Cargo Qty : 2,039.900 mt Charter party : Vegoilvoy In Days
Time Allowed (Loading) 70 mtph Time Allowed (Loading) 29.14 hrs 31 05:08 Time Allowed (Discharging) 110 mtph Time Allowed (Discharging) 18.54 hrs 30 18:32 Reversible as per C/P (Yes/No) Yes Cumulative (if reversible) 47.69 hrs 31 23:41
Actual time Loading : 31.83 hrs
Actual time Discharging : 68.83 hrs Demurrage to be Paid up : 25,386.58 USD Demurrage (Add if reversible) : 52.98 hrs
Loading Time sheet
N.O.R. Tendered Jun 29 - 2021 9:35
Berthed Jun 29 - 2021 12:05 *Start of Lay period Hoses On Jun 29 - 2021 18:30 Commenced Loading Jun 29 - 2021 18:50 Completed Loading Jun 30 - 2021 19:40 Hoses Off Jun 30 - 2021 19:55 *End of Lay period
From To Time Used Exceptions In Days
Jun 29 - 2005 12:05 Jun 30 - 2005 19:55 31.83 hrs
Total lay time used : 31.83 hrs 31 07:50
Time Allowed : 29.14 hrs 31 05:08 Under (+ve) / Over (-ve) -2.69 hrs Comments :
Discharging Time sheet
N.O.R. Tendered Aug 07 - 2021 21:25
Commence Lay period Aug 08 - 2021 3:25 *Start of Lay period Berthed Aug 10 - 2021 4:05 Hoses On Aug 10 - 2021 6:05 Commenced Loading Aug 10 - 2021 6:20 Completed Loading Aug 10 - 2021 23:50 Hoses Off Aug 11 - 2021 0:15 *End of Lay period
From To Time Used Exceptions In Days
Aug 08 - 2021 3:25 Aug 11 - 2021 0:15 68.83 hrs 01 20:50
Total lay time used : 68.83 hrs 01 20:50