176,168.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,247,045.00
E Overhead & Profit 15% X D 187,056.75
F Harga Satuan Pekerjaan ( D + E ) 1,434,101.75
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 20,880,980.00
E Overhead & Profit 15% X D 3,132,147.00
F Harga Satuan Pekerjaan ( D + E ) 24,013,127.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,593,800.00
E Overhead & Profit 15% X D 1,589,070.00
F Harga Satuan Pekerjaan ( D + E ) 12,182,870.00
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 202,962.50
E Overhead & Profit 15% X D 30,444.38
F Harga Satuan Pekerjaan ( D + E ) 233,406.88
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Memasang Langit-Langit Tripleks Ukuran (120 x 240) cm, tebal 6 mm
Satuan / Unit : M2
Analisa : AHSP PU A.4.5.1.5
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 25,739.00
E Overhead & Profit 15% X D 3,860.85
F Harga Satuan Pekerjaan ( D + E ) 29,599.85
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 138,556.25
E Overhead & Profit 15% X D 20,783.44
F Harga Satuan Pekerjaan ( D + E ) 159,339.69
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 138,556.25
E Overhead & Profit 15% X D 20,783.44
F Harga Satuan Pekerjaan ( D + E ) 159,339.69
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 21,120.00
E Overhead & Profit 15% X D 3,168.00
F Harga Satuan Pekerjaan ( D + E ) 24,288.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 32,200.00
E Overhead & Profit 15% X D 4,830.00
F Harga Satuan Pekerjaan ( D + E ) 37,030.00
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 103,278.00
E Overhead & Profit 15% X D 15,491.70
F Harga Satuan Pekerjaan ( D + E ) 118,769.70
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,175.00
E Overhead & Profit 15% X D 1,526.25
F Harga Satuan Pekerjaan ( D + E ) 11,701.25
Jenis Pekerjaan : Pengecatan Bidang Kayu Baru (1 x plamir, 1 x cat dasar,2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.4
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 9,635.00
E Overhead & Profit 15% X D 1,445.25
F Harga Satuan Pekerjaan ( D + E ) 11,080.25
ANALISA HARGA SATUAN PEKERJAAN
Jenis Pekerjaan : Pengecatan Tembok Baru (1 x plamir, 1 x cat dasar, 2 x cat penutup)
Satuan / Unit : M2
Analisa : AHSP PU A.4.7.1.10
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 11,650.00
E Overhead & Profit 15% X D 1,747.50
F Harga Satuan Pekerjaan ( D + E ) 13,397.50
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 9,260.00
E Overhead & Profit 15% X D 1,389.00
F Harga Satuan Pekerjaan ( D + E ) 10,649.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 160,400.00
E Overhead & Profit 15% X D 24,060.00
F Harga Satuan Pekerjaan ( D + E ) 184,460.00
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 676,700.00
E Overhead & Profit 15% X D 101,505.00
F Harga Satuan Pekerjaan ( D + E ) 778,205.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 16,550.00
E Overhead & Profit 15% X D 2,482.50
F Harga Satuan Pekerjaan ( D + E ) 19,032.50
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 75,835.00
E Overhead & Profit 15% X D 11,375.25
F Harga Satuan Pekerjaan ( D + E ) 87,210.25
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 24,015.00
E Overhead & Profit 15% X D 3,602.25
F Harga Satuan Pekerjaan ( D + E ) 27,617.25
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,016.00
E Overhead & Profit 15% X D 152.40
F Harga Satuan Pekerjaan ( D + E ) 1,168.40
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,176.00
E Overhead & Profit 15% X D 176.40
F Harga Satuan Pekerjaan ( D + E ) 1,352.40
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 1,496.00
E Overhead & Profit 15% X D 224.40
F Harga Satuan Pekerjaan ( D + E ) 1,720.40
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 2,296.00
E Overhead & Profit 15% X D 344.40
F Harga Satuan Pekerjaan ( D + E ) 2,640.40
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 3,336.00
E Overhead & Profit 15% X D 500.40
F Harga Satuan Pekerjaan ( D + E ) 3,836.40
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 4,776.00
E Overhead & Profit 15% X D 716.40
F Harga Satuan Pekerjaan ( D + E ) 5,492.40
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 6,536.00
E Overhead & Profit 15% X D 980.40
F Harga Satuan Pekerjaan ( D + E ) 7,516.40
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,936.00
E Overhead & Profit 15% X D 1,640.40
F Harga Satuan Pekerjaan ( D + E ) 12,576.40
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0370 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 3,770.00
E Overhead & Profit 15% X D 565.50
F Harga Satuan Pekerjaan ( D + E ) 4,335.50
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0370 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 7,465.00
E Overhead & Profit 15% X D 1,119.75
F Harga Satuan Pekerjaan ( D + E ) 8,584.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0400 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 11,160.00
E Overhead & Profit 15% X D 1,674.00
F Harga Satuan Pekerjaan ( D + E ) 12,834.00
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0450 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 24,265.00
E Overhead & Profit 15% X D 3,639.75
F Harga Satuan Pekerjaan ( D + E ) 27,904.75
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0600 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 62,855.00
E Overhead & Profit 15% X D 9,428.25
F Harga Satuan Pekerjaan ( D + E ) 72,283.25
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0680 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 87,530.00
E Overhead & Profit 15% X D 13,129.50
F Harga Satuan Pekerjaan ( D + E ) 100,659.50
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0720 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 98,280.00
E Overhead & Profit 15% X D 14,742.00
F Harga Satuan Pekerjaan ( D + E ) 113,022.00
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.0885 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 144,180.00
E Overhead & Profit 15% X D 21,627.00
F Harga Satuan Pekerjaan ( D + E ) 165,807.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Bahan -
C. PERALATAN
1 Peralatan Potong Pipa T2/Mekanik/Clinder Saw hari 0.1050 - -
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 190,080.00
E Overhead & Profit 15% X D 28,512.00
F Harga Satuan Pekerjaan ( D + E ) 218,592.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 15,060.00
E Overhead & Profit 15% X D 2,259.00
F Harga Satuan Pekerjaan ( D + E ) 17,319.00
Jumlah Bahan -
C. PERALATAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 64,200.00
E Overhead & Profit 15% X D 9,630.00
F Harga Satuan Pekerjaan ( D + E ) 73,830.00
ANALISA HARGA SATUAN PEKERJAAN
Jumlah Peralatan -
D Jumlah Harga Tenga Kerja, Bahan dan Peralatan ( A + B + C ) 10,700.00
E Overhead & Profit 15% X D 1,605.00
F Harga Satuan Pekerjaan ( D + E ) 12,305.00
ANALISA HARGA SATUAN PEKERJAAN
II Material / Bahan
1 Air M3 80,000.00
2 Air Liter 80.00
3 Ampelas Lembar
4 Baja Profil Kg
5 Bak Cuci Piring Logam Bh
6 Batu Bata Bh
7 Batu Kali/ Batu Belah (Sungai / Gunung ) M3
8 Besi Beton Polos Kg 18,000.00
9 Besi Beton Ulir Kg
10 Beton Rooster/ Kerawang Bh
11 Bubungan Seng M'
12 Cat Kayu Dasar Kg
13 Cat Kayu Mengkilat Kg
14 Cat Menie Besi Kg
15 Cat Tembok Kg
16 Dempul Kayu Kg
17 Engsel Jendela Pasang
18 Engsel Pintu Pasang
19 Floor Drain Bh
20 Gemuk Kg
21 Grendel Jendela / Pintu Bh
22 Hak Angin Bh
23 Kaca Bening Uk. 5 mm M2
24 Kawat Beton Kg 25,000.00
25 Kawat Bronjong Pabrikan Uk. ( 2 x 1 x 0,5 ) dia. 3 mm Unit
26 Kawat Duri Kg
27 Kawat Las Kg
28 Kayu Bakau / Dolken 10 Cm Btg 80,000.00
29 Kayu Kelas I M3 14,000,000.00
30 Kayu Kelas II M3 8,125,000.00
Harga Satuan Dasar
No Uraian Satuan
(Rp)
31 Kayu Kelas III M3 7,125,000.00
32 Kayu Kelas IV M3
33 Keramik Artistik M2
34 Keramik uk. 30 x 30 cm M2
35 Keramik uk. 40 x 40 cm M2
36 Kloset Jongkok Keramik Bh
37 Kuas Bh
38 Kunci Pintu Bh
39 Lem Kayu Kg
40 Lempengan Rumput M2
41 Minyak Bekisting Liter 22,700.00
41 Minyak Cat Liter
42 Minyak Hidrolik Liter
43 Minyak Pelumas Liter
44 Multiplek 4 mm Lbr
45 Multiplek 6 mm Lbr
46 Multiplek 9 mm Lbr 147,300.00
47 Nok / Rabung Seng 0,35 Cat Pabrik Lbr
48 Nok / Rabung Seng 0,35 tidak di cat Lbr
49 Paku Kayu Kg 21,300.00
50 Paku Seng Kg
51 Pasir Beton / Kerikil M3 235,000.00
52 Pasir Beton / Kerikil Kg 167.86
53 Pasir Pasang M3
54 Pasir Pasang Kg
55 Pasir Urug M3
56 Plamir Tembok Kg
57 Penjaga Jarak/Spacer bh
58 Residu Ltr
59 Reservoir Fiber Glass 1 M3 Unit
60 Reservoir Stainless Steel 1 M3 Unit
61 Semen Portland 40 kg Zak 75,000.00
62 Semen Portland Kg 1,875.00
63 Semen Putih 50 Kg Zak
64 Semen Putih Kg
65 Seng Gelombang BJLS 30 Cat Pabrik 8 kaki (90x240 cm) Lbr
66 Seng Plat BJLS 30 (90x240 cm) Lbr
67 Solar Industri Liter
68 Stop Kontak + Instalasi Titik
69 Tanah Timbun M3
70 Titik Lampu + Instalasi Titik
71 Gebalan Rumput M2
72 Aspal Kg
73 Kerosene liter
74 Agregat Kasar M3
75 Agregat Halus M3
76 Filler Kg
77 Sirtu M3
Harga Satuan Dasar
No Uraian Satuan
(Rp)
III Peralatan
1 Clinder Saw/Mesin Potong Pipa Sewa Hari
2 Excavator Jam
3 Mesin Las Jam
4 Mesin Penyambung HDPE / Butt Fusion Jam
5 Stamper Sewa Hari
6 Water Pass Sewa Hari
7 Theodolit Sewa Hari
8 Sewa Jack Hammer dan Mesin Cutter Jam
9 Asphalt Sprayer Jam
10 Air Compresor Jam
11 Wheel Loader Jam
12 AMP Jam
13 Motor Grader Jam
14 Wheel Loader Jam
15 Water Tanker Jam
16 Genset Jam
17 Dump Truck Jam
18 Asphalt Finisher Jam
19 Tandem Roller Jam
20 P. Tyre Roller Jam
21 Molen Beton 0,3 - 0,6 M3 Jam
22 Water Pump 4" Jam
No Uraian Satuan Harga
1 Mandor OH
2 Kepala Tukang Kayu / Cat OH
3 Tukang Kayu / Cat OH
4 Laden Tukang Kayu / Cat OH
5 Kepala Tukang Batu / Besi OH
6 Tukang Batu/ Besi OH
7 Laden Tukang Batu/ Besi OH
8 Pekerja Galian Tanah OH
9 Penjaga Malam OH
10 Penyelam OH
11 Supir OH
12 Operator OH
II Material / Bahan
1 Air M3
2 Air Liter
3 Baja Profil Kg
4 Bak Cuci Piring Logam Bh
5 Batu Bata Bh
6 Batu Kali/ Batu Belah (Sungai / Gunung ) M3
7 Besi Beton Polos Kg
8 Besi Beton Ulir Kg
9 Beton Rooster/ Kerawang Bh
10 Bubungan Seng M'
11 Cat Kayu Dasar Kg
12 Cat Kayu Mengkilat Kg
13 Cat Menie Besi Kg
14 Cat Tembok Kg
15 Dempul Kayu Kg
16 Engsel Jendela Pasang
17 Engsel Pintu Pasang
18 Floor Drain Bh
19 Grendel Jendela / Pintu Bh
20 Hak Angin Bh
21 Kaca Bening Uk. 5 mm M2
22 Kawat Beton Kg
23 Kawat Bronjong Pabrikan Uk. ( 2 x 1 x 0,5 ) dia. 3 mm Unit
24 Kawat Duri Kg
25 Kayu Bakau / Dolken 10 Cm Btg
26 Kayu Kelas I M3
27 Kayu Kelas II M3
28 Kayu Kelas III M3
29 Kayu Kelas IV M3
30 Keramik uk. 30 x 30 cm M2
31 Keramik uk. 40 x 40 cm M2
32 Kloset Jongkok Keramik Bh
33 Kunci Pintu Bh
34 Lempengan Rumput M2
35 Minyak Cat Liter
36 Multiplek 4 mm Lbr
37 Multiplek 6 mm Lbr
38 Multiplek 9 mm Lbr
39 Nok / Rabung Seng 0,35 Cat Pabrik Lbr
40 Nok / Rabung Seng 0,35 tidak di cat Lbr
41 Paku Kayu Kg
42 Paku Seng Kg
43 Pasir Beton / Kerikil M3
44 Pasir Pasang M3
45 Pasir Urug M3
46 Plamir Tembok Kg
47 Residu Ltr
48 Reservoir Fiber Glass 1 M3 Unit
49 Reservoir Stainless Steel 1 M3 Unit
50 Semen 40 kg Zak
51 Semen Putih 50 Kg Zak
52 Seng Gelombang BJLS 30 Cat Pabrik M2
53 Seng Plat BJLS 30 M2
54 Solar Industri Liter
55 Stop Kontak + Instalasi Titik
56 Tanah Timbun M3
57 Titik Lampu + Instalasi Titik
58
59
60
61
III Peralatan
1 Excavator Jam
2 Mesin Las Jam
3 Mesin Penyambung HDPE / Butt Fusion Jam
4
5