Professional Documents
Culture Documents
1 Personnel involved:
- Commissioning Engineer.
- Commissioning Technician.
3 Equipment:
Personal protective equipment including:
- Safety shoes.
- Safety gloves.
- Protection glasses.
- Coverall.
- Helmet.
4 Safety information:
The commissioning team should be:
To proceed correctly a permit to work should be signed (with risk assessment filled).
Tripping and locking the main circuit breaker (11-NX-705 EMAX3N): the key of the lock must be kept
with the commissioning team of GATECH SPA.
The lifting of the drawer must be done with a cart to prevent any injury to the commissioning team.
Any stain done inside the switchgear during drawer installation, the main breaker must be opened and
locked.
During the testing phase, the commissioning team must wear their personal protective equipment, such
as one person for testing and the other to control his colleague, in order to ensure his protection and
avoid his injury.
1) Turn OFF the circuit breaker of the drawer and pull and push the drawer by pressing the
indexing push button to ensure that the drawer is not blocked.
2) Turn ON the circuit breaker of the drawer and pull the drawer by pressing the indexing push
button to ensure that the drawer is blocked when it’s ON.
1) Ensuring that the status of the circuit breaker of the drawer provided by the auxiliary
terminal block is correct (according to EBT15063 02 222).
2) Ensuring that all the inputs of the circuit breaker of the drawer are powered by the vertical
riser of the switchgear by the measurement of drawer’s output when the circuit breaker is
ON.
3) Test the deferential relay by pressing its test button.
4) Test the circuit breaker of the drawer by pressing its test button.
5) Test the continuity between live part and the enclosure when the circuit breaker of the
drawer is ON and the main circuit breaker is OFF.