NO DETAIL URAIAN

1 Jenis Pekerjaan Timbunan Padat Vibro cbr 90 %


2 JENIS MATERIAL Limstone
3 Material Exs Rengel Tuban
4 Vol SPK 1.000.000
5 Pembayaran Skbdn Usant Aceptasi
6 Lokasi Pekerjaan Tanjung Awar Awar Jenu kab Tuban
7 Harga Spk/M3 135.000 135.000.000.000
8 Harga Curah Franco Site 75.000 75.000.000.000
9 Loss Dari Curah 25% 18.750 18.750.000.000
10 Pemadatan 3 Alat Berat / m3 18.000 18.000.000.000
11 Internal & Exsternal 4.500 4.500.000.000
12 Total Pelaksanaan 116.250 116.250.000.000
13 Net Profit /M3 18.750 18.750.000.000
14 Pro 13,89