Time Phased Data Histogram And S-CurveFor Evaluation Only

PLANTA MINERA

Reporting Period 1: Apr '15

Cost In USD x100.000

Bars 2015 2016 2017 Curves

abril mayo junio julio agos septi octu novi dicie ener febr marz abril mayo junio julio agos septi octu novi dicie ener febr marz abril
100 1,500

80 1,200

60 900

40 600

20 300

0 0
Period Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

Baseline Budget 1 2 2 4 18 40 47 47 56 65 74 89 95 97 94 78 61 62 57 60 59 40 37 39 24 BB

Late Budget 1 2 2 3 13 29 36 38 43 52 51 65 72 69 66 58 60 66 62 58 64 74 83 95 83 LB

To Date Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr

Baseline Budget 1 2 4 8 26 65 113 160 216 280 354 443 538 635 729 807 868 930 987 1,050 1,110 1,150 1,180 1,220 1,250 BB

Late Budget 1 2 4 7 20 49 86 124 167 219 270 336 408 477 543 601 661 727 788 846 910 984 1,070 1,160 1,250 LB

PRISM G2 - Time Phased Data Histogram And S-Curve - 1 Print Date/Time: 14/04/2019 11:00:02